Item 7b Report

ITEM NO.    7b Supp-2
DATE OF
MEETING November 3, 2009 





OS 





QUARTERLY 
PERFORMANCE 
REPORT


AS OF SEPTEMBER 30, 2009

TABLE OF CONTENTS 
Page 
I.        Portwide Performance Report                                               1-3

II.       Aviation Division Report                                                     4-8

III.      Seaport Division Report                                                    9-13

IV.    Real Estate Division Report                                14-18

V.    Capital Development Division Report                     19-20

VI.    Corporate Professional & Technical Services                   21-22

I.       PORTWIDE PERFORMANCE REPORT 9/30/09 

INCOME STATEMENT 
Report: Income Statement
As of Date: 2009-09-30
2008 YTD   2009 YTD  2009 YTD  2009 Var $  2009 Var %  2009 Annual  % of Annual
Dollars in thousands               Actual      Actual     Budget    Bud vs. Act  Bud vs. Act     Budget       Bud
Revenues:
Seaport                     73,233     70,545    73,543     (2,998)    -4.1%     94,829     74.4%
Real Estate                   24,956     23,389    23,246       143     0.6%     31,111      75.2%
Aviation                       265,684    263,463   269,302      (5,839)     -2.2%     358,956      73.4%
Capital Development                         81 -         81     0.0% -
Corporate                      840       986    1,129      (143)   -12.7%      1,470      67.1%
Total Revenues                 364,714   358,465   367,221    (8,756)    -2.4%    486,367     73.7%
Operating & Maintenance:
Seaport                     13,423     17,646    24,519     6,873    28.0%     32,315     54.6%
Real Estate                   30,420     20,746    24,005      3,259    13.6%     32,300      64.2%
Aviation                        92,680     88,591    99,623     11,032     11.1%     132,665      66.8%
Capital Development               5,868      4,207     5,231      1,024    19.6%      7,010      60.0%
Corporate                    48,126     47,299    55,568     8,269    14.9%     73,572      64.3%

Total O&M before Depreciation    190,517    178,488   208,946    30,457    14.6%    277,862     64.2%

Operating Income Before Depreciation   174,197    179,976   158,276    21,701    13.7%    208,506     86.3%
Depreciation                106,997    112,885   117,456     4,571     3.9%    157,036     71.9%
Total O&M and Depreciation   297,513    291,373   326,402    35,028    10.7%    434,897     67.0%
Operating Income after Depreciation     67,201    67,091   40,819    26,272    64.4%     51,470     130.4%







1

I.       PORTWIDE PERFORMANCE REPORT 9/30/09 

CAPITAL SPENDING RESULTS
($ Millions)
Annual Results:
2009 Plan of Finance                    $604.00
2009 Approved Budget                  $436.10
2009 Estimated/Actuals                  $377.61
Variance (Budget vs Estimated\Actuals)         $58.49

PORTWIDE INVESTMENT PORTIFOLIO 
The investment portfolio for the third quarter of 2009 earned 2.51% against our benchmark (The Merrill Lynch 3-
year Treasury/Agency Index) of 1.02%.For the past twelve months the portfolio has earned 3.04% against the
benchmark of 1.04%. Since the Port became its own Treasurer in 2002, the Port's portfolio life-to-date has
earned 3.80% against our benchmark of 2.93%.















2

I.       PORTWIDE PERFORMANCE REPORT 9/30/09 
EXECUTIVE SUMMARY
The first nine months of 2009 Port of Seattle's overall operating revenues were $358.5 million, $8.8 million below
the budget. Total operating expenses were $178.5 million, $30.5 million below budget. Operating income before
depreciation was $179.9 million, $21.7 million above the budget. Operating income after depreciation is $67.1
million, $26.3 million above the budget.
Port-wide Capital spending was $178.2 million for the first nine months and is forecasted to be $377.6 million for
the year, $58.5 million below the budgeted $436.1 million.
Aviation Division's Aeronautical revenues were $1.4 million unfavorable due to lower landing fee revenue. Non-
aeronautical revenues were unfavorable by $5.1 million due to underperformance of Public Parking and other
Landside revenues. Operating expenses were 17.6 million under budget due to expense project delays and
implementation of Expense Savings Plan. Operating revenues are forecasted to be $20 million unfavorable due to
decline of parking transactions, rental car activity, and concessions, in addition to lower forecast revenue
requirements for aeronautical cost centers. Operating expenses are forecasted to be $9.2 million favorable due to
savings from furlough, delay of expense projects and corporate allocations which offset with costs for emergency
generators and elevator/escalator repairs. Total capital expenditures for 2009 are projected at $238.8 million.
Seaport Division revenues were $2.9 million unfavorable primarily due to Security Grant projects commencing
later than assumed in budget. For the full year, Seaport is forecasting a $6.2 million unfavorable revenue
variance due to later start of Security Grant projects, implementation of the Container Customer Support
Package, default of tenant at Terminal 104 and the rent impact of the Terminal 30 crane cable issue. Operating
expenses were $8.1 million favorable through September primarily due to the implementation of the 2009
Expense Savings Plan, lower cost of the Terminal 18 maintenance dredge and the Terminal 30 upland dredge
disposal projects than budgeted, and due to timing differences in planned operating expenses. For the full year,
Seaport is forecasting a $6.9 million favorable expense variance due to later start of Security Grant projects,
implementation of the 2009 Expense Savings Plan, lower cost of the Terminal 18 maintenance dredge and the
Terminal 30 upland dredge disposal projects, and the reversal of prior year Other Post Employment Benefits
(OPEB) medical related expenses. Forecasted Net Operating Income for 2009 is estimated to be $0.7 million
favorable to the 2009 Budget and $6.5 million below 2008 Actual. As of September 30, 2009 total capital
spending for 2009 was projected at $50.3 million or 50% of the Approved Annual Budget amount of $100.4
million.
Real Estate Division revenues are virtually on budget for the year-to-date as a result of offsetting variances
within the business groups. For the full year, Real Estate is forecasting a $0.3 million unfavorable revenue
variance compared to budget due to lower occupancy at Shilshole Bay Marina and offsetting favorable and
unfavorable occupancy levels at commercial property sites. Operating expenses are $4.8 million favorable for the
year-to-date primarily due to timing and deferrals related to the 2009 Expense "Deferral" Plan. For the full year,
Real Estate is forecasting a $2.3 million favorable expense variance due to implementation of the 2009 Expense
"Deferral" Plan and reversal of prior year Other Post Employment Benefits (OPEB) medical related accruals.
Forecasted Net Operating Income for 2009 is estimated to be approximately $2.0 million favorable to the 2009
Budget and $1.7 million above 2008 Actual. As of the September 30th update, total capital spending for 2009
was projected at $100.1 million or 95% of the Approved Annual Budget amount of $105.2 million.
Capital Development expenses were $1.0 million favorable through nine months mainly due to unfilled staff
positions, delayed work and less capital work than original budgeted. A $609 thousand favorable variance at the
end of the year is forecasted due to less expense work than budgeted. The division delivers projects and provides
technical and contracting services in support of the business plans and infrastructure needs of the Port's operating
divisions. As such, the CDD does not have its own capital improvement program.
Corporate Professional and Technical Services performance for the first nine months of 2009 was $8.3 million
or 14.9% favorable compared to the approved budget and $827 thousand or 1.7% lower than the same period a
year ago. The $8.3 million favorable variance is due primarily to timing of spending and to the implementation of
the 2009 Expense Savings Plan. There aren't any major variances to report on since all departments are
favorable. However, the unfavorable variance of $10 thousand in Industrial Development Corporation is due to
charges incurred for the IDC/ET Fellowship Program. Year-end spending is projected to be $67.8 million, which
is $5.7 million below the approved budget.

3

II.      AVIATION DIVISION PERFORMANCE REPORT 9/30/09

FINANCIAL SUMMARY 
2007     2008     2009    2009    Forecast/Budget
Figures in $ 000s     Actual     Actual    Forecast   Budget     Var $   Var %
Revenues
Aeronautical                   195,029   204,361    193,908   202,913     (9,005)  -4.4%
Non-Aeronautical               143,975   150,528   137,309   148,289    (10,979)  -7.4%
Other                       8,483    3,440     8,804    8,804 -    0.0%
Total Revenues               347,487   358,329   340,021   360,006    (19,985)  -5.6%
O&M Expenses (excl. Env. Res.)     171,624   192,641   179,119   188,334     9,215   4.9%
Savings: OPEB Reversal             - - (5,574) -      5,574    n/a
Costs: VSP, HR10, Unemployment      - - 2,934 -      (2,934)    n/a
Environmental Reserve               - 2,542     1,390    1,187      (203) -17.1%
Total O&M Costs              171,624   195,183   177,869   189,521    11,652   6.1%
Net Operating Income            175,864   163,146   162,152   170,485     (8,333)  -4.9%
Capital Expenditures              298,387   209,813    238,767   214,743    (24,024) -11.2%
We forecast a shortfall of $10.98 million in non-airline revenues as Public Parking, Concessions and
other Landside departments will underperform against the budget due to decreased enplanements
and reduced amounts of revenue generated per enplaned passenger.
Operating expense is forecasted to be $9.2 million favorable due to $11.5 M of Expense Savings
Plan offset by $1.75M for emergency generators in preparation of Howard Hanson Dam flooding and
$2M for elevator/escalator repairs.
Environmental Reserve is forecast to overspend by 200K mainly due to an increase in reserves for
the Lora Lake property.
Total capital expenditures for 2009 are projected at $238.8 million.

A.  BUSINESS EVENTS 
Port staff have been preparing for possible flooding from Howard Hanson Dam failure.
Icelandair began service to Reykjavik in July to compensate for SAS discontinuing service in the
same month.
Lora Lake Apartments were demolished in October.
Cell Phone Lot reopened in Q3.

B.   KEY INDICATORS 
2008   2009   %      2008   2009   %
Figures in 000's     YTD     YTD Variance    Actual     Fcst Variance
Enplanements      12,441  11,925   -4.2%  16,081  15,361   -4.5%
Landed Weight      16,459   15,597   -5.2%  21,519  20,430   -5.1%
Enplanements vs. Prior Year                  Landed Weight vs. Prior Year
-0.50%
0%                             2%       0.38% 0.03%
-2.16%
Growth Rate                                           0%
-4.02% -3.87%
-4.59% -4.65%      -4.57%             -2%  -3.95%
-5%  -6.08%                               Growth Rate -4%                             -5.45%
-6.27%
-6%               -7.25% -7.37%
-8.11%                                                                              -7.84% -7.85%
-8%
-10%                                    -10%
Jan Feb Mar Apr May Jun Jul Aug Sept         Jan Feb Mar Apr May Jun  Jul Aug Sept

Enplanements are forecasted to decrease 4.5% from the 2008 actual.

4

II.      AVIATION DIVISION PERFORMANCE REPORT 9/30/09

2007     2008     2009    2009    Forecast/Budget
Actual    Actual   Forecast  Budget    Var $   Var %
Non-Aero NOI ($ in 000s)           87,714    86,474    81,209    86,393     (5,183)  -6.0%
Passenger Airline CPE             11.73    11.89     11.67    11.90      0.23   2.0%
Total Operating Cost / Enpl           10.96     12.13     11.82     11.99      0.18   1.5%
Debt Service Coverage              1.58     1.42      1.45     1.51     (0.06)  -3.9%
We forecast CPE to come in lower than both the 2009 budget and the 2008 actual, primarily due to
significantly lower interest rate paid to variable rate bond issues and savings from the decision to
discontinue OPEB medical benefits to Port retirees.

C.   OPERATING RESULTS 
Year-to-date Revenue and Expense 
2007 YTD 2008 YTD  2009 YTD  2009 YTD   Actual/Budget
Figures in $ 000s    Actual     Actual     Actual    Budget     Var $    Var %
Revenues
Aeronautical                    151,454   149,952   151,895   153,095    (1,201)   -0.8%
Non-Aeronautical                 103,949   114,980   105,400   110,467    (5,067)   -4.6%
Other                        6,373    1,342    6,305    6,528     (223)   -3.4%
Total Revenues              261,776   266,274   263,599   270,090    (6,490)   -2.4%
Expenses
Airport Expenses                 87,057    92,680    88,580    98,657    10,077   10.8%
Corporate                      12,930    22,288    22,820    26,981     4,161   15.4%
Police Costs                     6,576    11,148    10,147    11,900     1,753   14.7%
Other Charges/CDD              10,458    4,889    3,294    3,934     640   16.3%
Operating Expenses (excl Env. Res.)   117,020   131,005   124,841   141,473    16,632   11.8%
Environmental Reserve                - - 12      966      954   98.8%
Total Operating Expense            117,020   131,005   124,852   142,438    17,586   12.3%
Net Operating Income             144,756   135,269   138,747   127,651    11,096    8.7%

Non-aeronautical revenues are unfavorable year-to-date by $5M due to underperformance of Public
Parking and other Landside revenues.
Expenses are under budget due to expense project delays and implementation of Expense Savings
Plan. 






5

II.      AVIATION DIVISION PERFORMANCE REPORT 9/30/09

Division Summary 
2007     2008     2009     2009    Forecast/Budget
Figures in $ 000s     Actual     Actual    Forecast    Budget     Var $   Var %
Operating Revenues          347,487   358,329   339,912   360,006   (20,094)  -5.6%
Expenses
Payroll                         82,627    89,458    80,192    84,777     4,585    5.4%
Outside Services                 28,900    31,928    22,085    23,737     1,652    7.0%
Utilities                              12,603     12,636     14,817     13,571     (1,246)    -9.2%
Other                       8,981    13,301    10,097     9,393     (704)   -7.5%
Total Airport Expenses           133,110   147,323   127,190   131,478     4,287    3.3%
Corporate/Capital Development        24,260    30,031    37,509    41,113    3,604    8.8%
Police                        14,253    15,287    14,420    15,743     1,323    8.4%
O&M Exclude Env. Reserve       171,624   192,641   179,119   188,334    9,215   4.9%
Savings: OPEB Reversal                           (5,574)            5,574     n/a
Costs: VSP, HR10, Unemployment                    2,934           (2,934)    n/a
Environmental Reserve               - 2,542     1,390     1,187     (203)  -17.1%
Total Operating Expenses          171,624   195,183   177,869   189,521    11,652    6.1%
Net Operating Income          175,864   163,146   162,043   170,485    (8,442)  -5.0%
Depreciation Expense            101,118   107,349   115,213   115,605     392   0.3%
Non-Operating Rev/(Exp)
Grants & Donations Revenues        89,692    49,461    73,652    63,276    10,376   16.4%
Passenger Facility Charges          63,114    62,770    61,525    62,525    (1,000)   -1.6%
Customer Facility Charges           22,570    23,534    22,318    24,573    (2,255)   -9.2%
Other Non-operating Rev/(Exp)        (80,848)   (105,378)   (116,013)   (116,013) -     0.0%
Total Non-Operating Rev/(Exp)       94,527    30,386    41,482    34,361     7,121   20.7%
Total Revenue Over Expense      169,272    86,183    88,313    89,241     (929)  -1.0%

Operating revenues are forecasted to be $20 million unfavorable due to decline of parking transactions,
rental car activity, and concessions, in addition to lower forecast revenue requirements for aeronautical
cost centers. 
Operating expenses are forecasted to be $9.2 million favorable due to savings from furlough, delay of
expense projects and corporate allocations which offset with costs for emergency generators and
elevator/escalator repairs.
Grants and Donations revenues are forecasted to be $10.4 million higher due to TSA grants not
budgeted.






6

II.      AVIATION DIVISION PERFORMANCE REPORT 9/30/09

Aeronautical Business Unit Summary
2008     2009     2009    Forecast/Budget
Figures in $000s     Actual     Forecast     Budget     Var $    Var %
Revenues requirement:
Capital Costs                    81,535     78,791     80,350    (1,559)    0.0%
Operating Costs net Non-Aero        131,024    122,532    127,921    (5,389)   -4.2%
Total Costs                   212,559    201,323    208,271    (6,948)   -3.3%
FIS Offset                       (5,250)     (5,550)     (5,550) -      0.0%
Other Offsets                    (15,686)    (15,109)    (14,052)    (1,057)    7.5%
Net Revenue Requirement          191,623    180,664    188,670    (8,005)   -4.2%
Other Aero Revenues             12,738     13,244     14,244    (1,000)    0.0%
Total Aero Revenues            204,361    193,908    202,913    (9,005)   -4.4%
Non-passenger Airline Costs          13,039     14,660     14,830      170    1.1%
Net Pasenger Airline Costs          191,323    179,248    188,084     8,835    4.7%

2008     2009     2009    Forecast/Budget
Actual    Forecast   Budget    Var $   Var %
CPE:
Capital Costs / Enpl                5.07       5.13       5.09     (0.04)   -0.9%
Operating Costs / Enpl              8.15       7.98       8.10     0.12    1.5%
Offsets                        (1.30)      (1.34)      (1.24)     0.10    -8.4%
Other Aero Revenues              0.79      0.86      0.90     (0.04)   -4.4%
Non-passenger Airline Costs         (0.81)      (0.95)      (0.94)     (0.02)    1.7%
Passenger Airline CPE           11.89     11.67     11.90     0.23    2.0%

Operating costs are forecasted to be lower than budgeted due to budget savings from Expense Savings
Plan in addition to savings from the pending OPEB medical reversal.
The forecasted increase in passenger airline cost per enplanement (CPE) is lower than budget primarily
due to large savings forecasts against enplanements which are now only slightly less than the 2009
budget.
Forecasted aeronautical operating costs per enplanement of $7.98 are less than the budget of $8.10 due
to cost cutting measures.





7

II.      AVIATION DIVISION PERFORMANCE REPORT 9/30/09

Non-Aero Business Unit Summary 
2008     2009     2009    Forecast/Budget
Figures in $000s     Actual    Forecast    Budget     Var $   Var %
Revenues:
Public Parking                   59,111     51,963     57,377    (5,413)  -9.4%
Rental Cars                     35,592     33,850     35,867    (2,018)  -5.6%
Concessions                  33,181    30,300    32,821   (2,521)  -7.7%
Other                        22,644    21,196    22,224    (1,027)  -4.6%
Total Revenue                 150,528    137,309    148,289   (10,979)  -7.4%
Operating Expense             61,279    55,624    60,329    4,705   7.8%
Share of terminal O&M             16,396    17,323    18,105     781   4.3%
Less utility internal billing              (13,515)     (16,848)     (16,848) -      0.0%
Net Operating & Maint              64,160     56,100     61,586    5,486   8.9%
Net Operating Income           86,367    81,210    86,703   (5,493)  -6.3%

2008     2009     2009    Forecast/Budget
Actual   Forecast   Budget    Var $  Var %
Revenues / Enplanement
Parking                        3.67      3.38      3.63    (0.25)  -6.8%
Rental Car                       2.21      2.20      2.27     (0.07)  -2.9%
Concessions                   2.06     1.97     2.08    (0.10)  -5.0%
Other                         1.41      1.38      1.41    (0.03)  -1.9%
Total Revenue                   9.36      8.94      9.39     (0.45)  -4.8%
Primary Concessions Sales / Enpl     10.29      9.62     10.19    (0.57)  -5.6%

Public parking revenues are forecasted to continue to decline on a per enplaned passenger basis.
Rental car revenues are forecasted to come in lower than budgeted due to weak rental car activity
and the pending expiration of contract agreement in Q4, which will reduce minimum monthly
payments.
Concessions revenues are forecasted lower than budgeted due to decline in enplanements and
reduced revenues on Concourses A and D due to airline moves.

D.   CAPITAL SPENDING RESULTS
2009      2009       Forecast/Budget     2009 Plan
Figures in $000s   YTD Actual    Forecast      Budget       Var $       Var %     of Finance
R/W 16L/34R Reconstruction       52,631      59,631      71,000      11,369      16.0%     82,715
Rental Car Facility                34,010       92,907       40,562      (52,345)     -129.0%     119,011
MT 100% Baggage Screening       9,395     10,395     18,000      7,605     42.3%     21,727
Third Runway Projects             8,649      15,052      17,281       2,229      12.9%      47,027
All Other                      25,604       60,782       67,900       7,118      10.5%      77,722
Total                        130,289      238,767      214,743      (24,024)      -11.2%      348,202

Reduced budgeted spending by $109 million vs. plan of finance budget (31%) for 2009.
Rental Car Facility restarted after over six months of suspension.
2009 Budget had anticipated claims on Baggage Screening project from contractor which Port staff
successfully negotiated down.
8

III.     SEAPORT DIVISION PERFORMANCE REPORT 9/30/09
Financial Summary
2008      2009      2009     Forecast/Budget
$'s in 000's                      Actual      Forecast     Budget     Var $     Var %
Operating Revenue              85,453      86,187     90,131   (3,944)     -4%
Environmental Grants              8,833        850       850      0       0%
Security Grants                    850       1,747      3,955   (2,208)     -56%
Total Operating Revenues          95,136      88,784     94,935   (6,152)      -6%
Total Operating Expenses         44,921      45,055     51,928   6,873     13%
Net Operating Income            50,215      43,729     43,007    721      2%
NOI Excl Envir Grants/Reserve       47,254      46,708     45,532   1,176      3%
Capital Expenditures             88,523      50,274    100,425   50,151      50%
NOTE:* NOI Excl Envir Grants/Reserve is Before Depreciation
Total Seaport revenues were ($2.9) million unfavorable in YTD results primarily due to Security Grant projects
commencing later than assumed in budget. For the full year, Seaport is forecasting a $6.2 million
unfavorable revenue variance due to later start of Security Grant projects, implementation of the Container
Customer Support Package, default of tenant at Terminal 104 and the rent impact of the Terminal 30 crane
cable issue.
Total Operating Expenses were $8.1 million favorable through September primarily due to the implementation
of the 2009 Expense Savings Plan, lower cost of the Terminal 18 maintenance dredge and the Terminal 30
upland dredge disposal projects than budgeted, and due to timing differences in planned operating expenses.
For the full year, Seaport is forecasting a $6.9 million favorable expense variance due to later start of Security
Grant projects, implementation of the 2009 Expense Savings Plan, lower cost of the Terminal 18
maintenance dredge and the Terminal 30 upland dredge disposal projects, and the reversal of prior year
Other Post Employment Benefits (OPEB) medical related expenses.
Forecasted Net Operating Income for 2009 is estimated to be $0.7 million favorable to the 2009 Budget and
$6.5 million below 2008 Actual. 2008 Actual included $8.8 million in environmental cleanup grants and lower
expenses due to fewer one-time expense projects. 2009 expenses include $2.3 million for the Terminal 30
upland dredge disposal project. 
As of September 30, 2009 total capital spending for 2009 was projected at $50.3 million or 50% of the
Approved Annual Budget amount of $100.4 million. The reduction in capital spending is the result of
deferring projects. 

A.   BUSINESS EVENTS 
TEU volumes for Seattle Harbor are down 14.2% YTD 2009 compared to YTD 2008 levels. Total YTD 2009
volume is 1,121K TEU's.
Consolidated West Coast Port results for YTD 2009 show an overall decrease in TEU volume of 17.5%
compared to the same period last year.
TEU Volume (in 000's)  YTD 2009  YTD 2008  % change
Seattle                 1,121     1,307   -14.2%
Tacoma            1,194    1,414  -15.6%
Los Angeles           4,958    5,923   -16.3%
Long Beach           3,700    4,905  -24.6%
Oakland              1,507    1,704   -11.6%
Vancouver           1,604    1,902  -15.6%
Portland                 131      187   -29.9%
Prince Rupert             180      103   75.2%
West Coast - Total:     14,395    17,444   -17.5%

9

III.     SEAPORT DIVISION PERFORMANCE REPORT 9/30/09

Grain vessels shipped 3,912K metric tons of grain through Terminal 86 YTD 2009. Amount represents a
17.8% decrease compared to YTD 2008 record volumes, partially due to temporary closures of the Terminal
86 facility in 2009 for grain spout upgrades. Though lower than 2008 volume, actual YTD volume is 10% over
2009 budgeted volume. Market expected to be strong through the remainder of 2009.
Cruise passenger for the 2009 season exceeded budget in what was projected to be a soft market for the
industry--218 vessel calls with total revenue passenger counts of 875,433 ending in October.
In connection with the 2009 Expense Savings Plan, the Seaport Division reduced 2009 Budgeted Operating
Expenses by $1.8 million.

B.   KEY INDICATORS
Container Volume  TEU's in 000's






Grain Volume  Metric Tons in 000's





Cruise Passengers in 000's





10

III.     SEAPORT DIVISION PERFORMANCE REPORT 9/30/09

Net Operating Income By Business
In $ Thousands      2008 YTD  2009 YTD   2009 YTD    2009 Bud Var  Change from 2008
Actual     Actual     Budget     $ %      $ %
Containers              27,794    29,076      25,477   3,599    14%   1,282      5%
Container Support Props        984      455       1,046    (591)   -56%    (529)    -54%
Cruise                  6,010     7,196      5,248   1,948    37%   1,186     20%
Grain                  3,700     3,397      2,819    578    21%    (303)     -8%
Docks/Industrial Props        3,279      3,708       2,579   1,129    44%     429     13%
Security                   (891)     (1,088)      (1,560)    472    30%    (197)    -22%
Envir Grants/Reserve         3,859     (3,186)      (1,263)  (1,924)   -152%   (7,045)   -183%
Total Seaport           44,734    39,557      34,345   5,211    15%   (5,177)    -12%

C.   OPERATING RESULTS  IN THOUSANDS $ 
In $ Thousands            2008 YTD    2009 Year-to-Date      2009 Bud Var     Year-End Projections
Actual     Actual    Budget     $ %     Budget  Forecast  Variance
Operating Revenue               65,789     69,903    69,833     70     0%   90,131   86,187   (3,944)
Environmental Grants               6,846       643      425     218     51%     850     850       0
Security Grants                     744       207     3,392   (3,185)    -94%    3,955    1,747    (2,208)
Total Revenue                 73,378    70,753    73,649   (2,897)    -4%  94,935   88,783   (6,152)
Direct Expenses                 13,084     16,005    21,071   5,066     24%   27,234   23,424    3,810
Security Expense                  1,406       916     4,569   3,653     80%   5,431    2,562    2,869
Environmental Reserve              2,987     3,829     1,688   (2,142)   -127%   3,375    3,829    (454)
Divisional Allocations                 1,716      1,469     1,791     322     18%    2,378    2,275      103
Corporate Allocations                9,451      8,976    10,185    1,209     12%   13,510   12,964     545
Total Expense                 28,644    31,196    39,304   8,108    21%  51,928   45,055    6,873
NOI Before Depreciation           44,734     39,557    34,345   5,211    15%   43,007   43,729     721
Depreciation                     21,497     20,279    22,856    2,578     11%   30,903   30,439     464
NOI After Depreciation             23,237     19,278    11,489   7,789     68%   12,105   13,290    1,185
NOI Excl Envir Grants/Reserve*       40,875     42,743    35,608   7,135    20%   45,532   46,708    1,176
NOTE:* NOI Excl Envir Grants/Reserve is Before Depreciation
Total Seaport revenues were ($2,897K) unfavorable to budget. Key variances are as follows:
Containers and Support Properties - unfavorable ($2,107K).
Containers ($1,776K) unfavorable. Space Rent revenue ($994K) unfavorable primarily due to later lease
commencement at Terminal 30 as a result of crane cable issue. Crane Rent and Intermodal Lift Revenue
favorable $108K due to higher usage of port owned cranes at T18 than budgeted and unanticipated activation
of T18 intermodal yard. Operating Grant Revenue ($671K) unfavorable due to lower reimbursement from
King County for Terminal 30 upland disposal of dredge materials ($425K) because the project cost less than
anticipated in the budget and due to RFID grant activities that were budgeted but are no longer expected to
take place this year ($389K).
Support Properties ($331K) unfavorable primarily due to termination of lease at Terminal 104.



11

III.     SEAPORT DIVISION PERFORMANCE REPORT 9/30/09

Cruise and Industrial Properties - favorable $2,132K.
Cruise $1,205K favorable primarily due to higher than anticipated passenger volumes including sailings
rerouted from West Coast/Mexico itineraries earlier in the year, as well as Savings Rent received in 2009 in
excess of 2008 year-end accrual.
Bulk Terminals $350K favorable due to grain volume exceeding Budget by 10%.
Dock Operations $545K favorable due to a variety of sources including prior year billing adjustment for space
leased by American Seafoods $88K, implementation of TWIC related security tariff charges $54K, and higher
than anticipated Utility Revenue $92K. Dockage, Wharfage & Berthage revenue was also favorable $93K
primarily due to higher than anticipated revenue from preferential use customers.
Industrial Properties $32K favorable due to higher than expected Carnitech percentage rent ($77K), partially
offset by lower than budgeted revenue from Northland lease due to lower actual CPI adjustment than
assumed in budget.
Security - unfavorable ($3,185K).
Security Grants unfavorable ($3,185K) due to Rounds 6 and 7 grant activities commencing later than
planned. Amount more than offset by corresponding favorable expense variance.
Expenses were $8,108K favorable to budget. Key variances:
Security favorable $3,653K primarily due to Round 6 and 7 grant activities commencing later than planned.
Amount is partially offset by corresponding unfavorable revenue variance above.
Environmental Reserve unfavorable ($2,142K) due to increase in expected cleanup costs and new obligating
events.
Outside Services favorable $4,446K largely due timing except for the lower than budgeted cost of the
Terminal 30 Upland Dredge Disposal project $1,348K, Terminal 18 maintenance dredge project $770K and
certain project items that were eliminated or reduced in the 2009 Expense Savings Contingency Plan $784K.
Miscellaneous Expense favorable $954K due to timing of recognition and classification of expense
components of T30/T91 project $525K, and Seaport Expense Contingency favorable $225K due to timing.
Vehicle Operating Expense favorable $393K due to classification of the cost of the ABC Fuel's program as a
non-operating Public Expense $375K.
Bad Debt Expense unfavorable ($557K) due to default of tenant at Terminal 104 $304K with the remaining
variance primarily due to timing.
Maintenance favorable $103K due to lower overhead allocations $197K partially offset by higher direct
charges for work on projects related to Cruise and Seaport Industrial Properties $94K.
CDD costs, direct and allocated, unfavorable ($178K) due to more staff time spent working on Seaport
projects than budgeted.
Corporate costs, direct and allocated, favorable $1,415K due to implementation of cost reductions identified
in the 2009 Revised Budget ~$378K with the remainder of the variance due to timing.
All other variances netted to a favorable $21K or less than 1% of Total Expenses Budgeted.
NOI Before Depreciation was $5,211K favorable to budget.
Depreciation was $2,578K favorable to budget due to delay in booking of assets for new Terminal 91 Cruise
facility, 2 month delay of in-service date for Terminal 30 container facility, and the later than expected timing
of granted funded security capital projects.
NOI After Depreciation was $7,789K favorable to budget.




12

III.     SEAPORT DIVISION PERFORMANCE REPORT 9/30/09

FORECAST 
As of September 2009, Seaport anticipates ending the year $721K above budget for NOI Before Depreciation
assuming that the year-end Environmental Reserve is consistent with the 2009 forecasted level. Revenue is
expected to fall below budget ($6,152K) due to implementation of Container Terminal Customer Support
Package, default of tenant at Terminal 104, lower cost and thus lower than expected reimbursement from King
County for the Terminal 30 upland dredge disposal, 2 month later commencement of the Terminal 30 lease than
budgeted and rent abatements related to the crane trench cable issue. Operating expenses are estimated to be
favorable by $6,873K due to later start of Security Grant projects, implementation of the 2009 Expense Savings
Plan $2,591K, lower than expected cost of the Terminal 18 Maintenance Dredge and Terminal 30 Upland Dredge
Disposal projects, and reversal of prior year Other Post Employment Benefits (OPEB) Medical Expense.
Favorable amounts are somewhat offset by full year unfavorable Environmental Reserve variance.
CHANGE FROM 2008 ACTUAL 
NOI Before Depreciation decreased by ($5,177K) from 2008 with the majority of the decrease being the
retroactive Environmental Grant revenue recognized in 2008 of $6,846K which exceeds the Environmental Grant
revenue received in the current year by $6,202K. NOI Excluding Environmental Grants/Reserve increased by
$1,868K due to increase in Container and Cruise revenue partially offset by higher expenses relating to
significant expense projects in 2009 such as the T30 Upland Dredge Disposal. Container revenue increase
resulted from the 2009, nine month, year-to-date impact of the increase in Eagle Rate that went into effect in July
2008 and the commencement of the T30/25 lease. Cruise revenue increase resulted from higher activity and
higher rates as compared to 2008.

D.   CAPITAL SPENDING RESULTS---IN THOUSANDS $ 
2009     2009    Variance
Estimated  Approved  EstActs to  EstActs as a  2009 Plan
SEAPORT DIVISION             Actual    Budget   Budget   % of Budget of Finance
Container Support Yard                    0    28,900     28,900        0%    28,900
Terminal 30/91 Program                28,085    35,774      7,689       79%    46,445
Terminal 10                          453     4,091      3,638       11%     4,000
Green Port Initiative                          0      2,800       2,800         0%     2,800
Terminal 115                        4,025     4,995       970       81%    5,800
All Other                             18,811     23,865      5,054        79%    38,740
Total Seaport                        51,374    100,425     49,051        51%   126,685

Comments on Key Projects: 
Through third quarter, Seaport spent 41% of the approved budget. Full year spending is estimated to be
51% of the Approved Budget.
Projects with significant changes in spending were: 
Container Support Yard  Acquisition of land for a container support yard has been delayed due to
economic conditions.
Terminal 30/91 Program  Estimated spending reduced due to favorable resolution of potential risks
at Terminal 91 facility resulting in not using authorized contingencies including amounts set aside
for potential building foundation issues.
Terminal 10  Modification of project scope has pushed out the timing of the project.
Green Port Initiative  After performing a financial evaluation, plans to develop Port owned decant
stations have been put on an indefinite hold.
nd
Terminal 115 - Commission approved funding of construction for Berth 1 on June 2 . Timing of project was
adjusted with some additional spending to take place in 2010.
Changes between the 2009 Plan of Finance and the 2009 Approved Budget represent modifications in
2009 spending estimates made after determination of 2008 actual spending.

13

IV.   REAL ESTATE DIVISION PERFORMANCE REPORT 9/30/09

FINANCIAL SUMMARY 
2008     2009     2009    Forecast/Budget
In $ Thousands              Actual    Forecast   Budget    Var $   Var %
Operating Revenue              34,875     30,709     30,961    (252)    -1%
Environmental Grants                 1       150       150       0     0%
Total Operating Revenue          34,877    30,859    31,111    (252)    -1%
Total Operating Expense          38,819    33,096    35,391    2,295     6%
NOI Before Depreciation           (3,943)    (2,236)    (4,279)   2,043    48%
NOI Excl Envir Grants/Reserve       (3,340)    (1,472)    (3,304)   2,043    62%
Capital Expenditures            21,196    100,143    105,165    5,022     5%

Total Real Estate Division revenues are virtually on budget for the year-to-date as a result of offsetting
variances within the business groups. For the full year, Real Estate is forecasting a $0.3 million unfavorable
revenue variance compared to budget due to lower occupancy at Shilshole Bay Marina and offsetting
favorable and unfavorable occupancy levels at commercial property sites.
Total Operating Expenses are $4.8 million favorable for the year-to-date primarily due to timing and deferrals
related to the 2009 Expense "Deferral" Plan. For the full year, Real Estate is forecasting a $2.3 million
favorable expense variance due to implementation of the 2009 Expense "Deferral" Plan and reversal of prior
year Other Post Employment Benefits (OPEB) medical related accruals.
Forecasted Net Operating Income for 2009 is estimated to be approximately $2.0 million favorable to the
2009 Budget and $1.7 million above 2008 Actual. 2008 Actuals included the write-off of costs associated with
the North Bay project which were partially offset by higher activity at Bell Harbor International Conference
Center and higher occupancies for leased properties. 
th
As of the September 30 update, total capital spending for 2009 was projected at $100.1 million or 95% of the
Approved Annual Budget amount of $105.2 million. The most significant project in 2009 is the Eastside Rail
Corridor. 

A.   BUSINESS EVENTS 
Occupancy levels at Commercial Properties were at 94% at quarter-end which is just slightly below the 95%
target for the 2009 Budget and above comparable statistics for the local market.
Through the 3rd quarter, moorage occupancies at Fishermen's Terminal exceeded the 2009 Budget Target.
The Maritime Industrial Center, Shilshole Bay Marina, Harbor Island Marina and Bell Harbor Marina all came
in below 2009 Budget Targets.
In connection with the 2009 Expense "Deferral" Plan, the Real Estate Division reduced 2009 Budgeted
Operating Expenses by $1.4 million, including $0.6 million in Real Estate specific expense projects budgeted
in Capital Development.





14

IV.   REAL ESTATE DIVISION PERFORMANCE REPORT 9/30/09

B. KEY INDICATORS
Shilshole Bay Marina Occupancy
120.0%
100.0%
2008 
80.0%                                                    Actual
Occupied
60.0%                                                    2009 
Budget
Footage    40.0%                                                                            2009 
Actual
20.0%
Percent Linear
0.0%
Jan  Feb  Mar  Apr May  Jun  Jul  Aug  Sep  Oct  Nov  Dec
Fishermen's Terminal Moorage Occupancy
120.0%
100.0%
2008 
80.0%                                                    Actual
Occupied    60.0%                                                                        2009 
Budget
2009 
Footage    40.0%
Actual
20.0%
Percent Linear     0.0%
Jan  Feb  Mar  Apr May  Jun  Jul  Aug  Sep  Oct  Nov  Dec
Commercial Building 
110%
98%        98%        97%        97%
100%     95% 95%      95% 95%      95% 94%      95%
90%                                           2008 Actual
Percent Occupied  80%                                                       2009 Target
2009 Actual
70%
60%
Qtr 1  2Qtr 3Qtr 4  Qtr

Net Operating Income Before Depreciation By Business through 9/30/2009
In $ Thousands      2008 YTD  2009 YTD   2009 YTD    2009 Bud Var  Change from 2008
Actual     Actual     Budget     $ %      $ %
Recreational Boating         1,629     1,879       1,246    633    51%     250     15%
Fishing & Commercial         (958)    (1,211)     (1,907)    696    36%    (252)    -26%
Commercial & Third Party      2,106     1,244      (1,282)   2,526   197%    (863)    -41%
Eastside Rail                 0       (75)       (361)    286    79%     (75)     NA
RE Development & Plan      (7,056)     (130)      (361)    230    64%   6,926    -98%
Environmental Reserve       (1,018)     (124)       (488)    363    75%    894    -88%
Total Real Estate         (5,297)     1,582      (3,152)   4,735   150%   6,880    -130%

15

IV.   REAL ESTATE DIVISION PERFORMANCE REPORT 9/30/09

C.   OPERATING RESULTS  IN THOUSAND'S $ 
2008 YTD   2009 Year-to-Date      2009 Bud Var     Year-End Projections
In $ Thousands              Actual    Actual    Budget     $ %     Budget Forecast  Variance
Operating Revenue              25,826     23,168     23,171      (3)     0%   30,961   30,709    (252)
Environmental Grants              (1,015)        0       75     (75)   -100%     150     150       0
Total Revenue                24,812    23,168    23,246     (78)    0%  31,111   30,859    (252)
Direct Expenses                 28,945     19,908     23,997    4,089    17%   31,821   30,260    1,561
Environmental Reserve              (13)      124       563     438    78%   1,125    1,125       0
Divisional Allocations                (2,494)     (2,208)     (2,652)     (444)    -17%   (3,515)   (3,399)     (116)
Corporate Allocations               3,671      3,762      4,491     729     16%    5,960    5,110     850
Total Expense                30,109    21,586    26,399    4,813    18%  35,391   33,096    2,295
NOI Before Depreciation           (5,297)     1,582     (3,152)   4,735    150%   (4,279)   (2,236)   2,043
Depreciation                    7,518      7,417      7,896     478     6%   10,528    9,890     638
NOI After Depreciation           (12,815)     (5,835)    (11,048)    5,213    47%  (14,807)  (12,126)    1,405
NOI Excl Envir Grants/Reserve*      (4,296)     1,707     (2,665)   4,371    164%   (3,304)   (1,261)   2,043
NOTE:* NOI Excl Envir Grants/Reserve is Before Depreciation
Total Real Estate revenues were ($78K) unfavorable to budget. Key variances are as follows: 
Harbor Services: unfavorable ($165K) 
Recreational Boating unfavorable ($164K) primarily due to higher than budgeted vacancy at SBM.
Fishing and Commercial was in line with budget.
Portfolio Management: favorable $110K 
Commercial Properties unfavorable ($62K) due to tenants vacating their premises at Pier 2 and
Tsubota, lower than anticipated concession rent at Pier 66 Bell Street and lower than budgeted utility
revenue from the Maritime Industrial Center. Unfavorable variances were partially offset by above
budget occupancy at T-102. 
Third Party Managed Properties favorable $171K due to higher than anticipated activity at Bell
Harbor International Conference Center $351K partially offset by lower transient and monthly parking
revenue at the Bell Street Garage ($58K) and by fewer memberships and lower activity at the World
Trade Center Club ($127K).
Eastside Rail Corridor: unfavorable ($138K) 
Eastside Rail Corridor unfavorable ($138K) due to revenue expectations in the 2009 Budget based
on the assumption of acquiring the property prior to 2009.
RE Development and Planning: favorable $188K 
Terminal 91 General Industrial favorable $188K due to two tenants not anticipated to remain at T91
in the budget that have continued to occupy on a month to month basis $205K. The positive variance
is partially offset by lower than anticipated utility revenue.
Environmental Grants: unfavorable ($75K) 
No environmental grant revenue related to Real Estate Division properties thus far in 2009.




16

IV.   REAL ESTATE DIVISION PERFORMANCE REPORT 9/30/09

Expenses were $4,813K favorable to budget. Key variances:
Environmental Reserve favorable $438K due to lower cleanup costs than assumed in Budget.
Third Party Management Expense favorable $666K due to cost savings at Bell Harbor International
Conference Center and due to cost savings and lower activity at the World Trade Center Club.
Outside Services (excluding Maintenance, Corporate and Capital Development) favorable $1,405K due to
delay in closing Eastside Rail Corridor $300K and due to timing including charges from Environmental
Services, broker fees and tenant improvement expenses budgeted for the World Trade Center West Building.
Maintenance expenses favorable $713K primarily due to timing, more work charged to capital than budgeted
and the deferral of some work in connection with the 2009 Expense "Deferral" Plan.
Corporate and Capital Development costs direct and allocated favorable $1,633K primarily due to the
cancellation/deferral of projects in connection with the 2009 Expense "Deferral" Plan $1,127K and timing.
All other variances netted to an unfavorable ($42K) or less than 1% of Total Expenses Budgeted.
NOI BEFORE DEPRECIATION was $4,735K favorable to Budget.
Depreciation was $478K favorable primarily due to overstatement of Harbor Service's Depreciation in the
Budget.
NOI AFTER DEPRECIATION was $5,213K favorable to Budget.
FORECAST 
Real Estate anticipates ending the year $2,043K above budget for NOI Before Depreciation assuming that the
year-end environmental reserve adjustments are consistent with budget. Revenue is expected to come in below
Budget by ($252K) primarily due to lower occupancies at Shilshole Bay Marina. Operating expenses are
estimated to be favorable by $2,295K primarily due implementation of the 2009 Expense "Deferral" Plan and
reversal of prior year Other Post Employment Benefits (OPEB) medical accruals. NOI After Depreciation is
currently estimated to end the year $1,405K favorable to budget. NOI Excluding Environmental Grants and
Reserve, is expected to come in at $2,043K favorable to budget.
CHANGE FROM 2008 ACTUAL 
Net Operating Income Before Depreciation increased by $6,880K between September year-to-date 2008 and
2009. Operating Revenue decreased by $2,658K due to lower activity at Bell Harbor International Conference
Center and the Bell Street Garage, partially offset by higher revenues at Shilshole Bay Marina due to construction
completion. Environmental Grant Revenue was reported at a negative amount of ($1,015K) in 2008 due to an
accrual error. Expenses decreased by $8,523K in 2009 primarily due to the expensing in 2008 of capitalized
costs associated with the North Bay development project $7,224K, less activity at Bell Harbor International
Conference Center and the 2009 Expense "Deferral" Plan. These favorable variances were partially offset by
higher expenses at Shilshole Bay Marina related to higher occupancy.








17

IV.   REAL ESTATE DIVISION PERFORMANCE REPORT 9/30/09

D.   CAPITAL SPENDING RESULTS---IN THOUSANDS $ 
2009     2009    Variance
Estimated   Approved  EstActs to  EstActs as a 2009 Plan of
REAL ESTATE DIVISION       Actual   Budget   Budget  % of Budget  Finance
Eastside Rail Corridor                   96,302     96,302         0       100%    106,955
Small Projects                         778      1,753       975        44%     1,665
RE Division Green Initiative                   0      1,000      1,000         0%      1,000
Pier 69 North Apron Piling Cathodic            25      1,000       975         3%      1,060
Tenant Improvements - Capital              346       900       554       38%       800
All Other                             2,692      4,210      1,518        64%      4,809
Total Real Estate                     100,143    105,165      5,022        95%    116,289

Comments on Key Projects: 
Through third quarter, the Real Estate Division spent 1% of the approved budget. Full year spending is estimated
to be 95% of the Approved Budget.
Projects with significant changes in spending were: 
Eastside Rail Corridor  No change in estimated spending, but acquisition deadline deferred to 12/15/09.
Small Projects  Workload issues due to insufficient staffing have pushed the start of some projects into
later in 2009 with completion in 2010 or entirely into 2010.
Green Port Initiative  Construction of a stormwater improvement project now expected to take place in
2010.
Pier 69 North Apron Piling Cathodic System  Project pushed back until 2010.
Tenant Improvements Capital  Projects pushed back until 2010.
Changes between the 2009 Plan of Finance and the 2009 Approved Budget represent modifications in 2009
spending estimates made after determination of 2008 actual spending.











18

V.   CAPITAL DEVELOPMENT DIVISION PERFORMANCE REPORT 9/30/09

A.   BUSINESS EVENTS 
Mowat was the low bidder at 2.44% below the engineer's estimate for the East Marginal Way Grade
Separation (EMWGS) Project.
T115  Received Berth 1 permits.
Construction awarded to Pacific Pile and Marine.
Steel piling bids were approximately 10% below the engineer's estimate.
T-30 Apron Upgrade SSA commenced container operation on August 3, 2009 - first vessel call on
August 9, 2009.
Returned $23M in AV CIP project savings.
Runway 16L was reopened ahead of schedule and under budget after complete rebuilding.
Working with OSR in development of the small business program

B.   KEY INDICATORS 
rd
Cost Growth on Major Construction for projects completed in 3 Quarter (RE Completion memos issued).
PROJECT                  NON-     DISCRETIONARY
DISCRETIONARY    CHANGE 
CHANGE 
3RD RUNWAY 2007-08 CONSTRUCTION                 1.6%        2.6%
T-86 GRAIN SPOUT REPLACEMENTS                  3.7%        0%
T-91 BUILDING W-40 PARTIAL DEMOLITION PROJECT           1.3%         0%
T-18 CRANE 36 DEMOLITION                      3.0%         0%
STAGE 1 MECHANICAL ENERGY CONSERVATION PROJECT        1.2%       -0.7%
MAIN TERMINAL ROOF REPLACEMENT                 1.5%        0%
T-91 CRUISE SHIP TERMINAL                      10.3%        2.9%
EMWGS SR 99 COLUMN RELOCATION                0%      - 83.2%
EMWGS COLUMN RELOCATION  WATERLINE            32.7%       - 1.4%
C-1 100% BAGGAGE SCREENING                   7.8%       38.2%
SOUTH CRUISE INPUT PROJECT                    9.9%        0%
New Construction Management Standard Operation Procedure (SOP) on Field Directives being
developed. Review of revised Submittal SOP and new SOP #41 on Project Closeout.
rd
New Service Agreements in the 3 Quarter are:

CONTRACT        CONTRACT   DOLLAR         CATEGORY 
NUMBER    AMOUNT 
NAVIGANT CONSULTING       P-00316114  $186,000   CONSTRUCTION AUDITING FOR RCF 
PROJECT 
APPLIED PROFESSIONAL SERVICES  S-00316202  $100,000  UTILITY LOCATING SERVICE 

Small Business Participation:
PCS made WBE payments of 11%, SBE payments of 11.3%, MBE payments of 1.2 % and DBE
payments of 0.2% for a total 23.7% in Small Business Participation at the end of the third Quarter.
Goal: 30% PCS Small Business Participation.


19

V.   CAPITAL DEVELOPMENT DIVISION PERFORMANCE REPORT 9/30/09

C.   OPERATING RESULTS  IN THOUSANDS $
2008 YTD    2009 YTD     2009 Bud Var.      Year-End Projections
In $ Thousands         Actual  Actual  Budget    $ %  Budget Revised Forecast  Var.
Aviation Project Management Group     597   419   572   152  26.6%   761   721   759     2
Port Construction Services          2,854  1,094  1,059    (35)  -3.3%  1,449  1,431  1,384    65
Engineering                    906   724   973   250  25.6%  1,351  1,298  1,401    (50)
Seaport Project Management Group     560   542  1,096   554  50.5%  1,400   845   917   483
Central Procurement Office           916  1,179  1,110    (70)  -6.3%  1,494  1,636  1,664   (170)
Capital Development Division Admin.      34    249   421   172  40.9%   554    294   276   278
Total CDD          5,868  4,207  5,231  1,024  19.6%  7,010  6,226  6,401   609
The total YTD budget variance is $1,024K and the year-end variance forecast is $609K.
PCS negative variance due to less capital and more expense work/expense project overhead than
budgeted, plus the absorption of the full rent at Kilroy after CPO/Construction Services moved to
Logistics.
CPO negative variance due to FTE expense budgeted in another org but charged to CPO.
Positive variances throughout the division are primarily through unfilled positions, implementation of
Revised Budget features (i.e., furloughs, reduced travel, etc.), delayed or reduced purchase of equipment
and supplies.
Positive variances throughout the division are partially reduced (but not totally offset) by less capital work
than budgeted, resulting in increased Salary & Budget, Expense Project Overhead and reduced transfer
to Capital.













20

VI.   CORPORATE PROF. & TECHNICAL SERVICES PERFORMANCE REPORT 9/30/09

A.   BUSINESS EVENTS 
Planned and managed a media event to celebrate the inaugural flight of Icelandair.
Planned and managed a media event to celebrate the re-start of the Rental Car Facility.
Planned and managed multiple media events to celebrate the opening of 16L/34R runway.
In partnership with Human Resources, health care premium sharing and wellness rewards have been
established for 2010.
The Port's new LMS (Learning Management System) has been selected as the "Best Launch to an
Organization" at the Plateau annual conference.
ICT delivered numerous projects that improved operations, cost effectiveness, and employee productivity.
This included Infrastructure enhancements and upgrades needed to increase availability and reliability,
and to support continued rapid growth in demand. 
Finance and Budget began implementation of new banking platform. 
Implemented the Concur expense system "Cognos", a new and enhanced reporting tool, associated with
AFR's implementation late last year of Bank of America's new Concur expense reporting and
reimbursement system, a Port-wide web-based online travel, corporate credit card and expense
reimbursement system, which replaced the EAGLS system. 

B.   KEY INDICATORS
Program/Raptor Relocation program and our response to the US Airways bird strike garnered a second
place award from ACI-NA in the Public Relations Campaign category.
Received extensive local, regional, national, and international coverage of our Avian Radar/Wildlife
Management.
Port's first exclusively online Annual Report has received nearly 1,000 views from 16 different countries.
Port's public Web site visits at 2.67 million over the past year, up 20.67 percent over previous period
More than 200 attended the first three Port 101 series events: Airport, Duwamish River and Cruise.
Managed 20 delegation visits and tours at Seaport and P69.
Occupational injury rate decreased slightly from 5.89 in the third quarter of 2008 to 5.48 in the second
quarter of 2009. Injury cost per worker hour has also decreased from $1.13 in 2008 to $1.08 in 2009.
98% employee completion rate of the health assessment.
Opened 117 employment requisitions and processed 4,365 applications.
Approximately 48 individual job evaluations have been finalized as of 9/30/09.
ICT continued virtualization and data center consolidation strategies have offset over $2 million in new
hardware and hardware refresh costs to date.
Investment portfolio successfully managed within policy limitations.
Completed and presented the following audits to the Audit Committee in the third quarter.
o Police Department
o Fireworks Concession
o Aviation Security
o Aviation Acquisition & Relocation
o Hertz, Avis and Budget Rental Cars
East Marginal Way: Phase 1 - advertised and received bids; Phase 2 - secured FMSIB listing for $3.5M
and continued project definition with WSDOT and partners.
Police Department Indicators:
January  Sept.    CFS's (Calls for Service)  47,42
4
January  Sept    Arrests  No Warrant     441
January  Sept    Arrests  Warrant       626


21

VI.   CORPORATE PROF. & TECHNICAL SERVICES PERFORMANCE REPORT 9/30/09

C.   OPERATING RESULTS-- NET OPERATING EXPENSE (in THOUSANDS $) [REPORTED BY ORG] 
2008 YTD    2009 YTD   2009 Bud Var.     Year-End Projections
In $ Thousands                     Actual   Actual Budget     $ %  Budget Revised Forecast  Var.
Total Revenues                      840    986   1,129   (144) -12.7%   1,470   1,470   1,417   (53)
Executive                          1,250   1,056   1,173   117  10.0%   1,540   1,449   1,449   92
Commission                      704    608    675   67   9.9%   867   844   844   22
Legal                            1,992   1,904   2,039   135   6.6%   2,703   2,638   2,720   (16)
Risk Services                        2,110   1,913   2,150   237  11.0%   2,861   2,838   2,778   84
Health & Safety Services                   761    715     744    29   3.9%    985    947    927    58
Public Affairs                           2,915   2,393    3,304    911   27.6%   4,270   3,565   3,565   705
External Affairs                          808     905    1,021    116   11.4%   1,347   1,249   1,249    98
Economic & Trade Development           1,006   1,002   1,584   581  36.7%  2,099   1,638   1,638  462
Human Resources & Development          2,969   2,668   3,164   496  15.7%  4,165  3,926   3,766  398
Labor Relations                        500    458    541    83  15.4%    731    689    663   69
Information & Communications Technology     9,423  12,538  14,793  2,255  15.2%  19,658  18,404  18,404  1,253
Finance & Budget                    1,197   1,102   1,296   194  15.0%   1,719   1,645   1,482   236
Accounting & Financial Reporting Services      4,325   4,441   4,882   440   9.0%   6,541   6,352   6,286   255
Internal Audit                            502     758     895    137   15.3%   1,211   1,164   1,090   121
Office of Social Responsibility                606   1,062    1,271    209   16.5%   1,647   1,401   1,387   259
Regional Transportation                  280    315    374    59  15.8%    498    461    463   36
Police                             13,981  13,055   15,100  2,045  13.5%  19,979  18,379  18,371  1,607
Industrial Development Corporation            10     10 -     (10)   0.0%    - - 10   (10)
Contingency                      2,784    396    563   166  29.6%   750    750    750 -
Total Expenses                     48,126  47,299  55,568  8,269  14.9%  73,572  68,338  67,842  5,730

Corporate Professional and Technical Services performance for the first nine months of 2009 was $8.3 million
or 14.9% favorable compared to the approved budget and $827 thousand or 1.7% lower than the same period a
year ago. The $8.3 million favorable variance is due primarily to timing of spending and to the implementation of
the 2009 Expense Savings Plan. There aren't any major variances to report on since all departments are
favorable. However, the unfavorable variance of $10 thousand in Industrial Development Corporation is due to
charges incurred for the IDC/ET Fellowship Program. Year-end spending is projected to be $67.8 million, which
is $5.7 million below the approved budget.

D.   CAPITAL SPENDING RESULTS 
($ Millions)
Annual Results:
2009 Plan of Finance                  $ 12.8
2009 Approved Budget                $ 15.9
2009 Estimated/Actuals                $ 11.3
Variance (Budget vs Estimated/Actuals)       $ 4.6





22

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.