Item 6h Memo

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      6h 
Date of Meeting     June 2, 2009 

DATE:    May 11, 2009 
TO:     Tay Yoshitani, Chief Executive Officer 
FROM:    Scott Pattison, Manager, Industrial Properties and Business Development 
Mike Kuhlmann, Capital Project Manager 
SUBJECT:  Terminal 115 Berth 1 Improvements 
ACTION REQUESTED 
Staff requests Port Commission authorization to increase the authorized budget by
$6,431,410 to pre-purchase material, and to advertise, award and construct improvements
at Terminal 115 Berth 1 for a total new authorization of $35,219,410.
SYNOPSIS 
Northland Terminal Services, Inc. (Northland) entered into a term lease at Terminal 115
(T-115) in January 2003, initially leasing 24 acres with expansion to 44 acres to begin in
January 2004. Northland is a marine terminal operator, involved in the handling of
containerized, break-bulk and neo-bulk cargo, principally to markets in Alaska and
Hawaii. This terminal plays a significant economic role in the region through the
provision of 280 direct jobs at Northland (plus the direct employees of Northland's subtenant
) and the additional induced and indirect jobs resulting from Northland's movement
of hundreds of thousands of tons of cargo. 
T-115 is a marine cargo terminal with four berths capable of Roll-On/Roll-Off (Ro-Ro),
Pass-Pass, and crane transfers of cargo.
The first amendment to the lease was executed in November 2003 and provided for
expansion of Northland's premises at T-115 to 69.5 acres effective January 1, 2004. The
first amendment also recognized the need to repair or replace the entire 1,200 lineal foot
concrete apron due to concealed structural deterioration that was identified in
March 2003.
The second amendment to the lease agreed to structural repairs and replacements to
portions of the 1,200 lineal foot pier, rather than its entire replacement. In exchange, the
Port agreed to other improvements including those outlined for Berth 1.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
May 11, 2009 
Page 2 
Completion of Berth 1 upgrades at T-115 would complete the Port of Seattle's
obligations for outstanding pier repairs under the second amendment to the lease
agreement with Northland. This will sustain marine terminal operations through the
remaining lease term of 2032, and preserve the facility for future marine-industrial users.
Improvements to date have included uplands paving, stormwater systems and utility
upgrades, and reconstruction of Berths 2, 3, and 4. These improvements are complete.
This request is for funding to complete the reconstruction of Berth 1. 
PROJECT DESCRIPTION AND JUSTIFICATION 
Redevelop T-115 Berth 1 to improve cargo terminal operations by: 
Removing the center timber pier (Pier B) and replacing it with a ramp support
structure and A-frame to accommodate barge loading / unloading. 
Replacing the timber fender systems on Piers A and C with steel fenders. 
Replacing one (1) creosote treated timber mooring dolphin with a steel mooring
dolphin. 
Installing two (2) new mooring dolphins. 
Completing maintenance dredging at Berth 1 including removal of contaminated
sediments, installation of a clean cap, and construction of an underwater wall for
slope stabilization. This maintenance dredging project is located within the Lower
Duwamish Superfund site and will require sediment sampling, monitoring and dredge
material handling and disposal due to the superfund designation. Also, as part of this
project the Port is conducting pre-and post-dredge sampling and source sampling. 
PROJECT SCOPE OF WORK AND SCHEDULE 
Project Scope 
Demolish one creosote timber finger Pier B and mooring dolphins; 
Install a 440' sheet pile underwater wall; 
Dredge and upland dispose of approximately 3,000 cubic yards (CY) of sediment
from the berth area and install a clean cap; 
Construct a new cargo loading ramp supporting structure and A-frame, steel mooring 
dolphins, winches, fenders, and associated utilities and upland improvements. 
Project Permits 
This work requires several in-water permits. 
Hydraulic Project Approval thru Department of Fish and Wildlife, 
Water Quality Certification thru Ecology,

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
May 11, 2009 
Page 3 
Clean Water Act-Section 404 permit/Rivers & Harbors Act-Section 10 permit thru
the Corps of Engineers, 
Shoreline Permit from the City of Seattle, and 
Dredged Material Management Program approval. 
Associated with these permits/approvals is coordination/concurrence with Environmental
Protection Agency's Comprehensive Environmental Response, Compensation, and
Liability Act (CERCLA-Superfund) program, Ecology's Model Toxics Control Act
(MTCA) program, and Muckleshoot Indian Tribe. 
Project Schedule 
To complete the in-water elements during the next in-water work time period (in-water
construction targeted to occur between December 1, 2009  February 15,
2010)authorization is needed in June 2009 to pre-purchase long-lead sheet and pipe piles 
and to advertise the major construction in early August 2009. Important milestones
include: 
Construction is scheduled to start in November 2009 and be completed by March 15,
2010, when Northland's seasonal cargo operations resume and this berth must be
placed back into service. 
Pre-Purchase - To complete the project by March 15, 2010, the Port will need to pre-
purchase sheet and pipe piles  advertising in June 2009 and awarding in August,
with pre-purchased materials delivered in November 2009. The estimated cost of the
pre-purchase is between $1,100,000 and $1,200,000. 
Final design of the project is at 90% at this time.
Application for building permits has been submitted to the City of Seattle for review.
Final approval of the building permits is expected in July 2009. 
Approval of in-water work permits is expected in late June 2009. 
Completion of final construction contract bid documents is targeted for July 20, 2009. 
Advertising the project for construction is targeted for August 2009. 
BUSINESS PLAN OBJECTIVES 
The overall economic impact from Northland's cargo operations at T-115 is significant to
the Port and region. The Port collects market rent under the lease and the tenant directly
employs more than 280 people in the greater Seattle area, in addition to direct employees
of its sub-tenant. Indirect and induced economic impacts related to movement of
hundreds of thousands of tons of cargo through the terminal are equally significant,
accruing to a broad array of sectors including trucking, vessel charters, cooperage, and
consolidation services; vessel and fleet maintenance, repair and purchasing; supplies and
equipment purchases of fuel, lashing gear, containers, rigging, electronics/computers;

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
May 11, 2009 
Page 4 
insurance, legal services and health care; as well as induced purchases of durable and
non-durable goods and services. 
FINANCIAL ANALYSIS 
Budget/Authorization Summary 
Previous Authorizations                                   $28,788,000 
Current request for authorization                               $ 6,431,410 
Total Authorizations, including this request                        $35,219,410 
Remaining budget to be authorized                                  $0 
Project Cost Breakdown 
Yard      Pier     Dredging    Other      Total 
Construction costs          $0   $4,044,110   $1,278,000              $5,322,110 
Sales tax                 $0     $384,190    $121,410                $505,600 
Outside               $0    $150,000    $106,802              $256,802 
professional
services
Other                  $0    $994,000        $0              $994,000 
Total (Berth 1)            $0   $5,572,300   $1,506,212              $7,078,512 
Total Cost to Date    $7,798,566  $19,151,418         $0            $26,949,984 
Rent Abatement                                $201,434    $201,434 
Environmental                                $989,480    $989,480 
(GASB 49) 
Total Project      $7,798,566  $24,723,718   $1,506,212   $1,190,914  $35,219,410 
Costs 
Source of Funds 
The 2009 Plan of Finance contains $5,800,000 for 2009 and $1,200,000 for 2010, for a
total of $7,000,000 under Committed CIP C102451 Terminal 115 Dock Reconstruction.
The $6,431,410 request for authorization is for CIP 102541.
The current projected cash flow is $2,100,000 in 2009 and $5,700,000 in 2010. When
combined with spending of $200,000 in 2008, staff estimates the total project cost for
Berth 1 will be $8,000,000. The source of funds will be the Tax Levy.
The estimated $989,480 necessary to complete GASB 49 environmental work will be
paid out of Environmental Reserves. The source of funds will be the Tax Levy.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
May 11, 2009 
Page 5 
Financial Analysis Summary 
CIP Category  Renewal/Replacement 
Project Type   Infrastructure Upgrades 
Risk adjusted 7.5%
Discount rate 
Key risk     There is a potential risk that the specific finger design' dock
factors       replacement may not accommodate future tenants. This risk is mitigated
by the fact that the Northland lease has a term of 30 years.
Project cost   $35,219,410 
for analysis 
Business Unit Seaport Industrial Properties 
(BU) 
Effect on      Based on an estimated 50 year useful life, the $7.1 million cost for
business       Berth 1 design and construction will increase depreciation by
performance     $142,000 per year. 
Environmental costs will reduce NOI in the year in which the GASB
49 triggering event occurs.
IRR/NPV    The following tables summarize the returns to the Port as of 2003 when
the lease with Northland was executed. The table below outlines the
returns anticipated in the last authorization in May 2005, and the current
authorization request dated June 2009. 
Cash Analysis - $'s Millions
Commission Memo        Investment   NPV      (1)
IRR
Authorization - May 24, 2005       $28.8     $18.3     9.2%
Current Request - June 2, 2009     $35.2     $15.6     9.6%
When the opportunity cost of the land and the residual value of land and
improvements are included in the current authorization analysis, the
NPV is negative ($19.5) million and the IRR is 5.6%. 
Note (1): IRR is calculated using the Modified Internal Rate of Return method. 
STRATEGIC OBJECTIVES 
This project supports the Port's strategies to: 
Ensure Airport and Seaport Vitality by completing the obligations identified in the
lease. It will improve operating efficiency for the tenant and will enable maritime
trade and commerce to continue at this marine terminal.
Exhibit Environmental Stewardship through our Actions. Environmental benefits
include:

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
May 11, 2009 
Page 6 

o  Removing creosote mooring dolphins and replacing with steel piling dolphins; 
o  Benthic habitat will be improved by removal of 3000 CY of contaminated
sediments and installation of a clean sand cover in the dredge area. 
o  Replacement of a timber loading pier (Pier B) with a removable steel loading
ramp will reduce overwater coverage and remove creosote-treated wood from the
aquatic environment. 
o  Replacement of the treated timber fender systems with steel on Piers A and
C will remove treated wood from the aquatic environment. 
o  Installation of a sub-tidal retaining wall will stabilize the intertidal area
and prevent future sloughing of material into the berth. 
o  The overwater walkway to access the loading ramp from Pier C will include a
grated deck surface to enhance light penetration into the water. 
o  Restoring the authorized depth of water at the berth will minimize vessel
grounding and associated disturbance to the river bottom 
A State Environmental Policy Act (SEPA) review of the barge cargo facility repair and
replacement project is complete. A final SEPA Determination of Non-significance was
issued by the Port on April 11, 2005 (SEPA File Number: 05-06). 
Other environmental/community benefits include: 
Anti-snagging measures on the top of the sub-tidal retaining wall will prevent damage
to tribal fishing nets. 
Airmodest positive benefit resulting from increased efficiency of barge cargo
operations and associated reductions in air emissions generated by cargo handling
equipment. 
Energy and natural resourcesmodest reduction in fuel consumption associated with
cargo handling equipment anticipated as a result of increased efficiency in cargo
operations. 
Human factorsno change in site visual or view corridors will result, re-use of
existing facility maintains and improves long-term marine industrial use capacity and
associated marine industrial employment benefits. 
SUSTAINABILITY AND LIFE CYCLE COSTS: 
Specifications will encourage recycling of asphalt, concrete, timber and metal debris
removed from the project area as either construction material or as a source of energy. 
Off-site disposal of excavated soils has been minimized. However, in order to
upgrade the site infrastructure, excavation is required to install utilities. The project
represents a net disposal of in-ground materials.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
May 11, 2009 
Page 7 
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
Alternative 1Close out CIP with the completion of improvements at Berths 2, 3, and 4
only, without completion of Berth 1 work. This would require a re-negotiation of the
lease, resulting in lower revenue to the Port, and limit the operating ability of the tenant.
Therefore, this alternative is not recommended. 
Alternative 2  Complete the upgrades identified in the second lease amendment: 
o   Reconfigure and upgrade portions of the 1,200' concrete pier (completed May
2007).
o   Install new transfer spans to create 3 modern Ro-Ro berths (completed May 2007).
o   Improve a minimum of 15 acres of container yard space to support landside marine
terminal operations (completed January 2009). 
o   Replace one timber pier with A-frame and ramp, dredge and install related moorage
infrastructure at the fourth berth (Berth 1)(schedule for completion April 2010) 
This is the recommended alternative. 
ADDITIONAL INFORMATION 
As noted earlier, the second amendment to the lease proposed structural repairs and
replacements to portions of the pier structures, and other improvements to piers, dolphin
and transfer spans, rather than replacement of the entire 1,200' concrete pier structure.
This reduction in scope was estimated to provide savings of between 20% and 40% to the
Port versus total replacement of the 1,200' pier, and improved operational efficiency.
This second amendment also addressed an expressed need of Northland to upgrade and
strengthen a minimum of 15 acres of the CY for heavy equipment operations at a cost of
$8,000,000, with Northland agreeing to: 
1)  A reduced scope of repairs to the piers, while continuing to rent the entire pier area,
including those areas that will be restricted from use and access; 
2)  Extension of the base term of the lease from 15 years to a base term of 30 years; 
3)  Payment of additional rent in the amount of $11,700 per month for the balance of the
30-year lease term; and, 
4)  Waiver of the Port's obligation to maintain depth of water through future dredging of
the submerged premises adjacent to the 1,200 foot concrete pier for vessel berthing
and navigation for the balance of the 30-year lease term. 
This second amendment provided for a variety of structural and configuration
improvements to T-115 that will sustain marine terminal operations through the
remaining lease term and preserve the facility for future marine-industrial users.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
May 11, 2009 
Page 8 
Pier Upgrades (Exhibit 1)  Actual construction cost of $16,685,479. 
Demolish and replace six sections of the 1,200' concrete pier, adding one new notch
and loading ramp for Ro-Ro. 
Block off unimproved sections of the 1,200' concrete apron and restrict to pedestrian
use/vessel moorage. 
Other improvements related to the above upgrades. 
Schedule  This work was performed in two phases during the in-water work months
of 2005-2006 and 2006-2007. Work was completed in May 2007. 
Yard Upgrades (Exhibit 2) Actual costs $8,000,000.
Demolish and replace a minimum of 15 acres of container yard area at a total cost not
to exceed $8,000,000.
Scheduled yard work was completed in January 2009. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: 
January 14, 2003  Execution of a Term Lease with Northland Terminal Services,
Inc. 
September 23, 2003  Project-wide authorization for the funding of preliminary
design services associated with replacement of approximately 1,200 lineal feet of
concrete apron at Terminal 115 in the amount of $2,000,000. 
November 11, 2003  Execution of the First Amendment to Lease with Northland
Terminal Services, Inc., and Commission authorization for C100447 and transfer 
from C0001702 totaling $2,288,000 for uplands and dock improvements.
May 24, 2005  Execution of the Second Amendment to the Lease with Northland
Terminal Services, Inc., and project wide authorization for funding to perform work
and enter into professional service and construction contracts related to demolition
and construction of piers, transfer spans, dolphins, utilities, seawalls, and
paving/grading in the amount of $16,500,000 and container yard, underground
utilities, grading, drainage and paving of a minimum of 15 acres of container yard in
the amount of $8,000,000, for a total requested amount of $28,788,000. 
August 8, 2006 - When bids for Berths 2, 3 and 4 were received in August 2006,
Commission was provided an update that included the following information: 
o  There was sufficient funding to construct Berths 2, 3, and 4 and with Commission
agreement construction would proceed. 
o  With modifications needed to accommodate fishing and tenant needs, the cost of
Berth 1 would require an additional $7,500,000 to $9,000,000.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
May 11, 2009 
Page 9 
o  Staff was to return to Commission for additional funding once the Berth 1 scope
was defined.
Berth 1 reconstruction was originally included in the construction package with Berths 2,
3 and 4. However, during permit discussions it was apparent that the proposed design for
Berth 1 would impact tribal fishing areas, so it was removed from the construction
package. The construction package for Berths 2, 3, and 4 was bid in June 2006. 
After discussions with the tribes and several months of discussion with Northland, a new
scope of work for Berth 1 was finalized in December 2007. Berth 1 re-design and
permitting is nearly complete. 90% design was completed on April 20, 2009. The new
design requires maintenance dredging of Berth 1 and installation of a sheet pile wall for
slope stabilization.

II
aw
lIlI
I
I
I
m...F'l _' I
.IIIIIWIIIII
IIIII
MWIHWHII, _.II|\\\\\
\                                                                         :nExw

av 33!???
4.6 Nguun
w ummmw "R
am "In Int-II  I"

LEGEND                                                                                                             NORIHLMD
SYSTEM                                                                                                             '
\
STORM . 1-0
'
.06.  AREAS
lam REPAIRS.
3                               IMAM.
~N\" _u :  ' MARINEM_       W0mm". PAVEMENT
'
' $".\\\\\"'


' '7':"It
\\>':.' N
PLAN
us
'

V.\      E;
.,              SITE mum.
"'a3ss5i V
2
Exhibit
r'
' ..
.'q \
'f\\ *vulmu..         1' .   ,
'
*    ,"   fi.::.m- ngEEZQZZEQE _-
:                                                                                         WATERWAY
Roach
.
'
H       '    '    q      u
. p   I; .            I.
r
.    a"... .. .               V.               ..:' r.                   1 ;
'2 .'-
sundown
~ :
~
,    DUWAMISH
g3M
3
'. '-              'I'I
l; .1
'W .
'
-5                          < '.. .                                       :                                  ~ _               'i
'ty' J .
.-             DIIIII
. _ 3,. .
'
?                                                IIIII
E0                                                   "-~u?*s      :' .;
.~
"v-               4.3 . . .. . ..                =3          .3.              *
"
~
24* '
lllll
7' -     '
I,I   if" -
'ln
.
. ..
I!
"5i.- '        ' I           3
'
.
.. ..
v'                   'v
an
9
.
..
,'f
-
.
.,.                      ,
1.5,:-,. .-- .
. .'x                V l
'
, .uw'              
I   'r
\            n
Ir"
.

1

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.