Item 5a Memo

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      5a 
Date of Meeting    October 6, 2009 
DATE:    September 28, 2009 
TO:      Tay Yoshitani, Chief Executive Officer 
FROM:    Ralph Graves, Managing Director, Capital Development 
SUBJECT:  Change Order No. 0102 for the Consolidated Rental Car Facility Project Contract
MC-0315405 
ACTION REQUESTED:
Request authorization for the Chief Executive Officer to issue Change Order No. 0102 for the
Consolidated Rental Car Facility (RCF) in the amount of $302,885. 
SYNOPSIS:
This change order is required to: 1) enlarge several building foundations for the RCF building 
and the North Helix foundation, and 2) to revise the electrical equipment pads for the RCF
project. 
The original footing design was based on soil with a bearing pressure of 12,000 pounds per
square foot (psf). Once the site was cleared and additional access was made available to the
Geotechnical Engineer further investigation was performed on the site. This investigation
revealed that there were areas where the maximum bearing pressure of the soil reached only
2,000 psf. In these areas the structural footings had to be resized significantly to accommodate
the load of the structure. In some cases, the footings are now four times larger in size than
originally anticipated (i.e.: 14'x14 original to 25'x25' revised). 
The Port purchased the electrical equipment as part of the owner furnished materials for the RCF
project. As is standard practice due to the variability in various manufacturers' equipment, the
original design for the electrical equipment pads as bid by the subcontractor were based on the
general size and loading of estimated equipment. After the Port purchase was completed and the
actual equipment to be supplied was known, the electrical equipment pads had to be modified to
accommodate the actual size, weight and anchorage requirements.
CHANGE ORDER DESCRIPTION AND JUSTIFICATION: 
The following information relates to the pending change order scope and cost: 
Change Order No. 0102

COMMISSION AGENDA 
T. Yoshitani, Chief Executive Officer 
October 1, 2009September 28, 2009 
Page 2 of 2 

Scope of work: 1) Increase the size of the 8 footings between gridlines M through R/23
through 26 at the RCF and extend the footings at the North Helix to provide additional
structural support where the Helix ties into the RCF. 2) Modify the electrical equipment
pads to fit with the Owner Furnished Electrical Equipment.
Justification: 1) The bearing pressure of the existing soils under slabs and footings was
not adequate to transfer building loads. 2) The electrical pads for the owner supplied
equipment must adequately support the selected equipment.
Consequences of not proceeding: 1) The footings would not provide the required
structural support. 2) The electrical equipment would not be adequately supported on
required equipments pads. 

FINANCIAL ANALYSIS: 
Funds to pay for this change order are part of the project contingency funds that were included in
previously approved authorizations of $419,306,000.00. No additional project funds are bein g
requested as a result of this change order. 

CONTRACT INFORMATION: 
The following information relates to the contract and competitive award: 

Contract award date:                             May 30, 2008 
Original period of performance:           May 30, 2008 to April 1, 2011 
Previous contract extensions:                             0 Days 
Contract extension this change order:                        0 Days 
Current Contract Completion Date:                    April 1, 2011 
Original contract amount:                       $224,837,739.00 
Previous Change Order Nos. 001  101:                $4,405,835.00 
Current contract amount                         $229,243,574.00 
This request, Change Order No. 0102                   $302,885.00 
Revised contract amount:                       $229,546,459.00

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.