Item 5b Memo

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      5b 
Date of Meeting   November 3, 2009 
DATE:    October 22, 2009 
TO:      Tay Yoshitani, Chief Executive Officer 
FROM:    Ralph Graves, Managing Director, Capital Development Division 
SUBJECT:  Change Order #005 for the Duwamish Trail Link  West Marginal Way SW et al 
Project, Contract MC-0315437 
ACTION REQUESTED:
Requests authorization for the Chief Executive Officer to execute Change Order Number 005 for
the Duwamish Trail Link  West Marginal Way SW et al Project to add the additional time
required (196 days) to complete the project. 
SYNOPSIS:
This project constructed approximately 1030' of new trail for pedestrian and bicyclist use along
West Marginal Way in West Seattle. During the original period of performance, BNSF changed
the requirements for Railroad Protective Liability Insurance. The portions of the work that were
within the BNSF right-of-way could not proceed until the new insurance requirements were met
by the Contractor. Work was suspended until the contractor could comply. We are requesting
CO #005 be issued for an additional 196 days needed to complete the project. This is a no-cost
change order. 

CHANGE ORDER DESCRIPTION AND JUSTIFICATION: 
The following information relates to the pending change order scope and cost: 
Change Order No. 005 
Scope of work: The original contract completion date is 10/31/08. CO #005 will add an
additional 196 calendar days to the contract duration due to the suspension of work.
Justification: Although the Contract included provisions requiring the contractor to
procure Railroad Protective Liability insurance for the portions of the work that impinged
on the BNSF right-of-way, this insurance requirement was increased by the Railroad part
way through the contract work. The delay created by this additional insurance
requirement was exacerbated by the requirement that all the contractor's employees
undergo railroad safety training prolonging the duration of the suspension. The direct
costs with the additional insurance and additional required training were covered by CO
#004 issued previously for a total cost of $5000. CO #005 accounts for the time

COMMISSION AGENDA 
T. Yoshitani, Chief Executive Officer 
October 14, 2009 
Page 2 of 2 

associated with this change. The contractor has not asked for any further compensation
regarding this issue. 
Consequences of not proceeding: The contractor would be responsible for liquidated
damages due to no fault of their own and make claim for delays. 
FINANCIAL ANALYSIS:  This is a no-cost change order. 
CONTRACT INFORMATION:  The following information relates to the contract and
competitive award: 
Contract award date:                             June 06, 2008 
Original period of performance:                         147 Days 
Previous contract extensions:                             0 Days 
Current Contract Completion Date:                 October 31, 2008 
Contract extension this change order:                      196 Days 
Revised Contract Completion Date:                   May 15, 2009 
Original contract amount:                          $263,865.85 
Previous Change Order Nos. 001  004:                 ($9,500.00) 
Current contract amount                           $254,365.85 
This request, Change Order No. 005                        $0.00 
Revised contract amount:                          $254,365.85

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.