8f. Presenters

Waterfront Smart Meters Phase 1

Item No: 8f_supp
Meeting date: September 10, 2024
Waterfront Smart Meters Phase 1
Smart Meter Installation
Design Authorization
William Shelton - Capital Project Manager
Sarah Ogier- Director Maritime Environment and Sustainability
Jennifer Maietta - Director Real Estate Asset Management (Sponsor)
CIP # C801269
Project # N10380
Overview
• Action Requested
• Justification
• Project Location
• Project Scope
• Risks and Opportunities
• Preliminary Schedule
• Funding
2
Action Requested
Request Commission authorization for the Executive Director to:
1. Authorize completion of design and permitting for the
Waterfront Smart Meter Phase 1 project
Project Estimated Cost: $2,500,000
Design Authorization Request: $350,000
3
Justification
•
•
•
•
•
•
Supports Port of Seattle's Century Goal to be the greenest, most energy
efficient port in North America.
Needed to meet city and state energy and greenhouse gas reporting
requirements.
Provide transparent calculation of Energy Use Intensity to meet WA Clean
Building Performance Standard.
Will support cost recovery in the form of incentives for any Energy Efficiency
Measures that need to be implemented.
Provide efficient and safe energy-use data gathering and monitoring.
Better able to plan future building energy efficiency projects.
4
Project Location
Marine
Maintenance A1
World Trade
Center West
Pier 66
Fishermen's
Terminal C15
Terminal 91 C175
Terminal 91 Smith Cove
Cruise Terminal
5
Project Location
Terminal 91 C175
World Trade
Center West
Marine
Maintenance A1
Marine Maintenance A1
Terminal 91 Smith Cove
Cruise Terminal
Terminal 91 C175 & Terminal 91 Smith Cove
Cruise Terminal
Pier 66 Conference Center
and Cruise Terminal
Fishermen's
Terminal C15
World Trade Center West & Pier 66 Conference
Center and Cruise Terminal
Fishermen's Terminal C15
6
Project Scope
•
Port Construction Services (PCS) will install 25 electrical and natural gas smart meters at the following locations
-
-
-
-
-
-
•
•
•
•
Pier 66 Cruise and Conference Center
Terminal 91 Smith Cove Cruise Terminal
Terminal 91 Building C175
World Trade Center West
Marine Maintenance Building A1
Fishermen's Terminal Building C1
Install network infrastructure and integrate meters into Port of Seattle Energy Management System (EMS)
This is year 1 of a multi-year program to install smart meters throughout Port of Seattle waterfront facilities.
New buildings will be identified and prioritized each year based on regulatory compliance and impact.
Buildings for year 1 were selected and prioritized due to their building footprint size and use to meet upcoming
Washington Clean Building Performance Standards.
This project requires significant cross departmental and divisional engagement with Port Engineering, ICT,
Environment and Sustainability, and others.
7
Risks and Opportunities
•
RISKS
DESCRIPTION
Long Lead Items
Current estimated delivery time for smart meters is 6 weeks.
This may increase over the coming months
Power and Natural Gas
Outages
Installation of meters will require outages to natural gas and
electricity which may impact tenant operations
Interruptions to
buildings/operations
Installation of conduit may occur in retail, cruise or other client
facing spaces which may disrupt tenant business
PROBABILITY
IMPACT
MITIGATION
Medium
Medium
Monitor lead times for smart meters. Port of Seattle
High
Schedule outages during non-standard working
hours and only perform work that needs to be done
during the outage to minimize impact to tenants
Medium
Perform work at cruise terminal outside of cruise
season. For meters which are located far away from
the network gateway, consider using an LTE
connection.
High
High
Overall, smart meter installation has a low and manageable risk with significant benefits when complete.
8
Preliminary Schedule
Design Start (30%)
Commission design authorization
Commission construction authorization
Construction start
In-use date
February 2024
September 2024
January 2025
2025 Quarter 2
2026 Quarter 1
9
Funding
Cost Estimate/Authorization Summary
Capital
Expense
Total
COST ESTIMATE
Original estimate
$3,300,000
$0
$3,300,000
Current change
$(800,000)
0
$(800,000)
Revised estimate
$2,500,000
0
$2,500,000
Previous authorizations
$125,000
0
$125,000
Current request for authorization
$350,000
0
$350,000
Total authorizations, including this
request
Remaining amount to be authorized
$475,000
0
$475,000
$2,025,000
$0
$2,025,000
AUTHORIZATION
10
Questions?
11

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.