7c report reduced

Item Number: 7c_Report
Meeting Date: May 24, 2016


Commission Staff Briefing
Capital Improvement Projects
First Quarter Report 2016

This page intentionally left blank









ii  Port of Seattle 1Q 2016 Report

Port of Seattle
Capital Improvement Project Report
First Quarter 2016
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the status of the Port's capital projects.
Background
During 2016, the Port plans to invest $408,400,000 to expand and upgrade the infrastructure that supports marine and
aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping companies,
airlines, rental car companies, concessionaires and public parking. About 2 percent of the Port's capital budget comes
from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in transportation
facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, budget transfers, and cost growth of construction if it exceeds 10% of contract. The
report may include graphics that report project costs compared to authorization, construction costs (including change
orders (CO)) compared to the construction contract, location maps, and photographs. The Port implements a number
of different types of projects and not all information may be relevant to a specific project; as such, the reports may vary
in detail and content. Project types may range from construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (substantial completion). This section also includes "Project Status" illustrating at a
glance if the project is on schedule, and within budget, and the date Construction authorization received.
Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical    dates.
Budget addresses the total project budget and includes information on the overall budget status, recent
Commission authorizations, forecasted overruns or savings, and scope changes.
Change Orders provides information on current quarter's COs and total project COs including justification for CO's for
the reporting period and information on any CO over $200,000 or 10% of the contract value.
Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
Budget Transfers reports any transfers between authorized projects during the reportingperiod.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports intend to meet the reporting requirements of Port of Seattle General Delegation of Authority and the
Commission motion on January 8, 2008' regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page on the Port of Seattle web site to ask a question, make a comment or
request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 1Q 2016 Report  1

Aviation
Overall Project    Variance 
Status 
CIP Number   Project Title              Page      Schedule Budget
C101107..................160th GT Lot............................................................6..............................x
C102032.................Sanitary Sewer Pump Station Upgrade..................7.............ll.................x
C102112..................Hennelly Service Tunnel Renewal Rep...................8.............ll
C102573.................Airfield Pavement Replacement..............................9.............
C800019.................Gate Utilities Improvement.....................................10............
C800061.................Main Terminal South Low Voltage.......................... 11............ll
C800107.................C4 UPS System Improvements..............................12............ll.................x 
C800218.................Security Exit Lane Breach Control Phase I............13............ll
C800238.................Central Plant Pre-Conditioned Air..........................14............ll
C800247.................Cargo 2 West Hardstand........................................15.............................x
C800251.................Vertical Conveyance Modernization.......................16............ll 
C800253.................Parking System Replacement................................17.............................x
C800254.................Aircraft RON Parking Post Office Site..................18............ll.................x
C800274.................8th Floor Weather Proofing....................................19............ll 
C800324.................Long-Term Cell Phone Lot......................................20............ll.................x
C800335.................EGSE Electrical Charging Stations........................21............ll................x
C800390.................Cargo 6 Enhancements..........................................22............ll................x
C800406.................RW 16C/34C Reconstruction.............................. 23-24.........ll
C800451.................Doug Fox Site Improvement...................................25............ll................x
C800464.................Fiber Infrastructure to Gate Backstands................26............ll................. 
C800479.................Fire Station Electrical Upgrades.............................27.............................x
C800483.................Airfield Pavement Program....................................28............
C800495.................Facility Monitoring System Renewal......................29.............................x
C800497.................Airport Wide Mechanical Controls System............30............ll
C800538.................Utility ER Backup Standby......................................31............ll
C800544.................NorthSTAR Program.............................................32............
C800545.................NorthSTAR Main Terminal Improvements..............33............
C800549.................SSAT Interior Renovations.....................................34............ll................x....................x
C800551.................Grease Interceptor Augmentation..........................35.............................x
C800556.................NorthSTAR North Satellite Lobbies........................36.....................................................x
C800581.................Parking Garage Lights............................................37............
C800583.................International Arrivals Facility..................................38............





2  Port of Seattle 1Q 2016 Report

Aviation, cont.
Overall Project    Variance 
Status 
CIP Number   Project Title              Page      Schedule Budget
C800585.................Wi-Fi Enhancement for Ramp and Terminal..........39.............................x
C800612.................Checked Baggage Recapitalization/Optimzation...40............
C800629.................S1 Ramp.................................................................41............
C800637.................2014-15 Roof Replacement....................................42.............................x
C800638.................Dining and Retail Infrastructure Modernization......43............ll.......................................
C800642.................CCTV Camera Data Improvements ......................44............................. 
C800648.................Emergency Phones Rev.........................................45.............................x
C800653.................Passenger Loading Bridge Renew.........................46.............................x
C800657.................Domestic Water Piping...........................................47.............................x
C800658.................Mech Energy Conservation....................................48............
C800688.................Construction Logistics Expansion..........................49............
C800692.................2016 Fuel System Modifications.............................50.............................x 
C800695.................C3 Holdroom Expansion........................................51............
C800699.................Electric Utility SCADA Utility...................................52............
C800702.................2015-2016 C Concourse Roof Repl.......................53............
C800708.................S. Utility Tunnel Steam Pipe Upgrade....................54............
C800716.................Central Terminal Stairs...........................................55............
C800717................N. Terminal Utilities Upgrade..................................56............
C800722.................CTE HVAC..............................................................57............
C800724.................Concourse C New Power Center...........................58............
C800770.................AD Concourse B Roof Replacement......................59............
C800771.................D6 Gate Modifications............................................60............
C800781.................SSAT Narrow Body Configuration..........................61............
C800824.................Zone 5 Window Ticket Counter..............................62............
C800825.................Interim Baggage System Program.........................63......................................................
U00234-U00237.....Tenant US Air Ticketing ATO Zone 3....................64............
U00239...................NERA Program.......................................................65............
Other Aviation
Overall Project    Variance 
Status 
CIP Number   Project Title              Page      Schedule Budget
C200007.................Highline School Noise Insulation............................66............ll.................x
C200048.................Home Insulation Retrofit.........................................67............ll
C200093.................Single Family Home Sound Insulation...................68............ll
C800154.................Tenant Reimbursement..........................................69............ll


Port of Seattle 1Q 2016 Report  3

Maritime
Overall Project    Variance 
Status 
CIP Number   Project Title              Page      Schedule Budget
C102858 et al......... Street Vacations T-5/18/105...................................70............ll.................x
C800137.................FT C15 HVAC Improvements.................................71.............................x
C800160.................T-91 Lighting Upgrade............................................72............ll.................x
C800356.................Shilshole Tenant Service Buildings .......................73............................. 
C800439.................T-91 Substation Upgrades......................................74............................. 
C800546.................Argo Yard Truck Roadway......................................75............ll
C800678.................HIM E Dock Rehab ................................................76............ll
E102007..................East Marginal Way Grade Separation....................77............ll
E104324..................Viaduct Construction Coordination........................78.............................x
E104838..................FT Net Shed Code Compliance.............................79.............................x
E104840................T-5, T-18 and T-91 E. Maintenance Dredging........80.............................x
U00033...................T-18 Maintenance Dredging...................................81............ll

Economic Development 
Overall Project    Variance 
Status 
CIP Number   Project Title              Page      Schedule Budget
C800196.................T-102 Roof and HVAC............................................82............
C800691.................P69 Carpet Replacement.......................................83............ll.................x
C800698.................P69 Beam Rehab...................................................84............ll









4  Port of Seattle 1Q 2016 Report

Corporate
Overall Project    Variance 
Status 
CIP Number   Project Title              Page      Schedule Budget
C800162.................ID Badge Replacement..........................................85.............................x
C800519.................Contractor Data System Upgrade...........................86.............................x
C800521.................Construction Document Management...................87.............................x
C800709.................Terminal Wide Voice Paging System.....................88............
C800728.................Parking System Replacement................................89............
C800746.................Maximo Upgrade....................................................90............
C800748.................Remote Data Ctr Business Continuity....................91............
C800763.................Performance Management.....................................92............
C800788.................Ops Lane Core Switch Upgrade............................93............
C800800.................SEA Smartphone App............................................94............
C800827.................STIA Communication Infrastructure.......................95............


Key Project Status
ll Project within or ahead of target budget and schedule
ll Either target schedule or budget are off
ll Both target schedule & budget are off
Negative Variance Status
New Variance
x Previously Reported
Schedule Completion on the Project Reports refers to:
Beneficial Occupancy or Last Asset In-Use date







Port of Seattle 1Q 2016 Report  5

FIRST QUARTER REPORT, 2016 
So. 160th GT Lot Expansion 
Project: C101107              Improve lot drainage, underground    Project Status:
Budget: $3,559,000             existing overhead utility lines, fencing  Schedule: Delayed
Phase: Design                and landscaping.                Budget: On or Under
Start: 2/1/2013                                             Status Reset: 9/22/2015
Schedule Completion: 5/30/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
An SBE Contractor was awarded the construction contract. Their submittals
2.5
were reviewed and approved. Notice to proceed was issued to start                2.1
2           1.8
construction. The Contractor plans to mobilize in the second quarter.
Schedule
Major scope revision at 100% design has led to a delay in the project schedule.    Dollars in Millions 1.51               0.5
0.5
0
Budget                                       Authorized Forecasted  Costs
Incurred
The project forecast is within the approved budget and authorization. Project
savings of $300,000 was realized in the 1st quarter of 2016.
Construction Costs
None at this time 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The project may be subject to weather delays and a possible move of TNC
operations into the work zone.
Budget Transfers
Amount       From         To
$0



AIRPORT 
6  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016                                                           FIRST QUARTER REPORT, 2016 
So. 160th GT Lot Expansion                                              Sanitary Sewer Pump Station Upgrade 
Project: C101107              Improve lot drainage, underground    Project Status:                Project: C102032             Upgrade the aging control systems of 22  Project Status:
Budget: $3,559,000             existing overhead utility lines, fencing  Schedule: Delayed             Budget: $983,000            sanitary sewer lift stations.           Schedule: Delayed
Phase: Design                and landscaping.                Budget: On or Under            Phase: Construction                                     Budget: On or Under
Status Reset: 9/22/2015           Start: 3/1/2013                                             Status Reset: N/A
Start: 2/1/2013 
Schedule Completion: 5/30/2016                             (Commission Construction Auth.)        Schedule Completion: 6/30/2016                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred         Significant Developments                             Budget/Costs Incurred
An SBE Contractor was awarded the construction contract. Their submittals                               All control panels have been installed. Minor punch list items remain. This will
2.5                                                                                                                             1.1
1.2
were reviewed and approved. Notice to proceed was issued to start                2.1
1.8                      be the final report.                                                                               1.0
2                                                                                                    1
construction. The Contractor plans to mobilize in the second quarter.                                                                                                               0.8
1.5                                                                                                                      0.8
Schedule
Schedule                                      Dollars in Millions                                                                0.6
1
0.5             The project is behind schedule due to changes to the control panels and             0.4
Major scope revision at 100% design has led to a delay in the project schedule.    0.5                          installation challenges. We are carefully proceeding forward in a manner that     Dollars in Millions 0.2
0                               minimizes risk during and after system switchover.                            0
Budget                                       Authorized Forecasted  Costs                                                 Authorized Forecasted  Costs
Incurred
The project forecast is within the approved budget and authorization. Project
Incurred
Budget
savings of $300,000 was realized in the 1st quarter of 2016.
Construction Costs          The project forecast is within the approved budget and authorization.
Construction Costs
None at this time 
Change Order                                                                                           Not Applicable 
Change Order
Current Quarter     Project Total                                              Current Quarter     Project Total
Number of COs           0             0                                  Number of COs           0             0
Amount of Cos           $0             $0                                   Amount of Cos           $0             $0
Justification for COs: N/A                                                                   Justification for COs: N/A
Risks                                                               Risks
The project may be subject to weather delays and a possible move of TNC                                None identified at this time.
operations into the work zone.
Budget Transfers
Budget Transfers
Amount       From         To
Amount       From         To                               $0
$0



AIRPORT 
AIRPORT 
Port of Seattle 1Q 2016 Report  7

FIRST QUARTER REPORT, 2016 
Service Tunnel Renewal/Replace 
Project: C102112              Project will seismically retrofit and    Project Status:
Budget: $27,586,000            structurally strengthen the airport     Schedule: Within or Ahead
Phase: Design                Service Tunnel that resides between    Budget: On or Under
Start: 11/4/2012                the Main Terminal and Airport       Status Reset: 8/5/2014
Schedule Completion: 10/31/2018   Garage.                     (Commission Design Auth.)
Significant Developments                             Budget/Costs Incurred
Design and analysis models are complete and functioning. During a meeting
30           27.6
held with Aviation senior staff, a preferred design alternative was selected from
25
three possibilities for the central portions of the tunnel. The preferred
Dollars in Millions 20
alternative will have minimal operational impacts to the Departure and Arrivals
15
Drives during construction. The project will now move into the design.
10
4.6
5                  1.1
Schedule
0
Project is on schedule.                                             Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
The project is within budget.
None at this time 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Certain SAMP outcomes may impact this project. This project involves
coordinating with several other projects, and Aviation Operations and
Maintenance to minimize the risk of conflicts.
Budget Transfers
Amount       From         To
$0



AIRPORT 
8  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Airfield Pavement Replacement 
Project: C102573              This is a multi-year program to      Project Status:
Budget: $22,117,213            replace distressed pavement and joint   Schedule: Within or Ahead
Phase: Construction            seal on the airfield.              Budget: On or Under
Start: 5/2/2010                                             Status Reset: 4/1/2014
Schedule Completion: 9/30/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Remaining panels to be replaced will utilize quick setting concrete. Three
40
additional damaged panels have been identified over the winter and will be
30.2
included in this work by change order.                               30
23.3      22.1
20
Schedule
2015 Panel Replacement work was delayed to avoid interference with the 16C    Dollars in Millions 10
Reconstruction work. Work has been delayed for the winter season and is        0
scheduled now to resume in June 2016.                               Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
The project forecast is within the approved budget. $400,000 in savings was
returned back to the Overall Program in the 1st quarter of 2016.                20  17.1       16.8
15
Change Order
Current Quarter     Project Total         10
Number of COs           0             13           Dollars in Millions  5
Amount of Cos           $0           $100,024
0.1
0
Justification for COs: None this quarter.
Initial  Change  Spent
Orders
Risks
Phasing coordination with airline/operation gate impacts.                 Photo
Budget Transfers
Amount       From         To
$0



AIRPORT
Port of Seattle 1Q 2016 Report  9

FIRST QUARTER REPORT, 2016                                                          FIRST QUARTER REPORT, 2016 
Gate Utility improvements                                                Main Terminal Low Voltage 
Project: C800019              Upgrade the Concourse B loading     Project Status:                 Project: C800061             Renewal and replacement of low      Project Status:
Budget:  $16,734,282          bridges to the standard 400Hz power.   Schedule: Within or Ahead        Budget: 20,730,000          voltage (600 volts and below) electrical   Schedule: Within or Ahead
Phase:  Design              This will reduce aircraft emissions and  Budget: On or Under           Phase: Design             distribution equipment in the Main      Budget: On or Under
Start: 6/28/2007                noise; improve energy efficiency and   Status Reset: N/A               Start: 6/28/2007              Terminal.                      Status Reset: N/A
Schedule Completion: 10/16/2017   save money for the airlines.         (Commission Construction Auth.)        Schedule Completion: 7/31/2019                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred         Significant Developments                             Budget/Costs Incurred
Concourse B 400Hz project advertised for construction                   20                         Due to project deferral and the possibility of changes in site conditions and
16.7      16.7                                                                                                 25
building codes, the design phase changed from 100% to 0% complete.                   20.7
Schedule                                       15
Dollars in Millions                                        Commission re-approved the project in Q3 2014. Design team began 30%          20
On schedule                                                          9.6        design effort with expected completion in Q4 2016.                    15
10
10    8.1
Budget                                      5                   Schedule
5
1.0
The project is within the existing approved budget.                       0
Dollars in Millions
The scope of work, schedule and design budget finalized. The 100% design
0
Authorized Forecasted   Costs
documents scheduled for completion by the end of Q4 2017.                  Authorized Forecasted  Costs
Incurred
Incurred
Change Order
Current Quarter     Project Total                               Budget
Construction Costs                                                     Construction Costs
Number of COs           0             45                                  The forecast is within the approved budget.
6
Amount of COs          $0          $287,390                                                                            Not Applicable 
5.1          5.1
5
Justification for COs: None this quarter                                                          Change Order
Dollars in Millions   4                                                                                                                  Photo
Current Quarter     Project Total
3
Risks                                                                Number of COs           0             0
2
Bidding environment for previously sole sourced equipment could negatively                                Amount of Cos             $0              $0
1        0.3
impact costs in construction and increase risks associated with                                           Justification for COs: N/A
0
unknown/untested equipment.                                    Initial Change Spent
Orders                   Risks
Budget Transfers                                                        This area is a 24/7/365 operation. Sequencing of this work is critical and
Amount       From         To                          electrical power has to be maintained without interruptions. Significant work
$0                                                            growth is possible due to lack of project definition.
Budget Transfers
Amount       From         To
$0


AIRPORT                                             AIRPORT 
10  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Main Terminal Low Voltage 
Project: C800061             Renewal and replacement of low      Project Status:
Budget: 20,730,000           voltage (600 volts and below) electrical   Schedule: Within or Ahead
Phase: Design              distribution equipment in the Main      Budget: On or Under
Start: 6/28/2007              Terminal.                      Status Reset: N/A
Schedule Completion: 7/31/2019                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Due to project deferral and the possibility of changes in site conditions and
25
building codes, the design phase changed from 100% to 0% complete.                   20.7
Commission re-approved the project in Q3 2014. Design team began 30%       20
design effort with expected completion in Q4 2016.                      15
10    8.1
Schedule                                      Dollars in Millions 5
1.0
The scope of work, schedule and design budget finalized. The 100% design
0
documents scheduled for completion by the end of Q4 2017.                  Authorized Forecasted  Costs
Incurred
Budget
The forecast is within the approved budget.                          Construction Costs
Not Applicable 
Change Order
Photo
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
This area is a 24/7/365 operation. Sequencing of this work is critical and
electrical power has to be maintained without interruptions. Significant work
growth is possible due to lack of project definition.
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 1Q 2016 Report  11

FIRST QUARTER REPORT, 2016 
C4 UPS System Improvement 
Project: C800107             Replace existing Uninterruptible Power  Project Status:
Budget: $4,555,238          Supply (UPS) System, including      Schedule: Delayed
Phase: Design             batteries, with a new system located in   Budget: On or Under
Start: 4/14/2015              the Airport Combined Communications  Status Reset: 4/14/2015
Schedule Completion: 5/15/2017  and Command Center (C4).          (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Sixty percent design submittal issued. Comments received. Moving into the
$5    4.6      4.6
90% phase. No net change in construction budget.
$4
Schedule                                      Dollars in Millions $3                                            Project reactivated. Preliminary schedule shows Substantial Completion as May  $2
0.9
2017.                                               $1
$0
Budget                                       Authorized Forecasted  Costs
Incurred
New estimate has been developed based on new design concept.
Construction Costs
Change Order                               Not Applicable 
Current Quarter     Project Total
Number of COs           0             0          Photo
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The C4 center is a 24/7/365 operation. Detailed construction sequencing of
work in design documents. This is critical since electrical power has to be
maintained without interruptions. Risk mitiagated in design. Cut-overs limited
to short low traffic time frames.
Budget Transfers
Amount       From         To
$0



AIRPORT 
12  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Security Exit Lane Breach Control Exit B  Phase II 
Project: C800218              Procure and extend new automated,     Project Status:
Budget:  $1,558,300          exit-land breach control, equipment at   Schedule: Within or Ahead
Phase:  Construction           the Concourse B exit.             Budget: On or Under
Start: 3/1/2012                                             Status Reset: N/A
Schedule Completion: 11/30/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The security exit lanes opened on schedule. Opening of the side bypass lane for    2
emergency responders has been delayed due to the long lead time for light           1.6     1.5
fixtures and installation of additional security equipment.                   1.5
Dollars in Millions                        1.0
1
Schedule
The security exit lane doors opened on schedule. The opening of the side        0.5
bypass lane for emergency responders is scheduled to open in May 2016.         0
Authorized Forecasted   Costs
Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Not Applicable 
Change Order
Current Quarter     Project Total       Photo
Number of COs           0             0
Amount of COs           $0            $0
Justification for COs: N/A
Risks
No major risks at this time
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 1Q 2016 Report  13

FIRST QUARTER REPORT, 2016 
Central Plan Pre-Conditioned Air 
Project: C800238             Provide a centralized pre-conditioned   Project Status:
Budget: $55,140,463         air (PC-Air) plant (PCAP), associated   Schedule: Within or Ahead
Phase: Construction         heating and cooling piping systems,    Budget: On or Under
Start: 6/15/2009              and jet bridge terminal air handling     Status Reset: 2/25/2014
Schedule Completion: 3/31/2017  units to serve airplanes with heating    (Commission Construction Auth.)
and cooling while at the gates. 
Significant Developments                             Budget/Costs Incurred
The major-works Contractor's construction is complete. PC-Air is operating at
56    55.3     55.1
72 gates. Work on the four remaining gates is complete. Design to replace the
55
chilled water insulation, anchor and guides on Concourse A, and the anchors
Dollars in Millions 54
and guides on Concourse B, C and South Satellite is complete. This work is      53
being combined with the South Satellite Steam Upgrade into one major works     52               51.4
contract. Ready-to-bid documents will be ready in May.                   51
50
Schedule                                       49
Authorized Forecasted   Costs
One hundred percent documents for PC Air Chilled Water Piping regrade are                    Incurred
complete. Major works contract for this work will be advertised Q2 2016.
Work is expected to complete by Q1 2017.
Construction Costs
Budget
40              36.6
The major works contract is complete. Work for completing the remaining four     35
30   27.0
gates and anchors and guides is within the budget.
25
20
Change Order                                Dollars in Millions 15     9.9
10
Current Quarter     Project Total
5
Number of COs           0            230             0
Amount of Cos           $0          $9,886,034             Initial Change Spent
Orders
Justification for COs: None this quarter
Risks
None at this time
Budget Transfers
Amount       From         To
$0


AIRPORT 
14  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Cargo 2 West Cargo Hardstand 
Project: C800247             Enlarge the western cargo hardstand in the  Project Status:
Budget: $7,890,000           Cargo 2 area. Includes buyout of two      Schedule: Delayed
Phase: Construction          cargo buildings and tenant relocations;     Budget: On or Under
Start: 9/5/2012               relocation of FAA antenna, security gate,    Status Reset: 10/8/2013
Schedule Completion: 10/31/2015 and guard shack; and installation of 400Hz   (Commission Construction Auth.)
in-ground power. 
Significant Developments                             Budget/Costs Incurred
Due to the width of Gate E190 and the lengthy opening/closing times, the new
15
operating system is being upgraded with a magnetic induction mechanism and        12.5
is being installed separate from the contract. Modifications to the 400 Hz
Dollars in Millions 10
electrical vaults have been evaluated to address potential fall hazards                      7.2     6.9
Retrofit/replacement options were explored and pop-up power systems will be
5
installed. There are two 400 Hz vaults located at Cargo 2 and at least one
concrete panel will be replaced at each location for the retrofit. A new project is
0
being opened for completion of this work and will be performed under a           Authorized Forecasted  Costs
separate contract.                                                              Incurred
Schedule                                     Construction Costs
Anticipate new gate operating system to be installed Q2 2016 and new 400 Hz      5  4.5
electrical vaults and pop-up power systems Q2 2017.                                 3.9
4
Budget                                       3
The project forecast is within the approved budget and authorization. Project       2
savings of $400,000 returned back to the project in the 1st quarter of 2016.       Dollars in Millions  1
0.0
0
Change Order                                   Initial Change Spent
Orders
Current Quarter     Project Total
Number of COs           0             7
Photo
Amount of Cos           $0           $41,909
Justification for COs: None this quarter.
Risks
Long lead item of 400 Hz pop-up power system may impact the schedule.
Successful and on-time selection of 400 Hz pop-up power system from RFP
process impacts the overall project schedule.
Budget Transfers
Amount       From         To
$0

AIRPORT 
Port of Seattle 1Q 2016 Report  15

FIRST QUARTER REPORT, 2016 
Vertical Conveyance Modernization Program - Aeronautical 
Project: C800251             Perform modernization on 9 existing    Project Status:
Budget: $24,556,408          elevators and 4 escalators: SSAF, MT-2,  Schedule: Within or Ahead
Phase: Construction          MT-3, MT-4, MT-5, MT-6, MT-7, SSB,  Budget: On or Under
Start: 10/25/2011             SSC. Install new elevators SSM and     Status Reset: 11/11/2013
Schedule Completion: 10/30/2016 SSN. Install cooling packages on 12     (Commission Construction Auth.)
existing hydraulic elevators throughout
Main Terminal. 
Significant Developments                             Budget/Costs Incurred
Construction continued with the contractor working on the first six elevators.
20
Sky-bridge 6 has been closed to facilitate replacement of the 600 series              16.4
escalators.                                                    15          13.2
Schedule
10                   8.0
Construction is underway. Partial substantial completion of portions of the first    Dollars in Millions 5
phase of construction occurred in Q4 2015.
0
Authorized Forecasted   Costs
Budget                                                Incurred
The project forecast is within the approved budget and construction is
underway. Project has returned budget upon deferral of second phase of work.   Construction Costs
5    4.6
Change Order
4                 3.7
Current Quarter     Project Total
3
Number of COs           16            48
Amount of Cos          $61,553         $192,861          Dollars in Millions  2
Justification for COs: differing site conditions, sequencing of work, and          1
0.2
administrative changes.                                          0
Initial    Change    Spent
Orders
Risks
Contractor is projecting missing delivery milestones and will fail to complete
work on time in 2016.
Budget Transfers
Amount       From         To
$0


AIRPORT 
16  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Parking System Replacement 
Project: C800253              Replace the previous Parking Revenue  Project Status:
Budget: $5,427,364            Control System, which manages      Schedule: Delayed
Phase: Closeout               parking access and revenue collection   Budget: On or Under
Start: 4/6/2010                 in the Airport's Main Parking Garage.   Status Reset: 3/8/2011
Schedule Completion: 5/31/2014                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Scheidt & Bachmann (S&B) system is operational and exhibits accuracy and
12
availability rates above 99.99%. A letter, reviewed by the Legal and ICT             9.8
10
departments, informing the contractor of the Port's intention to close out their
8
contract was mailed. The Port letter noted the contractor's inability to deliver a    Dollars in Millions 6          5.1     5.1
key certification, and our intent to withhold payment for this task.
4
2
Schedule
0
The system is complete and in use. However, a critical Payment Card Industry       Authorized Forecasted  Costs
Incurred
(PCI) certification issue remains outstanding.
Budget                                    Construction Costs
None this quarter 
The project remains within its' approved budget. Savings of $298,799.70 has
been returned to the Overall Program's budget in the 1st quarter of 2016.       Photo
Change Order
Current Quarter     Project Total
Number of COs           0             9
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Scheidt and Bachmann could respond adversely to the Port's letter.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 1Q 2016 Report  17

FIRST QUARTER REPORT, 2016 
Aircraft RON Parking USPS Site 
Project: C800254              Prepare the site for the construction of  Project Status:
Budget: $41,456,350            hardstands for use as Remain        Schedule: Delayed
Phase: Construction            Overnight (RON) parking of aircraft at  Budget: On or Under
Start: 8/26/2008                the Cargo 5 areaincluding new      Status Reset: 10/8/2013
Schedule Completion: 9/30/2015    Security Guard Shelter at Gate E125.   (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
E125 Security Guard Shelter  Gate E125 operating system is being upgraded
50    45.6
with a magnetic induction mechanism for greater open/close speed. Additional              38.3
40                  36.7
safety measures have been completed for the Variable Message Sign
maintenance.                                           Dollars in Millions 30
20
Schedule
10
Hardstand was completed and operational on schedule. E125 Security Guard      0
Shelter will be open as soon as TSA acceptance testing is completed. Gate         Authorized Forecasted  Costs
Incurred
operating system at E125 completion Q2, 2016 (not required for shelter
occupation and operation).
Construction Costs
Budget
30
25.4
The project forecast is within the approved budget and authorization.            25           22.3
20
Change Order                                 15
Current Quarter     Project Total         10
Number of COs           5             19           Dollars in Millions  5
0.1
Amount of Cos        ($118,003.51)       $132,930.56          0
Initial  Change  Spent
Justification for COs: 1) Modify 60Hz Receptacle; 2) Cargo 5 Electric Cables            Orders
and Duct bank changes; 3) Raised structures additional height due to grade
revision at Cargo 5; 4) Force account Bid item changes; 5) Contractor Extended  Photo
Overhead.
Risks
A significant amount of contaminated soil at Cargo 5 was managed through
construction contingency. Two POs are still outstanding and negotiations are
on-going regarding two claims filed by the contractor.
Budget Transfers
Amount       From         To
$0

AIRPORT 
18  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
8th Floor Weatherproofing 
Project: C800274              Removal and replacement of the floor  Project Status:
Budget: $9,324,000            covering system on the eighth floor of   Schedule: Within or Ahead
Phase: Closeout               the STIA parking garage and of the    Budget: On or Under
Start: 3/23/2010                expansion joints and flashing.        Status Reset: 6/14/2011
Schedule Completion: 10/31/2013                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The project is in close out. Port is waiting on final documentation from                WP 104325
15    13.1
contractor to complete release of retainage. This will be the final report.
Dollars in Millions 10             8.4       8.4
Schedule
Project is complete.                                             5
Budget
0
The project forecast is within the approved budget and authorization. Project        Authorized Forecasted  Costs
Incurred
saving of $203,969.39 was returned during the 1st quarter of 2016.
Construction Costs
Change Order
Current Quarter     Project Total          7  6.1      5.9
6
Number of COs           0             34
5
Amount of Cos           $0           $184,555          Dollars in Millions  4
Justification for COs: None this quarter.                                3
2
Risks                                           1     0.2
0
None.                                               Initial Change Spent
Orders
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 1Q 2016 Report  19

FIRST QUARTER REPORT, 2016 
Long-Term Cell Phone Lot 
Project: C800324              Construct a new cell phone waiting lot  Project Status:
Budget:  $3,300,000           to replace the existing lot that is being  Schedule: Delayed
Phase:  Construction           displaced, including permanent access  Budget: On or Under
Start: 12/31/2012               control on South 170th Street.        Status Reset: 4/14/2015
Schedule Completion: 12/31/2018                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Coordinated with the City of SeaTac and determined that a traffic signal, and      6         5.2
associated roadway improvements, is the likely permanent access solution.       5
Given the uncertainty of future development associated with the Sustainable      4
Airport Master Plan, continue to evaluate options in order to minimize the
3.3
2.7
3
overall investment.                                           Dollars in Millions 2
1
Schedule                                       0
Authorized Forecasted   Costs
Recommendation on the permanent access solution delayed to Q3 2016, given
Incurred
delays in the Sustainable Airport Master Plan work.
Construction Costs
Budget
The current authorized budget for the Cell Phone Lot is $3,300,000. The total       1
0.8
budget forecast is $5,200,000, which includes the permanent access solution.      0.8   0.7
0.6
Change Order
0.4
Current Quarter     Project Total        Dollars in Millions         0.2
0.2
Number of COs           0             6
0
Amount of Cos           $0           $204,664              Initial  Change  Spent
Orders
Justification for COs: None this quarter.
Risks                                        Photo
Displacement of completed improvements by future development in 5-10 years.
Until completion of the permanent access solution, congestion and complaints
during summer/holiday months continue. Completion of the permanent access
solution improvements to satisfy State Environmental Protection Agency and
roadway standard requirements.
Budget Transfers
Amount       From         To
$0

AIRPORT
20  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Electrical Ground Support Equipment (EGSE)
Electrical Charge Stations 
Project: C800335             Airport-wide electrical charging system Project Status:
Budget: $30,700,000         for electrical ground support equipment  Schedule: Delayed
Phase: Design             at the Concourses and the North and    Budget: On or Under
Start: 10/26/2010             South Satellites.                 Status Reset: 12/21/2012
Schedule Completion: 12/29/2017                           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
EGSE Phase 2 Project  Concourse A, Concourse B and South Satellite:     40
Completed GSE charger materials take-off for Concourse A, B and South              30.7
30    25.6
Satellite and submitted purchased requisition to CPO to purchase chargers
for Concourse A. Chargers for Concourse A to ship in May 2016.          20              16.1
Design re-mobilization is underway for Concourse A, B and South Satellite.   Dollars in Millions 10
AE completed site walk and will be submitting scope of work and level of
effort to complete 100% final bid documents.                        0
Authorized Forecasted   Costs
Incurred
Schedule
Phase 1- Completed this phase of the Charger Program on December 21, 2015.  Construction Costs  Phase 2
Phase 2- Construction scheduled for late 2017.                       Only
Not Applicable
Budget
Project forecast is within the approved budget. Request authorization for       Photo
construction funds and authority to advertise for construction when the design
and bid documents are complete for EGSE Charger Phase 2 Project.
Phase 1 completed for $14,200,000.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of COs          $0            $0
Justification for COs: None this quarter
Risks
Coordinate with other airfield projects and Airline Gate Realignment program.
Budget and schedule may affect project implementation and completion of the
EGSE Phase 2 Project.
Budget Transfers
Amount       From         To
$0
AIRPORT
Port of Seattle 1Q 2016 Report  21

FIRST QUARTER REPORT, 2016 
Cargo 6 Enhancements 
Project: C800390             Enlarge the Cargo 6 off-gate hardstand  Project Status:
Budget: $6,428,000          to allow simultaneous nose-loading of   Schedule: Delayed
Phase: Construction         wide-body freight aircraft as well as    Budget: On or Under
Start: 9/25/2012              provide fuel hydrant and ground power   Status Reset: 10/8/2013
Schedule Completion: 7/31/2015   capabilities.                   (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Modifications to the 400Hz electrical in ground vaults for fall protection have
8
been evaluated. Retrofit/replacement options are being explored and pop-up          6.3
5.9
power systems will be installed. There are three 400 Hz vaults located at Cargo    6               5.1
6 and at least one concrete panel will be replaced at each location for the
retrofit. A new project is being opened for completion of this work and will be
4
performed under a separate contract.                               Dollars in Millions 2
0
Schedule                                        Authorized Forecasted  Costs
Incurred
Hardstand is complete and operational. New 400 Hz electrical vaults and popup
power systems are anticipated to be installed Q2, 2017.
Construction Costs
Budget
4
3.4          3.4
The project forecast is within the approved budget and authorization. Project
3
savings of $500,000 returned back to the project in the 1st quarter of 2016.
2
Change Order                                Dollars in Millions 1     0.5
Current Quarter     Project Total
Number of COs           2             8             0
Initial  Change  Spent
Amount of Cos         $53,539.83       $529,767.71
Orders
Justification for COs: 1) Restore Swissport Parking Lot; 2) Cargo 6 Electrical
Ductbank change.                                      Photo
Risks
Long lead item of 400 Hz pop-up power system may impact the schedule.
Successful and on-time selection of 400 Hz pop-up power system from RFP
process impacts the overall project schedule.
Budget Transfers
Amount       From         To
$0

AIRPORT
22  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 20116 
RWW16C/34C Design annd Reconsttruction 
Projject: C8004406            Produce finaP      al design andd reconstructt the   Prooject Status:
Budget: $101,3395,000          existing RWe       16C/34C inn its existingg       Scchedule: Wiithin or Ahead 
Phasse: Construuction          location, repl       lace TW C aand N,         Buudget: On oor Under 
Starrt: 5/4/2010                reconfigure Tr        TWs H and JJ, install FOOD     Sttatus Reset: 12/2/2014 
Scheedule Comppletion: 10/331/2016  detection equd      uip, and LEDD lighting syystem.  (CCommission Coonstruction Autth.) 
ReconstructR      blast pads of RW16L/344R. 
Signnificant Deevelopmentts                          Budget/Coosts Incurrred 
Runnway 16C/344C and assocciated taxiwaays reopenedd on Decembber 18th.
120   110. 2
Runnway 16L/344R closed at 0001 Fridayy, April 1st ffor a maximuum of 45
100           84.6
dayss. Design at 100% for thhe SR 518 Innterchange RRestoration, wwhich
80                  71.7
was used as a haaul route forr airfield projjects.
Schhedule                                  Dollars in Millions 604020
2015 work was completed bbehind scheddule. 2016 wwork is aheadd of
0
scheedule. Runwway 16L/34RR closed on AApril 1st and is scheduledd to re-       Authori z ed Forecasted  Costs
openn by May 155th. Runway 16C/34C wiill close in Juune to finishh punch                   Incurred
list iitems and peerform warraanty work. SSR 518 Intercchange Resttoration
consstruction is pplanned to occur in Q3 too Q4 2016.                Construction Costs
57. 0
60
Buddget                                          49 . 5
50
The project foreecast is withiin the approvved budget aand authorization.
40
30
Chaange Orderr
20
Current QuC     uarter    Project TTotal     Dollars in Millions 10     1.9
Nuumber of COOs         16            27          0
Ammount of Coss        $703,323..12       $1,949,528.03          Initi a l Change Sp e nt
Orders
Justtification forr Co's beloww: 
1) PPCCP  ACPP Joint replaccement; 2) RRevisions to 16C ALSF        Photo
Threeshold Bar; 3) Weather IImpact  Accceleration; 44) Modify thhe
Airffield Lightinng; 5) FAA HHandholes annd Ductbankks; 6) Weathher
Imppact  Acceleeration; 7) AAdditional Paanel Replaceement (Taxiwway F);
8) Innfield Drainage Improveements; 9) TTemporary Bypass for C Line; 10)
Alteernate PCCPP section; 11)) Raise 34C MALSR Ligghts; 12) Ligght Can
PCCCP Joint Connflict; 13) Neew Pulsing RRunway Guaard Light Moodules;
14) Temporary Emergency Generator foor ASDE-X;; 15) C2 Stopp Bar
Equuipment Plann Discretionaary Revisionns; 16) Ping TTesting for FFOD
senssors. 


Port of Seattle 1Q 2016 Report  23

Risks
Inclement weather could impact the schedule for the remaining work.
Budget Transfers
Amount       From        To
$0 












AIRPORT 
24  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Doug Fox Lot Service Upgrades 
Project: C800451              Construct a new drainage system,     Project Status:
Budget:  $6,909,000          asphalt resurfacing, improved lot     Schedule: Delayed
Phase:  Construction           lighting, new building, and road      Budget: On or Under
Start: 2/29/2012                signage to improve lot appearance,     Status Reset: 1/6/2015
Schedule Completion: 3/31/2015   function, and revenue generation .     (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The Port has received protests (claims) from the contractor totaling $303,491      7   6.9     6.9
and has hired outside legal services to support the on-going dispute resolution     7
process.                                                  Dollars in Millions 7
6                  6.2
Schedule                                       6
The overall project was delayed with project beneficial occupancy occurring on    6
February 27, 2015. Closeout is delayed by the Contractor's claim.              6
Authorized Forecasted   Costs
Incurred
Budget
Project forecast, including the resolution of the claims, is within the revised     Construction Costs
budget.
5                 4.4
4.0
Change Order                                  4
Current Quarter     Project Total          3
Number of COs           1             43
2
Amount of Cos           $0           $51,467          Dollars in Millions  1
Justification for COs: Revision to general conditions in support of dispute                  0.1
0
resolution process.                                                  Initial  Change   Spent
Orders
Risks
Project is complete  no additional risks identified.                      Photo
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 1Q 2016 Report  25

FIRST QUARTER REPORT, 2016 
Fiber Infrastructure to Gate Backstands 
Project: C800464             Extend airport-provided           Project Status:
Budget: $3,195,000          communications infrastructure to      Schedule: Delayed
Phase: Construction         additional gates, gate information      Budget: On or Under
Start: 7/9/2013               displays to all gates and Wi-Fi antennas  Status Reset: 5/26/2015
Schedule Completion: 9/30/2016  throughout Concourses A and B.      (Commission Construction Auth.)
Provide redundant fiber backbone
between Concourse A communication
rooms and MDR-2. 
Significant Developments                             Budget/Costs Incurred
Project work complete except for the installation of the gate information display
4
brackets and the wireless access points.                                   3.20    3.01
3                  2.50
Schedule
2
Construction has taken longer than anticipated, in part due to project
complexities as well as unforeseen field conditions.                      Dollars in Millions 1
Budget                                      0
Authorized Forecasted   Costs
On budget                                                           Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable 
Number of COs           5             5
Amount of COs         $29,000         $29,000
Justification for COs: discretionary, unforeseen field conditions
Risks
The project has fallen behind schedule.
Budget Transfers
Amount       From         To
$0



AIRPORT 
26  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016                                                          FIRST QUARTER REPORT, 2016 
Fiber Infrastructure to Gate Backstands                                         Feeder 101 Taps Replacement/Fire Station
Electric Upgrades 
Project: C800464             Extend airport-provided           Project Status:
Budget: $3,195,000          communications infrastructure to      Schedule: Delayed              Project: C800479           Replace: 1) existing 208V transformer,   Project Status:
Phase: Construction         additional gates, gate information      Budget: On or Under             Budget: $4,775,000          12.47 KV feeder, add a 500 KVA       Schedule: Delayed
Start: 7/9/2013               displays to all gates and Wi-Fi antennas  Status Reset: 5/26/2015             Phase: Construction           generator and a 1000KVA transformer;    Budget: On or Under
Schedule Completion: 9/30/2016  throughout Concourses A and B.      (Commission Construction Auth.)          Start: 4/1/2013              2) electrical feeds to 13 locations along    Status Reset: 7/1/2014
Provide redundant fiber backbone                                  Schedule Completion: 10/31/2016 Air Cargo Road; and 3) electrical        (Commission Construction Auth.)
between Concourse A communication                                                   transformer and associated switchgear for
rooms and MDR-2.                                                               Air Cargo #4.
Significant Developments                             Budget/Costs Incurred          Significant Developments                             Budget/Costs Incurred
Project work complete except for the installation of the gate information display                                All work on the major construction contract is complete. The record drawings
4                                                                                                    5
brackets and the wireless access points.                                                           are complete.                                                     4.8     4.8
3.20     3.01                                                                                                 4.8
3
Dollars in Millions                        2.50                                                                                              4.6
Schedule                                                            Schedule                                      4.4
2
Construction has taken longer than anticipated, in part due to project                                                                                                  4.2                4.1
The project is complete with the exception of replacing breakers in the existing
4
complexities as well as unforeseen field conditions.                       1                           switchboard. The breakers will be replaced by Q2 2016.                   Dollars in Millions 3.8
Budget                                      0                                                             3.6
Authorized Forecasted   Costs            Budget                                                                   Authorized Forecasted   Costs
On budget                                                           Incurred                                                                         Incurred
The project is on budget.
Change Order                               Construction Costs                                                  Construction Costs
Change Order
Current Quarter     Project Total       Not Applicable 
2.5   2.3          2.3
Number of COs           5             5                                                  Current Quarter     Project Total
2
Amount of COs         $29,000         $29,000                                 Number of COs           8             40
Justification for COs: discretionary, unforeseen field conditions
Amount of Cos          -$6,554         $152,060           1.5
Justification for COs: Reconciled several items for reduction in price. Added     Dollars in Millions  1
Risks                                                                punchlist items and Neutral Conductors at Fire Station.
0.5          0.2
The project has fallen behind schedule.
Risks                                           0
Budget Transfers                                                                                                        Initial Change Spent
The replacement ATS is delayed.                                       Orders
Amount       From         To
$0                                                            Budget Transfers
Amount       From         To
$0


AIRPORT 
AIRPORT 
Port of Seattle 1Q 2016 Report  27

FIRST QUARTER REPORT, 2016                                                            FIRST QUARTER REPORT, 2016 
Airfield Pavement Program                                              Facility Monitoring System Renewal 
Project: C800483               This is a multi-year program to     Project Status:                  Project: C800495             Provide a system upgrade that will allow Project Status:
Budget: $32,500,000            replace distressed pavement and    Schedule: Within or Ahead          Budget: $2,096,500           the system to maintain and expand      Schedule: Delayed
Phase:  Design               joint seal on the airfield starting in   Budget: On or Under             Phase: Construction         monitoring of critical systems such as    Budget: On or Under
Start: 5/5/2011                 2016 through 2020.             Status Reset: 2/24/2015             Start: 10/23/2011             elevators, escalators, moving walks,     Status Reset: 12/10/2013
Schedule Completion: 6/30/2021                            (Commission Design Auth.)            Schedule Completion: 4/11/2015  passenger boarding bridges and baggage  (Commission Construction Auth.)
systems.
Significant Developments                             Budget/Costs Incurred         Significant Developments                             Budget/Costs Incurred
2016 Airfield Replacement Project has been delayed to 2017. The scope of this                              F&I and maintenance will need to work with manufacturer to complete the
40                                                                                                     4
work has been significantly reduced. It is at 60% design and is being combined              32.5                                                                           3.4
efforts.
with NSTAR Taxiway A SMGCS project into a single contract. There is        30
Dollars in Millions                                                                                                                          3
potential impact on 16L, with it needing to be utilized as taxiway during                                    Schedule                                                             2.1     1.9
20                                                                                                     2
construction.                                                                            Project is anticipated to be completed by Q2 2016.
10                                                                                                     1
Schedule                                          0.2        0.1       Budget                                       Dollars in Millions
0                                                                                                    0
Projects will occur annually through 2020. Current work has been delayed until      Authorized Forecasted  Costs         The forecast is within the approved budget and authorization..                 Authorized Forecasted  Costs
Incurred
2017, anticipated completion November 2017.                                                                                                                    Incurred
Change Order
Budget                                    Construction Costs                                                  Construction Costs
None at this time                                      Current Quarter      Project Total
Within budget                                                                       Number of COs            0               6             0.4   0.3          0.3
Amount of Cos           $0           $1,310          0.3
Change Order
Justification for COs: None this quarter.                              0.3
Current Quarter     Project Total
0.2
Number of COs           0             0                                  Risks                                           0.2
Amount of Cos           $0             $0
None identified at this time.                                       Dollars in Millions 0.1
Justification for COs: None at this time
0.1
Budget Transfers
0.0
Risks                                                                                                                     0.0
Amount       From         To           Initial Change Orders Spent
Coordination of Runway 16L closure is necessary to complete the Taxiway                                       $0
work  significant impact to airline operations with runway closure.
Budget Transfers
Amount       From         To
$0


AIRPORT 
AIRPORT 
28  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Facility Monitoring System Renewal 
Project: C800495             Provide a system upgrade that will allow Project Status:
Budget: $2,096,500           the system to maintain and expand      Schedule: Delayed
Phase: Construction          monitoring of critical systems such as    Budget: On or Under
Start: 10/23/2011             elevators, escalators, moving walks,     Status Reset: 12/10/2013
Schedule Completion: 4/11/2015  passenger boarding bridges and baggage  (Commission Construction Auth.)
systems.
Significant Developments                             Budget/Costs Incurred
F&I and maintenance will need to work with manufacturer to complete the
4    3.4
efforts.
3
Schedule                                      Dollars in Millions        2.1    1.9
2
Project is anticipated to be completed by Q2 2016.
1
Budget
0
The forecast is within the approved budget and authorization..                  Authorized Forecasted  Costs
Incurred
Change Order
Construction Costs
Current Quarter     Project Total
Number of COs           0             6            0.4   0.3         0.3
Amount of Cos           $0           $1,310          0.3
Justification for COs: None this quarter.                              Dollars in Millions 0.30.2                                                           Risks                                                     0.2

None identified at this time.                                       0.1
0.1
Budget Transfers
0.0             0.0
Initial  Change Orders  Spent                                                                                                                 Amount                   From                      To
$0



AIRPORT 

Port of Seattle 1Q 2016 Report  29

FIRST QUARTER REPORT, 2016 
Airportwide Mechanical Controls System 
Project: C800497             Upgrade the Mechanical Control System Project Status:
Budget: $3,350,000           for Concourse A at the Airport. This    Schedule: Within or Ahead
Phase: Construction          includes adding a wireless connection to  Budget: On or Under
Start: 5/1/2013               the Logistics area to the south of the     Status Reset: 12/9/2014
Schedule Completion: 3/11/2016  Airport.                       (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Conduit installation for the fiber optics "backbone" completed.               4   3.5     3.4
Schedule                                          3
Dollars in Millions                        2.2
Project is within schedule.                                         2
1
Budget
Project is within budget.                                          0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0
2.5
Amount of Cos           $0             $0                2.2
2.0
Justification for COs: N/A                                                     1.5
1.5
Risks                                          1.0
Unplanned electrical shut downs could affect the project schedule. The         Dollars in Millions 0.5
contractor is running conduit through mechanical chases, there are possible               0.0
0.0
conflicts. An allowance added to the estimate.                              Initial Change Spent
Orders
Budget Transfers
Amount       From         To
$0




AIRPORT 
30  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Alternate Utility Facility
Project: C800538               Build and house a new 25MW     Project Status:
Budget: $37,200,000            electrical backup power generation   Schedule: Within or Ahead
Phase:  Planning              facility for the Airport.          Budget: On or Under
Start: 8/4/2015                                          Status Reset: 8/4/2015
Schedule Completion: 9/30/2017                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Building Engineered Systems Procurement was advertised on March 11, 2016.
40    37.2     37.2
Schedule                                       30
Project is currently on schedule.                                    20
Budget                                     Dollars in Millions 10
0.3
Project is on budget per the amount authorized by the Commission.            0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0
Not applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Federal regulatory requirements may adversely impact schedule and budget.
Budget Transfers
Amount       From         To
$0




AIRPORT
Port of Seattle 1Q 2016 Report  31

FIRST QUARTER REPORT, 2016 
NorthSTAR Program 
Project: C800544             Includes programmatic project        Project Status:
Budget: $19,514,150          management and project controls costs   Schedule: Within or Ahead
Phase: Design              for the NorthSTAR program; consisting   Budget: On or Under
Start: 4/5/2012               of 5 capital projects that represent a      Status Reset: N/A
Schedule Completion: Q4 2020   unique partnership between the Port and   (Commission Construction Auth.)
Alaska Airlines.
Significant Developments                             Budget/Costs Incurred
Coordination began with Port Finance & Budget to evaluate potential PFC
25
Passenger Facility Charge (PFC) funding of NorthSTAR projects. AIP Grant               19.5
20
funding does not appear feasible as procurement of contractor is complete.
Dollars in Millions 15
Schedule                                       10
4.3
Continue programmatic linkage coordination to assure airport-wide gate                        3.6
5
availability is not compromised during construction.                      0
Authorized Forecasted   Costs
Incurred
Budget
The project forecast is inclusive of Programmatic Management Reserve and is
Construction Costs
within the approved budget.
None at this time 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Communication and coordination across multiple teams and stakeholders along
with identification/monitoring of all "linked" Capital projects outside of
NorthSTAR.
Budget Transfers
Amount       From         To
$0
.


AIRPORT 
32  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
NorthSTAR Main Terminal Improvements 
Project: C800545             Renovate the North Main Terminal    Project Status:
Budget: $29,200,000          security checkpoint, curbside and       Schedule: Within or Ahead
Phase: Design              ticketing lobby areas incorporate self-    Budget: On or Under
Start: 12/3/2013              operated technologies and improve      Status Reset: N/A
Schedule Completion: 11/29/2018 aesthetics.                      (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
An analysis of the final design determined there is insufficient space to
40
accommodate security checkpoint and passenger check-in/circulation
29.2
requirements. The final report was issued in September.                   30
Dollars in Millions 20
This will be the final quarterly report until project is restarted.
10
1.5               0.4
Schedule                                       0
Authorized Forecasted   Costs
Project is on HOLD pending SAMP recommendation for project area.                       Incurred
Budget                                    Construction Costs
Project forecast is within the approved budget.                        Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Project scope definition could increase scope and budget.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 1Q 2016 Report  33

FIRST QUARTER REPORT, 2016 
South Satellite Interior Renovations 
Project: C800549             Modify the mezzanine and concourse   Project Status:
Budget: $5,167,000          levels of the South Satellite to improve  Schedule: Delayed
Phase: Construction         the passenger experience.          Budget: Forecast Overrun
Start: 11/4/2012                                          Status Reset: 12/9/2014
Schedule Completion: 10/31/2016                           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Commission Authorization was received to award the contract. Contract
awarded.                                             6   5.13    5.13
5
Schedule                                      Dollars in Millions 4
Project is behind schedule due to lengthy design reviews. Increased flight        3
2
activity has reduced the construction window of opportunity built into the                        1.11
1
project schedule and will lengthen construction as well.
0
Authorized Forecasted   Costs
Budget                                                Incurred
This project is on budget.
Construction Costs
Change Order                               Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of COs          $0            $0
Justification for COs: N/A
Risks
Heavy passenger traffic makes for shorter work hours could lead to
unanticipated gate closures making the construction run longer than anticipated.
Budget Transfers
Amount       From         To
$0



AIRPORT 
34  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Grease Interceptor Augmentation 
Project: C800551             Install one underground 9,000 gallon   Project Status:
Budget: $1,484,200          grease interceptor and one 6,000 gallon  Schedule: Delayed
Phase: Construction         above ground interceptor to service the   Budget: On or Under
Start: 5/1/2013               South Satellite, as well as hooking up    Status Reset: N/A
Schedule Completion: 6/11/2016  an existing interceptor to concessions at  (Commission Construction Auth.)
Concourse C.
Significant Developments                             Budget/Costs Incurred
PCS has installed below grade interceptor at SSAT. Procurement for above           1.5    1.5
1.6
grade interceptor is underway for early May installation. Piping work at SSAT     1.4
is nearing completion. PCS piping revisions requested at C1 are being reviewed    1.2
for acceptance.
1
0.8                           0.6
0.6
Schedule                                      Dollars in Millions 0.4
0.2
Construction began February 3, 2016. PCS and piping contractor Apollo         0
Authorized Forecasted   Costs
continue on schedule for June 11, 2016 substantial completion date.
Incurred
Budget
Construction Costs
The project forecast is within the approved budget with PCS performing work.  Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Revised layout for above grade interceptor location requested by PCS requires
review and final acceptance by Fire Marshall. Need to mitigate construction
impacts to Delta Operations at SSAT. Risk of encountering contaminated soil
in excavation- but not expected.
Budget Transfers
Amount       From         To
0


AIRPORT 
Port of Seattle 1Q 2016 Report  35

FIRST QUARTER REPORT, 2016 
NorthSTAR North Satellite Renovation and NSTS Lobbies 
Project: C800556             Renovation and expansion of the North  Project Status:
Budget: $421,682,944         Satellite (NSAT), including NSAT      Schedule: Within or Ahead
Phase: Design              Satellite Transit System (STS) stations   Budget: Forecast Overrun
Start: 7/24/2012              "refresh", ramp level, Concourse level,    Status Reset: 12/8/2015
Schedule Completion: Q4 2020   and new rooftop airline lounge.        (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Submitted MII documents for March 31st airline vote. Construction phasing             TOTAL
criteria for preliminary work package 1 has been incorporated into the design     600.0        542.9
and issued for bid. Began decision analysis process to identify construction       500.0
phasing options to maintain 14 terminal adjacent gates through NSAT          400.0
construction per AAG request. Developed criteria for Safegate Aircraft         300.0
Docking system and began coordination with Art Program artists. Identified     Dollars in Millions 200.0  157.7
gate C17 Passenger Loading Bridge replacement as a "hot project" due to        100.0             23.5
restrictions created by dual taxi-lanes during construction.                    0.0
Authorized Forecasted  Costs
Incurred
Schedule
Continuing to evaluate and finalize construction phasing options in
Construction Costs
collaboration with the GC/CM contractor and AAG. Progressed Concession
coordination along with additional temporary infrastructure requirements for    Not Applicable 
transition between construction phases 1 & 2. Discussing construction contract
requirements with GC/CM in preparation to begin construction work.
Budget
Scope additions by Port Operations and AAG and updating the forecasted
budget to $543M (Capital/Expense) required sending out an additional MII
vote.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Potential negative MII vote may delay construction start by four months. Scope
addition and delayed concurrence for construction phasing have impacted
design schedule.
Budget Transfers
Amount       From         To
$0
AIRPORT 
36  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Parking Garage Lights (CA) 
Project: C800581             Use current technology to replace all    Project Status:
Budget: $5,535,000           normal lighting in the Airport Parking    Schedule: Within or Ahead
Phase: Construction          Garage on all 8 floors and in the helices.  Budget: On or Under
Start: 1/31/2014              This will reduce energy consumption     Status Reset: N/A
Schedule Completion: 12/31/2019 over 60%.                     (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Phase 1 Major Works: Work is continuing and has moved to the first floor.
7    6.2
There are no significant issues.
6
Phase 2 Maintenance: Maintenance will continue to complete their scope as      5         4.5
time permits. We are in the new rebate period and the work does not have to be   Dollars in Millions 4
completed until a few more years in order to receive the full rebate amount.       3                2.4
2
Schedule                                       1
0
The Project is on schedule.                                         Authorized Forecasted  Costs
Incurred
Budget
The forecast is within the approved budget and authorization.              Construction Costs
1.2
1.0
1.0                 0.9
Change Order
0.8
Current Quarter     Project Total
0.6
Number of COs           0             1
0.4
Amount of Cos           $0           $2,403          Dollars in Millions 0.2
Justification for COs: None this quarter                                        0.0
0.0
Initial  Change  Spent
Risks                                                Orders
No risks at this time.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 1Q 2016 Report  37

FIRST QUARTER REPORT, 2016 
International Arrivals Facility (IAF) 
Project: C800583             Planning, design, and construction of a   Project Status:
Budget: $608,365,000         new Federal Inspection Services (FIS)    Schedule: Within or Ahead
Phase: Planning            facility including an international       Budget: On or Under
Start: 6/25/2013              passenger bridge connecting the South    Status Reset: 12/8/2015
Schedule Completion: 11/9/2019  Satellite and seven Concourse A gates to  (Commission  Authorization to start
the new IAF.                   Design & Construction)
Significant Developments                             Budget/Costs Incurred
On December 8, 2015, the Commission approved $275,500,000 for the IAF
700
Program. The Design-Builder's contract was amended on January 4, 2016, and              608.4
600
work began on the second of the three phases of Design-Build Contract - the
Dollars in Millions 500
Guaranteed Maximum Price (GMP) Development Period.                400  300.0
300
Schedule                                       200
The project is on schedule. The Design Builder (DB) submitted a Target         100              19.4
0
Schedule for design and construction, which finishes in 4th Quarter 2019.
Authorized Forecasted  Costs
Incurred
Budget
The Target budget delivered by Clark/SOM is in alignment with the overall    Construction Costs
program Budget. The GMP will be negotiated between the IAF team and the    Not Applicable 
DB at approximately 60% overall design, when both parties agree that the risks
and opportunities presented by this project have been sufficiently identified and
addressed.
Change Orders
Current Quarter     Project Total
Number of COs           0             0
Amount of COs          $0            $0
Justification for COs: N/A
Risks
Potential cost and schedule impacts from forecasted shortages of materials
and skilled labor in the current robust Seattle construction market.
Programming and scope changes driven by dynamic operational
environment and emerging customer/stakeholder interests and requests
Budget Transfers
Amount         From           To
$0

AIRPORT 
38  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Wi-Fi Enhancement 
Project: C800585              Upgrade Wi-Fi system in the public   Project Status:
Budget: $9,880,000            and ramp operational areas of the      Schedule: Delayed
Phase: Design                Airport. Provide micro-distribution     Budget: On or Under
Start: 11/4/2012                cabinets on the ramp of each         Status Reset: N/A
Schedule Completion: 9/29/2017    concourse to extend communications   (Commission Construction Auth.)
infrastructure.
Significant Developments                             Budget/Costs Incurred
Sixty percent design review is nearing completion.
12           10.68
10
Schedule
8
Design has taken longer than anticipated to start. Currently, good progress is     Dollars in Millions 6
being made toward design completion. Anticipate the first construction          4
1.95
authorization in Q2 2016.                                       2               0.52
0
Budget                                       Authorized Forecasted  Costs
Incurred
Within budget; however, the project is now forecast to exceed its estimate. A
request for additional budget is forthcoming to cover the cost increase as a part
Construction Costs
of the next authorization.
Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of COs          $0            $0
Justification for COs: N/A
Risks
Wi-Fi signal audits have prescribed more access points than currently budgeted.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 1Q 2016 Report  39

FIRST QUARTER REPORT, 2016 
Checked Baggage Recapitalization/Optimization 
Project: C800612             TSA approached the Airport in 2012    Project Status:
Budget: $320,550,000         with plan to replace all federally owned   Schedule: Within or Ahead
Phase: Design              and operated baggage scanning        Budget: On or Under
Start: 2/26/2013              equipment, known as Explosive        Status Reset: N/A
Schedule Completion: 12/31/2024 Detection System (EDS) equipment.     (Commission Construction Auth.)
The EDS equipment is approaching the
end of its life.
Significant Developments                             Budget/Costs Incurred
The 100% design documents were received from our design team January 15,
400
2016. The documents were sent to TSA, Airlines, Airline Technical                     320.5
Representative, and Port Stakeholders for review. All comments on the 100%     300
design document are due to the project team April 6, 2016.TSA has completed
their review and has issued comments. The Project team will be working with
200
all stakeholders to close out design review comments by end of April.          Dollars in Millions 100
20.4             15.3
0
Schedule                                         Authorized Forecasted  Costs
Incurred
The project is currently on schedule, but is being reviewed for 10-year plan
Budget                                    Construction Costs
The project forecast is within the approved budget. When the bid documents are  Not Applicable 
completed, request Commission Authorization for construction funding and
authority to advertise for construction.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0


AIRPORT 
40  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Gate S1 Ramp 
Project: C800629             Install a ramp to facilitate travel       Project Status:
Budget: $1,405,000           between the ramp surface and the       Schedule: Within or Ahead
Phase: Construction          International arrivals facility for       Budget: On or Under
Start: 11/24/2013             passenger use.                    Status Reset: 12/9/2014
Schedule Completion: 6/1/2015                               (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The steel has been fabricated and installed for weather protection work. Glazing
1.5     1.4
has been ordered.                                                      1.2
1.1
Dollars in Millions 1
Schedule
Project is on schedule to be completed by June 1.
0.5
Budget
0
The project forecast is within approved budget and authorization.               Authorized Forecasted  Costs
Incurred
Change Order
Construction Costs
Current Quarter     Project Total
Not Applicable 
Number of COs           0             0
Amount of Cos            0             0           Photo
Justification for COs: N/A
Risks
The project team will continue to monitor the weather protection work to
remain within the project budget.
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 1Q 2016 Report  41

FIRST QUARTER REPORT, 2016                                                          FIRST QUARTER REPORT, 2016 
Alaska Hangar One Roof                                              Dining and Retail Infrastructure Modernization 
Project: C800637             Remove and replace the current roofing Project Status:                  Project: C800638             Project is to provide infrastructure     Project Status:
Budget: $1,927,000          system on the Alaska Hangar One and   Schedule: Delayed             Budget: $13,953,000         modifications, re-demise of spaces, two  Schedule: Within or Ahead
Phase: Design             associated maintenance building.      Budget: On or Under            Phase: Design             new elevators, and two new Children's   Budget: Forecast Overrun
Start: 4/1/2014                                           Status Reset: N/A                Start: 10/28/2014             Play Areas in support of the Airport     Status Reset: N/A
Schedule Completion: 10/2/2016                            (Commission Construction Auth.)         Schedule Completion: 6/30/2020  Dining and Retail concessions plan.     (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Significant Developments                             Budget/Costs Incurred
Design Package #2 (CTE) 90% complete. Design Package #3 is 30% complete.
Project has been bid and Notice of Intent to Award is pending. Construction                                                                                         15         13.95
2.5
scheduled to start in third quarter.                                          1.9     1.9
2                              Schedule
10    8.83
Schedule                                      Dollars in Millions 1.5                   Developing the overall schedule of Lease Groups. Design and construction
packages will follow from that.
Project is behind schedule while the project scope is being reviewed against the     1                                                                                   5
1.46
Strategic Airport Master Plan.                                     0.5               0.2                                                                 Dollars in Millions
Budget
0
0
Currently forecasting a budget increase due to: changes made to the sequence       Authorized Forecasted  Costs
Budget                                        Authorized Forecasted Costs                                                          Incurred
Incurred          and timing of leasing activities which have directly impacted construction,
Project forecast is within the approved budget.
scope changes and additions. Returning to Commission to request additional
Construction Costs
Construction Costs          budget in the 2nd Quarter.
Change Order                                                                                            Not Applicable 
Not Applicable 
Current Quarter     Project Total                               Change Order
Number of COs           0             0                                                 Current Quarter     Project Total
Amount of Cos           $0             $0                                   Number of COs           0             0
Justification for COs: N/A                                                                    Amount of COs             $0               $0
Justification for COs: N/A
Risks
Delaying this project could increase costs.                                                         Risks
1. Construction is linked with leasing;
Budget Transfers
2. Projects in the Central Terminal are linked with other projects and delays in
Amount       From         To                          those projects could impact this project.
$0
Budget Transfers
Amount       From         To
$0


AIRPORT 
AIRPORT 
42  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Dining and Retail Infrastructure Modernization 
Project: C800638             Project is to provide infrastructure     Project Status:
Budget: $13,953,000         modifications, re-demise of spaces, two  Schedule: Within or Ahead
Phase: Design             new elevators, and two new Children's   Budget: Forecast Overrun
Start: 10/28/2014             Play Areas in support of the Airport     Status Reset: N/A
Schedule Completion: 6/30/2020  Dining and Retail concessions plan.     (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Design Package #2 (CTE) 90% complete. Design Package #3 is 30% complete.
15           13.95
Schedule
10    8.83
Developing the overall schedule of Lease Groups. Design and construction
packages will follow from that.                                   Dollars in Millions 5
1.46
Budget
0
Currently forecasting a budget increase due to: changes made to the sequence       Authorized Forecasted  Costs
Incurred
and timing of leasing activities which have directly impacted construction,
scope changes and additions. Returning to Commission to request additional
Construction Costs
budget in the 2nd Quarter.
Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of COs          $0            $0
Justification for COs: N/A
Risks
1. Construction is linked with leasing;
2. Projects in the Central Terminal are linked with other projects and delays in
those projects could impact this project.

Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 1Q 2016 Report  43

FIRST QUARTER REPORT, 2016 
CCTV Camera and System Enhancement 
Project: C800642             Add cameras and improve the video    Project Status:
Budget: $13,000,000         management system at the Airport.     Schedule: Delayed
Phase: Design             Project funded by a TSA Other       Budget: On or Under
Start: 11/4/2012              Transaction Agreement (OTA)        Status Reset: N/A
Schedule Completion: 7/1/2019                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Design for ramp cameras is nearly complete. Remaining camera installation
projects are in pre-design. The video management system upgrade is           15        13.00
progressing on schedule.
10
Schedule
5    4.07
Design took longer than anticipated to begin. This delay now cannot be
recovered. Project team has re-phased the project to complete high priority      Dollars in Millions                 0.51
0
locations first. Ramp cameras design is anticipated to complete in May 2016
Authorized Forecasted   Costs
with a construction start in Summer 2016. Additional camera installations will                   Incurred
follow.
Construction Costs
Budget                                    Not Applicable 
Project continues to be within approved budget.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of COs          $0            $0
Justification for COs: N/A
Risks
The project team is reviewing as-built information and site conditions in order
to understand variances.
Budget Transfers
Amount       From         To
$0


AIRPORT 
44  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Emergency Phones 
Project: C800648               Overhaul and modernize the      Project Status:
Budget: $536,000              Airport Parking Garage Emergency  Schedule: Delayed
Phase:  Design               Phone System.              Budget: On or Under
Start: 7/9/2015                                          Status Reset: N/A
Schedule Completion: 12/31/2015                           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The new conduit runs are approximately 80% complete. PCS started installation
of the new overhead signs.                                       0.6   0.5    0.5
0.5
Schedule                                       0.4
Schedule was originally delayed due to availability of open order small works     0.3
0.2
0.2
electrical contract resources. Electrical work has to be bid due to the lack of
0.1
availability of open order small works contracting. Remaining schedule is       Dollars in Millions
0
dependent on working areas availability in the parking garage. PCS is working
Authorized Forecasted  Costs
closely with AV Operations to work around peak times, etc.                               Incurred
Budget                                    Construction Costs
Currently within the budget.                                     Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: None
Risks
Limited availability of construction crew resources may increase the schedule.
The work is in the Airport parking garage. Need to coordinate closely with
Operations to minimize potential delays. 
Budget Transfers
Amount       From         To
$0


AIRPORT
Port of Seattle 1Q 2016 Report  45

FIRST QUARTER REPORT, 2016 
Passenger Loading Bridge Renew 
Project: C800653               Renewal/Replacement of Passenger  Project Status:
Budget: $6,250,000             Loading Bridges B6, B8, B14, C3,   Schedule: Within or Ahead
Phase:  Design               S15 and C17               Budget: On or Under
Start: 7/18/2014                                          Status Reset: 4/26/2016
Schedule Completion: 3/31/2017                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Gate C17 was authorized by Commission in April. All previous gate work has
8.0    7.25
been completed.                                                    6.25
6.0
Dollars in Millions                        4.34
Schedule
4.0
C17 is expected to proceed on schedule.
2.0
Budget
0.0
Within Budget                                              Authorized Forecasted  Costs
Incurred
Change Order
Construction Costs
Current Quarter     Project Total       Not Applicable at this time 
Number of COs           0             0
Amount of COs          $0            $0
Risks
None
Budget Transfers
Amount       From         To
$0




AIRPORT 
46  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Domestic Water Piping 
Project: C800657             Replace domestic water piping       Project Status:
Budget: $1,450,000          branches and manifolds including     Schedule: Delayed
Phase: Design             valves.                     Budget: On or Under
Start: 11/4/2012                                          Status Reset: 5/13/2014
Schedule Completion: 6/7/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Project was successfully bid. Partial Notice to proceed (NTP) was issued mid-
$3
March.                                                2.0
$2
Dollars in Millions                1.5
Schedule                                       $2
Substantial completion scheduled for June 7, 2016. Contractor is late with pre-     $1
NTP submittals. NTP was expected in early January, 45 days after execution of    $1               0.2
contract. Partial NTP was issued in mid-March, which puts construction
$0
completion at risk. Contractor is evaluating how best to recover the schedule.        Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
Project is within budget.
Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Schedule as noted above.
Budget Transfers
Amount       From         To
$0



AIRPORT
Port of Seattle 1Q 2016 Report  47

FIRST QUARTER REPORT, 2016 
Mech Energy Conservation (CA) 
Project: C800658             Stage 3 Mechanical Energy          Project Status:
Budget: $3,500,000           Conservation to improve the efficiency   Schedule: Within or Ahead
Phase: Audit/Notebook        of portions of the mechanical         Budget: On or Under
Start: 8/25/2014              infrastructure system at the Airport.      Status Reset: N/A
Schedule Completion: 12/31/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Project is on hold pending review and decision by the Airport directors. This
4           3.5
will be the final report until a decision has been made.
3
Schedule
Project construction schedule has not been finalized as this project only
2
received commission approval for audit and preliminary design. Final schedule   Dollars in Millions 1
0.3               0.2
will be affected by length of time required to complete Airport directors project
0
review, second MII vote due to increased budget, commission approval process      Authorized Forecasted  Costs
Incurred
and construction schedule.
Budget                                    Construction Costs
Future Commission authorization required for construction funds after        Not Applicable 
completion of Aviation division approvals. Facilities and Infrastructure is
recommending an increase in budget to $5,019,000. The requested amount
could change if further scope changes are made or construction costs change
due to project timing.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Project is complex due to diversity in scope of work and location of nine
separate energy conservation measures. Project financials are complicated as
they are impacted by assumptions in airport growth and future costs of energy.
Budget Transfers
Amount       From         To
$0

AIRPORT 
48  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Construction Logistics Expansion 
Project: C800688              The expansion and reconfiguration of   Project Status:
Budget:  $9,600,000          the existing construction logistics      Schedule: Within or Ahead
Phase:  Construction           facilities (including contractor parking)   Budget: On or Under
Start: 8/1/2014                and the renovation of Port field offices.   Status Reset: 2/23/2016
Schedule Completion: 12/30/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Completed construction of the Contractor Parking Lot (CPL), and Logistics      12.0
Lots 1 and 2. Issued noticed to proceed on February 19, 2016 for the remaining         9.6    9.6
10.0
Construction Logistics facilities and began work in Lots 4 and 5. Commission     8.0
authorized construction for the Field Office renovation and the new scope, CPL    6.0
Bus Stops, on February 23, 2016. Completed final design, advertised, and       Dollars in Millions 4.0              2.4
opened bids for the Field Office renovation. Lowest responsive bidder was       2.0
Regency NW Construction with a bid that was less than 1% above the          0.0
Engineer's Estimate. Completed 90% design for the CPL Bus Stops.             Authorized Forecasted  Costs
Incurred
Schedule
Construction Costs
The project is currently on schedule with completion dates of Q3 2016 for
Construction Logistics; Q4 2016 for Field Office Renovation and CPL Bus        4
3.4
Stops.
3
Budget                                       2
1.4
The overall budget has increased to $9.6 million with CPL Bus Stops.          Dollars in Millions  1
0.1
Change Order                                  0
Initial    Change    Spent
Current Quarter     Project Total                 Orders
Number of COs           5             5
Amount of COs         $52,382         $52,382
Photo
Justification for COs: designer error and omission ($17,382), owner error and
omission ($0), and regulatory ($35,000).
Risks
Construction Logistics: Completion of the work to support Capital Program.
Field Offices: Additional scope due to unknown building conditions.
CPL Bus Stops: Completion of the work to support Capital Program.
Budget Transfers
Amount       From         To
$0
AIRPORT
Port of Seattle 1Q 2016 Report  49

FIRST QUARTER REPORT, 2016 
C3 Holdroom Expansion 
FIRST QUARTER REPORT, 2016 
2016 Fuel System Modifications                                             Project: C800695             Provide a 1,500 square foot      Project Status:
Budget: $3,300,000             building addition at the concourse   Schedule: Within or Ahead
Project: C800692               Airline activity growth at the      Project Status:                   Phase:  Design                level to increase the size of the Gate  Budget: On or Under
Budget: $4,680,000             Airport is requiring the installation   Schedule: Delayed               Start: 4/4/2016                C3 passenger holdroom.         Status Reset: N/A
Phase:  Construction           of a new fuel pits in 2016.        Budget: On or Under             Schedule Completion: 6/30/2018                          (Commission Construction Auth.)
Start: 11/6/2013                                          Status Reset: 11/11/2014
Schedule Completion: 10/30/2016                           (Commission Design Auth.)
Significant Developments                             Budget/Costs Incurred
Started design work.
Significant Developments                             Budget/Costs Incurred                                                        4
3.30
Scope was increased by five additional new fuel pits to accommodate the new                               Schedule                                                3
5    4.7      4.7
narrow body gate configurations at the South Satellite, bringing the total to nine                                Project is on schedule.
2
new fuel pits.                                                  4
Dollars in Millions 3                                      Budget                                                                          1    0.65
Schedule                                       2                                                                Dollars in Millions             0.10
Project is on budget.                                              0
Project advertised for construction in Q1 2016 with low bid 18% over the
1                                                                                                      Authorized Forecasted   Costs
0.2
engineer's estimate. Commission action required prior to award. Anticipate                                                                                                       Incurred
Change Order
0
beginning construction in Q3 2016 with completion in Q4 2016.               Authorized Forecasted  Costs                           Current Quarter      Project Total
Incurred                                                                                Construction Costs
Number of COs           0             0
Budget                                                                                                 None at this time 
Amount of COs          $0            $0
Commission Authorization to increase authorization and scope was approved   Construction Costs
on November 10, 2015.                                    None at this time                                                                   Photo
Risks
Change Order                                                     Investigating existing conditions.
Current Quarter     Project Total                               Budget Transfers
Number of COs           0             0
Amount       From         To
Amount of Cos           $0             $0
$0
Justification for COs: None at this time
Cost Growth of Construction
Risks
N/A
Potential for gate configuration changes could affect fuel pit locations.
Budget Transfers
Amount       From         To
$0


AIRPORT
AIRPORT 
50  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
C3 Holdroom Expansion 
Project: C800695               Provide a 1,500 square foot       Project Status:
Budget: $3,300,000             building addition at the concourse   Schedule: Within or Ahead
Phase:  Design               level to increase the size of the Gate  Budget: On or Under
Start: 4/4/2016                 C3 passenger holdroom.          Status Reset: N/A
Schedule Completion: 6/30/2018                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Started design work.
4
3.30
Schedule                                       3
Project is on schedule.
2
Budget                                     Dollars in Millions 1  0.65
0.10
Project is on budget.                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total
Construction Costs
Number of COs           0             0
None at this time 
Amount of COs          $0            $0
Photo
Risks
Investigating existing conditions.
Budget Transfers
Amount       From         To
$0
Cost Growth of Construction
N/A




AIRPORT
Port of Seattle 1Q 2016 Report  51

FIRST QUARTER REPORT, 2016 
Electric Utility SCADA 
Project: C800699               Install a Supervisory Control and   Project Status:
Budget: $9,650,000             Data Acquisition (SCADA) system   Schedule: Within or Ahead
Phase:  Design               for the Airport's 12.47 kV Medium   Budget: On or Under
Start: 8/5/2015                 Voltage (MV) power distribution    Status Reset: 8/4/2015
Schedule Completion: 10/25/2017   network.                   (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Thirty percent design started.                                      12
9.7
10
Schedule
8
Project is on schedule. Thirty percent design is scheduled to complete Q3 2016    6
Budget                                     Dollars in Millions 4
1.6
2
0.1
Project is within budget.                                           0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: None at this point.
Risks
Controls are being added to an existing electrical system that includes several
manufacturers' equipment resulting in potential coordination challenges.
Unplanned shutdowns may also occur, but is being mitigated through site
investigations.
Budget Transfers
Amount       From         To
$0




AIRPORT
52  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
2015-2016 Concourse C Roof Replacement 
Project: C800702             Remove and replace the existing roof  Project Status:
Budget: $5,596,000           system (approximately 83,000 square   Schedule: Within or Ahead
Phase:  Design             feet) on Concourse C; install a new    Budget: On or Under
Start: 5/26/2010              elastomeric roofing system; ladders    Status Reset: N/A
Schedule Completion: 11/30/2016  and fall protection; and replace and                          (Commission Construction Auth.)
refurbish the existing skylight
window/walls.
Significant Developments                             Budget/Costs Incurred
Project is out for bid.
8
5.90     5.90
Schedule                                       6
Project is on schedule                                           4
Budget                                     Dollars in Millions 2           1.00
Project is within budget.                                           0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          None at this time
Amount of Cos           $0             $0
Risks
This project was advertised later in the bid season which could lead to higher
than planned bids. If the bid comes in high, they will need to be evaluated and
a decision will need to be made to accept or rebid in 2017.
Budget Transfers
Amount       From         To
$0




AIRPORT
Port of Seattle 1Q 2016 Report  53

FIRST QUARTER REPORT, 2016 
South Satellite Steam Piping Utility Upgrade 
Project: C800708             Replace expansion joints in the SSAT   Project Status:
Budget: $1,000,000          steam piping supply system.         Schedule: Within or Ahead
Phase: Design                                      Budget: On or Under
Start: 11/1/2015                                          Status Reset: n/a
Schedule Completion: 12/31/2016                           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Sixty percent documents were received and reviewed in March.
$1
1.0       1.0
$1
Schedule
$1
Design began in January 2016. Sixty percent documents are complete. Ninety    Dollars in Millions $1
percent are due in April. Ready-to-bid documents are due in May.             $0
$0                         0.1
Budget                                     $0
Authorized Forecasted   Costs
Project is within budget.                                                         Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable 
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Schedule as noted above.
Budget Transfers
Amount       From         To
$0




AIRPORT
54  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Central Terminal Stairs 
Project: C800716               This project will build two       Project Status:
Budget: $2,217,000             stairways near the central         Schedule: Within or Ahead
Phase:  Design               checkpoint to provide egress      Budget: On or Under
Start: 2/15/2015                capacity from the mezzanine level   Status Reset: n/a
Schedule Completion: 5/21/2017    to the ticketing level on the non-    (Commission Construction Auth.)
secure side of the airport.
Significant Developments                             Budget/Costs Incurred
Design concept review and 30% Design Review completed.
3
Upcoming activities:                                                   2.6
2.5
60% Design Review
2
1.5
Schedule                                      Dollars in Millions  1
0.5
The project is on schedule.                                        0.5               0.1
0
Budget                                        Authorized Forecasted Costs
Incurred
Project is within the budget. 
Construction Costs
Change Order
None at this time
Current Quarter     Project Total
Number of COs           0             0          Photo
Amount of Cos           $0             $0
Risks
Traffic increases have complicated construction phasing which may extend the
project past the completion date.
Budget Transfers
Amount       From         To
$0




AIRPORT
Port of Seattle 1Q 2016 Report  55

FIRST QUARTER REPORT, 2016 
Terminal Utilities Upgrade Project 
Project: C800717               Replace and extend the steam,     Project Status:
Budget: $9,950,000             condensate and chilled water       Schedule: Within or Ahead
Phase:  Design               supply and return piping from the    Budget: On or Under
Start: 9/21/2010                Central Mechanical Plant to the end  Status Reset: N/A
Schedule Completion: 3/1/2018     of mechanical room four and to the   (Commission Construction Auth.)
ends of the South and West Loops.
Significant Developments                             Budget/Costs Incurred
Fifteen percent design received. Investment Committee decision required for
25000          20,456.
next steps.                                                               0
20000
Schedule                                     15000
Project design delayed in order to coordinate design efforts with Baggage      10000
Optimization designer. Overall project completion not impacted at this time.     5000  Dollars in Millions     2.0           0.1
0
Budget                                       Authorized Forecasted  Costs
Incurred
Additional Commission authorization needed to complete entire project to meet
future airport growth.
Construction Costs
Change Order                               Not Applicable
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Risks
Risk to schedule and budget routing large sections of pipe through a very
densely developed part of the airport. Risks to be minimized during design.
Budget Transfers
Amount       From         To
$0



AIRPORT
56  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
CTE HVAC Upgrade 
Project: C800722               Install two new air-handling units   Project Status:
Budget: $6,612,000             (AHUs) on the roof above the N.    Schedule: Within or Ahead
Phase:  Design               and S. mezzanine levels of the     Budget: On or Under
Start: 5/8/2015                 central terminal to provide heating,   Status Reset: n/a
Schedule Completion: 12/31/2017   ventilation, and air conditioning     (Commission Construction Auth.)
infrastructure systems.
Significant Developments                             Budget/Costs Incurred
Thirty percent design submittal received.                              8
6.6
Schedule                                       6
Project is on schedule.                                          Dollars in Millions 4
2    1.1
Budget
0.2
Project is within budget.                                          0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: None at this time
Risks
Risk to project budget if significant structural upgrades to the penthouse roofing
systems are required. Risk to be mitigated during design process.
Budget Transfers
Amount       From         To
$0




AIRPORT
Port of Seattle 1Q 2016 Report  57

FIRST QUARTER REPORT, 2016 
Concourse C New Power Center 
Project: C800724               Add new 5000A double ended unit  Project Status:
Budget: $10,500,000             substation (power center) on Ramp   Schedule: Within or Ahead
Phase:  Design                level at column line F/40 for a new   Budget: On or Under
Start: 10/26/2014               electrical room in Concourse C.     Status Reset: n/a
Schedule Completion: 12/31/2017    The existing distribution panels will  (Commission Construction Auth.)
be re-fed from the new power
center and new distribution panels
and branch circuit panels will be
added. 
Significant Developments                             Budget/Costs Incurred
Working with CPO and Consultant to develop Service Directive scope of work,
12           10.5
level effort. Staff is currently reviewing Consultant submittals.
10
Schedule
8
6
Probable completion of 100% design bid documents 3rd Qtr. 2016.           Dollars in Millions 4
2.0
Probable construction completion date 4th Qtr. 2017                      2
0.1
0
Budget                                       Authorized Forecasted  Costs
Incurred
The project cost forecast is within the September 22, 2015 Commission
approved budget 
Construction Costs
Change Order                               Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Airline Gate Realignment program may affect Concourse C projects.
Budget or schedule may be affected if site conditions differ from record
files.
Contractor purchased equipment may not fit in Concourse C allocated space
for this new power center room
Budget Transfers
Amount       From         To
$0

AIRPORT
58  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Concourse B Roof Replacement 
Project: C800770               Remove and replace approx. 86,500 Project Status:
Budget: $7,262,000             sq ft of roofing system on        Schedule: Within or Ahead
Phase:  Design               Concourse B. Also add stairs,      Budget: On or Under
Start: 3/8/2016                 ladders, fall protection and        Status Reset: N/A
Schedule Completion: 11/18/2018   refurbish or replace Kalwall       (Commission Construction Auth.)
windows/skylights.
Significant Developments                             Budget/Costs Incurred
Developing Service Directive for design.                             8         7.2
Schedule                                       6
Project is on schedule                                           4
Budget                                     Dollars in Millions 2  1.2
0.3
Project is within budget                                           0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          None at this time
Amount of Cos           $0             $0
Risks
No major risks at this time.
Budget Transfers
Amount       From         To
$0





AIRPORT
Port of Seattle 1Q 2016 Report  59

FIRST QUARTER REPORT, 2016 
D6 Gate Modifications 
Project: C800771               Add casework to the holdroom,    Project Status:
Budget: $1,733,000             access control to the exterior door   Schedule: Within or Ahead
Phase:  Design               and an ADA sloped walkway from   Budget: On or Under
Start: 9/20/2015                the holdroom to the ramp level for   Status Reset: N/A
Schedule Completion: 3/31/2017    passengers to gain access to buses   (Commission Construction Auth.)
that will transport them to remotely
parked aircraft.
Significant Developments                             Budget/Costs Incurred
Thirty percent design completed.
2    1.7      1.7
Schedule                                      1.5
The project is on schedule.
1
Budget                                     Dollars in Millions 0.5           0.2
Project is within budget.                                           0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total
Construction Costs
Number of COs           0             0
None at this time
Amount of Cos           $0             $0
Photo
Risks
None at this time.
Budget Transfers
Amount       From         To
$0




AIRPORT
60  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
South Satellite Narrow Body Configuration 
Project: C800781              Planning, design and construction   Project Status:
Budget: $5,500,000             of three new narrow body positions   Schedule: Within or Ahead 
Phase: Design               at the South Satellite. Scope       Budget: On or Under 
Start: 2/23/2010                includes one new passenger loading  Status Reset: 2/23/2016 
Schedule Completion: 12/31/2017   bridge (PLB), one new fuel pit, a    (Commission Construction Auth.)
new staircase and ADA lift at S10,
new portable equipment, and
pavement marking. 
Significant Developments                              Budget/Costs Incurred 
On February 23, 2016, the Commission approved the $5.5M for the SSAT
6    5.5      5.5
Narrow Body Project. This contract will be an amendment to Clark's IAF
5
contract but will be tracked and treated as a separate project. We are waiting for
Dollars in Millions 4                                                                              an updated cost estimate from Clark in order to execute the contract
3
amendment. 
2
1
Schedule                                                   0.0
0
The project is on schedule and will blend with the IAF's design and              Authorized Forecasted  Costs
construction schedule. Completion of the Narrow Body Project will be finished                  Incurred
in 4th Quarter 2017. 
Construction Costs
Budget                                    N/A 
The budget for project is $5.5M, however, this is expected to decrease when we
Photo
negotiate Clark's design and construction fee in the contract addendum. 
Change Order
Current Quarter     Project Total
Number of COs           0              0 
Amount of Cos           $0             $0 
Risks
Current gating needs limit the ability to take gates out of service.
Current IAF schedules project this work to be completed in 2017. Since
all of the work is outside construction schedule could be impacted by
weather.
This chance in the layout of the SSAT (specifically adding parking
positions) will trigger and addendum to the SEPA and NEPA for the
IAF Project.
Budget Transfers
Amount       From         To
$0 
AIRPORT
Port of Seattle 1Q 2016 Report  61

FIRST QUARTER REPORT, 2016 
Zone 5 Ticket Lobby Reconfiguration 
Project: C800824               Project is to add seven Common    Project Status:
Budget: $1,781,000             Use ticket counters positions for    Schedule: Within or Ahead
Phase:  Design               new airline entrants within Zone 5   Budget: On or Under
Start: 10/5/2015                and the reconfigure existing AA     Status Reset: 4/22/2016
Schedule Completion: 5/26/2017    ticket counters and kiosks.        (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Original project concept was to install the Common Use counters along the
2
window wall and add a bag belt into the dog house. Since then, AA has come               1.78
back with a proposal to give up space within their ticketing counters and adjust    1.5
their lease space to have their counters moved over and use the window wall
lobby for AA kiosks. This development should save time and money and will
1
be evaluated as the design develops.                                Dollars in Millions 0.5   0.32
0.01
0
Schedule                                        Authorized Forecasted  Costs
Project is on schedule.                                                          Incurred
Budget                                    Construction Costs
Project is within budget.                                         None at this time
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Risks
None
Budget Transfers
Amount       From         To
$0



AIRPORT
62  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Interim Baggage System Program 
Project: C800825             Implement program of individual      Project Status:
Budget: $14,200,000          projects with the objective of increasing   Schedule: Within or Ahead
Phase: Construction          reliability and capacity through the      Budget: Forecast Overrun
Start: 12/13/2015             interim period between the upcoming    Status Reset: N/A
Schedule Completion: 10/1/2017  summer and Baggage Optimization      (Commission Construction Auth.)
Project.
Significant Developments                             Budget/Costs Incurred
Baggage Input Load Balancing: Design is underway.                       14.2    14.2
15
Security Zone Tracking Enhancements: Design scope of work is in progress.
TSA Search Room Expansion: Design has started.
10
Clear Bag Reconciliation: Scope of work is being drafted.
5
Schedule                                      Dollars in Millions             0.4
All four elements of this project are considered hot and on a fast track schedule.    0
The project is on schedule.                                         Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
The project forecast is within the approved budget and authorization. 
Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Any project on the fast track schedule has potential risks of not meeting
schedule or budget. The team is working together to utilize all resource
avenues to get this completed on time.
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 1Q 2016 Report  63

FIRST QUARTER REPORT, 2016 
RM Abatement for Tenant Projects 
Project: U00234  U00237         Provide regulated materials       Project Status:
Budget: $1,800,000             abatement support as needed in four  Schedule: Within or Ahead
Phase:  Construction           locations in the Main Terminal that   Budget: On or Under
Start: 12/1/2015                will be leased by airline tenants.     Status Reset: 8/4/2015
Schedule Completion: 9/30/2016                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The abatement work under this project has been separated into four Work
2    1.8      1.8
Projects as follows:
U00234  Former US Airways Ticketing and ATO  Abatement completed Q1   1.5
2016                                                        0.8
U00235  North Mezzanine Office Space  Abatement completed Q4 2015
1
U00236  Former Lounge Space Checkpoint #5  Abatement underway       Dollars in Millions 0.5
U00237  Vacant ATO Space Zone 7  Abatement scheduled for Q2
0
Authorized Forecasted   Costs
Schedule                                                  Incurred
Completed projects finished on schedule and those currently in progress are on
schedule. Alaska has requested that a portion of the abatement work at Zone 7   Construction Costs
be held off until after Labor Day to accommodate operational requirements.
0.5
0.4
Budget                                      0.4
0.3
The remaining projects are on budget or haven't been started as of this
reporting date.                                                Dollars in Millions 0.2
0.1
Change Order                                       0.0  0.0
0
Current Quarter     Project Total            Initial Change Spent
Orders
Number of COs           0             0
Amount of Cos           $0             $0
Risks
None at this time.
Budget Transfers
Amount       From         To
$0


AIRPORT
64  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
North East Redevelopment Area Program 
Project: U000239               This is an FAA funded project with  Project Status:
Budget: $5,000,000             participation from the City of      Schedule: Within or Ahead
Phase:  Design               Burien but led by Port (500K each).  Budget: On or Under
Start: 8/16/2015                The project is to redevelop the Area  Status Reset: 10/14/2014
Schedule Completion: 5/12/2019    north of the airport in the City of    (Commission Construction Auth.)
Burien.
Significant Developments                             Budget/Costs Incurred
Economic Development Real Estate Group Selected Developer for Site
6
Improvements January 2016.                                     5.0    5.0
5
Service Directive 2 - "Survey and Basemap Prep" executed February 2016.
4
Service Directive 3 - "30% Design" negotiated to be executed May 2016.
3
2
Schedule                                      Dollars in Millions 1            0.2
The project schedule completed and project is currently on schedule.           0
Authorized Forecasted   Costs
Incurred
Budget
Project is within commission authorization. 
Construction Costs
Change Order                               None at this time
Current Quarter     Project Total       Photo
Number of COs           0             0
Amount of Cos           $0             $0
Risks
Developer selected and Port unable to come to terms on lease.
Budget Transfers
Amount       From         To
$0




AIRPORT
Port of Seattle 1Q 2016 Report  65

FIRST QUARTER REPORT, 2016 
Highline Schools Noise Insulation 
Project: C200007              Highline School Insulation Agreement  Project Status:
Budget: $101,797,000           will provide funding for sound       Schedule: Delayed
Phase: Construction            insulation for 15 schools that are      Budget: On or Under
Start: 3/23/1999                impacted by aircraft noise from Sea-    Status Reset: N/A
Schedule Completion: 11/30/2021   Tac Airport                  (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Port funds authorized for availability when the FAA, the State of Washington,
120
and the Highline School District (HSD) provide matching funds. HSD has been        102.1   101.8
100
unable to pass a school bond vote. Project has an unknown timeframe until a
bond passes.                                              Dollars in Millions 80              63.4
60
40
Schedule
20
The schedule for state funds is unknown. The district's schedule is dependent on     0
obtaining general election bonds at various intervals. The district's construction       Authorized Forecasted  Costs
Incurred
schedule at this point is unknown.
Budget                                    Construction Costs
Not Applicable 
The project forecast is within the approved budget and authorization.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Project delayed due to funding issues with HSD. There is a risk if there are no
bonds passed in the general election, and if FAA Airport Improvement Program
(AIP) Grant funding is not available.
Budget Transfers
Amount       From         To
$0


AIRPORT 
66  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Home Insulation Retrofit 
Project: C200048              Storm window retrofit of previously   Project Status:
Budget: $4,060,147            insulated homes.                Schedule: Within or Ahead
Phase: Construction                                     Budget: On or Under
Start: 1/11/2005                                            Status Reset: N/A
Schedule Completion: 4/30/2016                             (Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
All known eligible homes have been identified and owners have been notified     6   5.3
by certified mail. At this point, no further applications were received for this       5
4.1
project.                                                      Dollars in Millions 4                3.4
3
Schedule                                       2
The project is in the process of being closed.                            1
0
Authorized Forecasted   Costs
Budget                                                Incurred
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                               Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The ability to accomplish the retrofit is dependent on homeowner's voluntary
participation.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 1Q 2016 Report  67

FIRST QUARTER REPORT, 2016 
Single Family Home Sound Insulation 
Project: C200093             Sound insulate remaining homes that are Project Status:
Budget: $13,747,395          within the 1998 65 decibel day night     Schedule: Within or Ahead
Phase: Construction          level (DNL) noise contour.           Budget: On or Under
Start: 3/27/2007                                           Status Reset: N/A
Schedule Completion: 11/1/2016                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The final two homes are in the process of receiving sound insulation.
15    13.7     13.7
Schedule
Dollars in Millions 10
Project is on schedule. Anticipate completion by 4th quarter 2016.
5.4
5
Budget
The project forecast is within approved budget and authorization to complete all    0
homes currently in progress.                                        Authorized Forecasted  Costs
Incurred
Change Order
Construction Costs
Current Quarter     Project Total
Number of COs           0             0                3.8
4
Amount of Cos           $0             $0
3
Justification for COs: N/A                                       Dollars in Millions  2           1.8
Risks
1
The ability to accomplish the insulation is dependent on the homeowner's                0.0
schedules, willingness to sign an aviation easement, obtain a subordination        0
Initial  Change  Spent
agreement from their lender, and structural integrity of the home.                     Orders
Budget Transfers
Amount       From         To
$0



AIRPORT 
68  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Tenant Reimbursement 
Project: C800154              Build-out of spaces for new and      Project Status:
Budget: $4,709,577            existing tenants. If more than a "basic   Schedule: Within or Ahead
Phase: Construction            finish", condition space is built for the   Budget: On or Under
Start: 8/14/2007                tenant. Tenant is required to reimburse  Status Reset: N/A
Schedule Completion: TBD      the Port for the cost of the work      (Commission Construction Auth.)
beyond the "basic finish. Reimb
allowed under the guidelines in the
"Tenant Reimb. Policy:
Significant Developments                             Budget/Costs Incurred
In 2016, anticipate reimbursement for some reimbursable work that tenants
5    4.7      4.7
have done on their project buildouts (Delta, Alaska, and American), whereby
4
the Port's Fire Department has required the tenant to upgrade the fire sprinkler
system in areas they are building out, as well as additional code upgrades.       Dollars in Millions 3
2                  1.3
Schedule
1
Schedules vary to meet the tenant's needs.                             0
Authorized Forecasted   Costs
Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 1Q 2016 Report  69

FIRST QUARTER REPORT, 2016 
Street Vacations T-5 and T-18 
Project: C102858, C102875        Street vacation related real estate   Project Status:
Budget: $5,300,000              negotiations and agreements  T-5,   Schedule: Delayed
Phase: Permitting              and T-18                   Budget: On or Under
Start: 6/1/2010                                            Status Reset: N/A
Schedule Completion: 2016                                (Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
Master easement complete except for asset transfer agreement and easement      5.3   5.3    5.3
encroachment issues. Port of Seattle's (POS) Stormwater Utility District is        5.3
negotiating an asset transfer agreement for stormwater drains. Century Link      5.2
staff completed design and cost estimates to reconfigure the hut to remove it
5.2
from the encroachment. Three-party meeting scheduled for June 2016 to
5.1                     5.1
5.1
discuss design of reconfigured hut to eliminate Century Link hut from         Dollars in Millions 5.0
encroachment of SPU easement..                                5.0
Authorized Forecasted  Costs
T-5 work is being delayed in order to complete T-18 issues.                                Incurred
Schedule                                     Construction Costs
Complete T-18 Street Vacations by end of 2016. Schedule is not dependent     None at this time
only on POS or NWSA staff, it is dependent on efforts made by City of Seattle
and private businesses interested in resolving loose ends associated with       Photos
completion of T-18 Redevelopment Project, T-5 Street Vacations will be dealt
with after completion of T-18 work.
Budget
The budget is on track and is currently within the authorized budget. 
Change Order
Current Quarter     Project Total
Number of COs           0             2
Amount of Cos           $0          $20,390.33
Justification for COs: None this quarter
Risks
Not applicable
Budget Transfers
Amount       From         To
$0
MARITIME 

70  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
FT C15 HVAC Improvement 
Project: C800137               Replace existing HVAC systems    Project Status:
Budget: $4,887,000             within Building C-15 that are at the   Schedule: Delayed
Phase:  Closeout              end of their service life.         Budget: On or Under
Start: 5/1/2010                                          Status Reset: 10/8/2013
Scheduled Completion: 6/30/2014                           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Claims, change orders and liquidated damages negotiation ongoing but
5
remained slow. Overall, the project is expected to stay within budget at the end         4.9     4.9
4.9
of project close-out. Received $49,081 conservation incentive rebate check
from Seattle City Light. This update would be the last report on the project.      Dollars in Millions 4.84.74.6                4.5
Schedule                                      4.5
4.4
Construction is complete and project is in the close-out phase.
4.3
Authorized Forecasted   Costs
Budget                                                Incurred
Project is within the October 8, 2013 Commission funding authorization and
though claims, change orders, and liquidated damages negotiation is still       Construction Costs
ongoing, staff expects there are adequate budget to close out the project. 
3.5   3.0
3             2.6
Change Order                                 2.5
Current Quarter     Project Total          2
1.5
Number of COs           0             16           Dollars in Millions  1
Amount of COs          $0           $61,040
0.5          0.1
Justification for COs: None this quarter                                0
Initial  Change  Spent
Orders
Risks
Some significant cost items have been raised by the contractor but Port
Photo
disagrees with their merits. These are being negotiated along with liquidated
damages from contractor's delays that Port will assess. This negotiation process
is anticipated to be lengthy but should be resolved in 2016.
Budget Transfers
Amount       From         To
$0


MARITIME 
Port of Seattle 1Q 2016 Report  71

FIRST QUARTER REPORT, 2016 
T-91 Lighting Upgrade 
Project: C800160               Lighting upgrade at Terminal 91    Project Status:
Budget: $1,160,000                                     Schedule: Delayed
Phase: Construction                                    Budget: On or Under
Start: 6/23/2014                                          Status Reset: 4/25/2016
Schedule Completion: 2/26/2016                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The installation of the lighting and controls is complete. Commissioning of the
1.18
controls and training are scheduled to occur in May 2016 following ICT            1.16    1.16
1.16
development of an online control access.
1.14
Schedule                                      1.12 Dollars in Millions             1.11
Expect to finish the project in May 2016.                             1.1
1.08
Budget                                       Authorized Forecasted  Costs
Incurred
The budget was increased by $125,000; now totaling $1,160,000 for the total
project cost. The project is expected to complete within the revised project     Construction Costs
budget.                                                    Not Applicable
Change Order                               Photos
Current Quarter     Project Total
Number of COs           4             2
Amount of Cos          $18,155         ($24,845)
Justification for COs: Add additional fixtures to meet the goals of this project.
Risks
None
Budget Transfers
Amount       From         To
$0



MARITIME 

72  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Shilshole Tenant Service Buildings 
Project: C800356               Replacement/rehabilitation of five   Project Status:
Budget: $5,500,000 to $6,500,000    restrooms and laundry facilities at    Schedule: Delayed
Phase: Design                Shilshole Bay Marina by June 2017  Budget: On or Under
Start: 1/6/2015                  for $5.5-6.5M.                Status Reset: N/A
Schedule Completion: 6/30/2018                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Consultant selected, scope confirmation and design is underway. Public
2
outreach for tenant feedback and priorities with moorage and business tenants               1.61
continues. Investigation of including a second floor on one or more of the       1.5
restrooms, however current market costs indicate this would likely be
1
prohibitively costly.                                                 0.71
0.5
Schedule                                      Dollars in Millions             0.02
0
Customer feedback has changed the scope from the original site plan. This         Authorized Forecasted  Costs
Incurred
outreach work, the resulting changes to scope to include a north restroom and
anticipated time for permitting have delayed the project by one year. Current
schedule is to complete the design by year end 2016, permitting and bidding    Construction Costs
complete by June 2017 and construct the new facilities to be online by May of   None at this time
2018. This still allows us to take advantage of off season construction to
minimize disruption to operations.
Budget
Project is within the approved budget. 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant known risks at this time
Budget Transfers
Amount       From         To
$0

MARITIME 
Port of Seattle 1Q 2016 Report  73

FIRST QUARTER REPORT, 2016 
T-91 Substation Upgrades 
Project: C800439               Upgrade/replace existing        Project Status:
Budget: $2,058,000             substations/equipment at Substation  Schedule: Delayed
Phase: Construction            Nos. 1, 14 and 15.             Budget: On or Under
Start: 11/4/2013                                          Status Reset: 3/10/2015
Schedule Completion: 4/30/2016                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Contractor mobilized in January and began substation work. Substation 1 work,
2.5
except for the new transformer installation, is nearing completion. Substation         1.995    1.995
14 work is progressing well and should be completed late April. Substation 15     2
work is also progressing well and is expected to be completed sometime in
May.                                                      0.737
Schedule                                      Dollars in Millions 1.51 0.5
0
Due to transformer manufacturer's fabrication delay in order to comply with        Authorized Forecasted  Costs
Incurred
new Department of Energy's regulations, the unit is not expected to be onsite
until May/June. This will delay the construction completion date. 
Construction Costs
Budget
1.2   1.1
On budget 
1
Dollars in Millions                   0.8
0.8
Change Order
0.6
Current Quarter     Project Total         0.4
Number of COs           3             5            0.2     0.1
Amount of Cos          $5,000          $5,000            0
Justification for COs: Address temporary power needs and additional City of         Initial Change Spent
Orders
Seattle's permit conditions.
Risks                                        Photo
Department of Energy's new requirements caught major transformer equipment
manufacturers off guard and transformer manufacturing delays will impact the
project and would have cost ramifications, including additional staff labor costs
and assessment of liquidated damages. Project team has worked out a plan with
the contractor to complete remaining work at Substation 1. The contractor is
expected to swap out the temporary transformer with a new and permanent
transformer in May/June.
Budget Transfers
Amount       From         To
$0

MARITIME
74  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Argo Yard Truck Roadway 
Project: C800546, E104751,       New Port of Seattle owned truck    Project Status:
E104754                   roadway between East Marginal    Schedule: Within or Ahead
Budget: $7,750,000             Way and Colorado Avenue South    Budget: On or Under
Phase: Construction            right-of-way.                Status Reset: 4/22/2014
Start: 3/11/2012                                          (Commission Construction Auth.)
Schedule Completion: 4/15/2015
Significant Developments                             Budget/Costs Incurred
Union Pacific (UP) railroad crossing improvements (POS sharing costs) still to
10
be completed; awaiting finalization of construction agreements and scheduling        7.75    7.75
8
of UP crew. UP Element III Argo Yard improvements FMSIB funding (POS to                  6.10
administer) has now been approved by WSDOT.                     Dollars in Millions 6
4
Schedule
2
UP railroad crossing improvements anticipated to be completed by Q4 2016.      0
UP Element III Argo Yard improvements anticipated to be completed in 2017       Authorized Forecasted  Costs
Incurred
or 2018.
Budget                                    Construction Costs
Project is currently within the budget authorized by Commission on April 22,       6
5.05
2014.                                                 5         4.50
4
Change Order                                  3
Current Quarter     Project Total          2
Number of COs           14            34           Dollars in Millions  1     0.41
Amount of COs         $156,932         $408,681           0
Initial  Change  Spent
Justification for COs: Construction requirements not addressed by design                Orders
documents.
Risks
No significant known risks at this time.
Budget Transfers
Amount       From         To
$0


MARITIME 

Port of Seattle 1Q 2016 Report  75

FIRST QUARTER REPORT, 2016                                                           FIRST QUARTER REPORT, 2016 
HIM E Dock Improvements                                           East Marginal Way Grade Separation 
Project: C800678               Dock currently under consideration  Project Status:                    Project: E102007               FAST Corridor funded project;     Project Status:
Budget: $500,000             for improvements ranging from    Schedule: Within or Ahead          Budget: $56,256,171           FHWA, State, City with Port      Schedule: Within or Ahead
Phase:  Planning              partial elements (walers, rub strips,   Budget: On or Under              Phase: Closeout              commitment of $22,480,807. Scope  Budget: On or Under
Start: 9/1/2014                 cleats, etc.) replacement to        Status Reset: N/A                  Start: 5/1/2006                 is to construct grade separation in    Status Reset: 4/22/2014
Scheduled Completion: TBD      complete floats and pile         (Commission Construction Auth.)          Schedule Completion: 6/30/2016    vicinity of T5 and T18 to minimize   (Commission Construction Auth.)
replacements and electrical system                                                             truck traffic/rail conflicts.
upgrade.
Significant Developments                             Budget/Costs Incurred
Significant Developments                             Budget/Costs Incurred           Coordination continued with City of Seattle for properties and easements
56.5   56.25    56.25
No development in first quarter to report as project is currently on hold pending                                 conveyance to City. Proposed Lot Boundary Adjustment for POS properties
0.5             0.47
Harbor Island Marina TCO analysis being performed by Maritime Finance and                              under final review by Seattle DCI. POS preparing proposed easement          56.0
Maritime Management to subsequently decide on final project improvements     0.4                          documents for review by SDOT as well as Seattle City Light and Seattle Public
scope and schedule.                                         Dollars in Millions                                                                                   55.5             55.30
0.3                                        Utilities.
0.2                                                                                                                          Dollars in Millions  55.0
Schedule
0.1    0.07               0.06               Schedule
54.5
Final schedule to be determined.                                                               Anticipate final acceptance by Seattle Department of Transportation (SDOT) in       Authorized Forecasted  Costs
0                                                                                                                       Incurred
Authorized Forecasted   Costs             2016.
Budget                                                Incurred
Construction Costs
Budget dependent on final scope decision.                                                         Budget
Construction Costs             Project is on track within the April 22, 2014 Commission authorization.         25  22.0     22.0
Change Order                               None at this time
20
Current Quarter     Project Total                                Change Order
15
Number of COs           0             0                                                   Current Quarter     Project Total
10
Amount of COs          $0            $0                                    Number of COs           0             97
5        2.0
Justification for COs: N/A                                                                      Amount of COs             $0            $1,922,967           Dollars in Millions
Justification for COs: None this quarter.                                0
Initial  Change  Spent
Risks                                                                                                                    Orders
Nothing significant at this time.                                                                   Risks
No risks at this time.
Budget Transfers
Amount       From         To                           Budget Transfers
$0                                                                 Amount         From           To
$380,000         102007       104866 & 104739



MARITIME 
MARITIME 
76  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
East Marginal Way Grade Separation 
Project: E102007               FAST Corridor funded project;     Project Status:
Budget: $56,256,171            FHWA, State, City with Port      Schedule: Within or Ahead
Phase: Closeout               commitment of $22,480,807. Scope  Budget: On or Under
Start: 5/1/2006                  is to construct grade separation in    Status Reset: 4/22/2014
Schedule Completion: 6/30/2016    vicinity of T5 and T18 to minimize   (Commission Construction Auth.)
truck traffic/rail conflicts.
Significant Developments                             Budget/Costs Incurred
Coordination continued with City of Seattle for properties and easements
56.5   56.25    56.25
conveyance to City. Proposed Lot Boundary Adjustment for POS properties
under final review by Seattle DCI. POS preparing proposed easement           56.0
documents for review by SDOT as well as Seattle City Light and Seattle Public   Dollars in Millions 55.5             55.30
Utilities.
55.0
Schedule
54.5
Anticipate final acceptance by Seattle Department of Transportation (SDOT) in       Authorized Forecasted  Costs
Incurred
2016.
Budget                                    Construction Costs
Project is on track within the April 22, 2014 Commission authorization.           25  22.0       22.0
20
Change Order
15
Current Quarter     Project Total
Number of COs           0             97
10
Amount of COs          $0          $1,922,967         Dollars in Millions  5     2.0
Justification for COs: None this quarter.                                0
Initial  Change  Spent
Orders
Risks
No risks at this time.
Budget Transfers
Amount       From         To
$380,000         102007       104866 & 104739



MARITIME 
Port of Seattle 1Q 2016 Report  77

FIRST QUARTER REPORT, 2016 
Viaduct Construction Coordination 
Project: E104324, E104535-38       Participate in the design &       Project Status:
Budget: $2,900,000             construction of the bored tunnel, N.  Schedule: Delayed
Phase: Implementation          & S. portals, Holgate to King St,    Budget: On or Under
Start: 1/1/2009                  Central Waterfront surface streets,   Status Reset: N/A
Schedule Completion: 12/31/2018   & related projects to ensure       (Commission Construction Auth.)
adequate connection to port
facilities.
Significant Developments                             Budget/Costs Incurred
Tunneling resumed and then stopped for planned maintenance break prior to
4
tunneling under the Viaduct, which will result in two week closure. Funding
2.90
agreement modified to allow for delayed payment in September 2016. Seawall     3
and Mercer corridor construction continued.
2           1.75
1.19
Schedule                                      Dollars in Millions 1
Tunneling project is now tracking completion in two years. Mercer West
0
construction will continue through mid-2016. Seawall Phase I construction to       Authorized Forecasted  Costs
Incurred
be completed in late-2016. Central Waterfront start/completion depends on
completion of SR99 tunnel and Viaduct demolition.
Construction Costs
Budget                                    Not Applicable
Port staff costs are within anticipated 2016 spending. 
Photos
Change Order                               North Access to SR99 Tunnel 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Project delays due to repairs to the tunneling machine.
Budget Transfers                                 South Access to SR99 Tunnel
Amount       From         To
$0


MARITIME 
78  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
FT Net Shed Code Compliance 
Project: E104838               FT Net Sheds 3-11: Improvements  Project Status:
Budget: $2,950,000             required per City of Seattle building  Schedule: Delayed
Phase: Construction            & fire codes.                Budget: On or Under
Start: 5/1/2012                                            Status Reset: 6/25/2013
Schedule Completion: 6/30/2015                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Maintenance is completing installation of exterior receptacles. The close
3    2.95
coordination between PCS, FT's Operations staff, Maintenance, and Seaport
Project Management paid off with many happy net locker tenants despite       2.8
significant interruptions and impacts the project had on them. This will be the
last report on this project.
2.54     2.52
2.4
Schedule                                      Dollars in Millions 2.6
2.2
All work within the net lockers is complete.                                  Authorized Forecasted  Costs
Incurred
Budget
Project budget is on track and projected to come in about $410,000 below      Construction Costs
authorized budget upon project close out.                            Port Self Perform Construction
Change Order                               Photo
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None
Budget Transfers
Amount       From         To
$0



MARITIME 
Port of Seattle 1Q 2016 Report  79

FIRST QUARTER REPORT, 2016 
T-5 and T-91 Maintenance Dredging 
Project: E104840, E105038, U00067,  Maintenance Dredge at T-5 all     Project Status:
E105050,                    three berths and at T-91 East cruise  Schedule: Delayed
Budget: $4,800,000             berth.                     Budget: On or Under
Phase: Closeout                                       Status Reset: N/A
Start: 8/14/2012                                          (Commission Construction Auth.)
Schedule Completion: 2/28/2016
Significant Developments                             Budget/Costs Incurred
T-5 Maintenance Dredging was completed earlier in 2014.
6
T-91 East Cruise Berth: Successfully completed under-water regrading in           4.80
5
February 2016. Project closeout is in progress. This is likely the last report on             3.80
Dollars in Millions 4                      3.58
this project.
3
2
Schedule
1
Construction completed on schedule based on revised delayed schedule.         0
Authorized Forecasted   Costs
Incurred
Budget
Project is on budget. 
Construction Costs
None
Change Order
Current Quarter     Project Total       Photo
Number of COs           1             3
Amount of Cos          $937.20         $21,327.53
Justification for COs: Mast for mounting monitoring equipment on
construction barge
Risks
N/A
Budget Transfers
Amount       From         To
$0



MARITIME 
80  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
T-18 Maintenance Dredging 
Project: U00033 and U00231       Design, permitting, and         Project Status:
Budget: $3,216,000             construction of T-18 Maintenance   Schedule: Within or Ahead
Phase:  Closeout              Dreddging; Advertise and execute   Budget: On or Under
Start: 2/10/2015                an on-call major construction       Status Reset: N/A
Schedule Completion: 2/28/2016    dredging contract             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Construction completed early in March 2016. Project is in closeout. This is the
4
last report on the project.                                                3.21
3
Schedule                                      Dollars in Millions        2.40
2
Project was slightly behind schedule due to a delay in permitting, however, we
0.79
completed construction in early March with an extension to the permit.          1
0
Budget                                       Authorized Forecasted  Costs
Incurred
Project is under budget. Costs incurred does not reflect construction contract
payments in progress. The Forcasted cost reflect expected final project cost at
Construction Costs
closing.
None
Change Order
Photo
Current Quarter     Project Total
Number of COs           1             1
Amount of Cos          $920           $920
Justification for COs: Disposal of unforeseen concrete column
Risks
N/A
Budget Transfers
Amount       From         To
$0



MARITIME 
Port of Seattle 1Q 2016 Report  81

FIRST QUARTER REPORT, 2016 
T-102 HMCC Roofs and HVAC Units
Replacement 
Project: C800196               Replace Corporate Center building  Project Status:
Budget:  $6,200,000           roofs, final group (3rd phase) of     Schedule: Within or Ahead
Phase:  Design               rooftop HVAC units, and all      Budget: On or Under
Start: 9/1/2014                 rooftop gas piping. Assets are at the  Status Reset: N/A
Scheduled Completion: 10/31/2016   end of their service lives.         (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Final design completed, construction funding authorized, bids received, and
8
construction contract executed.                                        6.2     6.2
6
Schedule
Project on schedule for start of construction in May 2016.                  Dollars in Millions 4
2
0.4
Budget
0
Project currently within authorized budget.                               Authorized Forecasted  Costs
Incurred
Change Order
Construction Costs
Current Quarter     Project Total       Not applicable at this time
Number of COs           0             0
Amount of COs          $0            $0
Justification for COs: None at this time
Risks
Nothing significant at this time.
Budget Transfers
Amount       From         To
$0



ECON. DEVELOPMENT 
82  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
P69 Carpet Replacement 
Project: C800691               Replace approximately 10,200 sq.   Project Status:
Budget: $1,200,000             yards of carpeting on the second    Schedule: Delayed
Phase: Construction            and third floors of the Port's       Budget: On or Under
Start: 7/7/2014                  Corporate Headquarters.          Status Reset: 4/25/2016
Schedule Completion: 9/30/2014                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The Contractor has successfully completed 100% of the contract scope. Due to
1.5
an ongoing labor determination, the project close-out has been postponed. The        1.20    1.20
primary concern is in regards to appropriate labor rates and application of small
business involvement. Final closing documents have been received.
1                  0.77
Schedule                                      Dollars in Millions 0.5
The Port has submitted final documents to the State for review. Anticipated       0
closure of the project is May of 2016.                                  Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
We do not anticipate any additional costs to be incurred other than internal
Not Applicable
processing soft costs. 
Change Order
Current Quarter     Project Total
Number of COs           0             3
Amount of Cos           $0           $4,700
Justification for COs: None this quarter
Risks
None at this time
Budget Transfers
Amount       From         To
$0



ECON. DEVELOPMENT 
Port of Seattle 1Q 2016 Report  83

FIRST QUARTER REPORT, 2016 
P69 Beam Rehabilitation Project 
Project: C800698               Rehabilitate five rows of concrete   Project Status:
Budget: $3,024,000             roof beams supporting top of      Schedule: Within or Ahead
Phase: Design                clerestory windows at P69.        Budget: On or Under
Start: 7/1/2014                                            Status Reset: 10/27/2015
Schedule Completion: 11/30/2016                           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Contract award to Western Ventures in progress. Scaffolding construction
4
underway as of March 28, 2016. Full NTP for rehab work expected by mid-          3.02
April.                                                      3
2.09
2
Schedule                                      Dollars in Millions 1
Project had a two month bid period due to building permit delay, and holiday                     0.30
periods in November / December. Timeline goal remains substantial           0
completion by end of November 2016.                              Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
Current approved total budget is $3,024,000. Contractor bid at $896,200 is 49%
None at this time
below Engineer Estimate of $1,765,250. Bid was validated by bidder. Bidder
confirmed responsible by staff. Current project estimate is $2.091M, reduced
Photos
from $3.024M. 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Contractor access during construction will restrict space and create visual
impacts on third floor and second floor atrium for an estimated 7.5 months.
Need to mitigate environmental impacts due to presence of lead paint / concrete
silica dust / asbestos insulation behind interior flashing.
Need to hire security guard. Contractor expects 4-10 night shifts for typical
work, and weekend (Saturday) for painting.
Budget Transfers
Amount       From         To
$0

ECON. DEVELOPMENT 
84  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
ID Badge System Replacement 
Project: C800162               Procurement and replacement of    Project Status:
Budget: $2,500,000             the Portwide ID Badge system      Schedule: Delayed
Phase: Implementation          including software, hardware, and   Budget: On or Under
Start: 5/1/2012                  equipment.                   Status Reset: N/A
Schedule Completion: 9/30/2016                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The first phase of the new Badge System deployed on November 5, 2014. A     2.6
2nd deployment to add mobile functionality and authorized signer efficiencies is        2.50    2.50
2.5
in the implementation stage.
2.4
Schedule                                      Dollars in Millions 2.3            2.25
Prior Report: A critical project to replace the vendor providing an interface with   2.2
TSA for the badging process security checks will redirect Port resources        2.1
Authorized Forecasted   Costs
resulting in a delay of the final components of the ID Badge System
Incurred
Replacement project by five months.
Construction Costs
Budget
Not Applicable
On budget 
Change Order
Current Quarter     Project Total
Number of COs           0             1
Amount of Cos           $0           $108,497
Justification for COs: None this quarter
Risks
Resource availability may continue to delay the second phase mobile
deliverables.
Budget Transfers
Amount       From         To
$0



CORPORATE 
Port of Seattle 1Q 2016 Report  85

FIRST QUARTER REPORT, 2016 
Contractor Data System Upgrade 
Project: C800519               Upgrade of the Contractor Data    Project Status:
Budget: $675,000              System used by Engineering and    Schedule: Delayed
Phase: Implementation          other groups to track contracts for   Budget: On or Under
Start: 7/1/2013                  construction projects.            Status Reset: N/A
Schedule Completion: 6/30/2016                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Development is in progress.                                    0.8
0.68     0.68
Schedule                                      0.6
Dollars in Millions                        0.45
Good progress is being made in this development project and consistent        0.4
business review, prioritization, and validation ensures we are working on the
0.2
highest priority features. Resource availability due to competing priorities will
delay the final deployment by four months.                            0
Authorized Forecasted   Costs
Incurred
Budget
On budget                                            Construction Costs
Not Applicable
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount       From         To
$0




CORPORATE 
86  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Construction Document Management 
Project: C800521               Replacement of the Construction   Project Status:
Budget: $900,000              Document Management System;    Schedule: Delayed
Phase: Implementation          used by Construction Management,   Budget: On or Under
Start: 9/10/2013                 to accept, review, and distribute     Status Reset: N/A
Schedule Completion: 6/30/2016    critical documentation.          (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Design and configuration in progress.                                1   0.90    0.90
0.8
Schedule
Dollars in Millions 0.6                                                                                     Prior Report: Implementation is in progress but vendor has significantly                                     0.37
0.4
underestimated work in contract resulting in a schedule delay to second quarter
2016.                                               0.2
0
Budget                                       Authorized Forecasted  Costs
Incurred
On budget 
Construction Costs
Change Order                               Not Applicable
Current Quarter     Project Total
Number of COs           2             2
Amount of Cos         $121,000         $121,000
Justification for COs: 1) Original software recommendation in RFP for license
type did not meet all requirements. CO initiated to purchase full licenses. Credit
given for original purchase. 2) Additional requirements were identified during
requirements workshops
Risks
Vendor has significantly underestimated work in contract and may further delay
implementation in contract disputes.
Budget Transfers
Amount       From         To
$0


CORPORATE 
Port of Seattle 1Q 2016 Report  87

FIRST QUARTER REPORT, 2016                                                          FIRST QUARTER REPORT, 2016 
Airport Voice Paging Upgrade                                             Parking System Replacement 
Project: C800709               Upgrade the Voice Paging System  Project Status:                   Project: C800728               Replacement of the Airport Main     Project Status:
Budget: $1,600,000             used by Airport Operations and     Schedule: Within or Ahead           Budget: $5,500,000             Garage Parking System           Schedule: Within or Ahead
Phase: Planning               Airlines for customer service      Budget: On or Under              Phase: Planning                                       Budget: On or Under
Start: 3/28/2016                 announcements.               Status Reset: N/A                 Start: 1/6/2015                                           Status Reset: N/A
Schedule Completion: 5/31/2017                            (Commission Construction Auth.)          Scheduled Completion: 6/30/2017                           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred          Significant Developments                             Budget/Costs Incurred
Planning, design, and procurement in progress                          2                          Vendor contract completed. Planning in progress.                       6   5.50    5.50
1.60     1.60
5
Schedule                                      1.5                     Schedule
4
On schedule                                           Dollars in Millions 1                        On schedule                                            3
2
0.5
Budget                                                          Budget                                     Dollars in Millions 1
0.00                                                                                                               0.09
On budget                                              0                         On budget                                              0
Authorized Forecasted   Costs                                                                                     Authorized Forecasted   Costs
Incurred                                                                                                     Incurred
Change Order                                                     Change Order
Current Quarter     Project Total       Construction Costs                            Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable                 Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0                                    Amount of Cos           $0             $0
Justification for COs: N/A                                                                    Justification for COs: N/A
Risks                                                                Risks
No significant risks at this time                                                                    No significant risks at this time.
Budget Transfers                                                         Budget Transfers
Amount       From         To                              Amount       From         To
$0                                                                   $0




CORPORATE                                       CORPORATE 
88  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Parking System Replacement 
Project: C800728               Replacement of the Airport Main     Project Status:
Budget: $5,500,000             Garage Parking System           Schedule: Within or Ahead
Phase: Planning                                       Budget: On or Under
Start: 1/6/2015                                            Status Reset: N/A
Scheduled Completion: 6/30/2017                           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Vendor contract completed. Planning in progress.                       6   5.50    5.50
5
Schedule
4
On schedule                                              3
2
Budget                                     Dollars in Millions 1           0.09
On budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time.
Budget Transfers
Amount       From         To
$0





CORPORATE 
Port of Seattle 1Q 2016 Report  89

FIRST QUARTER REPORT, 2016 
Maximo Upgrade 
Project: C800746               Upgrade Maximo System used by   Project Status:
Budget: $1,000,000             Aviation and Maritime          Schedule: Within or Ahead
Phase: Implementation          Maintenance and Information &    Budget: On or Under
Start: 5/10/2015                 Communication Technology       Status Reset: N/A
Schedule Completion: 8/31/2016                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Project Kickoff completed. Requirements and design in progress.            1.2
1.00     1.00
1
Schedule
0.8
On schedule                                           0.6
0.4
Budget                                     Dollars in Millions 0.2           0.04
On budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount       From         To
$0




CORPORATE 
90  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Data Center Operations/Business Continuity 
Project: C800748               Build out of the remote data center  Project Status:
Budget: $1,200,000             to support automated backup and    Schedule: Within or Ahead
Phase: Design                recovery                   Budget: On or Under
Start: 1/12/2016                                          Status Reset: N/A
Schedule Completion: 10/31/2016                           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Planning, design, and procurement in progress                         1.5
1.20     1.20
Schedule
Dollars in Millions 1
On schedule
0.5
Budget
0.02
On budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount       From         To
$0




CORPORATE 
Port of Seattle 1Q 2016 Report  91

FIRST QUARTER REPORT, 2016 
Employee Performance Management System 
Project: C800763               Implement the PeopleSoft        Project Status:
Budget: $400,000              e-Performance Management system  Schedule: Within or Ahead
Phase: Implementation          to support the Port Performance     Budget: On or Under
Start: 5/17/2015                 Management Program.           Status Reset: N/A
Schedule Completion: 5/31/2016                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Configuration and testing completed for a planned go-live of April 18, 2016.     0.5
0.40     0.40
0.4
Schedule
On schedule
Budget                                     Dollars in Millions 0.30.20.1           0.02
On budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount       From         To
$0




CORPORATE 
92  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Airport Data Network Switch Upgrade 
Project: C800788               Equipment and software upgrade   Project Status:
Budget: $3,000,000             for the network supporting Airport   Schedule: Within or Ahead
Phase: Planning               Operations systems.            Budget: On or Under
Start: 2/23/2016                                          Status Reset: N/A
Schedule Completion: 4/30/2017                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Planning, design, and procurement in progress                          4
3.00     3.00
Schedule                                       3
On schedule                                           2
1
Budget                                     Dollars in Millions            0.01
On budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount       From         To
$0




CORPORATE 
Port of Seattle 1Q 2016 Report  93

FIRST QUARTER REPORT, 2016 
SeaTac Smartphone App 
Project: C800800               Upgrade the Voice Paging System  Project Status:
Budget: $500,000              used by Airport Operations and     Schedule: Within or Ahead
Phase: Planning               Airlines for customer service      Budget: On or Under
Start: 2/23/2016                 announcements.               Status Reset: N/A
Schedule Completion: 2/28/2017                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Planning, design, and procurement in progress                         0.6
0.50     0.50
0.5
Schedule
On schedule                                           Dollars in Millions 0.40.30.2                                                   Budget                                             0.1
0.00
On budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount       From         To
$0




CORPORATE 
94  Port of Seattle 1Q 2016 Report

FIRST QUARTER REPORT, 2016 
Airport Telecommunications Capacity
Increase 
Project: C800827               Increase of copper and fiber      Project Status:
Budget: $565,000              telecommunications capacity to     Schedule: Within or Ahead
Phase: Planning               meet Port and Tenant requirements   Budget: On or Under
Start: 2/23/2016                                          Status Reset: N/A
Schedule Completion: 12/31/2016                           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Planning, design, and procurement in progress                         0.6   0.57    0.57
0.5
Schedule
On schedule
Budget                                     Dollars in Millions 0.40.30.20.1           0.00
On budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount       From         To
$0




CORPORATE 
Port of Seattle 1Q 2016 Report  95

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.