Item 5d Memo
PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 5d Date of Meeting August 11, 2009 DATE: August 3, 2009 TO: Tay Yoshitani, Chief Executive Officer FROM: Ralph Graves, Managing Director, Capital Development Division SUBJECT: Change Order #010 for the North and South Satellites Food Courts Flooring Replacement Project Contract MC-0315494 ACTION REQUESTED: Requests authorization for the Chief Executive Officer to issue Change Order Number 010 for the North and South Satellites Food Courts Flooring Replacement Project to add the additional time required (61 days) to complete the project. SYNOPSIS: During demolition of the existing floor and installation of the new finishes, the contractor encountered multiple obstacles and Change Order (CO) #009 was executed. It was understood at the time that the total time impact could not be determined completely and that a second change order would be necessary to reconcile the remaining days. We are requesting CO #010 be issued for an additional 61 days needed to complete the project. This is a no-cost change order. CHANGE ORDER DESCRIPTION AND JUSTIFICATION: The following information relates to the pending change order scope and cost: Change Order No. 010 Scope of work: The original contract completion date is 04/06/09. CO #009 added 60 calendar days for a new completion date of 06/05/09. CO #010 will add an additional 61- calendar days for the completion of the column cover work. Justification: The contractor encountered multiple obstacles in the demolition of the existing floor. This included pitted substrates with Asbestos Containing Material (ACM) embedded in the pits; unanticipated ACM material was found in the expansion joints; an improperly repaired structural floor dating back to the last remodel of the area; and revised phasing brought about by tenant concessionaire requests. There were concurrent delays by both the Port and contractor which prolonged the completion of the project and as a result 60 calendar days (28 non-compensable and 32 compensable) were awarded. These impacts were analyzed and settled in the execution of Change Order #009. Additionally, new stainless steel column wraps for the food court area are to be installed COMMISSION AGENDA T. Yoshitani, Chief Executive Officer August 3, 2009 Page 2 of 2 as part of this project. It was suggested by both the Designer of Record and the contractor that a more superior finish would be achieved if the fabrication of the column covers began after the finish floor height was established with the completion of the flooring operations. The contractor agreed that this activity could be done at a later time with no additional cost to the project; however additional days would be needed to extend the contract date so that the fabrication of the column covers could wait until after the finish floor was completed. It was determined that an additional 61 calendar days would be required to complete this work. We are requesting Change Order Number 010 be issued for these remaining days. Consequences of not proceeding: While the column covers could have been manufactured prior to the installation of the finished floor, the best results would be achieved with this method. FINANCIAL ANALYSIS: This is a no-cost change order. CONTRACT INFORMATION: The following information relates to the contract and competitive award: Contract award date: August 07, 2008 Original period of performance: August 07, 2008 to April 06, 2009 Previous contract extensions: 60 Days Current Contract Completion Date: June 5, 2009 Contract extension this change order: 61 Days Revised Contract Completion Date: August 05, 2009 Original contract amount: $918,000.00 Previous Change Order Nos. 001 009: $193,950.00 Current contract amount $1,111,950.00 This request, Change Order No. 010 $0.00 Revised contract amount: $1,111,950.00
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.