8d. Memo

MIC Electrical Infrastructure Replacement Design

COMMISSION 
AGENDA MEMORANDUM                        Item No.          8d 
ACTION ITEM                            Date of Meeting      October 11, 2022 

DATE:     September 8, 2022 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Kelly Purnell, Capital Project Manager IV 
Melinda Miller, Director Real Estate Asset Management 
Kenneth R. Lyles, Director, Maritime Operations and Security 
SUBJECT:  Maritime Industrial Center  (MIC)  Electrical Infrastructure Replacement Design
Authorization (CIP # C801241) 
Amount of this request:                 $800,000 
Total estimated project cost:          $6,440,000 

ACTION REQUESTED 
Request Commission authorization for the Executive Director to proceed with design of the
Maritime Industrial Center Electrical Infrastructure Replacement Project using internal design
engineering services in the amount of $800,000 and a total estimated project cost of $6,440,000. 
EXECUTIVE SUMMARY 
This project will replace the electrical infrastructure at the Maritime Industrial Center (MIC). The
site, located just west of Fishermen’s Terminal, currently has a tenant mix of storage, warehouse,
maintenance and repair shops, boatyard and marine services, and fishing vessel support
operations.  A  large  majority  of  the  electrical  infrastructure  that  serves  the  tenants  is
approximately 25 years old. Though electrical systems generally last 20 to 30 years, their
proximity to seawater has caused it to deteriorate at an expedited rate. An Arc Flash Study and
condition assessment were performed on the property in 2020 and determined that several
pieces of equipment need replacement for safety reasons as they are not compliant with National
Electrical Code (NEC) standards and too dangerous to service properly. 
It is critical to replace the infrastructure to maintain reliable and resilient electrical service to the
MIC facilities, ensure that the Port meets its tenant obligations, and continues to leverage the
economic opportunities that result in well managed and maintained assets. 


Template revised January 10, 2019.

             COMMISSION AGENDA – Action Item No. __8d__                              Page 2 of 6 
Meeting Date: October 11, 2022 
JUSTIFICATION 
This project supports the following Century Agenda and Maritime Division strategic goals: 
Century Agenda: 
1.  Responsibly Invest in the Economic Growth of the Region and all its’ Communities 
2.  Be a Highly Effective Public Agency 
Maritime Division: 
1.  Asset Management 
2.  Sustainability 
The project will include necessary upgrades to the electrical system by replacing current
equipment that is dangerous to work on and at risk of failure. This investment will increase the
asset value of the MIC by ensuring that the site facilities are functioning well and efficiently,
removing dangerous water intrusion into electrical areas, and increasing the reliability of power
to the Port’s tenants. The project also includes preparation for future sustainable EV charging
capabilities  and  potential  additional  shore  power  by  providing  minimal  make-ready
infrastructure that will eliminate the need for operational disturbances in the future. 
Diversity in Contracting 
This project is at the conceptual phase and will be developed utilizing internal design engineering
resources. Therefore, the details of WMBE aspirational goals have not yet been established. 
WMBE goals and inclusion plans will be determined at the construction phase of the project. 
DETAILS 
Maritime Industrial Center – 2700 Commodore Way, Seattle, WA 98199 
Tenant Mix: 
Building A-1: 
• Mix of storage, warehouse, repair and maintenance shops, silk screen printing 
Building A-2, yard and moorage: 
• Boat yard and marine services (metal fabrication, woodwork, heating and cooling,
electronics) 
Building A-3, A-4, A-5, yard and moorage: 
• Fishing vessel support operations 
The project consists of demolishing existing switchboards, structural concrete pads, and
decommissioning conduits and wire. The structural infrastructure, conduits, wires, switchboards, 
and associated equipment will also be replaced. The switchboards will be upsized from existing
capacity between 400 and 600 amps to 1200 amps for the smaller switchboards and from 2500
Amps to 4000 Amps for the main switchboard for future capacity needs (EV chargers, shore
power). This project will not increase the electrical load at the site at this time. Total project costs

Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. __8d__                              Page 3 of 6 
Meeting Date: October 11, 2022 
are estimated to be $6,440,000. Funding for this project was included in the 2023 capital budget
and plan of finance.
Scope of Work 
The following electrical equipment will be replaced: 
1)  Switchboard 4SP and 2SPN (service entry to site) 
2)  Switchboard 4W and 2W (wharf) 
3)  Switchboard 4P and 2P (NE Side of Building A-1) 
4)  Switchboard EY4 (East side of Building A-1) 
5)  Switchboard SEY4 (lighting connection for east lot) 
6)  Switchboards EY4 and SEY4 will be consolidated with 4P and 2P in one location that has
better access. Additionally, this will eliminate a stormwater intrusion point at EY4. 
7)  New electrical conduits, wires, and vaults will be constructed to connect the Seattle City
Light transformer that feeds the site and provide make-ready infrastructure at the
switchboards for future EV charging and upgraded shore power. 
Schedule 
Activity 
Commission design authorization               2022 Quarter 4 
Design start                                       2022 Quarter 4 
Commission authorization for major electrical   2023 Quarter 1 
equipment procurement 
Commission construction authorization          2023 Quarter 3 
Construction start                                2024 Quarter 1 
In-use date                                       2024 Quarter 3 
Cost Breakdown                                     This Request           Total Project 
Design                                                    $800,000               $850,000 
Construction                                                      0             $5,590,000 
Total                                                           $800,000              $6,440,000 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1 – Defer the project: maintain the current state and delay electrical upgrades and
repairs.
Cost Implications: 
Assuming a 6% escalation (current escalation is 13% but expected to lower) is applied to the
project over the next four years delaying the project would cost an additional $250,000 for each


Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. __8d__                              Page 4 of 6 
Meeting Date: October 11, 2022 
year it is delayed. Current maintenance has been minimal, and the equipment cannot be safely
worked on by Port Electricians; therefore, costs to maintain are not included. 
Pros: 
(1)   Lower initial capital cost. 
Cons: 
(1)   The equipment cannot currently be serviced safely. 
(2)   The equipment is already in a state of advanced disrepair due to the proximity to
saltwater and areas of stormwater intrusion. 
(3)   If the equipment fails, a long-term diesel generator will be required to provide power
to the tenants. This will impact air quality and cost significantly more over time, in large
part due to high fuel costs. 
This is not the recommended alternative. 
Alternative 2 – Phased approach: Replace switchboards one at a time as separate projects. 
Cost Implications: $6M to $8M 
Pros: 
(1)   Phases upfront capital costs for major electrical equipment over several fiscal years. 
(2)   Advances Century Agenda goals of investing in maritime industries. 
Cons: 
(1)   Over time, this alternative will cost more due to piecemeal design costs, construction
escalation costs, piecemeal ordering of large electrical equipment, and mobilization of
construction crews for each separate project. 
(2)   This alternative will take much longer to implement due to phasing and long-lead times
for major electrical equipment (12-18 months). The individual projects would either
need to be overlapped, or the risk accepted that large gaps in equipment replacement
may result in existing equipment failure. 
(3)   This alternative would be difficult to implement due to the needed conduit and vault
system replacement resulting in complex logistics and planning. 
(4)   This alternative will require multiple planned power outages to switch over the new
equipment, rather than a single outage to switch over all the equipment at once. 
This is not the recommended alternative. 
Alternative 3 – Replace all electrical infrastructure as a single capital project to bring the
equipment up to National Electrical Code (NEC) standards and provide for a safe working
environment with reliable power to the MIC facilities. 
Cost Implications: $6.4M (initial planning level estimate) 
Pros: 
(1)   Advances Century Agenda goals and Maritime Division strategic goals. 
(2)   Upgrades and replaces degraded electrical infrastructure that is not safe to maintain
and does not meet current National Electrical Code (NEC) standards. 

Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. __8d__                              Page 5 of 6 
Meeting Date: October 11, 2022 
(3)   Reduces potential construction escalation costs as it will replace the equipment sooner
than the other alternatives. 
(4)   Removes stormwater intrusion points within the project. 
(5)   Allows earlier procurement of the major electrical equipment, reducing the potential
for long-lead materials to impact the project schedule. 
(6)   Reduces the risk of equipment failure that increases the longer the project is delayed. 
(7)   Will provide for a stronger tenant experience by increasing power reliability and
resiliency and removing potential safety hazards at the site. 
(8)   Will provide for additional electrical capacity for future EV charging and possible
increased shore power. 
Cons: 
(1)   There will be some operational impacts to the site during construction. 
(2)   This alternative will have an initial higher upfront cost. 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
Cost Estimate/Authorization Summary              Capital        Expense           Total 
COST ESTIMATE 
Original estimate                                 $1,500,000               $0      $1,500,000 
Current change                                 $4,940,000               0      $4,940,000 
Revised estimate                                $6,440,000               0      $6,440,000 
AUTHORIZATION 
Previous authorizations                             $50,000                0         $50,000 
Current request for authorization                  $800,000                0        $800,000 
Total authorizations, including this request         $850,000                0        $850,000 
Remaining amount to be authorized            $5,590,000             $0     $5,590,000 
Annual Budget Status and Source of Funds 
This project was included in the 2023 Capital Plan under CIP #801241 Maritime Industrial Center
Electrical Infrastructure Replacement at an estimated total project cost of $6,440,000. 
This project will be funded by the General Fund. 
Financial Analysis and Summary 
Project cost for analysis              $6,440,000 
Business Unit (BU)                  Maritime Portfolio Management 


Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. __8d__                              Page 6 of 6 
Meeting Date: October 11, 2022 
Effect on business performance     The project will maintain annual gross revenue over 
(NOI after depreciation)             $500K from MIC tenants. Depreciation will increase by
$128,880 per year, thereby reducing the NOI by the same
amount. 
IRR/NPV (if relevant)                No incremental revenue. The NPV is the present value of
the project cost. 
CPE Impact                       N/A 
Future Revenues and Expenses (Total cost of ownership) 
This project will provide for reliable and resilient electrical power to the MIC facilities for the next
25-30 years. This upgrade will provide protection of Port assets and extend their useful life,
provide for additional future electrical capacity to support Port sustainability goals and increase
economic development potential. Maintaining existing assets will preserve the economic vitality
of our operations and serve the Port, tenants, and their customers well by providing a safe and
sustainable working environment. 
ADDITIONAL BACKGROUND 
N/A 
ATTACHMENTS TO THIS REQUEST 
(1)   Presentation slides 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
None. 








Template revised June 27, 2019 (Diversity in Contracting).



Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.