8j. Memo
Air Cargo Buildings and Access Controls
COMMISSION AGENDA MEMORANDUM Item No. ACTION ITEM Date of Meeting DATE: September 5, 2024 TO: Stephen P. Metruck, Executive Director FROM: Eileen Francisco, Director Aviation Project Management Group Wendy Reiter, Director Aviation Security 8j September 10, 2024 SUBJECT: Air Cargo Buildings 167A and 167B Access Controls (CIP# C801288) Amount of this request: Total estimated project cost: $ 500,000 $2,500,000 ACTION REQUESTED Request Commission authorization for the Executive Director to increase the budget of the Air Cargo Building 167A/B Access Controls project at Seattle-Tacoma International Airport for a total estimated project cost of $2,500,000. The amount of this request is $500,000. EXECUTIVE SUMMARY Extending bussed hard stand passenger service operations to Cargo 5 has expanded the Airport's Secured Area to include Air Cargo Building 167A and 167B, as defined and regulated by the Transportation Security Administration (TSA). These buildings are owned by the Port and leased to tenants. To comply with Secured Area regulations, this project is installing the Airport's Access Control system at doors providing access to the Secured Area. This work will require support infrastructure connecting back to the Airport's Main Terminal. During design, deficiencies in both the building's electrical capacity and its connectivity to the Main Terminal have resulted in scope development that has increased the project estimate and require additional budget to complete the project. JUSTIFICATION To meet TSA security regulations, this project will provide the Airport's Access Control System to manage doors that connect the interior of the building to the Airport's Secured Area. Users will be required to use Airport issued identification badges to gain access similar to other secured areas. As the project team advanced the design of the project, and a more thorough review of existing conditions occurred, it became apparent that the buildings' existing electrical service and the proposed data pathway to connect to the Main Terminal could not support the project. This has resulted in scope additions to the project that could not be absorbed within the current project budget. Template revised January 10, 2019. COMMISSION AGENDA - Action Item No. 8j Meeting Date: September 10, 2024 Page 2 of 4 Diversity in Contracting For design, the Indefinite Delivery Indefinite Quantity (IDIQ) designer has a 25% Women and Minority Business Enterprise (WMBE) goal and for this project is achieving a 49% participation. For construction, the project team will utilize an existing Job Order Contract, which has a 6.3% goal. DETAILS Scope of Work This project will install the Port's access control system at doors that provide access to the Secured Area from this building. This project will also provide all required infrastructure including power and communications to support the access control system. Schedule This project experienced schedule delays due to resource limitations needed for other prioritized work, and labor availability. Activity Design start Construction start In-use date Cost Breakdown Design Construction Total 2023 Quarter 2 2024 Quarter 3 2025 Quarter 2 This Request $0 $500,000 $500,000 Total Project $600,000 $1,900,000 $2,500,000 ALTERNATIVES AND IMPLICATIONS CONSIDERED As it became apparent that the design had to change, the project team evaluated several alternatives to minimize cost growth, including scope reduction (eliminating Access Control to one door) and alternative sources of electrical power and data connectivity. Alternative 1 - Refurbish and reuse existing telecom cabinets Cost Implications: $450,000 additional funding Pros: (1) (2) Save $50,000 material cost Schedule savings: Refurbishment may take less time than procurement Cons: (1) (2) Additional design effort to determine fit Additional installation effort to adjust to fit Template revised June 27, 2019 (Diversity in Contracting). COMMISSION AGENDA - Action Item No. 8j Meeting Date: September 10, 2024 (3) Page 3 of 4 Refurbished cabinets may be more susceptible to leaks This is not the recommended alternative. Alternative 2 - Proceed with the project as planned with new telecom cabinets Cost Implications: $500,000 additional funding Pros: (1) (2) (3) Completes construction as planned Allows the building to meet regulatory requirements. Provides additional project contingency to address remaining project risks Cons: (1) Higher cost than Alternative 1 This is the recommended alternative. FINANCIAL IMPLICATIONS Cost Estimate/Authorization Summary Capital Expense Total COST ESTIMATE Original estimate Previous changes - net Current change Revised estimate $592,000 $2,000,000 $500,000 $2,500,000 $0 $0 $0 $0 $592,000 $2,000,000 $500,000 $2,500,000 AUTHORIZATION Previous authorizations Current request for authorization Total authorizations, including this request Remaining amount to be authorized $2,000,000 $500,000 $2,500,000 $0 0 0 0 $0 $2,000,000 $500,000 $2,500,000 $0 Annual Budget Status and Source of Funds The Air Cargo Building 167A/B Access Controls #C801288 was included in the 2024-2028 capital budget and plan of finance with a budget of $2,000,000. The capital budget increase of $500,000 was transferred from the Aeronautical Allowance CIP C800753 resulting in no net change to the Airport capital budget. The funding source will be the Airport Development Fund. Template revised June 27, 2019 (Diversity in Contracting). COMMISSION AGENDA - Action Item No. 8j Meeting Date: September 10, 2024 Financial Analysis and Summary Project cost for analysis Business Unit (BU) Effect on business performance (NOI after depreciation) IRR/NPV (if relevant) CPE Impact Page 4 of 4 $2,500,000 Airfield Commercial Area NOI after depreciation will decrease NPV of ($2,218,000) N/A Future Revenues and Expenses (Total cost of ownership) As a result of this project, Aviation Maintenance anticipates an increase in ongoing operations and maintenance for Electronic Systems. Maintenance for the additional cameras, biometric card readers and intercoms will amount to roughly 50 additional labor hours annually. The cost at 2024 rates is roughly $5,500. ATTACHMENTS TO THIS REQUEST None PREVIOUS COMMISSION ACTIONS OR BRIEFINGS March 14, 2023 - The Commission authorized complete design and construction of the Air Cargo Building 167A/B Access Controls project at Seattle-Tacoma International Airport for a total estimated project cost of $2,000,000. Template revised June 27, 2019 (Diversity in Contracting).
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.