Item 6a Attach

Item No.     6a_Attach 
Meeting Date:  March 24, 2009 
COMMISSION STAFF BRIEFING 
ATTACHMENT A 

Terminal 30 Container Terminal Project Status 
The Terminal 30 major construction is estimated to be 81% complete. Construction is
progressing behind schedule and on budget. The contractor GCC experienced schedule delays
from severe weather conditions between 12/12/08 thru 1/8/09. The Port and the contractor have
agreed on a time extension until May 12, 2009 for beneficial occupancy and the contractor has
been requested to accelerate the schedule back to May 11, 2009.
North end berth is available for receiving cranes. Waterside crane beam is 90% complete. 
Concrete work for truck scale pedestals is in progress. Primary storm drains installation is
complete. Longshore building interior framing is in progress. RTG runways work is near
complete. Paving work is in progress. Reefer Racks are nearly complete. Final testing of reefer
rack substation is pending installation of the reefer rack electrical components. Raising the
Utility Castings is 50% complete. The T30 light pole drilled shafts are complete. Fabrication of
the concrete barrier is in progress. Demolition of the maintenance canopy is complete. Placement
of the new concrete footings to allow for relocation of the columns is ongoing. OCR structure at
T25 in progress 
Terminal 30 Upland Dredge Disposal Update 
Dredging is complete 
Terminal 91 Cruise Terminal Project Status 
The Terminal 91 cruise terminal building construction by PCL is estimated to be 99% complete.
City issued temporary certificate of occupancy of the building on February 24, 2009, and PCL is
currently projecting to receive the final certificate of occupancy on March 10, 2009. The T91 
cruise terminal is on schedule to receive the first cruise vessel on April 24, 2009. 
Punchlist work by PCL is in progress. Offsite signage fabrication/installation coordination with
City of Seattle continues. Cruise building & yard signage fabrication/installation work is also in
progress. Seattle City Light is mobilizing to begin shore power cable installation. Utility
installation for the north end parking lot is underway and approximately 85% of the parking lot
striping is complete. Installation of metal canopy north of the terminal building has begun.
Security and access control integration contract is underway. Coordination with local pilots on
navigation aids installation is on-going. 
Terminal 30 Project Schedule 
The current schedule is showing the project being complete on May 11, 2009. 

Page 1 of 3

The contractor GCC and Port have settled time impacts due to severe weather in December and
January and have agreed on revised beneficial occupancy target date of May 12, 2009. The
contractor has submitted a recovery schedule with revised beneficial occupancy date of May 11,
2009. The recent heavy rain and cold temperature in the month of February and March has
greatly affected the contractor abilities to pave. The contractor has further requested a 13-day
extension due to the recent weather impact. Further schedule analysis is pending. 
The main substation will need phone line installed and payment to SCL before substation is online.
The critical work with installation of water side crane beam is progressing on schedule. 
Terminal 91 Project Schedule 
PCL received temporary certificate of occupancy from the City of Seattle on February 24, 2009
and final certificate of occupancy is anticipated on March 10, 2009. 
The T91 facility is on-schedule to receive its first vessel on April 24, 2009. The period between
beneficial occupancy and operations will be used to allow move-in and other activities to occur. 
Terminal 30/91 Program Budget 
The program forecast value is changed from the previous month reporting of $119,355,000 to
$118,339,000. The forecast (including the foundation change, but without the upland disposal
changes) is on target to be completed within the baseline budget of $118,339,000.
The additional authorization of $3,186,000 for cruise terminal building foundation changes
remained unused. This additional authorization will not be used until existing cruise building 
construction contingency fund is fully exhausted. Currently, staff does not anticipate utilizing the 
additional authorization for the foundation work. 
As of the end of February, the T91 cruise building contract has an un-trended construction
contingency or available contingency of $469,000. The T30 Container Terminal project has an
un-trended construction contingency of $755,000. 
Commission approved additional funding for the T30 upland dredge disposal change order on
October 14, 2008, in the amount of $4,800,000. A separate expense project has been created to
track this work and it will not be considered part of the overall T30/91 program budget. See
Table A 
Terminal 30 Container Terminal Risk Factors 
Weather continues to be a risk factor for the project schedule. 
Terminal 91 Cruise Terminal Risk Factors 
Shore power installation and mobile gangway fabrication need to be fully completed and
commissioned prior to start of 2009 cruise season.

Page 2 of 3

C800085 T30 / T91 Program 
Monthly Status Report  February 2009 
Program Schedule Summary 

T30 Container Terminal 
2008 Cruise Operation             Commence Dredging 
Commences  04/23/08           12/01/08                      Availability for Crane off-loading and
Commissioning 3/15/09  (originally 3/1/09)
Mar-08  Apr-08  May-08  Jun -08 Oct-08  Nov-08  Dec-08  Jan-09  Feb-09  Mar-09  Apr-09  May-09
Cruise Facility Building
Phase 1 Beneficial
Available for Demolition 
Occupancy  03/31/08                                                        Phase 2 Beneficial
11/01/08                                        Occupancy  05/11/09
(originally 5/1/09)
The project is impacted by severe weather and unforeseen conditions, and the contractor and Port have settled on time 
impacts and necessary recovery plans. Currently, the Beneficial Occupancy date for the T30 Container Terminal is 
showing on May 11, 2009. 
T91 Cruise Terminal Facility 
Port/Tenant begin install
IT equipment and
furnishing  02/11/09
T91 Facility available to
receive vessels  04/24/09

Mar-08  Apr-08  May-08  Jun -08 Oct-08  Nov-08  Dec-08  Jan-09  Feb-09  Mar-09  Apr-09  May-09

Beneficial Occupancy for Major
Construction  03/06/09
(originally 12/20/08 )
The building contractor is projected to receive beneficial occupancy of the cruise terminal building on March 6, 2009. The
T91 facility is still on-schedule to be available to receive its first vessel on April 24, 2009. The period between beneficial
occupancy and operations will be used to allow move-in and other activities to occur. 

Program Cost Summary 
$140,000
Status Date: 2/28/09                     $118,339
$120,000
$102,211
Originally Planned                          $118,339
$100,000
$102,659
Thousands $80,000                                               Estimated Actual Costs
$60,000
$40,000
$20,000
$-
2006   Sep-07   Dec-07   Mar-08   Jun-08   Sep-08   Dec-08   Mar-09   Jun-09   Sep-09   Dec-09
Planned Costs     Forecasted Costs     Actual Costs
The Program Forecast value is adjusted to reflect the Monte Carlo analysis performed for trends through 2/28/08. The
Upland Dredge Disposal work is NOT included in the program analysis graph. Earned value is tracking very close to
planned costs. The for ecast is on target to complete within the baseline budget.

Page 3 of 3

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.