Item 9a Supp3

Item No.: ________9a_Supp_3_______
Date of Meeting: __Oct. 20, 2009______

Real Estate Division
2010 Capital Budget
(Impact of $67 million flat levy amount 2010-2014)

October 20, 2009

1

Real Estate 2010 Capital Budget
Impact of Flat Levy Amount 2010-2014
Real Estate 2010 Capital Budget presented at October
6th Budget Workshop
To show impact of $67 million flat levy amount, Capital
Budget amounts shown by year for 2010-2014 in this
presentation
Projects and amounts are unchanged
Categorization of projects are unchanged
Impact of the 5 year $67 million flat levy amount
shown in final slide

2

Real Estate Capital Plan Summary
$'s in 000's             2010     2011    2012    2013    2014   2010-2014
Committed         15,346  16,300   5,156  1,725   1,781   40,308
Bus Plan Prospective    5,620  12,000  16,505  18,200   9,000   61,325
20,966  28,300  21,661  19,925   10,781   101,633
Other Prospective         0   1,250   4,021   5,135   20,275   30,681
Total               20,966  29,550  25,682  25,060   31,056   132,314



3

Real Estate Committed Capital Plan

$'s in 000's             2010     2011    2012    2013    2014   2010-2014
Under Contract         122     0     0     0      0     122
Commission Auth      1,075   5,861     0     0     0    6,936
Division Pending      14,149  10,439   5,156   1,725   1,781   33,250
Total               15,346  16,300   5,156   1,725   1,781   40,308




4

Real Estate Committed Capital
Under Contract
$'s in 000's                  2010     2011    2012    2013    2014   2010-2014
SBM Infrastru,Bldgs, Site Imp       62      0      0      0      0      62
SBM Landside Projects          60      0      0     0      0      60
Total                     122      0      0      0      0     122




5

Real Estate Committed Capital
Commission Authorized
$'s in 000's                  2010     2011    2012    2013    2014   2010-2014
FT East Portion S. Wall (FVO)      675   4,150      0      0      0    4,825
MIC Seawall Replacement        400   1,711      0     0      0    2,111
Total                    1,075   5,861      0      0      0    6,936




6

Real Estate Committed Capital
Division Pending
$'s in 000's                     2010     2011    2012    2013    2014   2010-2014
RE Maintenance Shop Solution       3,300    300      0     0      0    3,600
RE Div: Green Port Initiative         2,600   2,000   2,500      0      0    7,100
FT NW Dock E Fender Sys Replace   2,000   2,000     0     0      0    4,000
Small Projects                  1,810    540     500    500     500    3,850
Tenant Improvements -Capital        1,220    224    856    125     181    2,606
Fleet Replacement               950    600    600    600     600    3,350
FT C15 HVAC Improvements         800   3,050     0     0      0    3,850
P69 N Apron Piling Cathodic          560    800    200      0      0    1,560
Other                       909    925    500    500     500    3,334
Total                      14,149  10,439   5,156   1,725   1,781   33,250



7

Real Estate Capital
Business Plan Prospective

$'s in 000's            2010     2011    2012    2013    2014   2010-2014
Renewal/Enhancement     5,620  10,300  11,505  12,200   5,000   44,625
Revenue/Capacity Growth      0   1,700   5,000   6,000   4,000   16,700
Total                5,620  12,000   16,505  18,200   9,000   61,325




8

Real Estate Business Plan Prospective
Revenue/Capacity Growth

$'s in 000's                   2010     2011    2012    2013    2014   2010-2014
T91 - NorthBay Utilities              0    1,500    3,000    6,000    4,000    14,500
Ship Supply Demo & Redevelop       0    200   2,000      0      0    2,200
Total                       0   1,700   5,000   6,000   4,000   16,700




9

Real Estate Business Plan Prospective
Renewal/Enhancement
$'s in 000's                    2010     2011    2012    2013    2014   2010-2014
Net Shed Solution              2,100   4,650    4,950   4,900      0    16,600
RE: Contingency Renew & Replace   1,000   1,000   4,000   4,000   5,000   15,000
FT Paving/Storm Upgrades          750    750      0      0      0    1,500
FT C2 Roof & HVAC Replacement     700     0      0     0     0     700
Pier 86 Fishing Dock              500   1,500      55      0      0    2,055
P66 Chiller Upgrades              270      0      0      0      0      270
SBM Paving                 150    450    400     0     0    1,000
SBM Slope Stabilization            100    900      0      0      0    1,000
P69 Built-Up Roof Replacement        50    850      0      0      0     900
FT C14 (Downey) Bldg TI             0      0      0   2,000      0    2,000
SBM Fuel Dock                0    200   1,000     0     0    1,200
T102 Bldg Roof Replacement          0      0   1,100      0      0    1,100
SBM Central Seawall Replacement      0      0      0   1,000      0    1,000
Repl. Anthony's Built Up Roof          0      0       0     300      0      300
Total                      5,620  10,300   11,505  12,200   5,000   44,625
10

Real Estate Capital Budget
Impact of $67 million Flat Levy Amount 2010-2014

Impact to Real Estate Capital Budget is need to defer $19 million
of 2010-2014 projects until 2015-2019
Projects most likely to be deferred are Business Plan Prospective
Renewal & Replacement projects and are highlighted in
following slide:


11

Real Estate Business Plan Prospective
Defer $19 Million Renewal/Enhancement
Projects until 2015
$'s in 000's                     2010     2011    2012    2013    2014   2010-2014
Net Shed Solution               2,100   4,650    4,950   4,900      0    16,600
RE:Contingency Renew & Replace*    1,000   1,000   4,000   4,000   5,000   15,000
FT Paving/Storm Upgrades           750    750      0      0      0    1,500
FT C2 Roof & HVAC Replacement      700     0      0     0     0     700
Pier 86 Fishing Dock               500   1,500      55      0      0    2,055
P66 Chiller Upgrades               270      0      0      0      0      270
SBM Paving                  150    450    400     0     0    1,000
SBM Slope Stabilization             100    900      0      0      0    1,000
P69 Built-Up Roof Replacement         50    850      0      0      0     900
FT C14 (Downey) Bldg TI              0      0      0   2,000      0    2,000
SBM Fuel Dock                 0    200   1,000     0     0    1,200
T102 Bldg Roof Replacement           0      0   1,100      0      0    1,100
SBM Central Seawall Replacement       0      0      0   1,000      0    1,000
Repl. Anthony's Built Up Roof           0      0       0     300      0      300
Total                       5,620  10,300   11,505  12,200   5,000   44,625
12
Note*: $3 million of 2012 Contingency Renewal & Replace must be deferred

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.