Item 9a Report

ITEM NO.   9a-Report
DATE OF
MEETING August 11, 2009





OS 




QUARTERLY 
PERFORMANCE 
REPORT


AS OF JUNE 30, 2009

TABLE OF CONTENTS 
Page 

I.    Portwide Performance Report                                                  3-4

II.   Aviation Division Report                                                        5-9

III.   Seaport Division Report                                                       10-14

IV.  Real Estate Division Report                                   15-18

V.  Capital Development Division Report                        19-21

VI.  Corporate Professional & Technical Services                      22-23









2

I.       PORTWIDE PERFORMANCE REPORT 6/30/09 

INCOME STATEMENT 
Report: Income Statement
As of Date: 2009-06-30
2008 YTD   2009 YTD  2009 YTD  2009 Var $  2009 Var %  2009 Annual  % of Annual
Dollars in thousands               Actual      Actual     Budget    Bud vs. Act  Bud vs. Act     Budget       Bud
Revenues:
Seaport                     51,821     44,093    47,305     (3,212)    -6.8%     94,829     46.5%
Real Estate                   17,040     15,495    15,399       96     0.6%     31,111      49.8%
Aviation                       174,457    172,318   168,234      4,084      2.4%     358,956      48.0%
Capital Development                         81 -         81     0.0% -
Corporate                      313       514      724      (210)   -28.9%      1,470      35.0%
Total Revenues                 243,631   232,502   231,661      840     0.4%    486,367     47.8%
Operating & Maintenance:
Seaport                      6,653     9,610    19,226     9,616    50.0%     32,315     29.7%
Real Estate                   15,405     13,464    16,076      2,612    16.2%     32,300      41.7%
Aviation                        60,678     58,251    67,665      9,414     13.9%     132,665      43.9%
Capital Development               3,314      2,758     3,432       674    19.6%      7,010      39.4%
Corporate                    30,154     29,930    37,327     7,397    19.8%     73,572      40.7%

Total O&M before Depreciation    116,203    114,014   143,726    29,712    20.7%    277,862     41.0%

Operating Income Before Depreciation   127,428    118,488   87,936    30,552    34.7%    208,506     56.8%
Depreciation                 70,220    75,243   77,877     2,634     3.4%    157,036     47.9%
Total O&M and Depreciation   186,423    189,257   221,602    32,346    14.6%    434,897     43.5%
Operating Income after Depreciation     57,209    43,245   10,059    33,186   329.9%     51,470     84.0%







3

I.       PORTWIDE PERFORMANCE REPORT 6/30/09 

CAPITAL SPENDING RESULTS
($ Millions)
Annual Results:
2009 Plan of Finance                    $ 604.0
2009 Approved Budget                  $ 436.1
2009 Estimated/Actuals                  $ 424.9
Variance (Budget vs Estimated\Actuals)         $ 11.2


PORTWIDE INVESTMENT PORTIFOLIO 
The investment portfolio for the second quarter of 2009 earned 2.82% against our benchmark (The Merrill Lynch
3-year Treasury/Agency Index) of 1.18%.For the past twelve months the portfolio has earned 3.39% against the
benchmark of 1.39%. Since the Port became its own Treasurer in 2002, the Port's portfolio life-to-date has
earned 3.82% against our benchmark of 2.98%.














4

I.       PORTWIDE PERFORMANCE REPORT 6/30/09 
EXECUTIVE SUMMARY
The first six months of 2009 Port of Seattle's overall operating revenues were $232.5 million, $840 thousand
above the budget. Total operating expenses were $114.0 million, $29.7 million below budget. Operating income
before depreciation was $118.5 million, $30.6 million above the budget. Operating income after depreciation is
$43.2 million, $33.2 million above the budget.
Port-wide Capital spending was $57.0 million for the first six months and is forecasted to be $424.9 million for the
year, $11.2 million below the budgeted $436.1 million.
Aviation Division's Aeronautical revenues were $5.2 million favorable due to a budgeting error relating to
seasonality. Non-aeronautical revenues are unfavorable year-to-date by $883K due to underperformance of Public
Parking and other Landside-affiliated revenues. Expenses are under budget due to expense project delays and
implementation of Expense Savings Plan. Aviation is forecasting a shortfall of $11.3 million in non-airline revenues
as Public Parking, Concessions and other Landside departments will underperform against the budget due to
decreased enplanements. Operating expense is forecasted to be $11.2 million favorable due to implementation of
the 2009 Expense Savings Plan. Total capital expenditures for 2009 are projected at $253.5 million.
Seaport Division revenues were ($3.1) million unfavorable primarily due to Security Grant projects commencing
later than assumed in budget, lower reimbursement on the Terminal 30 upland dredge disposal due to cost
savings on the project, and delayed lease commencement resulting from the Terminal 30 crane cable issue. For
the full year, Seaport is forecasting a $5.6 million unfavorable revenue variance due to later start of Security Grant
projects, implementation of the Container Terminal Customer Support Package, default of tenant at Terminal 104,
and the rent impact of the Terminal 30 crane cable issue. Total Operating Expenses were $10.8 million favorable
through June primarily due to timing and due to lower cost of the Terminal 18 Maintenance Dredge and the
Terminal 30 Upland Dredge Disposal projects than budgeted. For the full year, Seaport is forecasting a $3.3
million favorable expense variance due to later start of Security Grant projects, implementation of the 2009
Expense Savings Plan and the lower cost of the Terminal 18 Maintenance Dredge and the Terminal 30 Upland
Dredge Disposal projects. Amounts are partially offset by unfavorable Environmental Reserve variance.
Forecasted Net Operating Income for 2009 is estimated to be ($2.3) million unfavorable to the 2009 Budget and
($9.5) million below 2008 Actual. Total capital spending for 2009 is projected at $55.9 million or 56% of the
Approved Annual Budget amount of $100.4 million.
Real Estate Division revenues were ($0.05) million unfavorable in the second quarter primarily due higher
vacancy than anticipated at Shilshole Bay Marina. For the full year, Real Estate is forecasting a ($0.6) million
unfavorable revenue variance due to lower occupancies at Shilshole Bay Marina and the unbudgeted termination
or expiration of tenants at other sites. Total Operating Expenses were $3.7 million favorable through the second
quarter primarily due to timing and deferrals related to the 2009 Savings Plan. For the full year, Real Estate is
forecasting a $1.9 million favorable expense variance due to implementation of the 2009 Expense Savings Plan.
Forecasted Net Operating Income for 2009 is estimated to be approximately $1.4 million favorable to the 2009
Budget and $1.0 million above 2008 Actual. Total capital spending for 2009 is projected at $100.8 million or 96%
of the Approved Annual Budget amount of $105.2 million.
Capital Development expenses were $674 thousand favorable through six months mainly due to unfilled staff
positions, delayed work and less capital work than original budgeted. A $986K favorable variance at the end of the
year is forecasted due to less expense work than budgeted. The division delivers projects and provides technical
and contracting services in support of the business plans and infrastructure needs of the Port's operating divisions.
As such, the CDD does not have its own capital improvement program.
Corporate Professional and Technical Services performance for the first six months of 2009 was $7.4 million or
19.8% favorable compared to the approved budget and $224 thousand or 0.7% lower than the same period a year
ago. The $7.4 million favorable variance is due primarily to timing of the spending and implementation of the 2009
Expense Savings Plan. There aren't any major variances to report on since all departments are favorable. Yearend
spending is projected to be $67.9 million, which is $5.7 million below the approved budget. Total capital
spending for 2009 is projected at $14.9 million or 94% of the Approved Annual Budget amount of $15.9 million.

5

II.      AVIATION DIVISION PERFORMANCE REPORT 06/30/09 
FINANCIAL SUMMARY 
2007     2008     2009    2009    Forecast/Budget
Figures in $000's    Actual    Actual    Forecast   Budget    Var $   Var %
Revenues
Aeronautical                   195,029   204,361    195,499   202,913     (7,414)  -3.7%
Non-aeronautical                143,975   150,528    137,011   148,289    (11,278)  -7.6%
Other                       8,483    3,440     8,804    8,804 -    0.0%
Total Revenues               347,487   358,329   341,314   360,006    (18,692)  -5.2%
Total O&M Costs              171,624   195,183   178,321   189,521    11,200   5.9%
Net Operating Income            175,864   163,146   162,993   170,485     (7,493)  -4.4%
Capital Expenditures              298,387   209,813    253,462   214,743    (38,719) -18.0%
We forecast a shortfall of $11.3 million in non-airline revenues as Public Parking, Concessions and
other Landside departments will underperform against the budget due to decreased enplanements.
Operating expense is forecasted to be $11.2 million favorable due to implementation of the 2009
Expense Savings Plan.
Total capital expenditures for 2009 are projected at $253.5 million.

A.   BUSINESS EVENTS 
Mount Redoubt eruption forced diversion of both passenger and cargo flights from Anchorage to
Seattle in April.
Relocation of Delta to South Satellite finalized due to merger with Northwest.
Cell Phone Lot closed due to new tenant, reopened in Q3.
Restart of Rental Car Facility in progress.

B.   KEY INDICATORS 
2008   2009   %      2008   2009   %
Figures in 000's     YTD     YTD Variance    Actual     Fcst Variance
Enplanements       7,774   7,376   -5.1%  16,093  14,959   -7.0%
Landed Weight      10,517   10,079   -4.2%  21,515   20,437   -5.0%
Enplanements vs. Prior Year                  Landed Weight vs. Prior Year
0%                             2%           0.38%  0.03%
Growth Rate                                          0%
-4.02%   -3.87%
-4.59%   -4.65%        Growth Rate -2%
-3.95%
-5%  -6.08%
-4%
-8.11%                                                     -6.27%
-6%                       -7.25%  -7.37%
-10%                                    -8%
Jan   Feb   Mar   Apr   May   Jun            Jan   Feb   Mar   Apr   May   Jun
March and April landed weight augmented by cargo diversion from Anchorage due to volcanic activity.
Enplanements are forecasted to decrease 7% from the 2008 actual.
2007     2008     2009    2009    Forecast/Budget
Actual    Actual   Forecast  Budget    Var $   Var %
Non-Aero NOI ($ in 000s)           87,714    86,474    79,282    86,393     (7,110)  -8.2%
Passenger Airline CPE             11.73    11.89     12.09    11.90     (0.18)  -1.6%
Total Operating Cost / Enpl           10.96     12.13     11.95     11.99      0.05   0.4%
We forecast CPE to come in higher than both the 2009 budget and the 2008 actual, primarily due to
increased costs allocated to aeronautical cost centers and lower enplaned passengers.

6

II.      AVIATION DIVISION PERFORMANCE REPORT 06/30/09 

C.     OPERATING RESULTS 
Year-to-date Revenue and Expense 
2007 YTD 2008 YTD  2009 YTD  2009 YTD   Actual/Budget
Figures in $ 000's    Actual     Actual     Actual    Budget     Var $    Var %
Revenues
Aeronautical                  97,435    95,972    99,866    94,684     5,182    5.3%
Non-Aeronautical               66,082    74,179    68,314    69,197     (883)   -1.3%
Other                      4,255    4,296    4,177    4,352     (175)   -4.0%
Total Revenues            167,772   174,447   172,357   168,234    4,124    2.4%
Expenses
Airport Expenses               56,533    60,580    58,182    67,579    9,397   14.9%
Corporate                   12,930    13,681    14,288    18,077    3,790   21.0%
Police Costs                  6,576    7,377    6,445     8,029    1,584   19.7%
Other Charges/CDD              150    2,475    2,183    2,637     454   17.2%
Total Operating Expenses        76,189    84,113    81,098    96,323    15,225   15.8%
Net Operating Income            91,583    90,334    91,260    71,911    19,349   26.9%
Aeronautical revenues favorable $5.2 million due to a budgeting error relating to seasonality.
Non-aeronautical revenues are unfavorable year-to-date by $883K due to underperformance of
Public Parking and other Landside-affiliated revenues.
Expenses are under budget due to expense project delays and implementation of Expense Savings
Plan. 
Division Summary 
2007     2008     2009     2009    Forecast/Budget
Figures in $ 000's     Actual     Actual    Forecast   Budget    Var $   Var %
Operating Revenues         347,487   358,329   341,314   360,006   (18,692)  -5.2%
Expenses
Payroll                       82,627    89,458    81,072    87,779     6,707   7.6%
Outside Services               28,900    31,928    22,264    25,576    3,312  13.0%
Utilities                           12,603     12,636     13,330     13,571       240   1.8%
Other                      8,981    15,844     9,131    14,054    4,923  35.0%
Total Airport Expenses         133,110   149,865   125,796   140,979    15,183  10.8%
Corporate/Capital Development      24,260    30,031    38,105    32,800    (5,305) -16.2%
Police                      14,253    15,287    14,420    15,743    1,323   8.4%
Total Operating Expenses       171,624   195,183   178,321   189,522    11,201   5.9%
Net Operating Income        175,864   163,146   162,993   170,484    (7,491)  -4.4%
Depreciation Expense          101,118   107,349   115,213   115,605     392   0.3%
Non-Operating Rev/(Exp)
Grants & Donations Revenues      89,692    49,461    63,276    63,276 -    0.0%
Passenger Facility Charges        63,114    62,770    57,003    62,525    (5,522)  -8.8%
Customer Facility Charges         22,570    23,534    22,173    24,573    (2,400)  -9.8%
Other Non-operating Rev/(Exp)      (80,848)   (105,378)   (116,013)   (116,013) -    0.0%
Total Non-Operating Rev/(Exp)     94,527    30,386    26,439    34,361    (7,922) -23.1%
Total Revenue Over Expense    169,272    86,183    74,219    89,240   (15,021) -16.8%
Operating revenues are forecasted to be $9.3 million unfavorable due to decline of parking
transactions, rental car activity, and concessions. 
Operating expenses are forecasted to be $10.2 million favorable due to implementation of the 2009
Expense Savings Plan, offset by a $1.6 million unfavorable variance from Maintenance and Utilities
due to more snow and water storms than anticipated. 
7

II.      AVIATION DIVISION PERFORMANCE REPORT 06/30/09 
Aeronautical Business Unit Summary
2008     2009     2009    Forecast/Budget
Figures in $000's    Actual     Forecast    Budget     Var $    Var %
Revenues requirement:
Capital Costs                    81,535     80,350     80,350 -      0.0%
Operating Costs net Non-Aero        131,024    120,754    127,921     7,167    5.6%
Total Costs                   212,559    201,104    208,271     7,167    3.4%
FIS Offset                       (5,250)     (5,550)     (5,550) -      0.0%
Other Offsets                    (15,686)    (14,398)    (14,052)      346    -2.5%
Net Revenue Requirement          191,623    181,156    188,670    (7,514)   -4.0%
Other Aero Revenues             12,738     14,244     14,244 -     0.0%
Total Aero Revenues            204,361    195,400    202,913    (7,514)   -3.7%
Non-passenger Airline Costs          13,039     14,661     14,830      168    1.1%
Net Pasenger Airline Costs          191,323    180,738    188,084     7,345    3.9%

2008     2009     2009    Forecast/Budget
Actual    Forecast    Budget    Var $   Var %
CPE:
Capital Costs / Enpl                5.07       5.37       5.09     (0.29)   -5.6%
Operating Costs / Enpl              8.15       8.07       8.10     0.02    0.3%
Offsets                         (0.98)      (0.96)      (0.89)     0.07    -8.2%
Non-passenger Airline Costs          (0.81)      (0.98)      (0.94)     (0.04)    4.4%
Passenger Airline CPE           11.89     12.08     11.90    (0.18)   -1.5%

Operating costs are forecasted to be lower than budgeted due to budget savings from payroll, travel
and registration, and outside services.
The forecasted increase in passenger airline cost per enplanement (CPE) is higher than budget
primarily due to the fixed debt service costs spread out over fewer enplanements.
Forecasted aeronautical operating costs per enplanement of $8.07 are less than the budget of $8.10
due to cost cutting measures.








8

II.      AVIATION DIVISION PERFORMANCE REPORT 06/30/09 
Non-Aero Business Unit Summary 
2008     2009     2009    Forecast/Budget
Figures in $000's    Actual    Forecast    Budget    Var $   Var %
Revenues:
Public Parking                   59,111     51,963     57,377    (5,413)  -9.4%
Rental Cars                     35,592     33,850     35,867    (2,018)  -5.6%
Concessions                  33,181    29,998    32,821   (2,824)  -8.6%
Other                        22,644    21,200    22,224    (1,024)  -4.6%
Total Revenue                150,528    137,011    148,289   (11,278)  -7.6%
Operating Expense             61,279    57,284    60,329    3,045   5.0%
Share of terminal O&M             16,396    17,183    18,105     921   5.1%
Less utility internal billing              (13,515)    (16,848)    (16,848) -      0.0%
Net Operating & Maint              64,160     57,620     61,586    3,966   6.4%
Net Operating Income           86,367    79,391    86,703   (7,312)  -8.4%

2008     2009     2009    Forecast/Budget
Actual   Forecast   Budget    Var $  Var %
Revenues / Enplanement
Parking                        3.67      3.47      3.63    (0.16)  -4.3%
Rental Car                       2.21      2.26      2.27     (0.01)  -0.3%
Concessions                   2.06     2.01     2.08    (0.07)  -3.5%
Other                         1.41      1.42      1.41     0.01   0.8%
Total Revenue                   9.36      9.16      9.39    (0.23)  -2.4%
Primary Concessions Sales / Enpl     10.29      9.83     10.19    (0.36)  -3.5%

Public parking revenues are forecasted to continue to decline on a per enplaned passenger basis.
Rental car revenues are forecasted to come in lower than budgeted due to weak rental car activity
and the pending expiration of contract agreement in Q4, which will reduce minimum monthly
payments.
Concessions revenues are forecasted lower than budgeted due to decline in enplanements and
reduced revenues on Concourses A and D due to airline moves.

D.   CAPITAL SPENDING RESULTS
2009
2009     2009    Forecast/Budget  Plan of
Figures in $ 000's  YTD Actual   Forecast    Budget     Var $   Var %   Finance
R/W 16L/34R Reconstruction              16,737    71,737    71,000    (737)   -1.0%   82,715
Rental Car Facility                       20,639     91,997     40,562   (51,435) -126.8%   119,011
MT 100% Baggage Screening             8,125    11,300    18,000   6,700   37.2%   21,727
Third Runway Projects                    5,814     15,208     17,281    2,073   12.0%    47,027
All Other                              17,081     63,220     67,900    4,680    6.9%    77,722
Total                            68,396    253,462    214,743  (38,719)  -18.0%   348,202
Reduced budgeted spending by $94M vs. plan of finance budget (27%) for 2009.
Rental Car Facility restarted after over six months of suspension.
2009 Budget had anticipated claims on Baggage Screening project from contractor which Port staff
successfully negotiated down.

9

III.     SEAPORT DIVISION PERFORMANCE REPORT 06/30/09 
FINANCIAL SUMMARY 
2008      2009      2009     Forecast/Budget
$'s in 000's                      Actual     Forecast     Budget     Var $     Var %
Operating Revenue              85,453      85,851     90,131   (4,280)     -5%
Environmental Grants              8,833        850       850      0       0%
Security Grants                    850       2,648      3,955   (1,307)     -33%
Total Operating Revenues          95,136      89,348     94,935   (5,587)      -6%
Total Operating Expenses         44,921      48,650     51,928   3,278      6%
Net Operating Income            50,215      40,698     43,007   (2,309)     -5%
NOI Excl Envir Grants/Reserve       47,254      45,365     45,532    (167)      0%
Capital Expenditures             88,523      55,925    100,425   44,500      44%
Total Seaport revenues were ($3.1) million unfavorable in YTD results primarily due to Security Grant
projects commencing later than assumed in budget, lower reimbursement on the Terminal 30 upland dredge
disposal due to cost savings on the project, and delayed lease commencement resulting from the Terminal
30 crane cable issue. For the full year, Seaport is forecasting a $5.6 million unfavorable revenue variance
due to later start of Security Grant projects, implementation of the Container Terminal Customer Support
Package, default of tenant at Terminal 104, and the rent impact of the Terminal 30 crane cable issue.
Total Operating Expenses were $10.8 million favorable through June primarily due to timing and due to
lower cost of the Terminal 18 Maintenance Dredge and the Terminal 30 Upland Dredge Disposal projects
than budgeted. For the full year, Seaport is forecasting a $3.3 million favorable expense variance due to
later start of Security Grant projects, implementation of the 2009 Expense Savings Plan and the lower cost
of the Terminal 18 Maintenance Dredge and the Terminal 30 Upland Dredge Disposal projects. Amounts
are partially offset by unfavorable Environmental Reserve variance.
Forecasted Net Operating Income for 2009 is estimated to be ($2.3) million unfavorable to the 2009 Budget
and ($9.5) million below 2008 Actual. 2008 Actual included $8.8 million in environmental cleanup grants and
lower expenses due to fewer one-time expense projects. 2009 expenses include $2.3 million for the
Terminal 30 upland dredge disposal project. Forecasted Net Operating Income Excluding Environmental
Grants/Reserve is expected to be ($0.2) million unfavorable to the 2009 Budget. 
Total capital spending for 2009 is projected at $55.9 million or 56% of the Approved Annual Budget amount
of $100.4 million. The reduction in capital spending is the result of deferring projects and lower spending on
the T30/T91 Project. 

A.   BUSINESS EVENTS 
TEU volumes for Seattle Harbor are down 21.7% in 2009 compared to the same period in 2008. Total 2009
YTD volume is 691K TEU's. 2009 full inbound TEU's are down 26.9%, full outbound TEU's are down
18.8%, empty inbound TEU's are down 10.4%, and empty outbound TEU's are down 24.0%.
th
Maersk and CMA-CGM commenced their weekly service at Terminal18 on June 7 .
Grain vessels shipped 2,543K metric tons of grain through Terminal 86 YTD in 2009. Amount represents a
27.4% decrease compared to 2008 YTD. Reduction is partially due to temporary closures of the Terminal
86 facility in 2009 for grain spout upgrades. Market expected to be strong through remainder of 2009.
Smith Cove cruise facility opened on schedule for the 2009 cruise season with the first call at the new
th
terminal on April 24 .
Reactivation of Terminal 30 to a container facility is delayed two months until August 2009 due to crane
cable issues. 
In connection with the 2009 Expense Savings Plan, the Seaport Division reduced 2009 Budgeted Operating
Expenses by $1.8 million.

10

III.     SEAPORT DIVISION PERFORMANCE REPORT 06/30/09 

B.   KEY INDICATORS
CONTAINER VOLUME  TEU'S IN 000'S
2,000 
1,500 
TEU's in 000's                                                                                     2009 Actual
1,000                                                                 2009 Budget
2008 Actual
500 
0 
Jan    Feb    Mar    Apr    May    Jun    Jul    Aug    Sep    Oct    Nov    Dec
GRAIN VOLUME  METRIC TONS IN 000'S
8,000 
6,000 
Metric Tons in 000's                                                                                     2009 Actual
4,000 
2009 Budget
2,000                                                      2008 Actual
0 
Jan    Feb    Mar    Apr    May    Jun    Jul    Aug    Sep    Oct    Nov    Dec
CRUISE PASSENGERS IN 000'S
1,000 
800 
# of Passengers in 000's      600 
2009 Actual
400                                                    2009 Budget
2008 Actual
200 
0 
Jan   Feb   Mar   Apr   May   Jun    Jul   Aug   Sep   Oct   Nov   Dec

NET OPERATING INCOME BY BUSINESS
In $ Thousands      2008 YTD  2009 YTD   2009 YTD    2009 Bud Var  Change from 2008
Actual     Actual     Budget     $ %      $ %
Containers              20,356    19,108      15,722   3,386    22%   (1,249)     -6%
Container Support Props        608      266        648    (382)   -59%    (342)    -56%
Cruise                  1,536     1,792        562   1,230   219%    255     17%
Grain                  2,652     2,214      2,089    125     6%    (438)    -17%
Docks/Industrial Props        2,528      2,804       1,721   1,083    63%     275     11%
Security                    46      (638)      (1,025)    386    38%    (684)  -1488%
Envir Grants/Reserve         7,809      389      (1,475)   1,864   -126%   (7,420)    -95%
Total Seaport           35,537    25,934      18,242   7,693    42%   (9,602)    -27%


11

III.     SEAPORT DIVISION PERFORMANCE REPORT 06/30/09 
C.   OPERATING RESULTS  IN THOUSANDS $
In $ Thousands            2008 YTD    2009 Year-to-Date      2009 Bud Var     Year-End Projections
Actual     Actual    Budget     $ %     Budget  Forecast  Variance
Operating Revenue               43,268    43,704    44,597    (894)    -2%   90,131   85,851   (4,280)
Environmental Grants               7,809       389      213     177     83%     850     850       0
Security Grants                     744       129     2,537   (2,409)    -95%    3,955    2,648    (1,307)
Total Revenue                 51,821    44,222    47,347   (3,125)    -7%  94,935   89,348   (5,587)
Direct Expenses                  8,669     11,023    16,101   5,078     32%   27,234   24,174    3,061
Security Expense                   564       529     3,307   2,778     84%   5,431    3,657    1,774
Environmental Reserve                0        0     1,688   1,688    100%   3,375    5,517   (2,142)
Divisional Allocations                 1,157      1,001     1,187     187     16%    2,378    2,275      103
Corporate Allocations                5,893      5,736     6,823    1,087     16%   13,510   13,027     482
Total Expense                 16,285    18,287    29,105  10,818    37%  51,928   48,650    3,278
NOI Before Depreciation           35,537     25,934    18,242   7,693    42%   43,007   40,698   (2,309)
Depreciation                     14,021     13,571    14,810    1,239      8%   30,903   30,749     154
NOI After Depreciation             21,516     12,363     3,432   8,932    260%   12,105    9,950    2,155
NOI Excl Envir Grants/Reserve*       27,727     25,545    19,717   5,828    30%   45,532   45,365    (167)
NOTE:* NOI Excl Envir Grants/Reserve is Before Depreciation
Total Seaport revenues were ($3,125K) unfavorable to budget. Key variances
Containers and Support Properties unfavorable ($1,443K).
Containers ($1,441K) unfavorable. Space Rent revenue ($637K) unfavorable due to later lease
commencement at Terminal 30 as a result of crane cable issue. Operating Grant Revenue ($688K)
unfavorable due to lower reimbursement from King County for Terminal 30 upland disposal of dredge
materials ($425K) because the project cost less than anticipated in the budget and due to RFID grant
activities commencing later than assumed in budget ($260).
Support Properties ($4K) unfavorable due to lower volumes than budgeted at Terminal 18 liquid bulk facility
($13K) partially offset by unanticipated new lease at Terminal 106 $9K.
Cruise and Industrial Properties favorable $537K.
Cruise $314K favorable primarily due to higher than anticipated passenger volumes, including sailings
rerouted from West Coast/Mexico itineraries earlier in the year as well as Savings Rent received in 2009 in
excess of 2008 year-end accrual.
Bulk Terminals ($120K) unfavorable due to temporary closures of the Terminal 86 grain facility for grain
spout upgrades. As of the end of June, facility is fully back on-line and volumes are expected to be strong
for the remainder of the year.
Dock Operations $264K favorable due to prior year billing adjustment for space leased by American
Seafoods $114K, implementation of TWIC related security tariff charges $47K, and higher than anticipated
Utility Revenue. Amounts were partially offset by below budget Dockage & Wharfage Revenue ($14K).
While activity for fishing vessels and barges at Terminal 91 was favorable to budget, delays in executing
new preferential use agreement at Terminal 25, and lower usage for Golden Alaska at Terminal 46 and the
closing of the berth at Pier 34 more than offset the favorable variances.
Industrial Properties $78K favorable largely due to higher than expected Carnitech percentage rent.
Security Grants unfavorable ($2,409K) due to Rounds 6 and 7 grant activities commencing later than
planned. Amount more than offset by corresponding favorable expense variance.
Expenses were $10,818K favorable to budget. Key variances:
Security favorable $2,778K primarily due to Round 6 and 7 grant activities commencing later than planned.
Amount is partially offset by corresponding unfavorable revenue variance above.
Environmental Reserve $1,688K due to postponement of booking Quarter 2 update until July.
Outside Services favorable $3,983K largely due to timing except for the lower than budgeted cost of the
Terminal 30 Upland Dredge Disposal project $1,348K, Terminal 18 maintenance dredge project $770K and
certain project items that were eliminated or reduced in the 2009 Expense Savings Contingency Plan.

12

III.     SEAPORT DIVISION PERFORMANCE REPORT 06/30/09 
Miscellaneous Expense favorable $659K due to timing of recognition and classification of expense
components of T30/T91 project $525K and Seaport Expense Contingency $150K also favorable due to
timing.
Bad Debt Expense unfavorable ($403K) primarily due to default of tenant at Terminal 104.
Maintenance favorable $251K due to lower cost of or deferral of project work as well as lower overhead
allocations.
Corporate costs, direct and allocated, favorable $1,232K due to implementation of cost reductions identified
in the 2009 Revised Budget ~$252K with the remainder of the variance due to timing.
All other variances netted to a favorable $630K or about 2% of Total Expenses Budgeted.
NOI Before Depreciation was $7,693K favorable to budget.
Depreciation was $1,239K favorable to budget due to delay in booking of assets for new Terminal 91 Cruise
facility, 2 month delay of in-service date for Terminal 30 container facility, and later than expected start, and
thus completion, of granted funded security capital projects.
NOI After Depreciation was $8,932K favorable to budget.
FORECAST 
As of 2nd quarter, Seaport anticipates ending the year $2,309K below budget for NOI Before Depreciation
assuming that the year-end Environmental Reserve is consistent with the 2009 forecasted level. Revenue is
expected to fall below budget due to implementation of Container Terminal Customer Support Package, default
of tenant at Terminal 104 and 2 month later commencement of the Terminal 30 lease than budgeted. Operating
expenses are estimated to be favorable by $3,278K due to later start of Security Grant projects, implementation
of the 2009 Expense Savings Plan $2,591K and lower than expected cost of the Terminal 18 Maintenance
Dredge and Terminal 30 Upland Dredge Disposal projects. Amounts are partially offset by full year unfavorable
Environmental Reserve variance.
CHANGE FROM 2008 ACTUAL 
NOI Before Depreciation decreased by ($9,602K) from 2008 with the lion's share of the decrease being the
$7,809K in retroactive Environmental Grant revenue received in 2008. The balance of the decrease in NOI
reflects higher expenses in 2009 stemming from the Terminal 30 Upland Dredge Disposal and the Terminal 18
Maintenance Dredge projects.

D.   CAPITAL SPENDING RESULTS---IN THOUSANDS $  IN PROCESS 
2009     2009    Variance
Estimated  Approved  EstActs to  EstActs as a  2009 Plan
SEAPORT DIVISION             Actual    Budget   Budget   % of Budget of Finance
Container Support Yard                    0    28,900     28,900        0%    28,900
Terminal 10                          536     4,091      3,555       13%     4,000
Terminal 30/91 Program                29,440    35,774      6,334       82%    46,445
Green Port Initiative                          0      2,800       2,800         0%     2,800
Terminal 115                        4,026     4,995       969       81%    5,800
All Other                             21,923     23,865      1,942        92%    38,740
Total Seaport                        55,925    100,425     44,500        56%   126,685

Comments on Key Projects: 
Through second quarter, Seaport spent 37% of the approved budget. Full year spending is estimated to be 56%
of the Approved Budget.


13

III.     SEAPORT DIVISION PERFORMANCE REPORT 06/30/09 

Projects with significant changes in spending were: 
Terminal 30/91 Program  Estimated spending reduced due to favorable resolution of potential risks at
Terminal 91 facility resulting in not using authorized contingencies including amounts set aside for potential
building foundation issues.
Container Support Yard  Acquisition of land for a container support yard has been delayed due to
economic conditions.
Green Port Initiative  After performing a financial evaluation, plans to develop Port owned decant stations
have been put on an indefinite hold.
Terminal 10  Modification of project scope has pushed out the timing of the project.
Changes between the 2009 Plan of Finance and the 2009 Approved Budget represent modifications in 2009
spending estimates made after determination of 2008 actual spending.


















14

IV.   REAL ESTATE DIVISION PERFORMANCE REPORT 06/30/09 

FINANCIAL SUMMARY 
2008     2009     2009    Forecast/Budget
In $ Thousands              Actual    Forecast   Budget    Var $   Var %
Operating Revenue              34,875     30,381     30,961    (580)    -2%
Environmental Grants                 1       150       150       0     0%
Total Operating Revenue          34,877    30,531    31,111    (580)    -2%
Total Operating Expense          38,819    33,456    35,391    1,934     5%
NOI Before Depreciation           (3,943)    (2,925)    (4,279)   1,354    32%
NOI Excl Envir Grants/Reserve       (3,340)    (1,950)    (3,304)   1,354    41%
Capital Expenditures            21,196    100,771    105,165    4,394     4%

Total Real Estate Division revenues were ($0.05) million unfavorable in the second quarter primarily due
higher vacancy than anticipated at Shilshole Bay Marina. For the full year, Real Estate is forecasting a
($0.6) million unfavorable revenue variance due to lower occupancies at Shilshole Bay Marina and the
unbudgeted termination or expiration of tenants at other sites.
Total Operating Expenses were $3.7 million favorable through the second quarter primarily due to timing and
deferrals related to the 2009 Savings Plan. For the full year, Real Estate is forecasting a $1.9 million
favorable expense variance due to implementation of the 2009 Expense Savings Plan.
Forecasted Net Operating Income for 2009 is estimated to be approximately $1.4 million favorable to the
2009 Budget and $1.0 million above 2008 Actual. 2008 Actuals included the write-off of costs associated
with the North Bay project which were partially offset by higher activity at Bell Harbor International
Conference Center and higher occupancies for leased properties. 
Total capital spending for 2009 is projected at $100.8 million or 96% of the Approved Annual Budget amount
of $105.2 million. The most significant project in 2009 is the Eastside Rail Corridor. 

A.   BUSINESS EVENTS 
Occupancy levels at Commercial Properties were at 95% at quarter-end, which is at target for the 2009
Budget and above comparable statistics for the local market.
nd
Through the 2 quarter, moorage occupancies at Fishermen's Terminal exceeded the 2009 Budget Target.
The Maritime Industrial Center, Shilshole Bay Marina, Harbor Island Marina and Bell Harbor Marina all came
in slightly below or at 2009 Budget Targets.
Scoping meeting held regarding the supplemental EIS for the Burien NERA project.
In connection with the 2009 Expense Savings Plan, the Real Estate Division reduced 2009 Budgeted
Operating Expenses by $1.4 million, including $0.6 million in Real Estate specific expense projects budgeted
in Capital Development.





15

IV.   REAL ESTATE DIVISION PERFORMANCE REPORT 06/30/09 

B.   KEY INDICATORS 
Shilshole Bay Marina Occupancy
120.0%
100.0%
Percent Linear Footage Occupied    80.0%
2009 Actual
60.0%
2009 Budget
40.0%
2008 Actual
20.0%
0.0%
Jan   Feb   Mar   Apr   May   Jun   Jul   Aug   Sep   Oct   Nov   Dec

Fishermen's Terminal Moorage Occupancy





Commercial Building 





Net Operating Income By Business
In $ Thousands      2008 YTD  2009 YTD   2009 YTD    2009 Bud Var  Change from 2008
Actual     Actual     Budget     $ %      $ %
Recreational Boating          946     1,177        643    533    83%     231     24%
Fishing & Commercial         (589)     (657)     (1,204)    547    45%     (68)    -12%
Commercial & Third Party      1,524     1,001       (812)   1,813   223%    (523)    -34%
Eastside Rail                 0       (72)       (208)    136    65%     (72)     NA
RE Development & Plan       102      (137)      (206)    70    34%    (238)   -234%
Environmental Reserve         (17)       0       (525)    525   100%     17   -100%
Total Real Estate          1,966     1,312      (2,312)   3,624   157%    (654)    -33%

16

IV.   REAL ESTATE DIVISION PERFORMANCE REPORT 06/30/09 
C.   OPERATING RESULTS  IN THOUSAND'S $ 
2008 YTD   2009 Year-to-Date      2009 Bud Var     Year-End Projections
In $ Thousands              Actual    Actual    Budget     $ %     Budget Forecast  Variance
Operating Revenue              17,040     15,353     15,361      (8)     0%   30,961   30,381    (580)
Environmental Grants                 0        0       38     (38)   -100%     150     150       0
Total Revenue                17,040    15,353    15,399     (45)    0%  31,111   30,531    (580)
Direct Expenses                 14,454     13,126     15,898    2,772    17%   31,821   30,599    1,222
Environmental Reserve               0        0       563     563    100%   1,125    1,125       0
Divisional Allocations                (1,667)     (1,482)     (1,753)     (271)    -15%   (3,515)   (3,399)     (116)
Corporate Allocations               2,287      2,397      3,003     606     20%    5,960    5,131     829
Total Expense                15,074    14,041    17,710    3,669    21%  35,391   33,456    1,934
NOI Before Depreciation           1,966     1,312     (2,312)   3,624    157%   (4,279)   (2,925)   1,354
Depreciation                    4,988      4,944      5,264     320     6%   10,528    9,888     (639)
NOI After Depreciation            (3,022)     (3,632)     (7,576)    3,944    52%  (14,807)  (12,813)    1,994
NOI Excl Envir Grants/Reserve*       1,966     1,312     (1,787)   3,099    173%   (3,304)   (1,950)   1,354
NOTE:* NOI Excl Envir Grants/Reserve is Before Depreciation
REVENUES: UNFAVORABLE ($45K) 
Harbor Services: Unfavorable ($82K) 
Recreational Boating Unfavorable ($86K) primarily due to slightly higher than budgeted vacancy at
SBM.
Fishing and Commercial Favorable $5K was in line with budget.
Portfolio Management Unfavorable ($49K) 
Commercial Properties Unfavorable ($19K) due to lower than anticipated concession rent at Pier
66 and tenants vacating their premises at Pier 2 and Tsubota. The lower revenue was partially offset
by higher occupancy at T-102 than was anticipated in the budget.
Third Party Managed Properties Favorable $95K due to higher than anticipated activity at Bell
Harbor International Conference Center partially offset by lower transient and monthly parking
revenue at the Bell Street Garage.
Eastside Rail Corridor Unfavorable ($125K) due to revenue expectations in the 2009 Budget
based on the assumption of acquiring the property prior to 2009. The closing date has been delayed
indefinitely.
RE Development and Planning: Favorable $108K 
Terminal 91 General Industrial Favorable $108K due to two tenants not anticipated to remain at
T91 in the budget that have continued occupy on a month to month basis $151K. The positive
variance is offset by lower than anticipated utility revenue.
EXPENSES: FAVORABLE $3,669K. KEY VARIANCES:
Environmental Reserve favorable $563K due to postponement in finalizing Environmental Reserve
calculation until July.
Third Party Management Expense favorable $308K in the due cost savings at Bell Harbor International
Conference Center and due to cost savings and lower activity at the World Trade Center Club.
Outside Services (excluding Maintenance, Corporate and Capital Development) favorable $734K primarily
due to timing including charges from Environmental Services, broker fees and tenant improvement
expenses budgeted for the World Trade Center West Building, and Personal & Contracted Services
budgeted for the Eastside Rail Corridor.
Maintenance expenses favorable $556K primarily due to timing and the deferral of some work in connection
with the 2009 Expense Saving Plan.
Corporate and Capital Development costs direct and allocated favorable $1,269K primarily due to timing and
the cancellation/deferral of projects in connection with the 2009 Expense Savings Plan.
All other variances netted to a favorable $239K or less than 2% of Total Expenses Budgeted.
17

IV.   REAL ESTATE DIVISION PERFORMANCE REPORT 06/30/09 
NOI BEFORE DEPRECIATION was $3,624K favorable to Budget.
Depreciation was $320K favorable primarily due to overstatement of Harbor Service's Depreciation in the
Budget.
NOI AFTER DEPRECIATION was $3,944K favorable to Budget.
FORECAST 
nd
As of 2  Quarter, Real Estate anticipates ending the year $1,354K above budget for NOI Before Depreciation
assuming that the year-end environmental reserve adjustments are consistent with budget. Revenue is
expected to come in below Budget by ($580K) primarily due to lower occupancies at Shilshole Bay Marina and
the termination of tenants at other sites. Operating expenses are estimated to be favorable by $1,934K primarily
due implementation of the 2009 Expense Savings Plan. NOI After Depreciation is currently estimated to end the
year $1,994K favorable to budget. Excluding Environmental Grants and Reserve, NOI Before Depreciation is
expected to come in at $1,354K favorable to budget.
CHANGE FROM 2008 ACTUAL 
Net Operating Income Before Depreciation decreased by $654K between the first half of 2008 and first half of
2009. Revenue decreased by $1,687K due to lower activity at Bell Harbor International Conference Center and
the Bell Street Garage, partially offset by higher revenues at Shilshole Bay Marina due to construction
completion. Expenses decreased by $1,033K in 2009 primarily due to less activity at Bell Harbor International
Conference Center and the 2009 Savings Plan, both of which were partially offset by higher expenses at
Shilshole Bay Marina related to higher occupancy.

D.   CAPITAL SPENDING RESULTS---IN THOUSANDS $
2009     2009    Variance
Estimated   Approved  EstActs to  EstActs as a 2009 Plan of
REAL ESTATE DIVISION       Actual   Budget   Budget  % of Budget  Finance
Eastside Rail Corridor                   96,302     96,302         0       100%    106,955
Small Projects                        1,088      1,753       665        62%     1,665
RE Division Green Initiative                   0      1,000      1,000         0%      1,000
Pier 69 North Apron Piling Cathodic             0      1,000      1,000         0%      1,060
Tenant Improvements - Capital              346       900       554       38%       800
All Other                             3,035      4,210      1,175        72%      4,809
Total Real Estate                     100,771    105,165      4,394        96%    116,289
Comments on Key Projects: 
Through second quarter, the Real Estate Division spent 1% of the approved budget. Full year spending is
estimated to be 96% of the Approved Budget.
Projects with significant changes in spending were: 
Eastside Rail Corridor  No change in estimated spending, but acquisition deadline deferred to 12/15/09.
Small Projects  Workload issues due to insufficient staffing have pushed the start of some projects into
later in 2009 with completion in 2010 or entirely into 2010.
Green Port Initiative  Construction of a stormwater improvement project now expected to take place in
2010.
Pier 69 North Apron Piling Cathodic System  Project pushed back until 2010.
Tenant Improvements Capital  Projects pushed back until 2010.
Changes between the 2009 Plan of Finance and the 2009 Approved Budget represent modifications in 2009
spending estimates made after determination of 2008 actual spending.


18

V.   CAPITAL DEVELOPMENT DIVISION PERFORMANCE REPORT 06/30/09 

A.   BUSINESS EVENTS 
Commission approved the restart and funding for the Rental Car Facility. The contractor was then
given notice to restart construction work. The delay and slowdown of the project had impacted
workload and the assigning of Port staff, too.
Three additional Infrastructure projects were approved by the Aviation Investment Committee to
move forward.
During Q1 and Q2, PCS, in conjunction with the Office of Social Responsibility, participated in several
round table discussions with small businesses regarding how to do business with the Port of Seattle.
PCS preliminary results at the end of Q2 indicate that direct cost (contractor payments, materials &
equipment and crew wages) totaled $4.1 Million compared to $5.2 Million in 2008.
The PCS SharePoint site was updated to include a monthly featured project that includes
construction updates and customer comments.
Decrease in revenues has impacted the start of Fisherman's Terminal condition assessment and
expense project causing a delay from Q1 to Q2.
Uncertainty of Capital projects workload and hiring freeze has resulted in the use of more consultant
time in lieu of hiring more cost effective FTEs. This also has negatively impacted the overhead ratio.
Unemployment charges due to termination in 2008 that were not anticipated/not budgeted. This
variance is expected to continue through year-end.
4 CPO-1 trainings held in Q2. Total of 13 trainings with over 350 attendees.
Have scheduled 4 Drafting Evaluation Criteria (for Service Agreements) trainings for Q3.
T91 Cruise facility completed successfully. Received first cruise ship in April.
th
T30 Container Terminal Redevelopment is complete. First vessel call expected August 7 .
T86 Grain Terminal completed repairs and replacement of failed spouts.
T115 Berth 1 received permits. Will advertise for bids Q3 2009.

B.   KEY INDICATORS (as applicable) 
Construction Soft Costs: 19.1% of total capital project costs for period 2004-2009 to date.
Goal: no more than 25% of total project costs.
Cost Growth on Major Construction for projects completed in Q2 (RE Completion memos issued).
Project             Non-Discretionary Change  Discretionary Change
CMP Chiller Expansion Ph. 2 & Boiler              8.5%                0%
Expansion Upgrade
MT AHU-8 Acoustic Upgrades &               2.9%               0%
Miscellaneous HVAC Upgrades
Feeder 109/209 & 111/211 Installation and          5.2%                0%
Modification Part 2
Goal: no more than 4% discretionary and 4% non-discretionary cost growth.
Schedule: Projects on or ahead of schedule  30, Projects delayed  40 (1Q09 CIP Report).
Goal: no more than 10% average time growth.




19

V.   CAPITAL DEVELOPMENT DIVISION PERFORMANCE REPORT 06/30/09 
Small Business Participation:
o PCS made WBE payments of 8.1%, SBE payments of 10.4%, MBE payments of 0.8% and DBE
payments of 0.3 % for a total 19.6% in Small Business Participation for the first six months of 2009.
o SPMG: Small Business Participation Q2  Consultant contracts (not counting sub consultants):
Related to Expense        42.46%
Related to Capital          2.06%
o CPO made WBE payments of 1.8%, SBE payments of 5.9%, MBE payments of 1.8% for a total
of 7.9% in Small Business Participation for the first six months of 2009.
Goal: 30% of PCS, 8% of major construction
Customer Score Card: Not available
Goal: average 30 out of possible 35 points.
Environmental: Not available
Goal: Incorporate EX-15 or LEED in every project initiated in 2009.
Safety: 2 injuries YTD
Goal: 90 out of 100 on organizational Safety Evaluations; limit annual contractor
workplace injury rate to 6 accidents and 2 time-lost accidents.
Performance Review Timeliness: 62.5% of PREPs YTD completed within CDD guideline. 82.5%
completed within Port guideline (60 days).
Goal: 98% of PREPs within 4 weeks of review date.

C.   FTE SUMMARY [Double click the table to get to the Excel file before inputting] 
Budget                       Actual
New
Approved
FTEs in  (Eliminate        Revised  FTEs as                        FTEs at  Current
2009  d) FTEs in  Other   2009    of          Eliminated  Other  the End of  Vacant
Budget   2009  Changes  Budget  01/01/09 New Hires   FTEs   Changes  the Qtr   FTEs
271.30   2.00    (2.00)   271.30   224.30   4.50     0.00     (7.75)   221.05   48.25

FINANCIAL PERFORMANCE---- IN THOUSANDS $       [REPORTED BY ORG]
Explain variances, including explanation of reasons for not direct charging as budgeted
2008 YTD    2009 YTD     2009 Bud Var.    Year-End Projections
In $ Thousands  Actual  Actual Budget    $ %   Budget  Revised Forecast Variance
AvPMG      431   259   381  122    32.1%   761   721   592    169
PCS       1,204   571   669  99    14.7%  1,449   1,431  1,431    18
ENG       657   533  605  72    11.9%  1,351  1,298  1,290    61
SPMG      491  361  749  387   51.7%  1,400   845   780   620
CPO       531   873  741 (132)   -17.9%  1,494  1,636  1,636   (142)
CDD Admin      -    161   287  126    43.9%   554    294   294    260
Total CDD  3,314  2,758  3,432  674     19.6%   7,010   6,226   6,024     986



20

V.   CAPITAL DEVELOPMENT DIVISION PERFORMANCE REPORT 06/30/09 
TOTAL VARIANCE = $ 196,003
Budget -   YTD
YTD Revised Actual Var. Revised
YTD Actual   Budget      $     Var. %
AvPMG             258,791   360,918  102,127   28%
PCS (1700)              570,584    662,062   91,478    14%
ENG             532,952   565,956  33,004   14%
SPMG            361,425   403,957  42,532  11%
CPO             873,476   796,057  (77,419)  -10%
CDD Admin             161,268   165,549   4,281    3%
TOTAL       2,758,496  2,954,499  196,003    7%
Note:
CPO negative variance to Approved Budget includes T-18 Crane expense to be reclassed to Seaport, plus FTE
expense not originally budgeted to CPO. The FTE expense variance will continue through 2009.
CPO negative variance to Revised Budget includes T-18 Crane expense to be reclassed to Seaport.

EXPLANATION OF MAJOR VARIANCE [Double click the table to get to the Excel file before inputting]
Account Description    YTD Rev  YTD Rev               Explanation
Var. $   Var %
Sal & Benefits (Exp)         1,510,528    11.4%  Combination of use of consultants due to unfilled staff
positions, delayed work, less capital work than budgeted.

Equipment Expense         254,035   75.9% Delay in software, computer and filing system acquisitions,
plus less vehicle expense than planned.
Supplies & Stock            74,795    44.4%  Reduced and/or delayed general and emergency supplies.

Outside Services            819,807    53.7%  Some consultants have been released or delayed or not
used as originally budgeted. $85K T-18 Crane demolition to
be reclassed to Seaport
Travel & Other Employee       96,000    72.4% Timing difference between budget planned and actual
Expense                          spending.
Telecommunications         40,960   41.2% ICT backlog on charges

Worker's Comp            (3,102)  (28.20%) Over budget due to injury

General expense          (121,873)   (43.3%) Higher expense project OH allocation and Inter-dept
allocation than budgeted due to unfilled positions, fewer
consultants and fewer small works projects.
Internal Dept transfers          (7,147)  (119.7%)  Primarily CPO-1 manuals not budgeted.
Charges to Cap Projects     (2,471,062)   (18.9%)  Amount charged to Capital projects less than budgeted.
TOTAL       199,145

21

VI.   CORPORATE PROF. & TECHNICAL SERVICES PERFORMANCE REPORT 6/30/09

A.   BUSINESS EVENTS 
Joint Port of Seattle and Port of Tacoma Commission strategies: Commission meeting to recommend
transportation infrastructure priorities for road & rail projects/policies.
Attended the West Coast Port Executive's meetings in California and Washington, DC.
Implemented the $16.5 million Port-wide Expense Savings Plan.
Began the Modified Zero-Base Budgeting process for 2010 budget.
The Port was awarded the "Certificate of Achievement for Excellence in Financial Reporting" and
"Distinguished Budget Presentation" from the Government Finance Officers Association (GFOA) of the
United States and Canada.
Planned and managed media day at the new Smith Cove Cruise Terminal. Strong coverage gained on
local radio, print media and in trade publications. Program included University of Washington students
learning about the economic impacts of Seattle's cruise industry. Tours of the facility and a Holland
America ship followed the program.
HR&D staff produced initial and updated Emergency Furlough Program FAQ documents for posting on
the intranet and served as focal point for questions from employees and managers alike.
Completed several important ICT projects and initiatives: Aviation Dashboard, Internal Control Software,
Microsoft Office 2007 Upgrade, Common Use Terminal Replacement and IP Telephony.
The Police Department has applied for stimulus funded grants to help address the funding challenges
being faced by the department.

B.   KEY INDICATORS
Occupational injury rate decreased from 6.06 in the second quarter of 2008 to 4.70 in the second quarter
of 2009. This is a new Port record for the lowest injury rate in history of the Port.
93% employee completion rate of the health assessment.
Approximately 43 individual job evaluations have been finalized in the first half of 2009.
91 employment requisitions were opened and processed 4,101 applications.
Provided a timely, accurate, and improved Quarterly Financial Performance Report to the Commission
and Executive Team.
Created a new monthly Financial and Operational Indicators Report to the Commission and Executive
Team.
Rental car funding has an estimated opening CFC rate below the target rate of $6.50.
Garnered local and national coverage for the Port's decision to donate unused dog food to local shelters
and Northwest Harvest. Parlayed story into positive coverage of the new baggage handling system.
Sea-Air School Seaport and Airport Programs reached 5,969 students, teachers and parents.
Participants came from 28 cities and 73 schools.
The Port and King County are involved in study of cruise-ship waste disposal with the opening of the
new cruise terminal.
Completed and presented the following audits to the Audit Committee:
o Bell Harbor International Conference Center/Columbia Hospitality
o Anton Air Food
o World Trade Center West Management/Wright Runstad
o Louis Dreyfus
o Seaport Security Department
o World Trade Center Seattle Management/Columbia Hospitality
Police Department Indicators:
January  June   CFS's (Calls for Service)  30,711
January  June   Arrests  No Warrant     426
January  June   Arrests  Warrant        296

22

VI.   CORPORATE PROF. & TECHNICAL SERVICES PERFORMANCE REPORT 6/30/09

C.    OPERATING RESULTS---- NET OPERATING EXPENSE (in THOUSANDS $) [REPORTED BY ORG] 
2008 YTD     2009 YTD      2009 Bud Var.     Year-End Projections
In $ Thousands                    Actual   Actual Budget     $ %  Budget  Revised Forecast Variance
Total Revenues                    313    514    724    (210)  -29.0%   1,470   1,470   1,417    (53)
Executive                         876    715    803     89   11.0%   1,540   1,449   1,449     92
Commission                      477    422    472    50   10.6%   867    844    844    22
Legal                          1,230    975   1,372    397   28.9%   2,703   2,638   2,637     67
Risk Services                       1,413   1,253   1,430    177   12.4%   2,861   2,838   2,833     28
Health & Safety Services                 525    468    503     35    6.9%    985    947    947     38
Public Affairs                         1,815   1,587   2,240     653   29.2%   4,270    3,565   3,565     705
External Affairs                        518     612     654     42    6.4%   1,347   1,249   1,229     118
Economic & Trade Development           559    660   1,072    412   38.4%   2,099   1,638   1,638    462
Human Resources & Development         1,927   1,740   2,114    374   17.7%   4,165   3,926   3,926    238
Labor Relations                      313    319    362     42   11.7%    731    689    593    138
Information & Communications Technology   5,407   7,722   9,860   2,138   21.7%  19,658  18,404  18,404   1,253
Finance & Budget                    781    719    889    170   19.1%   1,719   1,645   1,482    236
Accounting & Financial Reporting Services    2,956   2,928   3,328    400   12.0%   6,541   6,352   6,331    210
Internal Audit                         318     460     575     115   20.0%   1,211   1,164   1,073     138
Office of Social Responsibility              341     531     842     311   37.0%   1,647    1,401   1,397     249
Regional Transportation                 176    208    251     43   17.2%    498    461    461     37
Police                            9,149   8,299  10,186   1,887   18.5%  19,979   18,379  18,312   1,666
Contingency                     1,371    313    375     62   16.5%    750    750    750 -
Total Expenses                   30,154  29,930  37,327   7,397   19.8%  73,572  68,338  67,873   5,699

Corporate Professional and Technical Services performance for the first six months of 2009 was $7.4 million
or 19.8% favorable compared to the approved budget and $224 thousand or 0.7% lower than the same period a
year ago. The $7.4 million favorable variance is due primarily to timing of the spending and implementation of
the 2009 Expense Savings Plan. There aren't any major variances to report on since all departments are
favorable. Year-end spending is projected to be $67.9 million, which is $5.7 million below the approved budget.

D.   CAPITAL SPENDING RESULTS 

($ Millions)
Annual Results:
2009 Plan of Finance                    $ 12.8
2009 Approved Budget                 $ 15.9
2009 Estimated/Actuals                  $ 14.9
Variance (Budget vs Estimated/Actuals)         $ 1.0





23

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.