Item 5d Memo

PORT OF SEATTLE 
MEMORANDUM 

COMMISSION AGENDA             Item No.      5d 
Date of Meeting    December 15, 2009 
DATE:    November 19, 2009 
TO:     Tay Yoshitani, Chief Executive Officer 
FROM:    Stephanie Jones Stebbins, Senior Manager, Seaport Environmental Programs 
Kathy Bahnick, Manager, Seaport Environmental Programs 
Fred Chou, Capital Project Manager 
SUBJECT:  Project-specific professional service contract to support negotiation of and
implementation of a Washington State Department of Ecology Agreed Order for the remediation actions
at Terminal 91 
Estimated Contract Cost: $500,000-700,000    Source of Funds: Tax Levy/Environmental Reserves 
ACTION REQUESTED: Request Port Commission to authorize the Chief Executive Officer to
execute a professional services contract for consultant services ranging from approximately $500,000-
700,000 to support negotiation and implementation of a Washington State Department of Ecology 
(Ecology) Agreed Order for the remediation actions at Terminal 91. 
SYNOPSIS:
The purpose of this contract is to provide a broad array of consultant support services for remedial
action activities at Terminal 91, including the design and planning of the cleanup, construction support,
and limited post-construction sampling and monitoring. 
PROJECT DESCRIPTION AND JUSTIFICATION: 
The Terminal-91 Site (T-91 Site), as currently defined, consists of a former tank farm that was
constructed in the 1920s. A portion of the Site was operated as a dangerous waste treatment and storage
facility under a Resource Conservation and Recovery Act (RCRA) permit, from 1980 until its closure in
the late 1990s. The remainder of the Site was operated as a fuel storage facility until 2005. 
The T-91 Site is regulated under both the RCRA permit and an Agreed Order. The Port of Seattle (Port)
and two other parties, Philip Services and Pacific Northern Oil (PNO), entered into the Agreed Order for
the site in 1998 (the "1998 Agreed Other"). Both Philip Services and PNO subsequently went out of
business, leaving the Port as the sole responsible party on the Agreed Order. Under  the 1998 Agreed
Order, the Port was required to develop a Remedial Investigation (RI), Feasibility Study (FS) and a
Cleanup Action Plan (CAP). 
For the last several years, the Port has been negotiating a replacement RCRA Permit and Agreed Order
with Ecology for the RI, FS and CAP development. The most significant change in these replacement
documents is that they will extend the geographic definition of the Site beyond the tank farm to
encompass the entire Terminal 91, including the piers and all upland properties owned by the Port. The
negotiation is nearly complete, and we expect that within the next several months we will be asking for
Commission authorization to enter into this RCRA Permit and Agreed Order (the "2009 Agreed
Order").

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
December 10, 2009 
Page 2 of 4 

The former tenants and/or the Port, beginning in the 1980s and continuing to the present time, have
performed numerous environmental investigations at the T-91 Site. A summary of these investigative
activities can be found in the 2007 final draft RI report and in the 2009 final draft FS report.  Port 
submitted to Ecology the final draft RI report to Ecology in August 2007 and submitted the final draft of
the FS report in November 2009. The FS report sets forth a range of potential cleanup alternatives and
their estimated costs, and a cleanup action was recommended for implementation.  Once the RI and FS
are approved, a Cleanup Action Plan (CAP) will be developed using the information generated in the
FS. The CAP will identify the cleanup approach selected by Ecology. Sometime in 2010, Ecology
expected to issue a new RCRA Permit and Agreed Order (the "2010 Agreed Order") for the Port to
conduct the cleanup action alternative that is selected. 
An ecology lead public comment period for the final draft RI/FS report is planned for the beginning of
January 2010, so that community or public concerns can be addressed prior to preparation of the CAP.
This public comment period will also address the 2009 RCRA permit and Agreed Order. 
The 2009 draft FS report recommended a cleanup action alternative based on Model Toxics Control Act
(MTCA) standards and selection process. The proposed cleanup action consists of the following actions: 
Former tank farm-- recovery of free-phase fuel from the groundwater, removal of existing tank
bases and other subsurface structures such as concrete pavement and footings, installation of a
new asphalt cap and installation of a slurry wall 
Solid Waste Management Unit 30  limited excavation of diesel-contaminated soil 
Underground fuel pipelines  cleaning and decommissioning in place 
Groundwater plume  well installation and monitoring to confirm that demonstrated natural
attenuation processes are continuing to break down fuel-related chemicals in groundwater. 
Based upon feedback during the public comment period, Ecology will consider the proposed cleanup
actions and will determine whether modifications are necessary for the FS to be approved. 
PROJECT SCOPE OF WORK AND SCHEDULE: 
The scope of the anticipated remediation-consulting contract includes the following: 
1.  Pre-Design, Planning and Communication 
2.  Compliance Activities 
a.  Complete any remaining scope of the 1998 and 2009 Agreed Order and support the Port 
in negotiating with the Washington Department of Ecology the scope of a 2010 Agreed
Order. 
b.  Prepare environmental reports as required by the Orders 
3.  Design cleanup per Ecology-approved Cleanup Action Plan 
4.  Support Port in procuring a construction contractor to perform the cleanup work 
5.  Provide oversight of construction contractor 
6.  Conduct Post-Construction confirmatory sampling 
7.  Prepare long-term operations and monitoring plan and perform the first year of operation and
monitoring 
Work is anticipated to begin in 2010 and be completed in 2014. Long-term monitoring under a separate
procurement will continue beyond 2014. Design work will not begin until the CAP is finalized, a new

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
December 10, 2009 
Page 3 of 4 

Agreed Order for the cleanup is negotiated and Commission approves the signing of the new Agreed
Order. 
A separate request for Commission authorization to procure a construction contract will be sought
during the design-phase. 
STRATEGIC OBJECTIVES: 
This project will be conducted in accordance with the Port's environmental objectives and will be in full
compliance with the Department of Ecology's Agreed Order. Cleanup of the site will be consistent with
potential T-91 improvements, as they are currently understood. 
BUSINESS PLAN OBJECTIVES: 
Proceeding with this project ensures compliance and continued cooperation with Ecology and will allow
productive use of the property in the future. 
FINANCIAL ANALYSIS: 
Cost Estimate 
The cost for professional consulting and design services will be based on Ecology's selected alternative
and the terms and schedule laid out in the Agreed Orders. Based on the current preferred alternative, we
estimate that this contract will be in the range of $500,000 to $700,000. 
Source of Funds 
The Port has obtained an Ecology grant of $220,000 for a portion of the investigation work. We will
apply for additional grant funding for the design and construction work. All costs will be paid from 
environmental reserves and charged to expense in accordance with Port Policy AC-9. The Port's Tax
Levy will pay the costs for the environmental cleanup project that are not covered by grants. T his site
was included in the Commission's 2010 environmental reserve spending authorization, anticipated to be
approved on November 30, 2009. Any additional environmental reserve funds that may be required as
the project moves forward will be reported to the Commission via routine environmental reserve reports
and spending authorization requests. 
SUSTAINABILITY AND LIFE CYCLE COSTS: 
State and federal laws require elimination of unacceptable levels of environmental risk caused by the
presence of contaminants in soil, groundwater and sediment. From the perspective of the surrounding
communities and the customers that we serve, the Port's participation in site remediation is the hallmark
of responsible environmental stewardship. 
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
Wait until the 2010 Agreed Order is issued to procure services. The Agreed Order will include
project schedules that must be adhered to or the Port could face enforcement action. Delaying
procurement could result in missed deadlines and possibly enforcement action. 
Procure only pre-design, planning, and communication support until a cleanup alternative is selected
and approved by Ecology. This alternative  would allow Port to initiate work at the time the 2010
Agreed Order is signed, but an additional procurement would be necessary for the design and
construction support work. This would incur additional costs to go through a second procurement

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
December 10, 2009 
Page 4 of 4 

process. In addition, it could result in a different consultant being awarded the second phase of work.
Consistency within and between the phases of work is important in order to meet the exacting
standards and deadlines in the pending 2009 and 2010 Agreed Orders. 
Procure all services for planning, pre-design, design, agency reporting, construction support,
development of operation and maintenance plans and performance of first year of operation and
maintenance. Starting the procurement process now will result in signing a contract with the
consultant shortly before the 2009 Agreed Order is signed.  The Port can then move forward on a
timely basis to meet the provisions of the Agreed Order with the selected consultant. This is the
preferred alternative

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.