10c. Presentation

SeaTac Concourse A Building Expansion for Lounges Proje

Item No.        10c_supp
Date of Meeting      May 10, 2022
Concourse A Building Expansion for Lounges
Budget Increase Request

Requesting Commission Authorization For:
Budget increase for project $26.5M
Reimbursement increase to Delta for construction under the
Tenant Reimbursement Agreement by approximately $24M


2

Background
Expansion of lounges will support increased passenger levels with the
opening of the International Arrivals Facility (IAF)
Shared lounge volumes have increased significantly since 2015
(compared to 2019)
a total of 390% in shared use lounges
899% in Concourse A lounge alone
The Club at SEA lounge today is undersized to meet growing demand
On average 861 passengers per month were turned away pre-pandemic
Delta Air Lines constructing an expansion of Concourse A using a TRA
Design of base building approved by Commission on April 27, 2021 and updated
based on the 60% design on December 14, 2021.
3

Concourse A Building Expansion for Lounges



4

Concourse A Building Expansion for Lounges



5

PLB  Maintenance Shop
Rel ocation to 188M Site


N
6

Cost Escalation Categories:
Scope Addition
known and indicated scope additions between 60% and 100% design. Includes the design
development for the Passenger Loading Bridge (PLB) Maintenance shop.
Market Conditions / Global Supply Chain
application of average material and anticipated labor cost escalation; costs reflective of the
challenging bid environment.
Buyout Contingency
additional contingency the contractor has applied to the proposal identifying cost risk until all
trade partners are under contract
Delta & Port Soft Costs
costs associated with design development, design support during construction, and risk
contingencies managed by the Port.

7

Areas of cost increase from 60% Design
Development to Final Design
Increase                   Variance                 Reason for Increase
Maintenance shop replacement, added sitework,
Scope Additions                              $8,000,000     HVAC and electrical scope additions, added
contractor markups
Material price increases, delayed construction
Market Conditions / Global Supply Chain       $8,500,000      start, increased construction schedule, added
contractor markups
Buyout Contingency / Risk Contingency         $5,600,000     Potential risks due to volatile construction market
Increased design fee for scope adds, Delta PM
Delta Soft Costs                                   $800,000
increase
Port Costs                                      $3,600,000      Increased Port management, Port contingency
TOTAL                                  $26,500,000

8

Risks
If design and permitting of the new 188M PLB Maintenance
shop takes longer than anticipated, construction of the
Concourse A expansion could be further delayed.
A longer construction duration within the adjacent Club at SEA
will increase the period for the temporary alternate
accommodation of passenger lounge users.


9

Budget and Schedule
Current Budget        $78,500,000
Requested Budget   $105,000,000
Schedule:
Construction Start         2022 Q3
Construction Finish        2024 Q1

10

Questions?

11

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.