4b

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA               Item No.      4b 
ACTION ITEM 
Date of Meeting      July 12, 2016 
DATE:    June 27, 2016 
TO:      Ted Fick, Chief Executive Officer 
FROM:   Jeffrey Brown, Director, Aviation Facilities and Capital Program 
Wayne Grotheer, Director, Aviation Project Management Group 
SUBJECT:  C60 Interim Baggage Handling System Project (CIP #C800825) 
Amount of This Request:             $0   Source of Funds:   Airport Development
Fund 
Est. Total Project Cost:         $14,200,000 
Est. State and Local Taxes:        $579,000 

ACTION REQUESTED 
Request Commission authorization, in accordance with Section 4.2.3.4 of the General Delegation
of Authority, for the Chief Executive Officer to execute a major public works construction
contract with the sole responsive and responsible bidder to perform the C60 Interim TSA Search
Room Expansion/Enhancement Project at Seattle-Tacoma International Airport previously
authorized on January 12, 2016. 
SYNOPSIS 
This action approves the bid for this project. The bid is less than the engineer's estimate and the
project is within budget. Per the General Delegation of Authority, Section 4.2.3.4, because the 
bid was the only bid received, it is necessary for Commission approval. 
The Commission approved design and procurement of this project on December 8, 2015. The
Commission also authorized the advertisement and execution of a major public works contract
for this project on January 12, 2016. The TSA Search Room Expansion/Enhancement work
element bid was opened and found to be irregular, as there was only a single bidder, on June 16,
2016. The single bid, received from a qualified bidder, is in the amount of $5,428,522, which is
ten percent (10%) less than the engineer's estimate of $6,055,000. As this work is considered
necessary to meet the airlines' growth and baggage handling demands, the project team
recommends accepting the current bid and authorizing execution of a major works contract with
the sole responsible bidder. At this time there is no change to the C60 Interim project budget due
to remaining project uncertainties. 


.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
June 27, 2016 
Page 2 of 6 
BACKGROUND 
The C60 system was in the process of being assembled as part of the South Terminal Expansion
Program (STEP) including construction of Concourse A when the events of September 11, 2001,
occurred. As a result, the bag screening capability of C60 was dramatically and rapidly built to
meet federal requirements while those requirements were still being developed. C60 was one of
the first operational in-line baggage scanning systems in the country. As new systems were built
and brought on line here in Seattle, lessons learned and best practices were added to avoid some
of the challenges that accompanied the C60 system design. 
Due to C60 capacity and performance issues during the summer of 2015, impacts to airline
customers have occurred, including delayed flights, delayed baggage, and customer
dissatisfaction. Delta Air Lines has indicated that the baggage system in Seattle is of great
importance to them as they grow their operation. Other airline users of the C60 system have
expressed similar concerns because of the impacts to their operations. Improving and upgrading
the security tracking-zone will bring value to the overall operation. This project is critical to
addressing airline's concerns as we move towards the next summer season. 
PROJECT JUSTIFICATION AND DETAILS 
This project, consisting of four distinct work elements, is focused on addressing the most urgent
C60 baggage system challenges. These elements are being proposed to meet interim baggage 
capacity needs prior to optimization. This authorization request is specifically to improve the
TSA search room and related components. 
Interim improvement projects are necessary to keep up with airline customers' rapid growth of
flights and passengers prior to when the Baggage Optimization project will affect this portion of
the airport. Meetings with both airline and TSA leadership and their respective technical staff
teams from across the country confirm that these interim elements are necessary. 
The urgency of this work is very high. The Port's airline customers have demanded that the
Airport find solutions to the frequent disruptions to their operations they experienced during the
summer of 2015, and be prepared to handle an even larger volume of passengers on the system in
2016. The elements of this project are designed to address these concerns. 
Project Objectives 
The project is necessary for the following reasons: 
The C60 baggage system has exceeded capacity during peak operations; 
Twelve airlines regularly use C60 for normal operations and all airlines may use it for
irregular operations; 
Delta Air Lines, the largest user of C60, intends to grow their operation for the next
several years including adding 33 flights to the 2016 summer schedule; 
Baggage Optimization will not be ready to replace the C60 system for several years  
estimated date of completion is 2023; 

Revised March 28, 2016  pjw

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
June 27, 2016 
Page 3 of 6 
Scope of work 
There are four work elements currently included in the C60 Interim Baggage Handling System
Project, one of which is a major construction contract. The status of these four work elements is: 
1.  The Baggage Input Load Balancing element adds crossover TX-4/TC9-OB1, which
allows for better utilization between two screening loops in the system and improves
efficiency. This element has been completed and in use since May 2016. This scope
element had an estimated cost of $970,000. 
2.  The TSA Search Room Expansion/Enhancement element will increase the TSA search
room capacity; eliminate a single point of failure; incorporate reinsertion/rescreening
equipment; and will improve the overall system functionality. This scope element has an
estimated cost of $7,730,000. New search tables to be utilized in this project will be
purchased by the Baggage Optimization Phase 1 construction authorization. The tables
will be temporarily utilized in the TSA Search Room Expansion/Enhancement project
until Phase 4 of Baggage Optimization. The subject of this authorization request is
accepting the current bid and authorizing execution of a major works contract with the
sole responsible bidder for this element of work. 
3.  The Security Zone Tracking Enhancements element will reduce error bags sent to the
TSA search room and improve the overall system capability and tracking. This element
has three sub components: 1) Slope Modifications to the exits of the Explosive Detection
System machines on seven (7) screening lines; this work has been completed and in use
since April 2016; 2) Photo eye and Encoder replacement and relocation work will be
completed by December 2016; 3) Re-control of the C60 baggage handling system will be
completed by June 2017. This scope element has an estimated cost of $5,200,000. 
4.  The Clear Bag Reconciliation Scanners element was cancelled due to TSA's security
concerns and will not move forward. This scope element had an estimated cost of
$300,000. 
Schedule 
The baseline goal of this project was to complete design and construction of all elements prior to
summer peak 2016 (Q3), or as soon thereafter as possible. As detailed above, we have met this
summer 2016 goal for some but not for all project elements. Immediately authorizing this
irregular bid may allow the TSA search room project element to be substantially completed 
before the end of 2016. 
FINANCIAL IMPLICATIONS 
Budget/Authorization Summary           Capital      Expense    Total Project 
Original Budget                     $14,200,000          $0   $14,200,000 
Previous Authorizations                $14,200,000          $0   $14,200,000 
Current request for authorization                  $0          $0          $0 
Total Authorizations, including this request    $14,200,000          $0    $14,200,000 
Remaining budget to be authorized               $0          $0          $0 
Total Estimated Project Cost             $14,200,000          $0   $14,200,000 

Revised March 28, 2016  pjw

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
June 27, 2016 
Page 4 of 6 
Project Cost Breakdown                  This Request        Total Project 
Design Phase                                   $0        $4,599,000 
Construction Phase                                $0        $9,022,000
State Tax                                       $0          $579,000 
Total                                           $0         $14,200,000 
Budget Status and Source of Funds 
This project was not included in the 2016-2020 capital budget and plan of finance. After the
2015 summer peak season, during which the C60 baggage system was regularly pushed to the
breaking point, staff worked to identify solutions to the most critical problems. The budget for
this project (C800825 was transferred from the aeronautical allowance CIP (C800404) resulting
in no net change to the Aviation Division capital budget. Since the expected average life of the
assets will be approximately seven years (until replaced by the Baggage Optimization project),
the funding source will be the Airport Development Fund.
From project conception to expected completion, the C60 Interim project was designed to move
at a rapid pace. The aggressive project schedule inherently carries high risks with scope,
schedule, and budget. Work elements completed to date have been under budget and the TSA
Search Room Expansion/Enhancement bid came in under the Engineer's Estimate; however, the
project team is recommending the total project budget of $14.2 million remain the same until
further progress has been made. The remaining scope elements that have yet to be completed are 
considered high risk elements due to the complexity of the scope of work and uncertainty
surrounding required TSA testing. 
Financial Analysis and Summary 
CIP Category             Renewal/Enhancement 
Project Type              Infrastructure Upgrades 
Risk adjusted discount rate     N/A 
Key risk factors             N/A 
Project cost for analysis        $14,200,000 
Business Unit (BU)          Baggage Equipment cost center 
Effect on business performance  NOI after depreciation will increase (capital costs added
to airline rate base, amortized over 7 years) 
IRR/NPV             N/A 
CPE Impact             $.09 in 2017 
Lifecycle Cost and Savings 
These elements are not anticipated to add significant cost or savings to the Aviation Maintenance
budget. It is anticipated these elements will improve system performance as their primary
objective. Staff recognizes the shorter useful life of these elements and is adjusting the
amortization period accordingly. 

Revised March 28, 2016  pjw

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
June 27, 2016 
Page 5 of 6 
STRATEGIES AND OBJECTIVES 
This project promotes the Port's Century Agenda objectives to make Sea-Tac Airport the West 
Coast "Gateway of Choice" for international travel, meet the region's air transportation needs at
Seattle-Tacoma International Airport for the next 25 years, and encourage the cost-effective
expansion of domestic and international passenger and cargo services. 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  Maintain status quo; do not award or proceed with the TSA Search Room
project element. 
Cost Implications: The design phase costs (approximately $415,000) for this scope element
would be expensed. 
Pros: 
(1)  No construction activity is required. 
(2)  Not performing the work eliminates the associated operational impacts to airlines,
TSA, and Port operations during the construction phase. 
(3)  Less capital expenditure will be required. 
Cons: 
(1) Not pursuing this work will result in the capacity and throughput of the TSA search
room remaining the same as the current state. Customer service will continue to suffer. 
(2) The current search room is considered a significant limitation to the system during 
peak operations. 
(3) Performance of the system during heavy load operations will continue to be degraded 
as growth continues. 
This is not the recommended alternative. 
Alternative 2  Cancel the bid and re-bid under the assumption that additional contractor interest
can be achieved. This alternative assumes that future contractor outreach and/or an extension of
the contract duration may result in more bidders than the previous effort. 
Cost Implications: Additional Port soft costs. Potential to receive a higher or lower bid. 
Pros: 
(1) Opportunity for increased competition. 
(2) Potential to receive an even lower bid. 
Cons: 
(1) Re-advertising the project could result in the construction schedule being delayed
enough to cause work to coincide with the next peak summer season in 2017. 
(2) No guarantee additional bids would materialize, and creates the potential of receiving
a higher bid. 

Revised March 28, 2016  pjw

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
June 27, 2016 
Page 6 of 6 
(3) Delaying this work will result in the capacity and throughput of the TSA search room
remaining the same during the 2016 holiday season. Customer service will continue
to suffer. 
(4) As the C60 system will eventually be replaced by the Baggage Optimization project,
delaying this work will decrease the useful life of these capital improvements. 
(5) Extending the contract duration will result in increased soft costs for both the Port and
contractor. 
(6) The responsive bidder has the necessary resources available at this time; re-bidding
may result in these resources being re-allocated to projects outside the Port. 
This is not the recommended alternative. 
Alternative 3  Accept the bid and authorize the execution of the major works contract with the
sole responsible bidder. 
Cost Implications: No additional cost to the airport, contractor's bid is 10% below the Engineer's
Estimate. 
Pros: 
(1)  Fastest method to provide operational relief and efficiency gains for the C60
system, which will give the airlines, TSA, and the airport the best opportunity to be
successful with continued growth. 
(2)  Award contract below Engineer's Estimate, keeping project on budget. 
(3)  Least impact to original completion schedule. 
Cons: 
(1) Baseline construction is delayed due to the need to gain Commission authorization. 
This is the recommended alternative. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
June 28, 2016  Baggage Program Briefing 
January 12, 2016  C60 Interim Baggage Handling System to advertise, award, and
execute a major public works contract. 
December 8, 2015  C60 Interim Baggage Handling System Project Design, use of Port
crews, and equipment purchase authorization. 
June 23, 2015  Baggage Optimization Briefing. 




Revised March 28, 2016  pjw

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.