Item 6a Memo

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA               Item No.     6a 
Date of Meeting   August 11, 2009 
DATE:    July 27, 2009 
TO:      Tay Yoshitani, Chief Executive Officer 
FROM:    Melinda Miller, Director, Portfolio Management 
Tim Leonard, Capital Project Manager 
SUBJECT:  The completion of the South Wall reconstruction at Fishermen's Terminal 
(CIP 800136) 
ACTION REQUESTED 
Authorization for the Chief Executive Officer to proceed with permitting, design, and project
management to be performed for the completion of the South Wall reconstruction at Fishermen's
Terminal (FT) in the amount of $980,000.
SYNOPSIS 
The Real Estate Division requests approval for permitting, design, and project management 
funding in the amount of $980,000 for the reconstruction of the final remaining section of the
original South Wall seawall at FT which has exceeded its service life and is at risk of structural
failure. The design, permitting, and project management will be performed by Port staff with the
exception of geotechnical and diving services which are estimated to cost approximately
$100,000. All design and permitting costs will be paid out of the $5,000,000 budgeted in the
2009 Draft Plan of Finance for this project under CIP C800136. Commission authorization for
construction funding will be sought upon completion of the engineering design and final
construction estimate. 
BACKGROUND 
The South Wall at Fishermen's Terminal (FT) was originally constructed in 1914 and currently
separates the facility's southern uplands from the harbor. A structural condition survey and
evaluation of FT, performed in 1999 by Reid Middleton engineers, determined that the
submerged timber relieving platform component had exceeded its service life and was at risk of
structural failure. This finding was primarily based on the severe dilapidation that has occurred
in the connectors holding the relieving platform together and the increased loads being placed
upon it by subsequent overlying wharf construction as well as the facility's current operations. 
The majority of the South Wall was reconstructed in 2003-2005 as a major works capital
improvement project. The only portion of the original timber relieving platform still remaining
is approximately 160 feet in length and located at the east end of the bulkhead that fronts the
parcel currently leased by Fishing Vessel Owners (FVO). Replacement of this section of the
seawall has been delayed due to various factors: The unavoidable disruption to FVO's business

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 27, 2009 
Page 2 of 4 
operations during construction, and the formerly planned monorail expansion through this area
that would have required additional reconstruction of the seawall. 

PROJECT DESCRIPTION AND JUSTIFICATION 
Project Description: 
Reconstruction of approximately 160 lineal feet of the east end of the South Wall seawall at FT.
Project Justification: 
This is a safety issue. The completion of the South Wall reconstruction is needed as the existing
underlying timber relieving platform is in poor condition due to severely dilapidated connectors. 
Consequently, this seawall section and the affected adjacent pavement area and marine rail
system are at risk of structural failure. Such a failure could also potentially result in significant
environmental impacts by disturbing possibly contaminated soils and thereby adversely affecting
the harbor's water quality. 
PROJECT SCOPE OF WORK AND SCHEDULE 
Project Scope: 
The proposed South Wall reconstruction scope is anticipated to closely follow that already
employed in the previous phases that were completed at FT in 2003-2005. In general, the
reconstruction will involve removal of the existing submerged timber relieving platform and
overlying fill material, and the subsequent installation of a new steel sheet pile bulkhead;
concrete deck panels and supporting piles; timber fender system; and overlying asphalt concrete
pavement. An additional scope element in this project will be the temporary disassembly and
retention of the existing in-place marine rail system and associated site infrastructure that FVO
currently utilizes to pull vessels out of the water in order to work on them. Details regarding this
will be finalized as part of the project engineering design. 
Project Schedule: 
Design and permitting to be completed by summer 2010. In -water construction to be completed
by April 15, 2011 - the end of the freshwater fish window. All construction is anticipated to be
completed by summer 2011. 
STRATEGIC OBJECTIVES 
This work, if authorized, is aligned with the Industrial Moorage Initiative as it is intended to
preserve and expand berth facilities to provide for a vibrant seaport that adequately serves the
requirements of all essential sectors of the maritime community. 
Best management practices will be deployed in selection of materials, work practices and
ongoing total cost of ownership.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 27, 2009 
Page 3 of 4 
BUSINESS PLAN OBJECTIVES 
This project is aligned with the business plan objectives to maintain safe facilities and assets and
provide customers with compelling value. It is a renewal and replacement project to rebuild the 
infrastructure (seawall) which is needed to continue to provide moorage & loading/unloading
capacity to commercial fishing vessels, commercial workboats and vessel repair businesses at the
FT. 
FINANCIAL ANALYSIS 
Previous Authorizations (Planning CIP)                          $ 50,000 
Current request for authorization                                $ 980,00
Total Authorizations, including this request                        $ 1,030,00 
Remaining estimated budget to be authorized (Construction)           $ 5,070,000 
Total Estimated Project Cost                                $ 6,200,000 
Current Authorization Cost Breakdown 
Design                                            $ 690,000 
Project Management                                   $ 200,000 
Permitting                                              $ 140,000 
Total                                                 $ 1,030,000 
Source of Funds: 
The FT South Wall Reconstruction project was included in the 2010 Draft Plan of Finance as a
committed project in the amount of $5,000,000 under CIP C800136. The project will be funded
from the tax levy. The addition $1,200,000 required to complete this project is available due to
anticipated timing delays in other 2009 Draft Plan of Finance committed projects.
Financial Analysis Summary 
CIP Category         Renewal/Enhancement 
Project Type          Renewal and Replacement 
Risk adjusted Discount   10.00% 
rate 
Key risk factors         1)  Permitting delays could result in a delayed construction schedule. 
2)  The timing of in-water work is defined by permitting agencies in
an effort to limit the impact to endangered species  currently
October 1 through April 15. 
3)  Construction costs may increase if required work is  more
extensive than currently known. 
Project cost for analysis     $6,200,000 (preliminary estimate) 
Business Unit (BU)      Portfolio Management Group, Real Estate Division

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 27, 2009 
Page 4 of 4 
Effect on business      This is a renewal and replacement project and, accordingly, this
performance          project preserves Net Operating Income (NOI). Net Operating
Income generated by the waterside operations of Fishermen's
Terminal at the South Wall location is approximately $14,000 per
year excluding major maintenance expenses.
As a result of this project, depreciation expense will increase
annually by $124,000 resulting in a corresponding reduction in Net
Operating Income After Depreciation.
IRR/NPV          Preliminary financial analysis - based on preserving Net Operating
Income (proxy for cashflow): 
NPV   IRR  Payback
(in $000's)   (%)   (in years)
($4,946)    NA     NA
SUSTAINABILITY AND LIFE CYCLE COSTS: 
This request is for authorization to design and permit, in preparation for authorization(s) to
advertise for construction bids and subsequently award for construction. As such, total costs and
life-cycle costs will be determined upon completion of the final improvement design.
Sustainability issues will also be considered further as part of the design process. The existing
seawall section to be reconstructed is at the end of its service life. 
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
Alternative 1: Do nothing. Without remediation, the existing connectors in the underlying
relieving platform timber structure will continue to deteriorate and the likelihood
of structural failure will continue to increase. For these reasons, Alternative 1 is
not recommended. 
Alternative 2: Complete the reconstruction of the South Wall as already done for the west and
central portions of the structure in 2003-2005. Staff is recommending this
alternative as it will alleviate the existing structural safety concern, correct the
current degrading condition, and restore this asset to its full beneficial use. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: 
July 28, 2009 commission meeting project briefing

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.