Tyee Pond Effluent Pipe Replacement
COMMISSION AGENDA MEMORANDUM Item No. 8f ACTION ITEM Date of Meeting November 14, 2023 DATE: November 7, 2023 TO: Stephen P. Metruck, Executive Director FROM: Keri Stephens, Director, Aviation Facilities & Capital Programs Eileen Francisco, Director, Aviation Project Management Group SUBJECT: Tyee Pond Effluent Pipe Replacement (C801173) Amount of this request: $2,275,000 Total estimated project cost: $2,900,000 ACTION REQUESTED Request Commission authorization for the Executive Director to take all steps necessary to complete the Tyee Pond Effluent Pipe Replacement project at Seattle-Tacoma International Airport (SEA). This request is in the amount of $2,275,000 for a total authorization of $2,900,000. EXECUTIVE SUMMARY The Tyee Pond stormwater pond and its control structures are a regional detention facility that the Port of Seattle owns, maintains, and operates. This detention facility is regulated by the Department of Ecology (DOE) Dam Safety Program. The downstream effluent pipe is over 30 years old and shows signs of damage and deterioration. The pipe must be replaced to ensure that the detention facility and downstream effluent pipe can function as designed for the next 50 years. Emergency repairs have already been needed and DOE issued a requirement for a permanent repair to be completed by 2025. JUSTIFICATION This project will support the following Century Agenda goals to be the greenest and most energyefficient port in North America by meeting or exceeding agency requirements for stormwater leaving Port-owned or operated facilities. In December 2021, a pipe assessment was completed that examined the existing pipe downstream of the repaired section (approximately 382 linear feet). The Pipe Assessment Report noted joint separation, deformation, and corrosion in the downstream pipe and recommended replacing the entire pipe. If the pipe completely fails, the hydraulics of Des Moines Creek will be affected impacting the downstream salmon bearing creek habitat. In the worst-case scenario, with the detention facility at full capacity, the pipe failure can result in the failure of the Tyee Template revised January 10, 2019. COMMISSION AGENDA – Action Item No. 8f Page 2 of 4 Meeting Date: November 14, 2023 Pond embankment sending several thousand gallons of stormwater towards downstream residents adjacent to Des Moines Creek in an uncontrolled fashion. Diversity in Contracting The design of this project utilized an existing indefinite delivery indefinite quantity (IDIQ) contract that has an established WMBE commitment of 10%. The project team will work with Diversity in Contracting establish the WMBE goal for the major works construction contract. DETAILS Tyee Pond is located south of SEA and is located on the east fork of Des Moines Creek flowing south from Bow Lake. The pond has a capacity of 19.7 acre-ft and is therefore regulated by DOE Dam Safety program. The pond and effluent pipe were originally constructed in the late 1980’s. In 2020, emergency repairs were made to a small section of the pipe (approximately 32 linear feet) that was leaking and causing sinkholes to appear on the pond embankment above the pipe. DOE accepted the interim repairs but required a permanent repair by 2025. During project definition the project scope was revised to reflect the actual shorter pipe length, and a full pipe replacement instead of relining using the cured-in-place pipe method. These changes resulted in $251,000 in project savings. The project has completed the environmental permitting requirements with DOE and the U.S. Army Corps of Engineers. This has led to additional regulatory requirements that has increased the project cost by $360,000 and delayed construction to the 2024 fish window. Scope of Work The project will replace the entire downstream effluent pipe with a 72-inch diameter reinforced concrete pipe. In addition, two manhole structures will be added to the northern section of the pipe to provide energy dissipation. Schedule Construction start 2024 Quarter 2 In-use date 2024 Quarter 4 Cost Breakdown This Request Total Project Design $0 $625,000 Construction $2,275,000 $2,275,000 Total $2,275,000 $2,900,000 Template revised June 27, 2019 (Diversity in Contracting). [Annotation] Mathews, Stuart Is it really worth having this as an alternative, since it is in now way viable? I get we like to have 3 alternatives, but we try to avoid alternatives that are not viable, and as we are under a requirement by DOE to make the repair, we don't have a choice to not do the improvements. I would just go with two alternatives in this case. [Annotation] Bornhorst, Heather @Mathews, Stuart We have this debate quite a lot but we are always told to include the no action. [Annotation] Cox, Sarah Does item #3 in Alternative 2 not apply here? [Annotation] Bornhorst, Heather @Cox, Sarah Comment addressed COMMISSION AGENDA – Action Item No. 8f Page 3 of 4 Meeting Date: November 14, 2023 ALTERNATIVES AND IMPLICATIONS CONSIDERED Alternative 1 – No Improvements Cost Implications: $0 Pros: (1) Requires no capital investment. Cons: (1) Does not address integrity of Tyee Pond dam required by DOE to perform permanent repairs by 2025. (2) Does not address long-term viability of the storm water infrastructure. (3) Potential to damage downstream salmon bearing creek habitat and residents (and trigger fines). This is not the recommended alternative. Alternative 2 – Utilize the bypass system. Cost Implications: $702,000 Pros: (1) Requires less capital investment. Cons: (1) Does not address integrity of Tyee Pond dam required by DOE to perform permanent repairs by 2025. (2) Does not address long-term viability of the storm water infrastructure. (3) Potential to damage downstream salmon bearing creek habitat and residents (and trigger fines). This is not the recommended alternative. Alternative 3 – Replace the effluent pipe. Cost Implications: $2,900,000 Pros: (1) Permanent solution ensuring Tyee Pond dam integrity. (2) Offers maximum stormwater flow control from the Tyee Pond. (3) Doesn’t adversely impact flow to downstream salmon bearing creek. (4) Fulfills DOE Dam safety regulatory obligations. Cons: (1) Requires greater capital investment. This is the recommended alternative. Template revised June 27, 2019 (Diversity in Contracting). [Annotation] Jason Olson Do we mention anywhere what this deduction was? [Annotation] Bornhorst, Heather The notebook approval included these changes - change in pipe length (shorter) and change from relining to replacing. We did not discuss this in the memo. [Annotation] Olson, Jason Yes, but might be worth a mention in the memo somewhere just in case someone asks. We do mention the $360K above, so I get why we can't combine. [Annotation] Nguyen, Hanh Is there a signed IC form for the budget increase? COMMISSION AGENDA – Action Item No. 8f Page 4 of 4 Meeting Date: November 14, 2023 FINANCIAL IMPLICATIONS Cost Estimate/Authorization Summary Capital Expense Total COST ESTIMATE Original estimate $2,791,000 $0 $2,791,000 Previous changes – net ($251,000) $0 ($251,000) Current change $360,000 $0 $360,000 Revised estimate $2,900,000 $0 $2,900,000 AUTHORIZATION Previous authorizations $625,000 $0 $625,000 Current request for authorization $2,275,000 $0 $2,275,000 Total authorizations, including this request $2,900,000 $0 $2,900,000 Remaining amount to be authorized $0 $0 $0 Annual Budget Status and Source of Funds This project CIP #801173 was included in the 2023-2027 capital budget and plan of finance as a budget of $2,540,000. A budget increase of $360,000 was transferred from the Aeronautical Allowance (CIP #800753) resulting in a zero-net change to the Aviation capital budget. The funding sources for this project will be the Airport Development Fund (ADF) and revenue bonds. Financial Analysis and Summary Project cost for analysis $2,900,000. Business Unit (BU) Airfield Movement Area. Effect on business performance NOI after depreciation will increase due to inclusion of (NOI after depreciation) capital (and operating) costs in airline rate base. IRR/NPV (if relevant) N/A. CPE Impact $0.01 in 2025. Future Revenues and Expenses (Total cost of ownership) Operations and maintenance costs are anticipated to be minimal. The pipe will be video inspected once every 3-5 years. ATTACHMENTS TO THIS REQUEST (1) Presentation. PREVIOUS COMMISSION ACTIONS OR BRIEFINGS April 26, 2022 – The Commission authorized an additional $390,000 for design. Template revised June 27, 2019 (Diversity in Contracting).
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.