Item 5f Memo

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      5f 
Date of Meeting     July 28, 2009 
DATE:    July 8, 2009 
TO:      Tay Yoshitani, Chief Executive Officer 
FROM:    Michael Burke, Senior Manager, Container Leasing and Operations 
Catherine Chu, Capital Project Manager IV 
SUBJECT:  Execution of a Pedestrian Crossing Construction and Maintenance Agreement
with BNSF at Klickitat Ave SW for the Terminal 18 Expansion Project 

ACTION REQUESTED:
Port staff requests Commission authorization for the Chief Executive Officer to execute a
pedestrian crossing construction and maintenance agreement with BNSF at Klickitat Ave SW for
the T18 expansion project. 
SYNOPSIS:
In December 1996, the Commission approved $66 million for initial funding for the Terminal 18
expansion project, which included expenditures for street vacations. The port later petitioned
and received City of Seattle conditional approvals for vacating streets on Harbor Island. The
Klickitat Ave pedestrian crossing is one of the conditions related to the street vacations that the
Port must meet. Not complying with the street vacation conditions may result in the City's
ultimate cancellation of the street vacations, which could result in up to a million dollars of
annual street use permit fees for the Port. The attached BNSF agreement stipulates that the Port
will perform construction of sidewalks approaching BNSF tracks. Port will reimburse BNSF to
do work on their tracks, and to provide flagging and inspections services.
FINACIAL IMPLICATIONS:
The total cost of the Klickitat pedestrian crossing project is estimated to be about $325K. It's
within the budget of the Commission previously authorized T18 Expansion Project. No
additional project funding is necessary. Port Construction Services will use its own labor to
construct the sidewalk approaching BNSF tracks for about $250K. The agreement will allow the
port to reimburse BNSF for work on their tracks, and for flagging and inspections services, for
about $50,000 to $75,000. The agreement further commits the port to future maintenance of the
improvements within public right-of-way. We expect that the actual maintenance costs for the
concrete sidewalk, once constructed, will be less than $5K per year. Port Legal and Risk
Management have reviewed the agreement and advised as to the risks.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.