9. Report

South Satellite Infrastructure Upgrade

INTERNAL AUDIT REPORT 
Operational Audit – Capital 
South Satellite Infrastructure Upgrade Project 





February 2019 – March 2022 
Issue Date: November 22, 2022 
Report No. 2022-15

                 South Satellite Infrastructure Upgrade Project 

TABLE OF CONTENTS 

Executive Summary ...................................................................................................................................... 3 
Background .................................................................................................................................................. 4 
Audit Scope and Methodology .................................................................................................................... 5 
Schedule of Findings and Recommendations ............................................................................................ 6 
Appendix A: Risk Ratings .............................................................................................................................. 8 














2

                 South Satellite Infrastructure Upgrade Project 
Executive Summary 
Internal Audit (IA) completed an audit of the South Satellite Infrastructure Upgrade Project
(SSIUP) for the period February 2019 through May 2022. The audit was performed to assure the
quality of the Port of Seattle’s (Port) monitoring of the SSIUP, to assess if it was meeting project
management standards, and to determine if change orders were allowable, properly approved,
and reasonable. 
We selected this project based on the number of designer error and omission change orders 
(COs), and the removal of critical milestones as reflected in the original contract. Our sample for
testing included the largest dollar value change orders, ones that changed the scope of the
project, and those that were the result of errors and omissions. 
The SSIUP is approximately 45 years old and was in need of complete renovation. The SSIUP 
serves a mix of domestic and international carriers and will continue to be a critical terminal asset
for Seattle-Tacoma International airport. The final construction estimate, performed by Port
Aviation Project Management (AVPM), totaled $32.98 million. In February 2019, the Port received
two bids for the project. The lowest bidder, James W. Fowler Co. (JWF), was awarded the contract
in the amount of $28.36 million. 
The project delivery method was a design-bid-build with a lumpsum contract. The total
construction cost as of September 28, 2022, was $31.09 million, which included approximately
$2.73 million in COs. The contract required that JWF substantially complete the work no later than
1,000 days following the contract execution date, which would have been November 28, 2021. 
The actual substantial completion and physical completion were achieved on December 22, 2021,
and March 13, 2022, respectively. Construction Management (CM) provided a time impact
analysis submitted by JWF for the delay of 24 days to achieve substantial completion. As of
September 2022, a change order for the approved days has not yet been issued. Port CM is
currently reviewing the contractor’s support for some of the Force Account change orders, to
assure accurate payment to the contractor. They anticipate the final closeout of the project by
December 2022. 
In general, Port management’s monitoring aligned with the Port’s policies and procedures. We
would like to extend our appreciation to the SSIUP Project team and staff at JWF, for their
assistance and timely responses to our requests. 
We identified an opportunity where internal controls can be enhanced or developed. This 
opportunity is listed below and discussed in more detail, beginning on page six of this report. 
(Low) We identified opportunities for Port management to strengthen controls over reconciliation
of Not to Exceed (NTE) COs. Additionally, we identified instances where SOPs were not followed.
Management has made corrections based on recommendations from prior audits, and these
should be reflected in future projects. 


Glenn Fernandes, CPA 
Director, Internal Audit 

Responsible Management Team 
Janice Zahn, Interim Chief Engineer and Director, Engineering Services 

3

                 South Satellite Infrastructure Upgrade Project 
Background 
The South Satellite Infrastructure Upgrade Project (SSIUP) improved the effectiveness and 
reliability, and increased the capacity of the Heating, Ventilation, and Air Conditioning (HVAC)
system, which has seen dramatic passenger growth since its construction in 1970’s, and 
expansion in 1982. The scope of the work included replacement and upgrades to the existing 
original air handler and HVAC system on the concourse level. Additionally, the Project updated
the ceiling, lights, fire sprinkler system, and carpet among other things. 
In June 2018, the Port provided the Commission with an estimated construction cost of $37.1
million which was amended to $32.98 million for the construction cost in January 2019. The project
was advertised on November 14, 2018, and the Port received two bids in February 2019. Both
bids received were below the engineer’s construction cost estimate with James W Fowler Co.
(JWF), being the lowest responsible bidder, was awarded the contract in the amount of $28.36
million. 
The project delivery method was a design-bid-build with a lumpsum contract. The construction
contract total as of September 28, 2022, was $31.1 million, which includes approximately $2.7
million in COs. The contract required that the contractor substantially complete the work no later
than 1000 days following the contract execution date, which would have been November 28,
2021. During the course of the project, there were an additional 24 days, that extended the 
substantial completion date to December 22, 2021, the contractor provided a time impact analysis
in January 2022 which was accepted by the Port for the delay; however, as of the date of this
report, a CO has not been issued. Once approved, JWF will have met both the substantial and
physical completion deadlines. 

Schedule (Per September 28, 2022 Trend Log) 
Original Contract Completion Date                        11/28/2021 
Approved Time Extension (Calendar Days)                       0* 
Revised Contract Completion                            12/22/2021 
Budget (Per September 28, 2022 Trend Log) 
Original Contract Sum                                  $28,360,000 
Executed COs and Potential Risk                        $2,912,098 
Projected Contract Amount                             $31,272,098 
Original Contingency                                     $4,767,000 
Less: Executed COs and Potential Risk                 $(2,912,098) 
Remaining Contingency                               $1,845,902 
* CO for approved days pending issuance. 




4

                 South Satellite Infrastructure Upgrade Project 
Audit Scope and Methodology 
We conducted the engagement in accordance with Generally Accepted Government Auditing
Standards and the International Standards for the Professional Practice of Internal Auditing.
Those standards require that we plan and conduct an engagement to obtain sufficient, appropriate
evidence to provide a reasonable basis for our findings and conclusions based on our
engagement objectives. We believe that the evidence obtained provides a reasonable basis for
our findings and conclusions based on our engagement objectives. 
In some cases, we used a judgmental method to determine the samples selected for our audit
test work. In those cases, the result of the work is not representative of the population of a whole,
as we did not select a statistical based random sample.
The period audited was February 2019 through May 2022 and included the following procedures: 
Change Orders 
• Obtained an understanding of the Port's change order review process, including creation,
negotiation, and approval. 
• Verified approvals were obtained by required personnel. 
• Confirmed that approved change order amounts tied to the Change Order Log. 
• Reviewed compliance with contract requirements. 
• Reviewed supporting documentation and claim submissions, specifically
errors/omissions, scope changes, overtime, and COVID-19 expenses. 
Critical Milestones 
• Obtained an understanding of the Port’s monitoring process. 
• Obtained an understanding of why critical milestones one, two, and three were removed. 
• Assessed the reasonableness of justification provided to removing milestones. 
• Confirmed there was no scope reduction due to removal of milestones. 
• Obtained the substantial completion date and letters of forbearance. 
• Reconciled the dates of actual substantial completion to the expected dates. 
• Assessed the reasonableness of excused/extended days approved through COs. 
• Assessed whether the contractor was liable for liquidated damages. 
Project Close-Out 
• Reviewed close-out Standard Operating Procedures and contractual requirements. 
• Obtained a copy of the substantial completion certificate. 
• Obtained a copy of the physical completion certificate. 
• Confirmed that the final punch-list items had been completed. 
• Confirmed if “As-Builts” drawings were submitted. 
• Obtained an understanding of when the Resident Engineer (RE) memo will be issued. 





5

                 South Satellite Infrastructure Upgrade Project 
Schedule of Findings and Recommendations 
1) Rating: Low 
We identified opportunities for Port management to strengthen controls over
reconciliation of Not to Exceed (NTE) COs. Additionally, we identified instances where
SOPs were not followed. Management has made corrections based on recommendations
from prior audits, and these should be reflected in future projects. 
Standard Operating Procedure (SOP) 40.01, “Change Management”, requires NTE – Force
Account COs to be reconciled. Tracking under Force Account is required for all reconciliation 
change orders unless a negotiated lump sum can be agreed on with the Contractor. SOP 40.04 
defines Force Accounting (FA) as a process that ensures an organized, identifiable, verifiable,
and accountable method of compensating the contractor for costs and expenses, including labor,
material, and equipment expended by the contractor and tracked daily. The SOP requires the
Resident Engineer (RE) to review the daily force account documentation signed off by the
inspectors and immediately correct any issues so that the remaining FA work is tracked properly.
Additionally, inspectors are required to attach the signed force account sheets to their inspector
daily reports (IDR). 
We selected ten COs for review, based on those that we considered to be high risk. Examples
include designer error and omissions, large dollar amounts, force accounts, and COVID related
expenses. Two of the COs that we reviewed were approved on a lumpsum basis. Those two COs
were properly supported, reviewed, and approved without exception. The remaining eight COs
that we reviewed were not to exceed (NTE) COs tracked on a FA basis. We noted instances
where FA sheets were not attached with the IDRs, the COs had not yet been reconciled, and
required signatures were missing from the daily FA sheets. The RE confirmed that there were
instances when the inspector did not provide FA sheets and the RE’s review was based on the
contractor’s copy of the FA sheets. 
We discussed these exceptions with the CM, who indicated that they were mindful of the gaps as
similar findings had been detailed in past audit reports and they noted the reconciliation process
would allow for any validation issues to be addressed. The review period of this audit is
comparable to the projects we have already audited where we experienced similar issues, and 
CM has been training their team and conveyed that these issues have been addressed going
forward. 
Additionally, the final reconciliation for several of the NTE COs we examined was still pending.
Payments were approved by the RE after reviewing the FA sheets that the contractor had
provided in order to meet prompt pay requirements, however, it would be a good practice to
reconcile COs as soon as possible because it will help in reducing risks associated with getting
money back from the contractor and finding sufficient supporting documentation. For some of
these COs, work was completed two years earlier. 
The following table details the NTE COs that have not yet been reconciled. 
CO   Purpose                 Authorized   Amount Paid   Work Completed   Observations 
Amount      to Date 
20     Penthouse air handling       $150,000       $150,000   November 2021    FA support submitted by
unit                                                                                   contractor in June 2022 
21     COVID-19 Safety Costs      $187,000       $187,000   June 2020          FA support submitted by
contractor in May 2022 
26     COVID-19 Safety Costs        $25,000        $19,476   June 2020          See footnote* 
39     COVID-19 Safety Costs      $173,000       $137,171   December 2021    See footnote* 
56     Install new mechanical,       $290,000        $96,419   November 2021    FA support submitted by
electrical, and plumbing                                                        contractor in January 2022 
* For Change order 26 and 39, Construction Management has requested and is waiting on the Contractor to provide supporting documentation. 

6

                 South Satellite Infrastructure Upgrade Project 

Recommendations: 
• Management should update the current SOPs to require more timely reconciliation of “Not to
Exceed” Change Orders. The SOPs should specify a reasonable timeframe. 
Management Response/Action Plan: 
Engineering – Construction Management agrees the reconciliation of “Not to Exceed” Change
Orders should be done as soon as practicable, but we need to further investigate if there is
specific, reasonable timeframe we can commit to based on project needs and staffing resources. 
Expediting the reconciliation process to complete this work within a specific timeframe will require
budget planning to determine if adding staffing to projects to perform this expedited function is
feasible in comparison to any potential risks for this continuing to be done under our current
process. We are not aware of any negative impacts on any projects related to our current process
which allows us to meet prompt pay requirements while work is being performed and to reconcile
these items before the final payment to the Contractor is issued. 
At a minimum, we will add language to SOP 40.01 Change Management to indicate this
reconciliation process should be performed ‘as soon as practicable’. 













7

                 South Satellite Infrastructure Upgrade Project 


Appendix A: Risk Ratings 
Findings identified during the audit are assigned a risk rating, as outlined in the table below. Only
one of the criteria needs to be met for a finding to be rated High, Medium, or Low. Findings rated
Low will be evaluated and may or may not be reflected in the final report.
Financial      Internal                                               Commission/
Rating                                   Compliance      Public 
Stewardship  Controls                                         Management 
High probability
Non-compliance
Missing or not                       for external audit   Requires
with Laws, Port
High       Significant     followed                          issues and / or     immediate
Policies, 
negative public     attention 
Contracts 
perception 
Moderate
Partial
Partial controls                        probability for
compliance with
external audit       Requires
Medium   Moderate                  Laws, Port
Not functioning                      issues and / or      attention 
Policies 
effectively                               negative public
Contracts 
perception 
Low probability
Functioning as   Mostly complies                      Does not
for external audit
intended but     with Laws, Port                        require
Low      Minimal                                   issues and/or
could be        Policies,                             immediate
negative public
enhanced       Contracts                          attention 
perception 









8



Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.