10b. Memo

South Concourse Evolution Project

COMMISSION 
AGENDA MEMORANDUM                        Item No.          10b 
ACTION ITEM                            Date of Meeting      October 25, 2022 

DATE :     October 18, 2022 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Keri Stephens, Director, Aviation Facilities and Capital Programs 
Eileen Francisco, Director, Aviation Project Management 
SUBJECT:  South Concourse Evolution Project Authorization Request 
Amount of this request:                   $100M 
Total estimated project cost:         $1.4B-$1.7B 
ACTION REQUESTED 
Request Commission authorization for the Executive Director to (1) advertise and execute 
project specific contracts for  project management including Airline Technical Representative
(ATR), construction management (CM), design services, and commissioning services to proceed
with  design  of  the  project,  (2)  utilize,  authorize,  advertise,  and  execute  a  General
Contractor/Construction Manager (GC/CM) contract to proceed with pre-construction services
and the delivery of the project, and (3) utilize Port crews for the South Concourse Evolution
Project  at  Seattle-Tacoma  International  Airport.   The  total  amount  of  this  request  is
$100,000,000. 
EXECUTIVE SUMMARY
The South Concourse Evolution project proposes the renovation of the existing South
Concourse,  located  at  Seattle-Tacoma  International  Airport  (SEA),  using  a  multi-phase
implementation strategy. The capital improvement project will extend the useful life of the
South Concourse and meet current code requirements. This includes structural, seismic, and
building system upgrades as well as modernization of passenger spaces. The scope addresses
the Port’s two-tiered objectives: 
(1) Addressing  critical  code  requirements,  including  structural  and  building  systems
upgrades.
(2) Providing enhancements to the passenger experience through a repurposing of the
existing Federal Inspection Service (FIS) area, Concourse Level renovations, and an
expanded Penthouse Level.


Template revised January 10, 2019.

            COMMISSION AGENDA – Action Item No. 10b                                Page 2 of 9
Meeting Date: October 25, 2022 
JUSTIFICATION 
The South Concourse Evolution project has completed the Project Definition Document (PDD) 
and has reached a design milestone of approximately 15% design.  The team is ready to
assemble its full delivery team and to begin full  design and execute the project.  This
commission action will provide the authorization and funding necessary to progress the project
to approximately the 90% design level, at which time the Maximum Allowable Construction
Contract value will be determined. The project team will return in the future for further
authorizations outside of and beyond this authorization. 
Project Delivery Selection: 
The team has selected an alternate delivery method, GC/CM, for this project. The project team
met with stakeholders and analyzed multiple delivery methods and has selected GC/CM as it
has proven to be an effective and successful delivery process for the Port as well as other public
agencies.  This delivery process partners with the designer and the general contractor while
allowing the Port to maintain separate contracts throughout the design and construction of the
project.  Staff are currently developing and preparing to begin procurements for the project
management, design, commissioning, and GC/CM contractor teams to kick-off the design
phase, a collaborative effort.
General Contractor/Construction Management Project Specific Contract:
The GC/CM delivery method will allow for the contractor to be part of the complex design and
intricate construction phasing and sequence development that will minimize risk to airport
operations, provide the highest level of customer service during construction, and gain earlier
insight to and control of construction costs.  The GC/CM is anticipated to aid the team with 
construction techniques,  validating the schedule phasing and sequencing, and preparing 
subcontract packages for the MACC.
Project Management Project Specific Contract:
The team is anticipating hiring an external project management firm with expertise in using the
GC/CM delivery method and with projects of this scope and complexity. The contract will
include a project specific ATR.  ATR’s have played a critical role in successfully delivering
previous mega projects and are recommended to represent the 25 airline carriers that utilize
the South Concourse.  The project would benefit from having a project specific ATR contract
through the life of the project to serve as a liaison between the project and Airlines. Having a 
dedicated ATR engaged through the life of the project is critical to the success of delivering the
project in such ways as decision making, communications, and implementation of plans.
Construction Manager Project Specific Contract:
The team plans to bring on board a CM firm that has expertise using the GC/CM delivery
method and with projects of this scope and complexity. The firm will assist staff in executing
the project from reviewing bid packages, negotiations on schedule and budget for MACC and
other  bid  packages  necessary  to  construct  the  project,  responding  to  contractor

Template revised June 27, 2019 (Diversity in Contracting).

            COMMISSION AGENDA – Action Item No. 10b                                Page 3 of 9
Meeting Date: October 25, 2022 
communication, and assisting the controls teams to provide the necessary metrics to track and
predict the schedule and cost trends.
Design Services Project Specific Contract:
A project specific design consultant will be procured to provide a comprehensive project design
and design support services through the duration of the construction. The design firm selected
will include architecture, structure, mechanical, electrical, civil, specialty, and other design
professionals to complete an aesthetic and seismically compliant concourse for the port to
utilize for many years to come. The design needs to respond to the needs of the infrastructure
and airlines while providing an elegant design for the region. 
Commissioning Manager Project Specific Contract:
The team plans  to  contract with an independent Commissioning Agent. Staff agree a
Commissioning Agent that is independent provides a unique third-party validation that the
design and construction meet the commissioning requirements by building code, building
commissioning authorities, and best practice. The firm selected i s expected to complete the
predesign and design commissioning services required to comply with the United States Green
Building Council LEED requirements for achieving project certification. 
Port Construction Crews:
Port construction crews are requested to support the project by providing construction services
outside of the major contract work. 
This next airport mega project will be a complex, multi-year effort and include regular and
robust engagement and communication with Commission, the public, the airlines, tenants,
staff, and diverse stakeholders. 
Diversity in Contracting 
This project has been proposed to the FAA as a recipient for federal grant funding; in
anticipation of that federal funding, the Port will be following the federal Disadvantaged
Business Enterprise (DBE) program guidelines as stated within CFR 49 Part 26, therefore,
Federal DBE goals will be set on this project.
DETAILS 
The South Concourse Evolution project scope includes structural, seismic, and building system
upgrades as well as modernization of passenger spaces.  The Port’s two-tiered objectives,
addressing critical code requirements, including structural and building systems upgrades; and
providing enhancements to the passenger experience  through the lower levels  and an
expanded Penthouse for Lounges.  The following are some focus areas that will be essential to
the success of the project as the team progress the design: 
(1) Partnership and collaboration.

Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 10b                                 Page 4 of 9 
Meeting Date: October 25, 2022 
(2) Structural and seismic engineering married with a constructable design concept. 
(3) Passenger flow, comfort, and communication. 
(4) Phasing and sequencing of a constrained site and airport impact. 
(5) infrastructure resilience. 
(6) Customer service and operational continuity during construction. 
(7) Ability to construct to budget and schedule. 
(8) The desired customer experience of blended holdrooms with dining and retail
options. 
(9) Collaborating with numerous public agencies and the community. 
(10) Implementing the evolution of the South Concourse to balance with surrounding
terminals. 
(11) Developing the team that can bring forward creative alternatives to reduce the
project cost. 
The airport is challenged to provide the airlines appropriate services while construction is
underway. The project scope and budget has assumed the airport can support a gate outage
strategy allowing for a two-phase project.  Staff have been exploring different alternatives to
provide the best customer experience during construction from an airport wide perspective.
The ability of the airport to support this endeavor has not been identified in detail. Temporary
and permanent solutions have been proposed but more effort, collaboration and partnership
are required with our airline partners, stakeholders, and other programs to assure success with
this project.  Staff is working on a gating strategy that addresses the airport wide gating and
phasing concerns of the airport and airline community. 
The project is currently at 15% design. More design development is needed to understand the
scope, schedule, budget and sustainability initiatives.  Staff conducted the Sustainable Project
Assessment and Review Collaboration meeting and developed the Sustainable Design Approach
document for the project. Sustainability strategies were identified for further analyses during
both PDD development and design, including a total cost of ownership analysis. The project
team will evaluate the environmental benefits and total cost of ownership for following
strategies: 
(1) Reducing solar heat gain. 
(2) Providing on-site food collection to support our food donation program. 
(3) Installing dishwashing utility connections to encourage reusable service ware. 
(4) Adding power to service new electric vehicle charging stations. 
(5) Reducing embodied carbon in construction materials, specifically concrete. 
(6) Integrating electric cooking to reduce natural gas use. 
(7) Reducing potable water use 10 and 20 percent below 2018 State Plumbing code. 
(8) Achieving LEED Silver Certification at minimum and the feasibility of achieving Gold. 


Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 10b                                 Page 5 of 9 
Meeting Date: October 25, 2022 
The project team will present the results of these analyses and recommendations to the
Commission's Sustainability, Environment And Climate (SEAC) Committee for review and
comment prior to 30% design. 

Project Schedule 
The team‘s near term focus will be on: 
(1) Assembling a full, qualified team of professionals and contractors to deliver this next
airport mega project. 
(2) Solidifying the management plans and procedures that will be used to ensure its
successful and collaborative execution. 
Launch PM Support (including the ATR liaison),         2022 Quarter 4 
Design, GC/CM, and Commissioning team
procurements 
Execute Project Management Plan                    2023 Quarter 2 
Execute contracts for delivery team to start            2023 Quarter 4 
design/pre-construction phase 
Start design/pre-construction phase                   2023 Quarter 4 

The team‘s current overall project schedule: 
Design complete                                     2025 Quarter 2 
Commission Authorization for MACC                  2025 Quarter 2 
Early Construction Work                               2026 Quarter 3 
Construction Phase 1                                 2029 Quarter 1 
Construction Phase 2                                  2031 Quarter 2 
Construction complete                               2031 Quarter 4 

Project Budget 
The current estimate is based on the programmatic scope of work defined in the Project
Definition Document (PDD), which has a level of detail equivalent to approximately 15% design.
The estimated cost includes allowances and contingencies.    Project risks, operational
mitigations, and environmental objectives will be further developed and are deferred to the
design once professionals are on board.   The level of detail for the estimate is normal and
customary at this stage of the project.
Current Estimate Range: $1.4B – $1.7B. 

Template revised June 27, 2019 (Diversity in Contracting).

            COMMISSION AGENDA – Action Item No. 10b                                Page 6 of 9
Meeting Date: October 25, 2022 
Cost Breakdown                                     This Request           Total Project 
Design Phase                                               $100M                $100M 
Construction Phase                                              $0             $1.3B-1.6B 
Total                                                              $100M              $1.4B-1.7B 

ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Various refinements of the 15% design were explored over the last year in preparing this design
option to be presented.  Port staff has evaluated design options for levels, passenger flow,
customer experience of the final building, and the return on investment of non-aeronautical
revenues to develop the club and ADR requirements for the project. A summary of different 
alternatives follows: 
Alternative 1 – A fully developed interior and exterior clerestory system provides for
daylighting throughout the concourse and a more refined mass exterior matches the exterior
façade areas high roof building mass of the N Concourse and the International Arrivals Facility. 
Cost Implications: $2.2B 
Pros:
(1)   Provides for daylighting of the entire concourse level.
(2)   Complies with the business plans of the concourse.
(3)   Meets the program goals for the airport.
Cons:
(1)   Anticipated costs cannot be supported by the business plans for the concourse.
This is not the recommended alternative. 
Alternative 2 – Improve only the critical code requirements, including structural and building
systems upgrades. 
Cost Implications: $1B 
Pros:
(1)   Complies with the business plans of the concourse.
Cons:
(1)   Does not meet the program goals for the airport.
This is not the recommended alternative. 

Template revised June 27, 2019 (Diversity in Contracting).

            COMMISSION AGENDA – Action Item No. 10b                                Page 7 of 9
Meeting Date: October 25, 2022 
Alternative 3 – Complete the project as presented in the PDD document.
Cost Implications: $1.4B-1.7B 
Pros:
(1)   Complies with the business plans of the concourse.
(2)   Meets the program goals for the airport.
Cons:
(1)   Does not fully commit the concourse to daylighting into the center of the facility on
the east and center areas. 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
The initial placeholder value for the project in 2020 was $1B, the current estimate range is
expected to be $1.4-1.7B.
Cost Estimate/Authorization Summary                 Capital     Expense            Total 
COST ESTIMATE 
Original estimate                                $1,000,000,000           $0   $1,000,000000 
Previous changes – net                            $370,00,000            0    $370,000,000 
Current change                                                          0                0 
Revised estimate                                 $1.4B - $1.7B            0     $1.4B - $1.7B 
AUTHORIZATION 
Previous authorizations                             $2,750,000            0       $2,750,000 
Current request for authorization                 $100,000,000            0    $100,000,000 
Total authorizations, including this request        $102,750,000             0    $102,750,000 
Remaining amount to be authorized                     TBD          $0             TBD 
Annual Budget Status and Source of Funds 
This project, CIP C801203, was included in the 2022-2026 capital budget and plan of finance
with a budget of $1 billion. A budget increase of $370,000,000 was transferred from the
Aeronautical Reserve CIP (C800753) resulting in zero net change to the Aviation capital budget.
The funding source would be revenue bonds, Airport Development Fund (ADF), and the
Bipartisan Infrastructure Law (BIL) grant funding through the FAA-AIP program. 
Financial Analysis and Summary 
Business Unit (BU)               Terminal       Terminal
Building         Building 
Project cost for analysis                   $1.4B           $1.7B 
Infrastructure grants                    $250M          $250M 
NPV incremental to Base              $(4.8)M        $(136)M 

Template revised June 27, 2019 (Diversity in Contracting).

            COMMISSION AGENDA – Action Item No. 10b                                Page 8 of 9
Meeting Date: October 25, 2022 
Non-aero cashflow in 2031            $(5.4)M       $(12.5)M 
Non-aero cashflow positive       In year 2038    In year 2044 
CPE Impact in 2031                     $2.24           $2.92 
The financial analysis looked at the implications of this project on both the aeronautical and
non-aeronautical businesses.  For the aeronautical business, this project will add significant
costs (primarily debt service on the bonds to fund the project) to the airline rate base, resulting
in an increase to the passenger airline cost per enplaned passenger (CPE). The project will also
allocate significant costs to the non-aeronautical business as a result of the space attributable
to airport dining and retail.   The table  above shows a net present value (NPV) of the
incremental net revenues compared to the costs for the non-aero business. At $1.4 billion, the
NPV is slightly negative. At $1.7 billion the NPV is much more negative. The other measure we
look at is non-aeronautical cash flow inclusive of the allocated debt service. This is important as
an indicator of the project’s impact on airport debt service coverage.  The result will be
negative cash flow in the early years, going positive in 2038 at $1.4 billion, and 2044 for $1.7
billion.  Consequently, the project will reduce airport debt service coverage for many years. 
The analysis above assumes the project receives $250 million of grant funding.  More grant
funding would improve the financial results.
Future Revenues and Expenses (Total cost of ownership) 
The cost savings of keeping the current terminal operational would likely present no long-term
savings even with discounting the risk of a potential catastrophic failure; the terminal is still in
need of upgrades driven by code and safety. Balancing the deferral of these costs against the
structural, seismic, and operational needs of the terminal is not recommended. 
ADDITIONAL BACKGROUND 
The South Concourse facility at SEA was opened in 1973 and is owned and operated by the
Port. The facility depends on building systems that are well past their useful service life,
and further development of the facility has been limited by the authorities having jurisdiction,
owing to concerns stemming from current building code minimum requirements. The building
systems  and  materials  used  in  the  original  construction, due  to  their  age  and
manufacture, are difficult to maintain.  The facility also contains areas of encapsulated
regulated materials, such as asbestos, complicating maintenance, renovation, and
development.  Since the South Concourse was constructed, passenger volumes and aircraft
operations have increased dramatically, security regulations have expanded, passenger level of
service expectations have evolved, and airlines and retailers have changed their marketing
strategies.  Recently, the South Concourse was connected directly to the new International
Arrivals Facility (IAF) across the taxi lane separating it via an above ground pedestrian walkway. 
The project will connect the continuity of design from the IAF and walkway to this project for a
seamless continuous terminal aesthetic. 


Template revised June 27, 2019 (Diversity in Contracting).

            COMMISSION AGENDA – Action Item No. 10b                                Page 9 of 9
Meeting Date: October 25, 2022 
ATTACHMENTS TO THIS BRIEFING 
(1)   Presentation slides. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
September 27, 2022 - The Commission was briefed on South Concourse Evolution and
project status. 
April 13, 2021 – The Commission was briefed on SSAT Renovation Renewal PDD. 















Template revised June 27, 2019 (Diversity in Contracting).



Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.