Item 6b Attach

Item No.     6b_Attach 
Meeting Date:  January 27, 2009 
COMMISSION STAFF BRIEFING 
ATTACHMENT A 

Terminal 30 Container Terminal Project Status 
Terminal 30 major construction is 68% complete. Construction on Phase 2 commenced in mid-
October and is progressing on schedule and on budget. The contractor has notified the Port of
schedule impacts due to severe weather between 12/18/08 and12/30/08, as well as, impacts
associated with investigation of an unknown substance discovered during dredging between
1/2/09 thru 1/6/09. 
Concrete pile driving is complete. The north end substation is nearly complete. Concrete work
for truck scales is in progress. Storm drain installation at the reefer rack and equipment slab is
complete, and storm drain work under cruise building is in progress. The Longshore building remodel
is in progress and form work below the deck at waterside crane beam is complete. 
Terminal 30 Upland Dredge Disposal Update 
Both dredging for upland and open water disposal has commenced as of December 1, 2008. The
dredging operation was delayed due to the snowstorm. It is expected to be completed prior to
February 15, 2009. 
Terminal 91 Cruise Terminal Project Status 
As of the end of December, Terminal 91 cruise terminal building construction is approximately
90% complete. Drywall installation is nearly complete with much of the second level walls
painted. Significant portion of the second level concrete floor has the final finish sealant applied.
Start-up of air handling units and HVAC system continues. Permanent lig ht fixtures are mostly
in place and trim work underway. Plumbing fixtures are being installed throughout the building.
Escalator and elevator commissioning process continues. Balcony topping slabs are in place.
Seattle City Light shore power agreement is being finalized. Coordination continues with City
of Seattle on city street sign fabrication and installation. The cruise building and terminal yard
sign contract advertised and the bid opening is scheduled for January 14th.
Terminal 30 Project Schedule 
The project was impacted by severe weather and unforeseen conditions and the contractor is in
the process of evaluating impacts and necessary recovery plans. Currently, the Beneficial
Occupancy date for the T30 Container Terminal remains May 1, 2009. 
Terminal 91 Project Schedule 
The building contractor is projecting beneficial occupancy of the cruise terminal building on
February 18, 2009 with temporary certificate of occupancy occurring a couple of weeks earlier if

Page 1 of 3

necessary. Snow events during late December may have minor impacts to the construction
schedule and the extent of impact is still being assessed.
The T91 facility is on-schedule to be available to receive its first vessel on April 24, 2009. The
period between beneficial occupancy and operations will be used to allow move-in and other
activities to occur. 
Terminal 30/91 Program Budget 
The program forecast value has been reduced from last month reporting to $119,355,000. The
forecast for base work (without the foundation and upland disposal changes) remains on target to
complete within the baseline budget of $118,339,000.
The additional authorization of $3,186,000 for cruise terminal building foundation changes
remained unused. This additional authorization will not be used until existing cruise building 
construction contingency fund is fully exhausted. Currently, staff anticipates the additional
authorization will be partially utilized due to the foundation related changes. 
As of the end of December, the T91 cruise building contract has an un-trended construction
contingency or available contingency of $346,000. The T30 Container Terminal project has an
un-trended construction contingency of $524,140. 
Commission approved additional funding for the T30 upland dredge disposal change order on
October 14, 2008 in the amount of $4,800,000. A separate expense project has been created to
track this work and it will not be considered part of the overall T30/91 program budget. See
Table A 
Terminal 30 Container Terminal Risk Factors 
Severe weather conditions have impacted this project in December. 
Terminal 91 Cruise Terminal Risk Factors 
Shore power installation and mobile gangway fabrication need to be fully completed and
commissioned prior to start of 2009 cruise season.






Page 2 of 3

C800085 T30 / T91 Program 
Monthly Status Report  December 2008 
Program Schedule Summary 

T30 Container Terminal 
2008 Cruise Operation             Commence Dredging         Availability for Crane off-loading and
Commences  04/23/08           12/01/08               Commisioning  02/28/09

Mar-08  Apr- 08  May-08  Jun -08 Oct-08  Nov-08  Dec-08  Jan-09  Feb-09  Mar-09  Apr-09  May-09
Cruise Facility Building
Phase 1 Beneficial                                                             Phase 2 Beneficial
Available for Demolition 
Occupancy  03/31/08                                                Occupancy  05/01/09
11/01/08
The project is impacted by severe weather and unforeseen conditions, and the contractor is in the process of evaluating
impacts and necessary recovery plans. Currently, the Beneficial Occupancy date for the T30 Container Terminal remains
May 1, 2009. 
T91 Cruise Terminal Facility
Port/Tenant begin install
furnishings and fixtures
02/18/09
T91 Facility available to
receive vessels  04/24/09

Mar-08  Apr-08  May-08  Jun -08 Oct-08  Nov-08  Dec-08  Jan-09  Feb- 09  Mar-09  Apr-09  May-09

Beneficial Occupancy for Major
Construction  02/18/09
(originally 12/20/08 )
The building contractor is projecting beneficial occupancy of the cruise terminal building on  February 18, 2009. The T91
facility is still on- schedule to be available to receive its first vessel on April 24, 2009. The period between beneficial
occupancy and operations will be used to allow move - in and other activities to occur.

Program Cost Su mmary
$140,000
Status Date: 12/31/08                          $119,355
$120,000
$95,878                          $118,339
$100,000                                  Originally Planned
Thousands $80,000                                              $88,951
Estimated Actual Costs
$60,000
$40,000
$20,000
$-
2006   Sep-07   Dec-07   Mar-08   Jun-08   Sep-08   Dec-08   Mar-09   Jun-09   Sep-09   Dec-09
Planned Costs     Forecasted Costs     Actual Costs
The Program Forecast value is adjusted to reflect the Monte Carlo analysis performed for trends through 12/31/08. The
Upland Dredge Disposal work is NOT included in the program analysis graph. Earned value is tracking very close to
previous forecasts. The forecast for base work remains on target to complete within the baseline budget.

Page 3 of 3

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.