7b attach

Item Number:  7b_Report
Meeting Date: December 9, 2014


Commission Staff Brieng
Capital Improvement Projects
Third Quarter Report 2014

This page intentionally left blank









ii  Port of Seattle 3Q 2014 Report

Port of Seattle
Capital Improvement Project Report
Third Quarter 2014
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the status of the Port's capital projects.
Background
During 2014, the Port plans to invest $295,200,000 to expand and upgrade the infrastructure that supports marine and
aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping companies,
airlines, rental car companies, concessionaires and public parking. About 4 percent of the Port's capital budget comes
from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in transportation
facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such, the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes "Project Status" illustrating at a
glance if the project is on schedule, and within budget, and the date Construction authorization was received.
x  Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x  Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x  Budget addresses the total project budget and includes information on the overall budget status, recent
Commission authorizations, forecasted overruns or savings, and scope changes.
x  Change Orders provides information on current quarter's COs and total project COs including justification for CO's for
the reporting period and information on any CO over $200,000 or 10% of the contract value.
x  Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x  Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x  Budget Transfers reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page on the Port of Seattle web site to ask a question, make a comment or
request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 3Q 2014 Report  1

Aviation
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C100266 et al .......Rental Car Facility ............................................... 6-7..........
C101107 ................160th GT Lot ..........................................................8 ...........
C102032 ...............Sanitary Sewer Pump Station Upgrade ................9 ........... ..............................
C102112 ................Hennelly Service Tunnel Renewal Rep ................10 ..........
C102573 ...............Aireld Pavement Replacement ...........................11 .......... ..............................
C800019 ...............Gate Utilities Improvement ...................................12 .......... ..............................
C800034 ...............North Expressway Relocation ..............................13 ..........
C800061 ...............Main Terminal South Low Voltage ..................... 14-15 ........
C800107 ...............C4 UPS System Improvements ............................16 .......... .............................. 
C800168 ...............C60-C61 BHS Modications ................................17 ..........
C800218 ...............Security Exit Lane Breach Control Phase I ..........18 .......... ..............
C800230 ...............Emergency Lighting Parking.................................19 .......... ..............................
C800238 ...............Central Plant Pre-Conditioned Air ..................... 20-21 ....... .............. ....................................
C800247 ...............Cargo 2 West Hardstand ......................................22 .......... .............................. 
C800251 ...............Vertical Conveyance Modernization.....................23 ..........
C800253 ...............Parking System Replacement ..............................24 .......... ..............................
C800254 ...............Aircraft RON Parking Post Ofce Site..................25 ..........
C800267 ...............Port Owned Loading Bridges ...............................26 ..........
C800274 ...............8th Floor Weather Proong ..................................27 .......... ..............................
C800324 ...............Long-Term Cell Phone Lot ....................................28 .......... .............................. ......................................
C800334 ...............Two new CTE Freight Elevators ...........................29 .......... 
C800335 ...............EGSE Electrical Charging Stations ................... 30-31 ....... ..............
C800368 ...............Refurbish Bag Claim Device 8..............................32 ..........
C800376 ...............SSAT HVAC Lights Ceiling Repl...........................33 ..........
C800382 ...............BHS (C22-C1, MK1 and TC3) ............................34-35 .......
C800390 ...............Cargo 6 Enhancements ........................................36 .......... .............................. 
C800406 ...............RW 16C/34C Reconstruction ...............................37 ..........
C800426 ...............FIS Improvement - Short Term .............................38 .......... ..............
C800451 ...............Doug Fox Site Improvement ..............................39-40 ....... .............................. ......................................
C800461 ...............IWTP Fiber Installation .........................................41 .......... ..............................
C800464 ...............Fiber Infrastructure to Gate Backstands ..............42 ..........
C800474 ...............Airport Signage .....................................................43 .......... ..............................
C800479 ...............Fire Station Electrical Upgrades ...........................44 ..........




2  Port of Seattle 3Q 2014 Report

Aviation, cont.
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C800490 ...............New Window Wall Ticket Zone 1 ..........................45 .......... ..............................
C800495 ...............Facility Monitoring System Renewal ....................46 .......... ..............................
C800497 ...............Airport Wide Mechanical Controls System ..........47 .......... .............................. ......................................
C800541 ...............RAC Baggage Claim Renovation .........................48 .......... ..............................
C800543 ...............Replace PLBs at S7, S9, B4 .................................49 ..........
C800544 ...............NorthSTAR Program.............................................50 ..........
C800545 ...............NorthSTAR Main Terminal Improvements............51 ..........
C800547 ...............NorthSTAR Concourse C Vertical Circ. ...............52 ..........
C800549 ...............SSAT Interior Renovations ...................................53 ..........
C800550 ...............Concourse D Roof Replacement..........................54 ..........
C800551 ...............Grease Interceptor Augmentation ........................55 .......... ..............................
C800555 ...............NorthSTAR Refurbish Baggage Systems ............56 ..........
C800556 ...............NorthSTAR North Satellite Lobbies ................... 57-58........
C800557 ...............Snowblower and Deicer Trucks ............................59 ..........
C800560 ...............MT Mezzanine Tenant Relocation ........................60 ..........
C800576 ...............Known Crew Member Employee Bypass .............61 .......... .............................. ....................................
C800581 ...............Parking Garage Lights ..........................................62 ..........
C800583 ...............International Arrivals Facility ................................63 ..........
C800585 ...............Wi-Fi Enhancement for Ramp and Terminal ........64 ..........
C800605 ...............Security Exit Lane Breach Control Phase 2 .........65 .......... ..............................
C800609 ...............NSAT - STS Ceiling Leak Repair ..........................66 .......... ..............................
C800612 ...............Checked Baggage Recapitalization/Optimzation.67 ..........
C800615 ...............Second Floor Mezzanine Infra Upgrade ..............68 .......... ..............................
C800629 ...............S1 Ramp ...............................................................67 ..........
C800637 ...............2014-15 Roof Replacement ..................................69 ..........
C800642 ...............CCTV Camera-Data Improvements .....................70 ..........
C800651 ...............Town-Country Stormwater Pipe ...........................71 ..........
C800658 ...............Mech Energy Conservation ..................................72 ..........
C800659 ...............North Utility Tunnel Steam Pipe ...........................73 ..........
C800662 ...............S4 and S6 IC Connection .....................................74 .......... ..............................
C800667 ...............Automated Passport Control ................................75 ..........
Other Aviation
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C200007...............Highline School Noise Insulation ..........................76 .......... ..............................


Port of Seattle 3Q 2014 Report  3

Other Aviation, Cont.
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C200042 ...............Highline Community College Noise Insulation .....77 ..........
C200048 ...............Home Insulation Retrot .......................................78 ..........
C200093 ...............Single Family Home Sound Insulation .................79 ..........
C800146 ...............RMU/Kiosk Concession Program ........................80 .......... ..............................
C800154 ...............Tenant Reimbursement ........................................81 ..........

Seaport
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C102554............... Terminal 46 Development....................................82 ..........
C102858 et al ....... Street Vacations T-5/18/105.................................83 .......... ..............................
C800090 ...............Pier 34 Mooring Dolphins .....................................84 ..........
C800132 ...............T-5 Berth Modernization .......................................85 ..........
C800160 ...............T-91 Lighting Upgrade ..........................................86 .......... ..............................
C800430 ...............T-91 Building C175 Roof Replacement ................87 ..........
C800439 ...............T-91 Station Upgrades..........................................88 ..........
C800546 ...............Argo Yard Truck Roadway ....................................89 .......... ..............................
C800603 ...............T-46 Dock Rehabilitation ......................................90 .......... ..............................
C800689 ...............T-115 Stormwater Separation ...............................91 ..........

WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation ..................92 ..........
E104324 ................Viaduct Construction Coordination ......................93 ..........
E104840................T-5, T-18 and T-91 E. Maintenance Dredging ......94 .......... ..............................
U00079 .................Clean Truck Program Truck Scrap & Repl ...........95 ..........
U00099 .................IHI Cranes Removal .............................................96 ..........





4  Port of Seattle 3Q 2014 Report

Real Estate
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C800137 ...............FT C15 HVAC Improvements ...............................97 .......... ..............................
C800314 ...............P69 Built-up Roof Replacement ...........................98 ..........
C800344 ...............FT C-2 Nordby Roof and HVAC ..........................99 ..........
C800527 ...............FT Net Shed 9 Roof Replacement ......................100 .........
C800691 ...............P69 Carpet Replacement ....................................101 ......... ..............................
C800698 ...............P69 Carpet Replacement ....................................102 .........
E104838................FT Net Shed Code Compliance ..........................103 .........

Corporate

Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C800162 ...............ID Badge Replacement .......................................104 ......... ..............................
C800321 ...............Enterprise Project Cost Management ..................105 ......... ..............................
C800323 ...............Network Switch Replacement ..............................106 .........
C800436 ...............Terrminal 91 Visitor Management ........................107 .........
C800519 ...............Contractor Data System Upgrade........................108 .........
C800520 ...............Computer Dispatch System Upgrade ..................109 .........
C800521 ...............Construction Document Management ................110 .........
C800586 ...............Radio Systems Upgrade...................................... 111 .........
C800693 ...............Noise Monitoring System Replacement ..............113 .........

Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Negative Variance Status
New Variance
Previously Reported
Schedule Completion on the Project Reports refers to:
Benecial Occupancy or Last Asset In-Use date


Port of Seattle 3Q 2014 Report  5

THIRD QUARTER REPORT, 2014
Rental Car Facility
Project Status:
Project:   C100266,     The program will construct a       Schedule: Within or ahead
C102167, C800032     consolidated rental car facility (RCF),  Budget: On or under
Status Reset: 6/30/2009
Budget: $387,232,993   off-site roadway improvements (ORI),
a bus maintenance facility (BMF),     (Commission Construction Auth.)
Phase: Construction
Start: 2/24/1998        improvements at the Main Terminal for
busing (MTI), plus purchase a fleet of
Schedule Completion:
buses.                     Budget/Costs Incurred
Q2 2012
398
395.51
Significant Developments                     396
394
The RCF program is substantially complete with projects either       Millions 392
closed or in closeout. The Contractor claims were settled,           390
authorized by the Commision August 8, 2014. The Resident                   387.23
Dollars in  388                         386.72
Engineer Completion Memo was issued September 11, 2014. This    386
is the final quarterly report.                                   384
382
Authorized   Forecasted  Costs Incurred
Schedule
RCF opened May 17, 2012. Final Contractor claims were authorized
by the Commission August 8, 2014.
Construction Costs
Budget                             300       276.93
251.16
The RCF program remains under budget with a total program budget    250
of $419,306,000. The total forecasted cost at completion for the      Millions 200
RCF program is $408,300,000.                           150
100
Change Order                          Dollars in 
50         25.83
Current Quarter   Project Total             0
Number of COs    5          1,624                   Initial Change Spent
Orders
Amount of COs    $9,242,827    $25,831,308
Justification for COs: all change orders are associated with the final   Photo
claim settlement and contract reconciliation.
Risks
None this quarter


6  Port of Seattle 3Q 2014 Report

Budget Transfers
Transferred $9,757.28 from capital to expense projects in support of project close out. Increased the
RCF budget by $10,200,000 (previously identified savings) for final claim settlement. Decreased the
BMF, ORI, and MTI budgets to return $2,365,000 in program savings.
Cost Growth of Construction
RCF Airport Wayfinding Signage and Curbside Modifications - MC-0316968 - This contract is closed
and the final cumulative change order percentage is 21.34%.
Consolidated Rental Car Facility - Small Operator Build Out - MC-0317022 - This contract is closed
with a final cumulative change order percentage of 3.97%.
Consolidated Rental Car Facility Offsite Roadway Improvements and SR99 Bridge Seismic Upgrade
MC-0316568 - This contract is closed with a final cumulative change order percentage of 38.84%.
Bus Maintenance Facility - MC-0316730 - This contract is closed with a final cumulative change order
percentage of 2.29%.
GCCM Final Construction (Phase 3 of 3)  MC-0315405 - This contract is complete and in closeout.
The final cumulative change order percentage is 9.08%.
TESC & Early Work (Phase 2 of 3)  MC-0315292 - This contract is closed with a final cumulative
change order percentage of 19.38%.
GCCM Pre-Construction (Phase 1 of 3)  MC-0314280  This contract is closed with a final
cumulative change order percentage of 170.55%.





AIRPORT
Port of Seattle 3Q 2014 Report  7

THIRD QUARTER REPORT, 2014
So. 160th GT Lot Expansion
Project Status:
Renovate existing building for       Schedule:  within or ahead
better functionality, improve lot
Project: C101107                           Budget:   on or under
draingage, underground existing
Budget: $4,532,000                          Status Reset: 11/22/2013
overhead utility lines, fencing and     (Commission Design Auth.)
Phase: Design      landscaping.
Start: 2/1/2013
Schedule Completion: 9/30/2015
Budget/Costs Incurred
Significant Developments
Thirty percent design for building renovation and site improvements     5         4.532
was completed and reviewed. Negotiations with utility companies
4
on agreements to underground existing overhead utility lines along    Millions 3
S. 160th are in progress.
Dollars in 
2
1.064024
Schedule
1
0.177918
Complete design December 2014. Advertisement for bids expected
0
in February 2015, followed by construction and beneficial occupancy       Authorized  Forecasted Costs Incurred
in September 2015.
Budget                           Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: Not Applicable
Risks
Unforeseen building or site conditions could increase design and
construction costs. Unforeseen complications in executing
agreements with utilities for undergrounding lines are a risk.
Budget Transfers
None

AIRPORT
8  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT,
Sanitary Sewer Pump Station Upgrade
Upgrade the aging control systems   Project Status:
Project:   C102032
of 22 sanitary sewer lift stations.     Schedule: Delayed
Budget: $1,133,000                         Budget: On or under
Phase: Construction                        Status Reset: Click here to
Start: 3/1/2013                                   enter a date.
Schedule Completion: 3/31/2015                  (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
Over half the panels have been installed. Performing measures on     1.2   1.13    1.13
some of these systems to enhance performance.                1
Millions 0.8
Schedule
0.6                        0.52
The project is behind schedule due to changes to the control panels    0.4
and installation challenges. We are carefully proceeding forward in a   Dollars in 
0.2
manner that minimizes risk during and after system switchover.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 3Q 2014 Report  9

THIRD QUARTER REPORT, 2014
Service Tunnel Renewal/Replace
Project Status:
Project:   C102112      Seismically upgrade the Service
Schedule: Within or ahead
Budget: $27,586,000     Tunnel that runs beneath the
Budget: On or under
Phase: Design        departures and arrivals drives of
Status Reset: 8/5/2014
the airport.
Start: 11/4/2012                                  (Commission Design Auth.)
Schedule Completion: 6/1/2018
Budget/Costs Incurred
Significant Developments
27.59
Commission authorized procurement of a design team. Design       30
scope was developed. Procurement is being coordinated with CPO.    25
Millions 20
Schedule                             15
10
Project is underway, and on schedule.                       Dollars in      4.57
5
0.07
0
Budget                               Authorized Forecasted Costs Incurred
Project is currently within budget.
Change Order                         Construction Costs
None at this time
Current Quarter   Project Total
Number of COs    0
Amount of COs    $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
10  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Airfield Pavement Replacement
Project Status:
Project:   C102573     This is a multi-year program to      Schedule: Delayed
Budget: $29,896,495    replace distressed pavement and   Budget: On or under
Phase: Construction    joint seal on the airfield.        Status Reset: 4/1/2014
Start: 5/2/2010                                  (Commission Construction Auth.)
Schedule Completion: 12/31/2016
Significant Developments                    Budget/Costs Incurred
Beneficial Occupancy was granted on October 22, 2014.           35
29.90
30    27.68
Schedule                            Millions 25
20                    17.85
Project is in close out.
15
Budget                            Dollars in  10
5
The project forecast is within the approved budget.                 0
Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total
Number of COs    0          10               2014 AIP Construction
Amount of COs    $0         $69,041            Costs
N/A
Justification for COs: Additional distressed panel was found south of
the South Satellite. Operations felt that it was necessary to replace it.  C102573 Total Major
It will be replaced in the 4th quarter of 2014.                    Construction Costs
20  17.14        17.02
Risks
15
None at this time.                                      Millions
10
Budget Transfers
None this quarter                                     Dollars in   5
0.85
0
Initial   Change   Spent
Orders


AIRPORT
Port of Seattle 3Q 2014 Report  11

THIRD QUARTER REPORT, 2014
Gate Utility Improvements
Project Status:
Upgrade the South Satellite Port-       Schedule: Delayed
Project:   C800019    owned loading bridges to the same     Budget: On or under
Budget: $11,650,480   standards, including 400Hz power and  Status Reset: Click here to
Phase: Construction  potable water. This will reduce air     enter a date..
Start: 6/28/2007       emissions, improve energy efficiency    (Commission Construction Auth.)
Schedule Completion:  and save money for the airlines.
8/29/2014
Budget/Costs Incurred
Significant Developments
14    12.65
The contractor is completing the final punchlist items and closing out               11.65
12
the project. Project to be complete October 17, 2014. Concourse B     10                 8.44
400Hz upgrade to begin Design in Q1 2015                    8
in Millions  6
Schedule                            Dollars  4
2
400 Hz and Portable water boxes have been in use since May 2014.
0
Working to complete switchboard room. Project to be complete
Authorized   Forecasted  Costs Incurred
10/17/14
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
6
5.05           5.25
Change Order                           5
Current Quarter   Project Total           Millions  4
Number of COs    6          44                  3
Amount of COs    $168,383.92   $329538.92             2
Dollars in     1          0.16
Justification for COs: Changes to existing conditions - designer and       0
owner, additional room for switchboard request by owner, and             Initial  Change  Spent
Orders
varying site conditions.
Risks
None
Budget Transfers
BT to C102066 $44,000

AIRPORT
12  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
North Expressway Relocation
Project:   C800034                             Project Status:
Reconstruct the Northern Airport
Budget: $102,726,300.                        Schedule: Within or ahead
Expressway, support the extension
Phase: Construction                        Budget: On or under
of light rail to the Airport, and
Start: 7/27/2004                                  Status Reset: 2/20/2014
construct improvements to Wall 14.  (Commission Construction Auth.)
Schedule Completion:
1/28/2015
Budget/Costs Incurred
Significant Developments
112    110.22
Reconstruction of the Northern Airport Expressway and the light rail    110
transit components are complete. The construction of the Wall 14     108
106
Improvements are underway. A damaged power conduit was found   Millions
104            102.73
on S 170th St and previous project savings were returned in order to                     101.20
102
replace the conduit.                                    Dollars in 100
98
Schedule                             96
Authorized   Forecasted  Costs Incurred
The Wall 14 improvements remains on schedule and the
replacement power conduit is planned to be completed next quarter.
Construction Costs
Budget
Project forecast is within the approved budget and authorization.       120                107.82
99.45
The total budget for the Wall 14 Improvements is $1,691,000 and      100
$120,000 for the replacement power conduit.                  Millions 80
60
Change Order
Dollars in  40
Current Quarter   Project Total            20         8.37
Number of COs        1         235             0
Amount of COs       $71,000     $8,370,789              Initial  Change Order  Spent
Justification for COs: unknown conditions
Photo
Risks
None identified at this time.
Budget Transfers
The budget was increased (return of savings) from $102,806,300 to
$102,926,300 in support of the replacement power conduit.
The budget was also decreased from $102,926,300 to $102,726,300
as project savings from the Wall 14 Improvements.

AIRPORT
Port of Seattle 3Q 2014 Report  13

THIRD QUARTER REPORT, 2014
Main Terminal Low Voltage
Project Status:
Project:   C800061   Renewal and replacement of low      Schedule: Within or ahead
Budget: $20,180,000.  voltage (600 volts and below) electrical  Budget: On or under
Phase: Design      distribution equipment in the southern   Status Reset: July 29, 2014.
Start: 6/28/2007       part of the Main Terminal            (Commission Design Auth.)
Schedule Completion: 7/31/2019
Budget/Costs Incurred
Significant Developments
25
20.18
Due to project deferral and the possibility of changes in site
20
conditions and building codes, the design phase changed from 100%   Millions 15
to 0% complete. The project was approved by Commission on July
29, 2014.                                          10   7.61
Dollars in   5
Schedule                                        0.13
0
Staff has finalized the scope of work, schedule and final design           Authorized  Forecasted Costs Incurred
budget. The 100% design documents are scheduled to be complete
by the end of December 2015.
Construction Costs
Budget                            Not Applicable
The project budget was increased. The forecast is within the
approved budget. Commission Authorization for design funding has   Photo
been approved.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will



14  Port of Seattle 3Q 2014 Report

Risks, cont.
be required to add additional crews to complete work in a timely manner. This area is a 24/7/365
operation. Sequencing of this work is critical and electrical power has to be maintained without
interruptions.
Budget Transfers
BT from C800231 $11,650,000 - a result of combing airport-wide low voltage work.











AIRPORT
Port of Seattle 3Q 2014 Report  15

THIRD QUARTER REPORT, 2014
C4 UPS System Improvements
Project Status:
Project:   C800107    Replace existing Uninterruptible Power   Schedule: Delayed Schedule
Budget: $4,555,238.   Supply (UPS) System, including      Budget: On or under
Phase: Planning     batteries, with a new system located in  Status Reset: Click here to
Start: 6/28/2007       the Airport Combined Communications   enter a date.
Schedule Completion:  and Command Center (C4).        (Commission Construction Auth.)
4/29/2016
Budget/Costs Incurred
Significant Developments
5             4.56
Due to project deferral and changes to site conditions and building
codes, the design phase changed from 100% to 30% complete. The     4
Investment Committee has approved the Notebook.             Millions 3
Dollars in 
1.99
Schedule                             2
The project was reactivated. Preliminary Schedule shows            1                0.54
Substantial Completion as April 29, 2016.                       0
Authorized   Forecasted  Costs Incurred
Budget
New estimate has been developed based on new design concept.    Construction Costs
Not Applicable
Change Order
Photo
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
The C4 center is a 24/7/365 operation. Sequencing of this work is
critical and electrical power has to be maintained without
interruptions. It is not known when the construction will proceed as
this is specialized equipment and due to the complexity the new
system will require rigorous testing during the commissioning phase.
Budget Transfers
BT from C800404 $2,568,005
BT to C800404 $348,767

AIRPORT
16  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
C60 - C61 BHS Modifications
Project Status:
Project:   C800168    This work represents a critical       Schedule: Within or ahead
Budget: $10,864,825.   component to providing improved     Budget: On or under
Phase: Construction   operational baggage in-line screening  Status Reset: 11/5/2013
Start: 6/1/2012        at the South end of the Airport and     (Commission Construction Auth.)
Schedule Completion:  more baggage make-up capacity for
airlines.
12/31/2014
Budget/Costs Incurred
14
Significant Developments                        11.86
12            10.86
MD Moore started Automatic Tag Reader (ATR) installation. Due to    10
the peak summer volumes we issued a stop work during the months   Millions 8
5.85
of July  September to decrease risks to the Airlines.                6
Dollars in   4
Schedule                             2
0
The project is currently on schedule.                             Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Change Order                           6 5.16
5
Current Quarter   Project Total
Number of COs    1          4                  Millions  4         3.38
Amount of COs    $2,000       $16,727                3
2
Justification for COs: The change order issued was due to varying      Dollars in   1
0.02
site conditions.                                             0
Initial   Change   Spent
Orders
Risks
None
Budget Transfers
None


AIRPORT
Port of Seattle 3Q 2014 Report  17

THIRD QUARTER REPORT, 2014
Security Exit Lane Breach Control - Phase 1
Project Status:
Project:   C800218      Procure and install new automated   Schedule: Delayed
Budget: $1,010,000.     exit lane breach control equipment  Budget: On or under
Phase: Close Out      at the Concourse B exit.       Status Reset: 4/2/2013
Start: 3/1/2012                                   (Commission Construction Auth.)
Schedule Completion: 6/30/2013
Budget/Costs Incurred
Significant Developments
Equipment was ordered for post-construction work to convert the      1.5   1.31
twin door lanes to triple door lanes.                                       1.01
Millions                           0.92
1
Dollars in 
Schedule
0.5
Construction completed July 2013.
0
Budget                               Authorized Forecasted Costs Incurred
Project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
No major risks at this time.
Budget Transfers
None this quarter.



AIRPORT
18  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Emergency Lighting - Parking
Project Status:
Project:   C800230     Provide electrical infrastructure for a
Schedule: Delayed
Budget: $3,602,717    new source of emergency power to
Budget: On or under
Phase: Construction   feed the parking garage emergency
Status Reset: Click here to
Start: 7/24/2012        lighting circuits and ensure that code-
enter a date.
Schedule Completion:   required level of egress illumination is
(Commission Construction Auth.)
provided for safety.
7/16/2014

Significant Developments                    Budget/Costs Incurred
Project is to meet substantial completion per the Contract date.         5   4.60
Contractor is still on site performing punchlist items.
4            3.60
Schedule                             3
2.07
Millions
Monitoring on the ESCO project has been completed; however, we      2
are still waiting for the verification report before the project can be      Dollars in 1
closed.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
2   1.69
Current Quarter   Project Total                        1.56
Number of COs    0          0                   1.5
Amount of COs    $0         $0                 Millions  1
0.5
Justification for COs: n/a                                   Dollars in           0.00
0
Initial   Change   Spent
Risks                                      Orders
None
Budget Transfers
None


AIRPORT
Port of Seattle 3Q 2014 Report  19

THIRD QUARTER REPORT, 2014
Central Plant Pre-Conditioned Air
Project:   C800238     Provide a centralized pre-conditioned  Project Status:
Budget: $54,310,463    air (PC-Air) plant (PCAP), associated  Schedule: Delayed
Phase: Construction    heating and cooling piping systems,  Budget: Forecast Overrun
Start: 6/15/2009        and jet bridge terminal air handling    Status Reset: 2/25/2014
units to serve airplanes with heating   (Commission Construction Auth.)
Schedule Completion:
and cooling while at the gates.
8/31/2013
Budget/Costs Incurred
Significant Developments
Contractor's work is complete PC-Air is operating at 68 gates. Four     56         54.31
gates are remaining, but operational needs and funding have         54
delayed work on these until fourth quarter of 2014 and the first        Millions 52
quarter of 2015. A request for funds was included on the first          50   49.22
Commission meeting agenda in October. Also as part of this item,                      47.83
funds are also requested to replace the chilled water insulation,       Dollars in  48
46
anchor and guides on Concourse A and the anchors and guides on
44
Concourse B, C and South Satellite.
Authorized   Forecasted  Costs Incurred
Schedule
All but four gates are complete. Three of these will be completed in   Construction Costs
2014 and the last one in the first quarter of 2015, contingent on
operational needs.                                      40           35.20
Millions   30   27.01
Budget
Negotiations with the contractor are complete. Approval of the final       20
Change Order was included in the October Commission agenda
Dollars in                8.41
10
item.
0
Change Order                             Initial Change Spent
Orders
Current Quarter   Project Total
Number of COs        28         230
Amount of COs      $1,649,355    $9,886,034

Justification for COs: piping and electrical site conflicts on the
concourse and at the gates.
Risks
None at this time

20  Port of Seattle 3Q 2014 Report

Budget Transfers
BT from C800404 $2,250,000
BT from RMM Exp Budg $170,463
Cost of Construction Growth
Cost growth occured due to shortcomings in the bid documents. Current cost of executed Change
Orders is 31% of the base contract price. The trended cost growth projection is currently 33% over
bid price. Approximately 20% are related to error and/or ommissions (owner or designer), 7% are
currently in some form of dispute. The remainder of the cost growth are due to site conditions,
discretionary tenant requests or scope changes and regulatory requirements respectively.









AIRPORT


Port of Seattle 3Q 2014 Report  21

THIRD QUARTER REPORT, 2014
Cargo 2 West Cargo Hardstand
Enlarge the western cargo hardstand   Project Status:
Project:   C800247    in the Cargo 2 area. Includes buyout   Schedule: Delayed
Budget: $9,247,875    of two cargo buildings and tenant     Budget: On or under
Phase: Construction   relocations; relocation of FAA      Status Reset: 10/8/2013
Start: 9/25/2012       antenna, security gate, and guard     (Commission Construction Auth.)
Schedule Completion:  shack; and installation of 400Hz in-
11/1/2014           ground power.
Budget/Costs Incurred
Significant Developments
15    12.77
Cargo 2 Hardstand pavement is complete. Electrical work is
underway towards completion.                          Millions          9.25
10
4.84
Schedule                             5
Partial Beneficial Occupancy was reached on August 11, 2014, with    Dollars in 
0
completion of the hardstand portion of the work. With weather
Authorized  Forecasted Costs Incurred
delays, the remaining items are scheduled to be completed by end of
the 4th Quarter, 2014.
Construction Costs
Budget
6
The project forecast is within approved budget and authorization.           4.98
Millions  4
Change Order
Current Quarter   Project Total            2
Number of COs    0          0                 Dollars in               0.50
0
Amount of COs    $0         $0
Initial      Change     Spent
Justification for COs: n/a
Photo
Risks
None identified at this time.
Budget Transfers
$82,000 to U00125 (ERL Project)
$2,500,000 to C800404 (Aeronautical Allowance)

AIRPORT
22  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Vertical Conveyance Modernization Program -
Aeronautical - Phase I
Project Status:
Project:   C800251   Perform modernization on 9 existing    Schedule: Within or ahead
Budget: $16,282,399  elevators and 4 escalators: SSAF,     Budget: On or under
Phase: Construction  MT-2, MT-3, MT-4, MT-5, MT-6, MT-   Status Reset: 11/11/2013
Start: 10/25/2011     7, SSB, SSC. Install new elevators     (Commission Construction Auth.)
Schedule Completion: SSM and SSN. Install cooling
10/30/2016         packages on 12 existing hydraulic
elevators throughout Main Terminal.
Budget/Costs Incurred
Significant Developments                     20
16.28
Construction began with contractor taking control of three elevators.         15.21
15
Millions
Schedule
10
Construction is underway with occupancy scheduled for the first
5
phase of construction in Q2 2015.                          Dollars in                  2.55
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and construction
is underway.
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Number of COs        3          3
Amount of COs       $2,000       $2,000
Justification for COs: Differing site conditions and administrative
changes.
Risks
None
Budget Transfers
BT to C800404 $41,009

AIRPORT

Port of Seattle 3Q 2014 Report  23

THIRD QUARTER REPORT, 2014
Parking System Replacement
This project replaced the previous     Project Status:
Project:   C800253     Parking Revenue Control System,    Schedule: Delayed
Budget: $5,577,364     which manages parking access and   Budget: On or under
Phase: Close Out     revenue collection in the Airport's Main Status Reset: 3/8/2011
Start: 4/6/2010         Parking Garage.               (Commission Construction Auth.)
Schedule Completion: 8/31/2012
Significant Developments                    Budget/Costs Incurred
The Scheidt & Bachmann (S&B) system is operational and exhibits     12
9.78
accuracy and availability rates above 99.99%. However, the Port      10
continues working with S&B to correct a limited number of          Millions 8
outstanding issues. Ports' Legal and ICT departments are also                  5.58
6                     5.13
involved.
Dollars in   4
2
Schedule
0
The system is complete and in use. However, PCI related issues         Authorized  Forecasted Costs Incurred
remain to be resolved prior to closing the project.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  None this quarter
Change Order                         Photo
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: Not applicable this quarter
Risks
The Port is working with the contractor to address outstanding PCI
and unique transaction identifier issues.
Budget Transfers
None this quarter

AIRPORT
24  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Aircraft RON Parking USPS Site
Project Status:
Prepare the site for the construction   Schedule: Within or ahead
Project:   C800254     of hardstands for use as Remain    Budget: On or under
Budget: $46,602,000    Overnight (RON) parking of aircraft at Status Reset: 10/8/2013
Phase: Construction    the Cargo 5 area.           (Commission Construction Auth.)
Start: 8/26/2008
Schedule Completion: 11/1/2014
Budget/Costs Incurred
Significant Developments
60
49.99
Mass excavation is complete. Major concrete and asphalt pavement    50         45.60
and retaining walls are complete. Drainage, ramp lighting, joint       Millions 40
sealing, striping, AOA fencing and bollard protection remain for
30                    22.87
completion.
20
Dollars in  10
Schedule
0
Construction began in the 1st quarter of 2014. Due to some weather       Authorized  Forecasted Costs Incurred
delays and minor design changes, completion is delayed and is
expected to be completed by the end of the 4th quarter of 2014.
Construction Costs
Budget
30    27.83
The project forecast is within the approved budget and authorization.
Change Order                          Millions 20
10
Current Quarter   Project Total
Dollars in                           1.56
Number of COs    0          4
0
Amount of COs    $0         $0                     Initial  Change Order  Spent
Justification for COs: n/a
Photo
Risks
There has been a significant amount of contaminated soil at Cargo 5
(approximately 20,000 TN to date). Contract bid quantity is 13,500
total TN's. Any overrun will be managed through construction
contingency.
Budget Transfers
None at this time

AIRPORT
Port of Seattle 3Q 2014 Report  25

THIRD QUARTER REPORT, 2014
Port-Owned Loading Bridge Renewal &
Replacement
Project Status:
Replace or refurbish Port-owned    Schedule: Within or ahead
Project:   C800267      Passenger Loading Bridges (PLBs)  Budget: On or under
Budget: $2,405,000      that have reached the end of their   Status Reset: 2/28/2012
Phase: Construction     service life.              (Commission Construction Auth.)
Start: 2/28/2012
Schedule Completion: 12/31/2014
Budget/Costs Incurred
Significant Developments
3
The work associated with this CIP has been completed and the            2.41    2.41
2.5
project is in closeout. The scope of work at Gate S4 is now being                         1.98
handled under CIP C800662 - 12th & 13th FIS Widebody Gate       Millions 2
project.                                                1.5
Dollars in   1
Schedule                             0.5
Work has been completed and bridge is in use.                  0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                           0.8  0.68     0.67
0.7
Current Quarter   Project Total
0.6
Number of COs    1          6                 Millions 0.5
Amount of COs    $0         $-12,385              0.4
0.3
0.2
Justification for COs: n/a                                   Dollars in   0.1       0.01
0
0.1   Initial   Change   Spent
Risks                                      Orders
No risks identified at this time.
Budget Transfers
None this quarter.


AIRPORT
26  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
8th Floor Weatherproofing
Project Status:
Project:   C800274      Removal and replacement of the   Schedule: Within or ahead
Budget: $9,324,000.     floor covering system on the eighth  Budget: On or under
Phase: Close Out      floor of the STIA parking garage   Status Reset: 5/27/2014
Start: 3/23/2010          and repair or replacement of      (Commission Construction Auth.)
Schedule Completion:    expansion joints and flashings.
7/31/2014
Budget/Costs Incurred
Significant Developments
14    13.05
PCL, the Port's contractor, was ordered to install deck coating in
12
areas were defective coating had been identified and removed. This              9.62
Millions 10
work was carried out and the project is now being closed out.                          8.12
8
6
Schedule
Dollars in   4
Construction was longer than anticipated, but was complete in Q3      2
2014.                                         0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
7    6.05               6.07
Current Quarter   Project Total            6
Number of COs    5          28                Millions 5
Amount of COs    $52,876      $122,434              4
3
2
Justification for COs: N/A                                 Dollars in 
1             0.12
0
Risks
Initial     Change Order     Spent
None at this time
Photo
Budget Transfers
None this quarter.


AIRPORT
Port of Seattle 3Q 2014 Report  27

THIRD QUARTER REPORT, 2014
Long-Term Cell Phone Lot
Project Status:
Schedule: Delayed Schedule
Project:   C800324      Construct a new cell phone waiting
Budget: On or under
Budget: $2,177,100.     lot to replace the existing lot that is
Status Reset: 5/6/2014
Phase: Construction     being displaced, and construct a
(Commission Construction Auth.)
Start: 12/11/2012         traffic control roundabout or signal
Schedule Completion:    adjacent to the lot on South 170th
Street.
10/31/2014
Budget/Costs Incurred
Significant Developments                        2.18   2.18
2.2
The Cell Phone Lot is in service. Construction of S 170th St utility
crossings for fire hydrants and wifi communications are complete but    2.1
the wifi system is not yet in operation. Staff is continuing to evaluate    Millions
2                    1.95
the cost and performance of the permanent traffic control solution.
Dollars in 1.9
Schedule                            1.8
Authorized  Forecasted Costs Incurred
A recommendation on the permanent traffic control method is
expected by year end, to be followed by a request to Commission for
additional design and construction authorization.
Construction Costs
Budget                             1.2          1.04
The current authorized budget for the Cell Phone Lot is $2,177,100.     1   0.89
Staff will request additional authorization for the permanent traffic      Millions 0.8
0.6
Dollars in 
control solution previously estimated at $1,222,000 to $2,855,000.
0.4
Change Order                                 0.15
0.2
Current Quarter   Project Total            0
Initial       Change       Spent
Number of COs        1          4                     Orders
Amount of COs       $80,000      $150,405
Photo
Justification for COs: A change in the scope for the completion of
the S 170th St utility crossings.
Risks
Coordination with the City of SeaTac for a recommended permanent
traffic control solution.
Budget Transfers
$30,000 to expense to fund permanent traffic control analysis and
evaluation.
AIRPORT
28  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Two New CTE Freight Elevators
Project Status:
Project:   C800334      Provide two new freight elevators   Schedule: Within or ahead
Budget: $8,290,100.     to support concession operations in  Budget: On or under
Phase: Construction     the Central Terminal/Pacific      Status Reset: Click here to
Start: 8/5/2011          Marketplace.                enter a date.
Schedule Completion: 7/31/2014                  (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
Construction is finishing. Both new elevators were delivered in the 3rd    8.5   8.29     8.29
Quarter.
8
Millions
Schedule
7.5                         7.28
As previously reported, the project is delayed by one-year due to
scope changes included in the redesign efforts, and delays in        Dollars in  7
reviews.
6.5
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
5   4.39         4.51
Current Quarter   Project Total
4
Number of COs        13         39
Amount of COs       $89,433      $294,295           Millions  3
2
Justification for COs: Differing site conditions and code compliance     Dollars in    1
improvements.                                           0.29
0
Initial   Change   Spent
Risks
Orders
No new risks identified this quarter.
Budget Transfers
None at this time


AIRPORT
Port of Seattle 3Q 2014 Report  29

THIRD QUARTER REPORT, 2014
Electrical Ground Support Equipment (EGSE)
Electrical Charge Stations
Project Status:
Project:   C800335      Airport-wide electrical charging     Schedule: Delayed Schedule
Budget: $30,198,000    system for electrical ground      Budget: On or under
Phase: Construction    support equipment (EGSE) at the   Status Reset: 10/23/2012
Start: 10/26/2010        Concourses and the North and     (Commission Construction
Schedule Completion:    South Satellites.            Auth.)
6/30/2016
Budget/Costs Incurred
Significant Developments
35            30.20
Continue to finalize GSE Phase 1 Project closeout and finalize        30   25.35
"Record Drawings" (includes Concourse C, Concourse D and North    25
Satellite). The GSE automatic data collection, storage and historical     20                15.20
report generation for electric GSE vehicle usage and energy         in Millions 15
consumption is operational. Port is working with Alaska Airlines to     Dollars  10
5
verify and confirm the accuarcy of each monthly report.
0
Authorized  Forecasted Costs Incurred
Design review for the GSE Charger Phase 2 Project continues and is
nearing completion and lessons learned from the GSE Phase 1
project are being incorporated in the design documents. Resolving    Construction Costs
design conflicts and coordinating with IAF and other project teams to
minimize construction conflicts. Reviewing GSE Phase 2 scope of       5               4.68
work and implementation schedule in order to complete                 3.88
4
infrastructure requirements within Concourse A, Concourse B and
South Satellite to support the GSE Phase Charging Corrals once the    Millions 3
IAF project defines scope of work on Concourse A and South         2
Satellite Terminal and Ramp areas.                         Dollars in            0.81
1
0
FAA, via the VALE grant process, has awarded the Port of Seattle a
Initial    Change Order    Spent
total of $5,500,000 for the GSE Charger Phase 2 Project.
Washington State Department of Revenue has approved sales tax
exemption for the construction phase of the GSE Charger Phase 2
Project.



30  Port of Seattle 3Q 2014 Report

Schedule
Phase 1 construction is complete except for finalizing the Record Drawings and other project related
documents. Phase 2 construction scheduled for completion mid-2016. Completion schedule for the
GSE Charger Phase 2 project, is impacted by the IAF and other projects that are in design and
scheduled for construction in 2015 and 2016
Budget
The project forecast is within the approved budget. The remaining authorization for the construction
funding and authority to advertise for construction will be requested when the design and bid
documents are completed for GSE Charger Phase 2 Project.
Change Order
Current Quarter   Project Total
Number of COs   9          104
Amount of COs   $102,364     $4,684,001.00
Justification for COs: Errors/Omissions - Designer & Owner, Varying Site Conditions, Scope Change,
and Regulatory Requirements.
Risks
Coordinate with other airfield projects and Airline Gate Realignment program. Budget and schedule
may affect project implementation and completion.
Budget Transfers
None this quarter.





AIRPORT
Port of Seattle 3Q 2014 Report  31

THIRD QUARTER REPORT, 2014
Refurbish Bag Claim Device
Project Status:
Project:   C800368     Refurbish Claim Device 8 and      Schedule: Within or ahead
Budget: $303,730      replace the current door to a more   Budget: On or under
secure type.                   Status Reset: Click here to
Phase: Design
enter a date.
Start: 6/24/2014
(Commission Construction Auth.)
Schedule Completion: 11/24/2014
Significant Developments                    Budget/Costs Incurred
Commission approved budget In June 2014. Design was completed
0.35     0.30       0.30
and permits have been received to begin Construction.
0.3
0.25
Schedule
0.2   Millions
Project is on schedule.                                  0.15
Dollars in  0.1
Budget                            0.05          0.03
0
The project forecast is within the approved budget and authorization.
Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                None at this time
Amount of COs    $0         $0
Justification for COs: N/A
Risks
None
Budget Transfers
None



AIRPORT
32  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
South Satellite HVAC, Lights, and Ceiling
Replacement
Project Status:
Replace the heating ventilation,      Schedule: Within or ahead
Project:   C800376     lighting and ceiling systems in the    Budget: On or under
Budget: $34,011,000    South Satellite.             Status Reset: Click here to
Phase: Design                            enter a date.
Start: 7/24/2012                                  (Commission Construction Auth.)
Completion: 7/31/2016
Budget/Costs Incurred
Significant Developments
Nothing significant to report.                                  40
34.01
30
Schedule                            Millions
20
The project is delayed until the Airport Master Plan effort clarifies the
future operational requirements for the South Satellite.              Dollars in  10   6.35
1.47
Budget                              0
Authorized  Forecasted Costs Incurred
The design service directive will be terminated in the fourth quarter.
Project costs will be evaluated for the amount to expense and the
amount to capitilize when the project is restarted.
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None
Risks
None
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 3Q 2014 Report  33

THIRD QUARTER REPORT, 2014
Baggage Handling System (C22-C1, MK1, and
TC3)
Replace the ticket counter (TC3)       Project Status:
conveyors and declines, reroute the
Project:   C800382                             Schedule: Within or ahead
conveyors of the C-22 system and      Budget: On or under
Budget: $5,585,000   connect it to the C-1 screening system,  Status Reset: 12/11/2012
Phase: Close Out    replace the existing makeup (MK1)    (Commission Construction Auth.)
Start: 3/1/2011        device, and install a new odd size
Schedule Completion:  baggage system.
5/31/2013
Budget/Costs Incurred
Significant Developments
8
6.76
None
5.59
6                    5.48
Millions
4
Dollars in 
Schedule
The project forecast is within the approved budget and authorization.
2
Budget                             0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Current Quarter   Project Total
Number of COs    0          44                  2            1.79
1.59
Amount of COs    $0         $202,744.00            1.5
1
Justification for COs: None this quarter
Millions
0.5              0.20
Risks                                Dollars in 
0
None identified at this time.                                      Initial  Change Order  Spent
Budget Transfers
None at this time
Cost of Construction Growth
Three changes represent the majority of the cost growth: 1) removed
the C1-CS1 curbside conveyor since replacement was no longer


34  Port of Seattle 3Q 2014 Report

Cost of Construction Growth, Cont.
required, 2) The contract design to replace make-up device MK1 did not include POS ergonomic
standards for this kind of device; and 3) the original contract design for the conveyors in the C1-CS2
conveyor line created unsafe electrical and mechanical conditions for maintenance works. Several
other smaller changes included fire sprinkler and architectural revisions, including a credit to remove
a small scope of work.












AIRPORT
Port of Seattle 3Q 2014 Report  35

Cargo 6 Enhancements                THIRD QUARTER REPORT, 2014
Project:   C800390    Enlarge the Cargo 6 off-gate        Project Status:
Budget: $6,345,875    hardstand to allow simultaneous     Schedule: Delayed Schedule
nose-loading of wide-body freight
Phase: Construction                        Budget: On or under
aircraft as well as provide fuel hydrant
Start: 9/25/2012                                  Status Reset: 10/8/2013
and ground power capabilities.
Schedule Completion:                        (Commission Construction Auth.)
12/31/2014
Significant Developments                    Budget/Costs Incurred
Cargo 6 Enhancements has been combined with Cargo Areas 2 and
7    6.35      6.35
5 as a single construction contract and has been successfully bid
6
and awarded.
5
4
Schedule
in Millions  3
Construction of the Cargo 6 hardstand enhancements began in 3rd     Dollars  2
0.62
quarter 2014. Due to weather delays and Fuel Hydrant design         1
0
changes with long lead times, completion is delayed to the 1st
Authorized  Forecasted Costs Incurred
quarter 2015.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
4    3.72
Change Order
3
Current Quarter   Project Total
2
Number of COs    0          0
Millions
Amount of COs    $0         $0                  1
Dollars in 
0
Justification for COs: n/a                                        Initial  Change Order  Spent
Risks                               Photo
None identified at this time.
Budget Transfers
None


AIRPORT
36  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
RW16C/34C Reconstruction
Project Status:
Project:   C800406    Produce final design and reconstruct
the existing RW 16C/34C in its       Schedule: Within or ahead
Budget: $99,538,000
existing location, replace TW C and    Budget: On or under
Phase: Design
N, reconfigure TWs H and J, install     Status Reset: Click here to
Start: 5/4/2010
FOD detection equipment, and install   enter a date.
Schedule Completion:   LED lighting system.           (Commission Construction Auth.)
11/30/2016
Budget/Costs Incurred
Significant Developments
Project is in final design. Reviewed 90% drawing package. A        120
99.54
Foreign Object Debris (FOD) detection system vendor has been      100
selected.                                           Millions 80
60
Schedule
Dollars in  40
Request for Commission authorization is scheduled for December 2,    20   10.68
1.58
2014. Advertisement is scheduled for December 4, 2014 with        0
construction to begin the first full week of April, 2014.
Budget                            Construction Costs
There will be a requested Capital increase of approximately        Not Applicable
$7,000,000 and a $3,200,000 Expense increase.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
$9,100,000 from C800404 (Aeronautical Allowance)
$90,000,000 from C800058 (RW 16C/34C Reconstruction)

AIRPORT                            Port of Seattle 3Q 2014 Report  37

THIRD QUARTER REPORT, 2014
Federal Inspection Services Short Term
Improvements
Short Term Improvements to the      Project Status:
Project:   C800426    Federal Inspection Service area at S.   Schedule: Delayed
Budget: $1,819,000.    Satellite to improve through put and   Budget: On or under
Phase: Construction   conditions for passengers waiting in   Status Reset: 12/10/2013
the International Corridor prior to       (Commission Construction Auth.)
Start: 4/1/2012
Primary Inspection.
Schedule Completion:
Budget/Costs Incurred
6/23/2014
2    1.82      1.82
Significant Developments
1.5                        1.38
Major Contract work is nearing completion. Light fixtures, new       Millions
podiums and painting is complete. Plastic laminate panel installation    1
and guardrail installation on new wayfinding walls is underway. PCS
Dollars in 0.5                                                                               has completed installation of permanent stanchions in the
international corridor and is installing new PA system.
0
Authorized  Forecasted Costs Incurred
Schedule
Delivery of the plastic laminate panels was delayed and will prevent
the contractor from completing work on time. The Port and the      Construction Costs
contractor are negotiating a new beneficial occupancy date at this
0.7   0.61           0.62
time.
0.6
0.5
Budget                             Millions 0.4
Dollars in 
The project forecast is within the increased, approved budget and       0.3
authorization.                                           0.2
0.1          0.06
Change Order                           0
Initial   Change   Spent
Current Quarter   Project Total                   Orders
Number of COs        7          7
Amount of COs       $56,123      $56,123
Justification for COs: n/a
Risks
Delayed completion is anticipated to have little impact on the
effectiveness of the new wayfinding walls. The Port and the
contractor are printing large scale temporary paper and foam core
"panels" that will remain on the new walls until work is complete.
Budget Transfers
None at this time.
AIRPORT
38  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Doug Fox Lot Service Upgrades
Project:   C800451    Construct a new drainage system,     Project Status:
Schedule: Delayed Schedule
Budget: $6,453,000   asphalt resurfacing, improved lot
lighting, new building, and road signage  Budget: Forecast Overrun
Phase: Construction
to improve lot appearance, function,     Status Reset: 10/8/2013
Start: 2/1/2012
and revenue generation.            (Commission Construction Auth.)
Schedule Completion:
3/31/2015
Budget/Costs Incurred
Significant Developments
8    6.90      6.90
Overall project construction is approximately 87% complete. The
parking lot, lighting, and storm drainage systems are complete. The     6
modular building was delivered to the site. The main pylon sign was    Millions                  4.28
4
installed.
Dollars in   2
Schedule
0
The overall project has been delayed with substantial completion
Authorized  Forecasted Costs Incurred
forecast for March 2015. Fabrication, delivery, and installation of the
modular building is critical path for project completion. Delays have
occurred prior to fabrication due to value engineering, and during     Construction Costs
fabrication due to State L&I review and approval.
5
3.99
Budget                              4
The project is forecast to be overrun with a total estimated budget of    Millions              3.14
3
$6,900,000. This is due primarily to the construction schedule
2
delays. Additional budget authorization will be requested in
December in order to complete the project.                    Dollars in   1
0.14
0
Change Order                             Initial Change Spent
Orders
None
Current Quarter   Project Total          Photo
Number of COs        7         15
Amount of COs       $52,970      $139,872
Justification for COs: Changes are primarily related to errors and
omissions (scope gap), supporting tenant improvements (site
camera systems), or regulatory requirements (grounding).

Port of Seattle 3Q 2014 Report  39

Risks
Additional delays in installation, final site inspection, and activation of the modular building, which are
the project critical path, will delay project completion. Wet weather conditons may delay asphalt
paving and striping.
Budget Transfers
None











AIRPORT
40  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Industrial Waste Treatment Plant (IWTP) Fiber
Installation
Project Status:
Install new Single Mode Fiber
Project:   C800461                             Schedule: Delayed Schedule
cable from Main Terminal to
Budget: $514,000                          Budget: On or under
IWTP and Gate E-45.
Phase: Construction                        Status Reset: Click here to
Start: 3/1/2012                                   enter a date.
Schedule Completion: 9/14/2014                   (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Construction completed as of September 14, 2014 and the fiber is
0.6
now operational.                                          0.51    0.51
0.5
Schedule                             0.4           0.36
Millions 0.3                                                                           The Project is now complete and is in closeout status.
Dollars in 0.2
Budget                             0.1
0
Forecast is currently within the approved budget and authorization.        Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                Not Applicable
Amount of COs    $0         $0
Justification for COs: n/a
Risks
No known risks.
Budget Transfers
None this quarter.



AIRPORT

Port of Seattle 3Q 2014 Report  41

THIRD QUARTER REPORT, 2014
Fiber Infrastructure to Gate Backstands
Extend airport provided            Project Status:
Project:   C800464
communications infrastructure and Wi-  Schedule: On Schedule
Budget: $2,296,000    Fi antennas to additional gates on    Budget: On or under
Phase: Design       Concourses A, and B.          Status Reset: Click here to
Start: 7/9/2013                                   enter a date.
Schedule Completion: 3/2/2016                   (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Wi-Fi Audit was completed and 90% Design was submitted for
2.5                   2.33
review.
2
Millions
Schedule                             1.5
The project is now at a 90% design submittal. The schedule has      Dollars in 
1      0.79
been updated to account for the delay of acquiring a Wi-Fi auditor
0.5                                0.25
and completing the Wi-Fi audit.
0
Authorized       Forecasted      Costs Incurred
Budget
The project forecast is within the approved budget. Commission
Authorization for construction funding and authority to advertise for    Construction Costs
construction will be requested when the bid documents are        Not Applicable
completed.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None
Budget Transfers
BT to C800622 $955,000

AIRPORT
42  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Airport Signage (Airline Realignment)
Project Status:
Project:   C800474      Provide airport directional signage   Schedule: Delayed
Budget: $523,000       for the airline realignment program.  Budget: On or under
Phase: Close Out                          Status Reset: 06/04/2012
Start: 06/01/2011                                 (Commission Construction Auth.)
Schedule Completion: 06/30/2013
Budget/Costs Incurred
Significant Developments
0.7     0.65
Project complete. This will be the last Quarterly report.
0.6               0.52       0.52
0.5
Schedule
0.4   Millions
As previously reported, the change in schedule was based on the      0.3
overall Airline Realignment Program Schedule. Airline relocations     Dollars in  0.2
were delayed.                                     0.1
0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget.
Construction Costs
Change Order
Not Applicable
Current Quarter   Project Total
Number of COs        4          4
Amount of COs       $10,191      $10,191
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers



AIRPORT

Port of Seattle 3Q 2014 Report  43

THIRD QUARTER REPORT, 2014
Feeder 101 Taps Replacement/Fire Station
Electric Upgrades
Project Status:
Project:   C800479    Replace the existing 208V transformer  Schedule: Within or ahead
Budget: $4,775,000.    and 12.47 KV feeder, and add a 500   Budget: On or under
Phase: Construction   KV generator and a 1000kVA      Status Reset: 7/1/2014
Start: 4/1/2013        transformer. Replace the electrical     (Commission Construction Auth.)
feeds to 13 locations along Air Cargo
Schedule Completion:
Road. Also, the electrical transformer
10/31/2016          and associated switchgear for Air
Cargo #4 will be replaced.
Budget/Costs Incurred
Significant Developments
Combined referenced projects (C800479 & C800234) in July 2014.      6
4.78      4.78
Bid in October 2014. Completed ready to bid package.              5
Millions  4
Schedule                             3
Project was bid in October 2014. Contract executed in November.       2
Dollars in                            0.79
Substantial completion scheduled for Q3 2016.                   1
0
Budget                               Authorized Forecasted Costs Incurred
The project is currently on budget.
Change Order                         Construction Costs
Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Unplanned electrical shut downs could impact the project schedule.
Budget Transfers
BT from C800234 $2,343,700

AIRPORT
44  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
New Window Wall Ticket Zone 1
Project Status:
Project:   C800490      Install new common use ticket
Schedule: Delayed Schedule
Budget: $5,636,000     counters and new baggage system
Budget: On or under
Phase: Close Out      along the window wall and
Status Reset: 5/13/2014
baggage system renovation.
Start: 7/1/2012                                   (Commission Construction Auth.)
Schedule Completion: 2/17/2014
Budget/Costs Incurred
Significant Developments                     5.8
5.64      5.64
Project is complete and in use. This will be the last Quarterly report.
5.6
Millions
Schedule                            5.4
5.21
The project schedule was delayed due to unforeseen structural and
Dollars in 5.2
design issues.
5
Authorized  Forecasted Costs Incurred
Budget
Additional funding was approved by the Commision on May 13,
2014.                                       Construction Costs
Change Order                           5
3.99
Current Quarter   Project Total              4  3.43
Number of COs    83         183                Millions  3
Dollars in 
Amount of COs    $453,442     $702,911
2
1        0.70
Justification for COs: Due to the accelerated nature of the project, a
number of design issues required addressing during construction.        0
Initial   Change   Spent
Orders
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 3Q 2014 Report  45

THIRD QUARTER REPORT, 2014
Facility Monitoring System Renewal
Project:   C800495     Provide a system upgrade that will    Project Status:
Budget: $3,420,180     allow the system to maintain and    Schedule: Delayed
Phase: Construction    expand monitoring of critical systems  Budget: On or under
Start: 1/22/2013        such as elevators, escalators, moving  Status Reset: 12/10/2013
Schedule Completion:   walks, passenger boarding bridges   (Commission Construction Auth.)
and baggage systems.
8/31/2015
Budget/Costs Incurred
Significant Developments
4
3.42       3.42
The FMS network upgrade and Baggage Reporting Software was
completed and accepted by the Port. Major construction work has      3
been advertised and awarded.                           Millions
2
1.08
Schedule                            Dollars in  1
Major construction work has been awarded and notice to proceed
0
was issued on October 31st.                                Authorized Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers


AIRPORT

46  Port of Seattle 3Q 2014 Report

Airportwide Mechanical Controls System       THIRD QUARTER REPORT, 2014
Project Scope and description:
Project:   C800497       Upgrade the HVAC Controls     Project Status:
Budget: $3,500,000.      System for the Airport. This    Schedule: Delayed
Phase: Design         includes adding a wireless     Budget: Forecast Overrun
Start: 5/1/2013            connection to the Logistics area to  Status Reset: 12/9/2014
the south of the Airport.         (Commission Construction Auth.)
Schedule Completion:
5/30/2016
Significant Developments                    Budget/Costs Incurred
Scope was added at 100%. The manufacturer of the control panels      4         3.50
notified us that replacement parts for existing control panels will no
longer be available in 2015. Thirty one additional control panels were     3
added.                                       Millions
2
Schedule                            Dollars in  1
0.27               0.19
100% design is on hold waiting for the next MII ballot and
0
Commission authorization to increase budget and authorize bidding.       Authorized  Forecasted Costs Incurred
Plan to request Commission authorization in Q4 of 2014.
Budget                            Construction Costs
The budget will increase to $3,500,000 with the added scope. The    N/A
increase was presented at the August MII meeting. Plan to return to
Commission in December.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Unplanned electrical shut downs could impact the project schedule.
Increased control component costs. An allowance was added to the
estimate.
Budget Transfers
BT from C800404 $1,343,000
AIRPORT
Port of Seattle 3Q 2014 Report  47

THIRD QUARTER REPORT, 2014
RAC Baggage Claim Renovation
Project:   C800541      Renovation of both rental car      Project Status:
Budget: $1,183,200.     counter locations in baggage claim  Schedule: Delayed Schedule
Phase: Closeout       into new waiting areas with vending  Budget: On or under
Start: 10/1/2012          machines and other facilities for     Status Reset: 4/2/2013
Schedule Completion:    special operations           (Commission Construction Auth.)
12/31/2013
Budget/Costs Incurred
Significant Developments
1.5
The master clock system was restored in Baggage Claim. The           1.32
1.18
1.10
project is in closeout.
Millions  1
Schedule
0.5
Beneficial Occupancy occurred on January 24, 2014, one month      Dollars in 
later than originally intended. The project is now in closeout.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
0.35                       0.30
Current Quarter   Project Total
0.3     0.26
Number of COs        0         12             0.25
Amount of COs        $0       $62,052            0.2 Millions
0.15
Justification for COs: None this quarter.                        Dollars in 0.1         0.06
0.05
0
Risks
Initial    Change Order    Spent
None this quarter.
Budget Transfers
Photo
Overall budget reduced from $1,318,200 to $1,183,200 as project
savings ($135,000).


AIRPORT
48  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Replace PLBs at S7, S9 & B4
Project Status:
Project:   C800543      Replace the Passenger Loading    Schedule: Within or ahead
Budget: $2,950,000      Bridges at S7 & S9 and install a    Budget: On or under
Phase: Construction     new bridge At B4           Status Reset: 1/21/2014
Start: 1/21/2014                                  (Commission Construction Auth.)
Schedule Completion:
12/31/2014
Significant Developments                    Budget/Costs Incurred
S9 installed in October 2014.
3.5
2.95      2.95
3
Schedule
Millions 2.5                        1.90
Project is on schedule.                                    2
1.5
Budget                             Dollars in  1
0.5
No issues
0
Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total
Number of COs    0          0                Construction Costs
Amount of COs    $0         $0                Not Applicable
Justification for COs: n/a
Risks
None at this time
Budget Transfers
None



AIRPORT
Port of Seattle 3Q 2014 Report  49

THIRD QUARTER REPORT, 2014
NorthSTAR Program
Project Status:
Project:   C800544   Includes programmatic project
management and project controls costs   Schedule: Within or ahead
Budget: $20,600,000.
for the NorthSTAR program, consisting    Budget: On or under
Phase: Design     of 5 capital projects that represents a    Status Reset: Click here to
Start: 4/5/2012       unique partnership between the Port     enter a date.
Schedule Completion: and Alaska Airlines.             (Commission Construction Auth.)
8/27/2020
Budget/Costs Incurred
Significant Developments
Initiated communications and coordination with Airport-wide Gate      25
20.60
Utilization taskforce. Reviewing the AAG roles and responsibilities.     20
15
Schedule
in Millions
10
Continue programmatic linkage coordination to assure airport-wide     Dollars      3.60
gate availability is not compromised during construction.             5                2.59
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is inclusive of Programmatic Management
Reserve and is within the approved budget.
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Communication and coordination across multiple teams and
stakeholders along with identification/monitoring of all "linked"
Capital projects outside of NorthSTAR.
Budget Transfers
$5,200,000 was transferred into Program "Management Reserve"
from C800547 - Concourse C Vertical Circulation & C800555 -
Refurbish Baggage System.

AIRPORT
50  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
NorthSTAR Main Terminal Improvements
Project Status:
Project:   C800545    Renovate the North Main Terminal     Schedule: Within or ahead
Budget: $29,200,000   security checkpoint, curbside and     Budget: On or under
Phase: Design      ticketing lobby areas incorporate self-   Status Reset: Click here to
Start: 12/3/2013       operated technologies and improve     enter a date.
Schedule Completion:  aesthetics.                 (Commission Construction Auth.)
9/18/2018
Budget/Costs Incurred
Significant Developments
40
Landrum and Brown under contract for facility determination
29.20
analysis.                                             30
Millions
20
Schedule
Kickoff meetings with project team began in early October.          Dollars in  10
1.50               0.09
0
Budget                               Authorized Forecasted Costs Incurred
Project forecast is within the approved budget. Commission
Authorization for construction funding and authority to advertise for
Construction Costs
construction is anticipated Q1 2017 when the bid documents are
Not Applicable
completed.
Change Order
Current Quarter   Project Total
Number of COs        n/a         n/a
Amount of COs        n/a         n/a
Justification for COs: n/a
Risks
Project scope definiton could increase scope and budget.
Budget Transfers
None


AIRPORT
Port of Seattle 3Q 2014 Report  51

THIRD QUARTER REPORT, 2014
NorthSTAR Concourse C Vertical Circulation
Project:   C800547    Construct exterior, weather protected   Project Status:
Schedule: Within or ahead
Budget: $15,400,000.   sloped walkways with elevators at
Gates C2/4, C10/12, and C14 to      Budget: Forecast Overrun
Phase: Construction
provide enhanced access from       Status Reset: 10/22/2013
Start: 11/6/2012
concourse to aircraft ramp for         (Commission Construction Auth.)
Schedule Completion:  Alaska/Horizon regional operations.
4/17/2015
Significant Developments                    Budget/Costs Incurred
18.60
Steel erected at C2 and C16 and elevators towers poured. AAG's      20
16.08
Gate C2 ground level passenger walkway near completion. eGSE
15
chargers relocation design 100% complete, permitted and          Millions
reinstallation construction started.                             10
4.37
Schedule                            Dollars in  5
0
The construction effort is progressing as planned. Forma
Authorized  Forecasted   Costs
Construction's initial schedule reflected a schedule slip due to early                    Incurred
delays in civil work. Working mitigation plans with contractor and
coordination with Alaska to recover schedule delay and minimize     Construction Costs
impact to Alaska/Horizon operations.
10    8.72
Budget                             8
The project is currently forecasting an overrun to the revised budget     6
after transferring too much funds initially identified as potential
Millions
4
savings to Program Management Reserve. The funding shortfall was   Dollars in  2
validated and funds will be returned to the project Management                 0.14    0.51
0
Reserve to cover.
Initial      Change      Spent
Orders
Change Order
Current Quarter   Project Total
Number of COs        6          7
Amount of COs      $135,886     $135,123
Justification for COs: Scope changes (Fire Hydrant at C14 &
extension of 4" HDPE Grease Interceptor piping.)
Risks
Potential for underground utility conflicts during construction.
Budget Transfers
$3,200,000 was transferred to C800544 as potential savings.
Subsequently, it was determined that this was excessive and
$1,000,000 will be returned.
52  Port of Seattle 3Q 2014 Report
AIRPORT

THIRD QUARTER REPORT, 2014
SSAT Interior Renovations
Project Status:
Project:   C800549     Modify the mezzanine and         Schedule: Within or ahead
Budget: $3,338,000    concourse levels of the South      Budget: On or under
Satellite to improve the passenger
Phase: Planning                          Status Reset: 5/31/2014
experience.
Start: 11/4/2012                                  (Commission Construction Auth.)
Schedule Completion: 6/1/2016
Significant Developments                    Budget/Costs Incurred
Design authorized August 5, 2014. Phase One design underway.
800    719.00
Schedule                            600
On schedule.                                    Millions
400
Budget                            Dollars in 200
Within budget.                                                 3.38    0.05
0
Authorized   Forecasted  Costs Incurred
Change Order
Current Quarter   Project Total
Number of COs    0          0                Construction Costs
Amount of COs    $0         $0                Not Applicable at this time
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
BT from C800404 $88,000



AIRPORT

Port of Seattle 3Q 2014 Report  53

THIRD QUARTER REPORT, 2014
Concourse D Roof Replacement
Project Status:
Project:   C800550     Remove and replace the roofing     Schedule: Within or ahead
Budget: $3,371,800    systems on Concourse D of the     Budget: On or under
Airport; install ladders, stairs and
Phase: Construction                        Status Reset: Click here to
fall protection on the penthouse
Start: 7/1/2013                                   enter a date.
sections; and make repairs and
Schedule Completion:                        (Commission Construction Auth.)
where required, replacements to
11/24/2014           the KalWall window system.
Budget/Costs Incurred
Significant Developments
4
All roofing systems have been replaced. KalWall skylight system           3.37     3.37
3.5
has been refurbished or replaced.
Millions     3
2.5                                2.08
Schedule                            Dollars in   2
1.5
This project is currently on schedule.
1
0.5
Budget                              0
Authorized       Forecasted      Costs Incurred
The project forecast is within the approved budget.
Change Order
Construction Costs
Current Quarter   Project Total
Number of COs    5          5                  2.5  2.30
Amount of COs    $47,910      $47,910               2         1.70
Millions  1.5
Justification for COs: Varying site conditions and measurement
1
discrepancy.
Dollars in   0.5
0.05
Risks
0
Stair, ladder and fall protection installation may be delayed by             Initial  Change  Spent
Orders
weather conditions.
Budget Transfers
None at this time.


AIRPORT
54  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Grease Interceptor Augmentation
Project Status:
Project:   C800551     Install two underground 9,000 gallon   Schedule: Delayed
Budget: $1,484,200.    grease interceptors to service the    Budget: On or under
Phase: Permitting     Concourse C and South Satellite.    Status Reset: Click here to
Start: 5/1/2013                                   enter a date.
Schedule Completion: 5/31/2015                  (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Design flaw discovered prior to bid. Grease Interceptor at S.
2
Satellite location is being revised. Revised design approved by Ops
1.48      1.48
and coordinated with S1 Ramp project (both in same location). Bid
1.5
documents being developed.                           Millions
1
Schedule
Dollars in 0.5                        0.26
Design revision has caused project schedule to slip.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
Construction Costs
be requested when the bid documents are completed.
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Construction impacts Delta Operations at S. Satellite.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 3Q 2014 Report  55

THIRD QUARTER REPORT, 2014
NorthSTAR Refurbish Baggage Systems
Project:   C800555    Refurbish existing baggage systems   Project Status:
Budget: $19,482,500.   in support of AAG operation at North   Schedule: Within or ahead
Phase: Construction   Satellite and Concourse D. The work  Budget: On or under
will extend the service life of part of
Start: 11/6/2012                                  Status Reset: 9/24/2013
the C92 systems, C88 North Satellite
Schedule Completion:                        (Commission Construction Auth.)
systems, and C88 tunnel systems.
5/15/2015
Budget/Costs Incurred
Significant Developments
Baggage control system and virtual servers installed and operating     25   21.48
19.48
for north end of terminal. Demolition of Concourse D mini-sort area     20
complete and construction started.                          15
in Millions 10
Schedule
Dollars   5                          2.68
Abatement for North Satellite baggage motor control center is
0
nearing completion. Concourse D mini-sort area is on schedule for        Authorized  Forecasted Costs Incurred
the November "in-use" milestone.
Budget                            Construction Costs
The project forecast is within the approved budget.
15
11.83
Change Order
10
Current Quarter   Project Total
Millions
Number of COs        6          6              5
Amount of COs      $491,987     $491,987           Dollars in          0.49    0.45
0
Initial      Change      Spent
Justification for COs: n/a                                             Orders
Risks
Project schedule has no float remaining and Motor Control Panel
room have impacted construction schedule. Mitigation options are
under investigation.
Budget Transfers
$2,000,000 identified as potential savings and transferred to
C800544 NorthSTAR Program "Management Reserve".

AIRPORT
56  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
NorthSTAR North Satellite Renovation and
NSTS Lobbies
Project:   C800556     Renovation of the North Satellite     Project Status:
Budget: $399,732,944   (NSAT) terminal, including North    Schedule: Within or ahead
Phase: Design       Satellite Transit System (STS)     Budget: On or under
Start: 7/24/2012        stations "refresh", ramp level,       Status Reset: Click here to
Concourse level, and new rooftop    enter a date.
Schedule Completion:
airline lounge.                   (Commission Construction Auth.)
2/13/2020
Budget/Costs Incurred
Significant Developments
Completed 30% design development and cost estimate
reconciliation. Solicited for GC/CM Contractor, received proposals     500
and shortlisted 3 firms for interview. Completed 30% design          Millions           399.73
400
Sustainability report and presented to Port and AAG Steering
Committees. Completed aircraft layout and ground equipment       300
analysis. Received MII approval and Commission authorization to     Dollars in 200
expand North Satellite footprint to 20 gates.
100    48.71
8.69
Schedule                             0
Authorized  Forecasted Costs Incurred
Obtain AAG concurrence on 30% design scope and cost estimate.
Begin 60% design effort while continuing to evaluate gate utilization   Construction Costs
and construction phasing options, selection of GC/CM Contractor    Not Applicable
and needs analysis for incorporation of future NSAT baggage system
expansion and infrastructure enhancements.
Budget
The project forecast is within the approved budget.
Change Order
Current Quarter   Project Total
Number of COs       0          0
Amount of COs       $0         $0
Justification for COs: n/a



Port of Seattle 3Q 2014 Report  57

Risks
Existing mechanical and electrical capacity may not be adequate for NSAT expansion. Taxi-lane
reconfiguration implications may impact design and construction schedules of early release packages
and overall construction costs.
Budget Transfers
None











AIRPORT
58  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Snow Blower and Deicer Trucks
Project Status:
Schedule: Within or ahead
Project:   C800557      Purchase1 Deicer Truck and      Budget: On or under
Budget: $2,200,000      2 Snow Blower Trucks        Status Reset: Click here to
enter a date.
Phase: Implementation
(Commission Construction Auth.)
Start: 4/4/2014
Schedule Completion: Deicer - 12/31/2014
Snow Blowers  12/2015       Budget/Costs Incurred
2.5     2.20       2.20
Significant Developments
2
(1) Deicer Truck Project #105068 to be purchased in 2014, and
(2) the two Snow Blower Trucks both to be purchased in 2015.        1.5  Millions
1
Schedule                            Dollars in 0.5
0.00
Not Applicable                                       0
Authorized  Forecasted Costs Incurred
Budget
$400,000 - 2014
$1,800,000 - 2015                                 Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
None
Budget Transfers
None


AIRPORT
Port of Seattle 3Q 2014 Report  59

THIRD QUARTER REPORT, 2014
Main Terminal Mezzanine Tenant Relocations
Project Status:
Project:   C800560    Construct new tenant leased spaces in  Schedule: Within or ahead
Budget: $2,025,000    order to move existing tenants and    Budget: On or under
Phase: Construction   provide new leasable office space for  Status Reset: 11/19/2013
Start: 3/26/2013        airlines on the mezzanine of the main   (Commission Construction Auth.)
Schedule Completion:   terminal.
3/30/2015
Budget/Costs Incurred
Significant Developments
Notice to Proceed granted on October 13, 2014. Airport Jobs and      2.5
2.03      2.03
Credit Union spaces are under construction.                     2
Millions 1.5
Dollars in 
Schedule
1
On schedule
0.5                        0.35
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within approved budget and authorization.
Change Order
Construction Costs
Current Quarter   Project Total          Not Applicable
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None at this time.



AIRPORT
60  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Known Crewmember Employee Bypass
Project Status:
Construct new Known          Schedule: Delayed Schedule
Project:   C800576      Crewmember Bypass and        Budget: Forecast Overrun
Budget: $780,000.      Employee Bypass locations at the   Status Reset: 12/11/2012
Airport.
Phase: Construction                        (Commission Construction Auth.)
Start: 12/11/2012
Schedule Completion: 12/31/2014
Budget/Costs Incurred
Significant Developments
New portals arrived end of October and installed in November.         1
0.78      0.78
0.8
Schedule                            Millions 0.6           0.45
Schedule impact of new vendor procurement complete. New portals
0.4
installed. Additional testing required is pushing activation of portals to
Dollars in 
December.                                   0.2
0
Budget                               Authorized Forecasted Costs Incurred
Commission authorized a budget increase of $130,000 for the costs
of responding to the original vendor going out of business, such as
re-design and re-procurement.                          Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Testing continues. New technology activation has proven
challenging.
Budget Transfers
BT from C800404 $130,000

AIRPORT

Port of Seattle 3Q 2014 Report  61

THIRD QUARTER REPORT, 2014
Parking Garage Lights (CA)
Use current technology to replace all   Project Status:
Project:   C800581     normal lighting in the Airport Parking   Schedule: Within or ahead
Budget: $6,235,700     Garage on all 8 floors and in the    Budget: On or under
helices. This will reduce energy      Status Reset: Click here to
Phase: Design
Start: 1/31/2014        consumption over 60%.           enter a date.
(Commission Construction Auth.)
Schedule Completion: 12/31/2019
Significant Developments                    Budget/Costs Incurred
Design is underway and is at 60% for Phase 1.                  7         6.24
6
Schedule
Millions  5
The project is on schedule.                                4
3
Budget                            Dollars in  2  1.28
1
0.00
The project forecast is within the approved budget and authorization.
0
Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total
Number of COs    0          0                Construction Costs
Amount of COs    $0         $0                None at this time
Justification for COs: n/a
Risks
No risks at this time.
Budget Transfers
None



AIRPORT

62  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
International Arrivals Facility (IAF)
Project Status:
Project:   C800583    Planning, Design, Construction of new  Schedule: Within or ahead
Budget: $344,000,000   Federal Inspection Services (FIS)    Budget: On or under
Phase: Planning     facility, including connector between   Status Reset: Click here to
Start: 6/25/2013        South Satellite and FIS and sterile     enter a date.
Schedule Completion:   corridors and walkways within      (Commission Construction Auth.)
Concourse A.
6/30/2018
Significant Developments                    Budget/Costs Incurred
Planning and repogramming effort completed. Preparing project for
400
344.00
turnover to AVPMG to refine scope, schedule and budget. Advancing    350
RFQ for issue in Q3 2014.
Millions  300
250
Schedule                             200
Dollars in   150
The project is currently on schedule.                          100
50     24.50
4.19
Budget                              0
Authorized      Forecasted     Costs Incurred
The project forecast indicates a budget increase may be required.
Change Order                         Construction Costs
Current Quarter   Project Total          Not Applicable
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Additional technical analysis of the South Satellite to Concourse A
connector will delay bridge or tunnel decision and advertisement of
RFP. Program budget may increase due to new scope being added
to the IAF, such as airline relocations.
Budget Transfers
None this quarter.


AIRPORT

Port of Seattle 3Q 2014 Report  63

THIRD QUARTER REPORT, 2014
Wi-Fi Enhance for Ramp & Terminal
Project Status:
Project:   C800585      Upgrade Wi-Fi system in the public
Schedule: Within or ahead
Budget: $9,880,000     and ramp operational areas of the
Budget: On or under
Phase: Design        Airport.
Status Reset: 5/13/2014
Start: 11/4/2012                                  (Commission Construction Auth.)
Schedule Completion: 6/4/2018
Budget/Costs Incurred
Significant Developments                     12
9.88
Commission approval received to begin design. An advertisement      10
published for an Infrastructure designer. Negotiate scope and fee for    Millions 8
Wi-Fi audits. Submitted project to the airlines for Majority-In-Interest      6
approval.                                           4
Dollars in        1.95
2
0.05
Schedule                             0
Authorized  Forecasted Costs Incurred
On schedule and created a Baseline schedule.
Budget                            Construction Costs
On budget                                   N/A
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: Not applicable
Risks
None identified at this time.
Budget Transfers
BT from C800404 $3,827,000
BT from C800622 $2,044,000
BT from C800624 $712,000
BT from C800633 $397,000


AIRPORT
64  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Security Exit Lane Breach Control-Phase 2
Project:   C800605    This project will procure and install new  Project Status:
automated breach control equipment at   Schedule: Delayed
Budget: $2,838,546
four security exits in the airport terminal.  Budget: On or under
Phase: Construction                        Status Reset: 9/10/2013
Start: 10/1/2012                                  (Commission Construction Auth.)
Schedule Completion: 11/30/2014

Significant Developments                    Budget/Costs Incurred
The construction contract was terminated by the Port and the project
7    6.41
suspended due to an inability to reach a funding agreement with        6
TSA. Until funding is secured this will be the last report.               5
4
2.91      2.84
Schedule
Millions
3
The project has been suspended by the Port.                   Dollars in  2
1
0
Budget                               Authorized Forecasted Costs Incurred
Project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Current Quarter   Project Total
Number of COs    2          2                   2  1.76
Amount of COs    $(1,602,006)   $(1,602,006)
Millions  1.5
Justification for COs: n/a                                     1
Risks                                Dollars in  0.5
0.158994
0
The project could resume if a funding agreement can be reached        0
with TSA.                                            Initial  Change  Spent
Orders
Budget Transfers
None this quarter.


AIRPORT
Port of Seattle 3Q 2014 Report  65

THIRD QUARTER REPORT, 2014
North Satellite - STS Ceiling Leak Repair
Eliminate ceiling leaks at the North   Project Status:
Project:   C800609
Satellite (NSAT) that occur        Schedule: Delayed
Budget: $1,750,000      between the satellite transit station  Budget: On or under
Phase: Design         (STS) and the elevators.       Status Reset: Click here to
Start: 5/1/2013                                   enter a date.
Schedule Completion: 10/4/2015                  (Commission Construction Auth.)
Significant Developments
Budget/Costs Incurred
The project was advertised and received a single, irregular bid. The
project will be re-advertised next year.                           2   1.75     1.75
1.5
Schedule                            Millions
The project construction schedule has been delayed by one year.       1
Dollars in 0.5                        0.21
Budget
0
The project forecast is within the approved budget. Commission
Authorized  Forecasted Costs Incurred
Authorized funds for construction and authority to advertise on April
1, 2014.
Construction Costs
Change Order
Not Applicable
Current Quarter   Project Total
Number of COs    0          0                Photo
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Single high bid was previously received and that could occur again.
Need driest time of the year for construction.
Budget Transfers
None this quarter.


AIRPORT
66  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT,
Checked Baggage Recapitalization/Optimization
Project Status:
Project:   C800612    TSA approached the Airport in 2012    Schedule: Within or ahead
Budget: $317,000,000   with plan to replace all federally owned  Budget: On or under
Phase: Design      and operated baggage scanning     Status Reset: Click here to
Start: 2/26/2013       equipment, known as Explosive       enter a date.
Schedule Completion:  Detection System (EDS) equipment.   (Commission Construction Auth.)
The EDS equipment is approaching
12/31/2024
the end of its life.
Budget/Costs Incurred
Significant Developments
350           317.00
Design work continues to progress towards 70% design. Completed
300
an industry wide technology evaluation of baggage system
250
components. Testing and verifying the components for use within the    Millions 200
design and continue to refine the project phasing. Coordinate with all
150
other programs within the capital program.                     Dollars in 100
50    19.85
4.74
Schedule
0
The project is currently on schedule. Overall schedule will be refined        Authorized  Forecasted Costs Incurred
to reflect a ten-year program.
Budget                            Construction Costs
The project forecast is within the approved budget. Commission     Not Applicable
Authorization for construction funding and authority to advertise for
construction will be requested when the bid documents are
completed.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter
AIRPORT
Port of Seattle 3Q 2014 Report  67

THIRD QUARTER REPORT, 2014
Second Floor Mezzanine Infrastructure Upgrade
Project:   C800615    Upgrade and extend the infrastructure  Project Status:
(HVAC, Communications, Electrical,
Budget: $2,472,000                         Schedule: Delayed Schedule
Plumbing, WiFi) to 14,000sq ft of future  Budget: On or under
Phase: Construction
lease space on the 2nd floor, including  Status Reset: 6/12/2013
Start: 8/1/2013         7,000 sq ft for a new USO.          (Commission Construction Auth.)
Schedule Completion:
2/13/2015
Significant Developments                    Budget/Costs Incurred
A contract was executed with Regency NW Construction Inc. on
3
August 5, 2014. Project is currently under construction.                2.47    2.47
2.5
Schedule                            Millions 2
1.5
Current project is to complete construction in February 2015.          1                0.64
The delay is due to design challenges existing from the second floor    Dollars in 0.5
to meet egress code requirements and to determine the routing of
0
the infrastructure, primarily HVAC.                               Authorized  Forecasted Costs Incurred
Budget
The forecast is within the approved budget and authorization..       Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
The risks are to ensure that the USO infrastructure and utility line up
with the Infrastructure project tie-ins.
Budget Transfers
None.

AIRPORT
68  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
2014-2015 Roof Replacement
Project Status:
Remove and replace the current
Project:   C800637                             Schedule: Within or ahead
roofing system on the Alaska Hangar
Budget: $4,416,000                         Budget: On or under
One and associated maintenance    Status Reset: Click here to
Phase: Design       building, the Air Cargo 6 facility, and  enter a date.
Start: 4/1/2014         the former United Cargo Building.     (Commission Construction Auth.)
Schedule Completion:
10/31/2015
Budget/Costs Incurred
Significant Developments
5            4.42
Completed 60 percent design.
4
Schedule                             3 Millions
Project is currently on schedule.                              2
Dollars in   1     0.45
Budget                                        0.03
0
Project forecast is within the approved budget.                      Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                None at this time
Amount of COs    $0         $0
Justification for COs: N/A
Risks
No risks identified at this time.
Budget Transfers
None at this time.



AIRPORT

Port of Seattle 3Q 2014 Report  69

THIRD QUARTER REPORT, 2014
CCTV Camera-Data Improvements
Project Status:
Project:   C800642      Add cameras and improve the
Schedule: Within or ahead
Budget: $11,000,000     video management system at the
Budget: On or under
Phase: Design        Airport. Project funded by a TSA
Status Reset: 5/13/2014
grant.
Start: 11/4/2012                                  (Commission Construction Auth.)
Schedule Completion: 9/28/2017

Significant Developments                    Budget/Costs Incurred
Commission Authorization for Design received September 11, 2014.    12        11.00
Preliminarily decided to upgrade current Genetech video            10
management system. RFQ to procure Infrastructure Design Services   Millions 8
6
Dollars in 
was published October 31, 2014. Monthly meetings with TSA have
begun and are held regularly.                              4
2    1.14
0.05
Schedule                             0
Authorized  Forecasted Costs Incurred
The project is proceeding on schedule. A baseline schedule has
been established.
Construction Costs
Budget                            N/A
Commission has authorized Design budget.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
70  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Town & Country Stormwater Pipe
Project Status:
Project:   C800651      Stormwater Pipe             Schedule: Within or ahead
Budget: $350,000                          Budget: On or under
Phase: Construction                        Status Reset: 9/3/2014
Start: 1/1/2014                                   (Commission Construction Auth.)
Schedule Completion: 9/30/2014
Budget/Costs Incurred
Significant Developments
Pipe is now installed but several pipe joints need repair kits to enable    0.36   0.35     0.35
passage of pressure test.                                0.34
Schedule                            0.32 Millions
0.30081
On schedule                                    0.3
0.28   Dollars in 
Budget
0.26
Project is within budget and forecast.                             Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                Not Applicable
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Further pressure testing setbacks or delays in procuring or installing
repair kits may cause budget or schedule overruns
Budget Transfers
None



AIRPORT
Port of Seattle 3Q 2014 Report  71

THIRD QUARTER REPORT, 2014
Mech Energy Conservation (CA)
Stage 3 mechanical energy        Project Status:
Project:   C800658     conservation to improve the        Schedule: Within or ahead
Budget: $3,500,000     efficiency of portions of the       Budget: On or under
mechanical infrastructure system     Status Reset: Click here to
Phase: Audit/Notebook
enter a date.
Start: 8/25/2014        at the Airport.
(Commission Construction Auth.)
Schedule Completion: 6/30/2016
Significant Developments                    Budget/Costs Incurred
Preliminary phase of Audit in progress. Reviewing drawings, site
4            3.50
visits, coordination meetings and collecting data in the Siemens
Control Building Automation System (DDC). Installed and collecting     3
temperature and flow information from temporary data loggers       Millions
placed where needed on the systems under audit.                2
Dollars in   1
Schedule                               0.33
0.01
Investment Grade Audit Final Report Submittal target for 1/16/15.       0
Authorized  Forecasted Costs Incurred
Schedule for completing audit is aggressive when considering scope
of work due to diversity of nine separate energy conservation
measures.
Construction Costs
Budget                            Not Applicable
Future Commission request will be made after completion of Audit
for additional funds with updated construction schedule.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs   $0        $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter.

AIRPORT

72  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
North Utility Tunnel Steam Pipe
Project Status:
Project:   C800659      Replace 45 year old steam piping   Schedule: Within or ahead
Budget: $1,250,000      expansion joints in the North Utility  Budget: On or under
Phase: Construction     Tunnel.                Status Reset: Click here to
Start: 3/18/2014                                  enter a date.
Schedule Completion: 10/8/2014                  (Commission Construction Auth.)
Significant Developments
All expansion joints have been replaced. Only testing, insulation and  Budget/Costs Incurred
demobilization remain.
1.4     1.25       1.25
1.2
Schedule
1
Project is on schedule to be completed Q4 2014.                Millions 0.8
0.6
0.36
Budget                             Dollars in 0.4
0.2
Currently the project is on budget.
0
Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total
Number of COs    3          3                Construction Costs
Amount of COs    $10,464      $10,464
0.5
0.39
Justification for COs: Unforeseen conditions                      0.4
Millions                     0.32
0.3
Risks
0.2
None                                  Dollars in  0.1
0.01
Budget Transfers                           0
Initial   Change   Spent
None                                         Orders




AIRPORT
Port of Seattle 3Q 2014 Report  73

THIRD QUARTER REPORT, 2014
S4 & S6 IC Connection
Project Status:
Project:   C800662      Installation of a fixed bridge and
Schedule: Delayed Schedule
Budget: $4,800,000.00    corridor extension to connect gates
Budget: On or under
Phase: Design        S6 and S4 to the International
Status Reset: 5/13/2014
Corridor
Start: 11/4/2012                                  (Commission Construction Auth.)
Schedule Completion: 10/22/2015
Budget/Costs Incurred
Significant Developments                     6
4.80      4.80
Advertisement anticipated in December 11, 2014.                5
Millions  4
Schedule                             3
2
Design completion extension of 1.5 months has pushed project
Dollars in   1
completion into October.                                                 0.13
0
Authorized  Forecasted Costs Incurred
Budget
Project is on budget after some scope reductions for HVAC in
corridor.                                              Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None this quarter
Budget Transfers
None this quarter


AIRPORT

74  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Automated Passport Control
Install fourteen (14) Automated     Project Status:
Project:   C800667
Passport Control (APC) kiosks in    Schedule: Within or ahead
Budget: $1,282,000.     the existing FIS at the South     Budget: On or under
Phase: Construction     Satellite.               Status Reset: Click here to
Start: 10/31/2013                                 enter a date.
Schedule Completion: 12/31/2013                 (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
Anticipating adding additional kiosks within the existing budget.        2.5   2.21
2
Schedule
Millions 1.5               1.28
Anticipating adding scope which will extend the schedule.                            1.16
1
Budget                            Dollars in 0.5
Project forecast is currently under budget due to the acceleration.       0
Added kiosks would be covered by existing budget.                  Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                Not Applicable
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT

Port of Seattle 3Q 2014 Report  75

THIRD QUARTER REPORT, 2014
Highline School Noise Insulation
Project Status:
Project:   C200007      Highline School Insulation        Schedule: Delayed
Budget: $101,797,000    Agreement will provide funding for  Budget: On or under
Phase: Construction     sound mitigation for 15 schools that  Status Reset: Click here to
Start: 3/23/1999          are impacted by aircraft noise from   enter a date.
Schedule Completion:    Sea-Tac Airport.            (Commission Construction Auth.)
11/30/2021

Significant Developments                    Budget/Costs Incurred
Port funds authorized for availability when the FAA, the State of       120
102.14     101.80
Washington, and the Highline School District (HSD) provide
100
matching funds. In the November 2014 election, the HSD Bond did
not receive voter approval. The Port will work with HSD to develop     Millions 80               63.41
60
future schedules.
Dollars in  40
20
Schedule
0
The schedule for state funds is unknown. The district's schedule is        Authorized  Forecasted Costs Incurred
dependent on obtaining general election bonds at various intervals.
Construction may resume in 2015 if a future voter approved bond is
secured.                                       Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Project delayed due to funding issues with HSD. There is a risk if no
bonds are passed in the general election, and if FAA Airport
Improvement Program (AIP) Grant funding is not available.
Budget Transfers
None this quarter
AIRPORT
76  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Highline Community College Noise Insulation
Project Status:
Project:   C200042      Highline Community College      Schedule: Within or ahead
Budget: $7,970,266.     Insulation Agreement will provide   Budget: On or under
Phase: Construction     funding for up to 22 eligible      Status Reset: Click here to
Start: 1/11/2005          buildings that are impacted by      enter a date.
Schedule Completion:    aircraft noise from Sea-Tac Airport.  (Commission Construction Auth.)
12/31/2013
Significant Developments                    Budget/Costs Incurred
Fourteen of the original 22 eligible buildings have been sound         8.3
insulated by the college. The College sound insulation program has         8.19
8.2
been dependent on receiving funds from FAA grants. The FAA       Millions
notified the Port that the Highline Community College Campus is no     8.1
Dollars in 
longer located within the 65 DNL Noise Contour and therefore is not     8         7.97     7.96
eligible for any further grant funding. Without the FAA's approval and
7.9
funding the remainder of the college buildings cannot be sound
7.8
insulated.
Authorized   Forecasted  Costs Incurred
Schedule
The construction is complete on the last building (Building #4) and    Construction Costs
the Noise Office is working with FAA to Close Grant AIP 127. Once   Not Applicable
the FAA sends Final Grant Closure documents, the project will be
closed.
Budget
The project forecast is within the approved budget. No further
authorization is anticipated with this project.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
The FAA will not allocate future grant funds to this project.
Budget Transfers
None at this time
AIRPORT
Port of Seattle 3Q 2014 Report  77

THIRD QUARTER REPORT, 2014
Home Insulation Retrofit
Project Status:
Project:   C200048      This project includes storm window
Schedule: Within or ahead
Budget: $4,060,147.     retrofit of previously insulated
Budget: On or under
Phase: Construction     homes.
Status Reset: Click here to
Start: 1/11/2005                                  enter a date.
Schedule Completion: 12/31/2015                 (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
The Port has identified eligible homes and notified homeowners of      6   5.34
their eligibility. The Port is continuing with storm window retrofit.
5
4.06
Project budget was reduced by $1,300,000 due to being unable to
identify additional eligible homes.
4                     3.44
3
Millions
Schedule                            Dollars in  2
1
The Port is reviewing other potential homes for eligibility. The project
0
is on hold until new eligible homes are identified.
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
The ability to accomplish the retrofit is dependent on homeowner's
schedules, and structural integrity of the home.
Budget Transfers
None at this time


AIRPORT
78  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Single Family Home Sound Insulation
Project Status:
Project:   C200093      Sound insulate remaining homes    Schedule: Within or ahead
Budget: $13,747,395     that are within the 1998 65 decibel  Budget: On or under
Phase: Construction     day night level (DNL) noise      Status Reset: Click here to
Start: 3/27/2007          contour.                   enter a date.
Schedule Completion: 12/31/2015                 (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Fifty-six homes are complete; and 25 homes are in the process of
15    13.75     13.75
receiving sound insulation.
Schedule                            Millions 10
Project is on schedule. Anticipate completion by 4th quarter 2015.                       5.40
5
Dollars in 
Budget
0
The project forecast is within approved budget and authorization to        Authorized  Forecasted Costs Incurred
complete all homes currently in progress.
Change Order                         Construction Costs
Current Quarter   Project Total
3.8
4
Number of COs    0          0
Amount of COs    $0         $0                  3
Millions                            1.78
Justification for COs: n/a                                    2
1
Risks                                Dollars in 
0
The ability to accomplish the insulation is dependent on the           0
Initial    Change Order    Spent
homeowner's schedules, willingness to sign an aviation easement,
obtain a subordination agreement from their lender, and structural
integrity of the home. If more eligible homes than anticipated are
identified in the future, then additional funding may be needed.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 3Q 2014 Report  79

THIRD QUARTER REPORT, 2014
RMU/Kiosk Concession Program
Design and fabrication of Retail        Project Status:
Project:   C800146
Merchandising Units (RMUs); power,    Schedule: Delayed
Budget: $879,146.
communications, and data to RMU     Budget: On or under
Phase: Construction  locations; and install floor-mounted    Status Reset: Click here to
Start: 11/20/2007      receptacles for the utilities to allow easy  enter a date.
Schedule Completion:  connection points as well as flexibility for  (Commission Construction Auth.)
2/5/2014           future utilization.

Budget/Costs Incurred
Significant Developments
We are working with the vendor to complete punchlist items.         1.4
1.21
1.2
Schedule                             1       0.88
0.75
0.8
Punchlist item were installed November 11, 2014; however the
in Millions
0.6
display arms sent by the manufacturer are the wrong color.
Dollars  0.4
0.2
Budget
0
The project forecast is currently within the approved budget and          Authorized  Forecasted Costs Incurred
authorization.
Change Order
Construction Costs
Current Quarter   Project Total          Not Applicable
Number of COs    0
Amount of COs    $0         $Pending
Justification for COs: Additional expenses are labor costs and
communication box installation.
Risks
None at this time.
Budget Transfers
None this quarter.

AIRPORT

80  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Tenant Reimbursement
Build-out of spaces for new and       Project Status:
Project:   C800154    existing tenants. If more than a "basic   Schedule: Within or ahead
Budget: $4,709,577    finish" condition space is built for the   Budget: On or under
Phase: Construction   tenant, the tenant is required to      Status Reset: Click here to
Start: 8/14/2007       reimburse the Port for the cost of the    enter a date.
Schedule Completion:  work beyond this "basic finish".      (Commission Construction Auth.)
TBD          Reimbursements allowed under the
guidelines in the "Tenant Reimb
Policy".                        Budget/Costs Incurred
5    4.69      4.71
Significant Developments                      4
Airport Management Services' office build-out on the ramp level of     Millions 3
Dollars in 
baggage claim in review. Anticipate payment in Q4 2014.
2                     1.30
Schedule                             1
Schedules vary to meet the tenant's needs.                     0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 3Q 2014 Report  81

THIRD QUARTER REPORT, 2014
T-46 Lease Improvements - Stormwater
Improvements
Project Status:
Project: U00050 (C102554)  Construct stormwater treatment    Schedule: Within or ahead
Budget: $8,000,000      system to comply with Ecology    Budget: On or under
Phase: Construction     order.                Status Reset: Click here to
enter a date.
Start: 4/12/2013
(Commission Construction Auth.)
Schedule Completion: 2020
Significant Developments                   Budget/Costs Incurred
Basin 5 and 6 are now completed. Completed sheetpile shoring and    10
installation of dewatering system for Basin 8. Installed two                8      8
8
additional dewatering wells due to lack of progress in reaching the
required design depth.                                 Millions 6
Dollars in 
4
Schedule                                        2.155
2
Installation of the three treatment vaults projected to be complete by
0
December 2014. The fourth treatment will be installed once
Authorized   Forecasted  Costs Incurred
Washington State Department of Transportation (WSDOT) vacates
the lease area.
Budget                           Construction Costs
$8,000,000 for Stormwater Treatment System. Currently within        2.5
budget.                                             1.949
2
Change Order                          Millions 1.5
0.943
1
Current Quarter   Project Total
Number of COs    3          3                 Dollars in  0.5
0.020
Amount of COs    $20,390      $20,390               0
Initial   Change   Spent
Orders
Justification for COs: CM coded as "Error/Omission - Designer"
Risks
Construction impact on terminal operation due to unforeseen
condition.
Budget Transfers
Not Applicable

SEAPORT
82  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Street Vacations T5,18,105
Project Status:
Street vacation related real estate      Schedule: Delayed Schedule
Project: C102858,
negotiations and agreements --T5,     Budget: On or under
C102875, E104366
T18, and T105 (complete).          Status Reset: Click here to
Budget: $1,500,000                         enter a date.
Phase: Permitting                         (Commission Construction Auth.)
Start: 6/1/2010
Schedule Completion: 2014
Budget/Costs Incurred
1.55
Significant Developments                         1.5    1.5
1.5
Draft Easement and Utility transfer documents have been prepared    Millions 1.45
by the City and are under Port Legal Department review for Terminal
1.378
18 (T-18). Discussion and Title work has begun for Terminal 5.        1.4
Dollars in 1.35
Schedule
1.3
Current schedule has T-18 completed by the end of 2014 (City           Authorized  Forecasted Costs Incurred
Council action by end of March 2015) and T-5 by the end of 2015 or
early 2016.
Construction Costs
Budget                            Not Applicable
The budget has been revised for 2014 and beyond.             Photo
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Not applicable
Budget Transfers
Budget Transfers Proposed. 91,000 to C102875; $4,867 to
C102874; and $95,867 to C102858.

SEAPORT
Port of Seattle 3Q 2014 Report  83

THIRD QUARTER REPORT, 2014
Pier 34 Mooring Dolphins
Project Status:
Project:   C800090      Replacement of four existing failed   Schedule: Within or ahead
Budget: $1,800,000      timber mooring dolphins with four   Budget: On or under
Phase: Design        new steel dolphin structures     Status Reset: Click here to
Start: 4/1/2014          located at Pier 34 at the head of    enter a date.
Schedule Completion:    the East waterway by March 2015   (Commission Construction Auth.)
for $1.8M
3/30/2015
Budget/Costs Incurred
Significant Developments                      2   1.8
1.611
Design completed, project is out for bid.
1.5
Millions
Schedule                             1
Expect contract to be awarded in Q4 2014.                    Dollars in  0.5
0.139
Complete construction by March 2015.
0
Authorized   Forecasted  Costs Incurred
Budget
Project is within approved budget.
Construction Costs
Change Order                         None at this time
None this quarter
Risks
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Budget Transfers
None


SEAPORT
84  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
T-5 Berth Modernization
Improvements to support larger     Project Status:
Project: C800132      vessels at T5, including crane rail   Schedule:  within or ahead
Budget: $5,000,000    strengthening, berth deepening,    Budget:   on or under
Phase: Design      and electrical upgrades.        Status Reset: 6/3/2014
Start: 6/3/2014                                 (Commission Construction Auth.)
Schedule Completion: 6/30/2018
Significant Developments                   Budget/Costs Incurred
Consultant selected and agreement executed to provide design
support services such as geotechnical investigation and             6
4.900      5.000
environmental analysis. 15 Percent design completed and all         5
reviewer comments addressed.                        Millions  4
3
Schedule                            Dollars in 
2
Significant progress toward 30% level design completion,                            0.751
1
completion expected in January. Environmental analysis and
0
geotechnical investigations are underway through                   Authorized   Forecasted  Costs Incurred
early 2015.
Budget                           Construction Costs
Budget is currently $5,000,000, which will cover 30% level design    None at this time
and initial environmental review and permit process.
Photo
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
Scope of work is subject to change depending on tenant selection
and lease negotiation. Interim uses will significantly impact
phasing/scheduling and total project costs. Environmental analysis
and review documentation is critical path.
Budget Transfers
None

SEAPORT
Port of Seattle 3Q 2014 Report  85

THIRD QUARTER REPORT, 2014
T91 Lighting Upgrade
Lighting upgrade at Terminal 91      Project Status:
Project: C800160
Schedule: Delayed Schedule
Budget: $1,035,000
Budget: On or under
Phase: Construction                       Status Reset: 3/4/2014
Start: 6/23/2014                                 (Commission Construction Auth.)
Schedule Completion: 10/17/2014
Significant Developments                   Budget/Costs Incurred
The fixtures are 95% and controls are 80% installed. We anticipate
1.05     1.04       1.04
the controls to be networked very soon and commissioning will
begin in November.                                  1
Millions0.95
Schedule
0.9                         0.89
Installation and oporational adjustments are 95% complete.         Dollars in 0.85
Commissioning is expected to begin in November.
0.8
Authorized   Forecasted  Costs Incurred
Budget
The project is anticipated to complete on budget.
Construction Costs
Change Order
Not Applicable
Current Quarter   Project Total
Number of COs    0          2
Amount of COs    $0         ($23,000)
Justification for COs: none this quarter
Risks
Because of a later start date, the work was coordinated around
cruise schedules and accomodations for the northern fleet are in
progress.
Budget Transfers
None


SEAPORT
86  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
T-91, Bldg C175 Roof Replacement
Project Status:
Schedule: Within or ahead
Project:   C800430      Replace roof on the C175 building   Budget: On or under
Budget: $2,450,000      at Terminal 91.            Status Reset: 1/14/2014
Phase: Construction                        (Commission Construction Auth.)
Start: 7/26/2011
Schedule Completion: 11/14/2014                 Budget/Costs Incurred
3
2.45
Significant Developments                     2.5       2.2
Construction is ongoing and the project is 95% complete. A small      2
amount of roofing remains; and the majority of the outstanding items    1.5
Millions
1.047
are the flashing, gutters, and punchlist items.                     1
Dollars in 
0.5
Schedule                             0
Authorized  Forecasted Costs Incurred
The late season rains have slowed the progress and will postpone
project completion. Project completion is estimated to occur in Early
December.
Construction Costs
Budget
2
1.65
The project is anticipated to be completed under budget
1.5
Change Order                          Millions         1.09
1
Current Quarter   Project Total
0.5
Number of COs    0          0                 Dollars in 
0
Amount of COs    $0         $0                   0
Initial   Change   Spent
Orders
Justification for COs: n/a
Risks                               Photo
None at this time
Budget Transfers
None


SEAPORT
Port of Seattle 3Q 2014 Report  87

THIRD QUARTER REPORT, 2014
T-91 Station Upgrades
Project Status:
Schedule: Within or ahead
Project:   C800439      Upgrade/replace existing        Budget: On or under
Budget: $424,000       substations/equipment at       Status Reset: 3/11/2014
Phase: Design        Substation Nos. 1, 14 and 15.     (Commission Construction Auth.)
Start: 11/4/2013
Schedule Completion: 12/31/2015
Budget/Costs Incurred
Significant Developments
0.5
Completed 30% design and 60% design development is underway.        0.424    0.424
0.4
Schedule                            Millions 0.3
On Schedule
0.2
Dollars in                            0.083
Budget                             0.1
On Budget                                    0
Authorized   Forecasted  Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                Not Applicable
Amount of COs    0          0
Justification for COs: n/a
Risks
None for the early design stage.
Budget Transfers
None



SEAPORT

88  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Argo Yard Truck Roadway
Project Status:
Project:   C800546,      New Port of Seattle owned truck    Schedule: Delayed
E104751, E104754       roadway between East Marginal   Budget: On or under
Budget: $7,750,000      Way and Colorado Avenue South   Status Reset: 4/22/2014
(Commission Construction Auth.)
Phase: Construction     right-of-way.
Start: 3/11/2012
Schedule Completion: 3/31/2015
Budget/Costs Incurred
Significant Developments
10
Construction is underway.
7.75       7.75
8
Schedule                             6 Millions
Construction is expected to be completed by end of Q1 2015.
4
Dollars in 
Budget                             2          1.246
Project is currently within the budget authorized by Commission on      0
Authorized  Forecasted Costs Incurred
April 22, 2014. This status may change depending upon the
outcome of several contractor claims currently being negotiated.
Change Order                         Construction Costs
Current Quarter   Project Total            1.2  1.05
Number of COs    0          0                   1
Amount of COs    $0         $0                 Millions 0.8
0.6
Justification for COs: n/a                                    0.4
Dollars in   0.2
Risks                                 0
Initial   Change   Spent
No significant known risks at this time                                  Orders
Budget Transfers
None



SEAPORT
Port of Seattle 3Q 2014 Report  89

THIRD QUARTER REPORT, 2014
T-46 Dock Rehabilitation
Project Status:
Project:   C800603      Terminal 46 Dock Rehabilitation    Schedule: Delayed Schedule
Budget: $1,854,000      Project                Budget: On or under
Phase: Design                            Status Reset: Click here to
Start: 11/6/2012                                  enter a date.
Schedule Completion: Q4 2018                   (Commission Construction Auth.)
Significant Developments
The project is at 90% design and is on hold. This project has been   Budget/Costs Incurred
posponed and will resume design upon completion of TIGER grant
2    1.854
contract execution. At this time this is the last report until the project
is resumed.                                       1.5
Millions                  1.023
Schedule                             1
The project has been postponed until completion of TIGER grant      Dollars in                  0.44
0.5
execution. Construction is anticipated to start in 2016
0
Authorized   Forecasted  Costs Incurred
Budget
The project is on budget
Construction Costs
Change Order
None at this time
Current Quarter   Project Total
Number of COs    0          0                Photo
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None at this time
Budget Transfers
None


SEAPORT
90  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Terminal 115 Stormwater Separation
Project Status:
Project:   C800689      Separate stormwater originating    Schedule: Within or ahead
Budget: $548,000       from the Port leased area and the   Budget: On or under
Phase: Construction     Common Use Area on T-115 from   Status Reset: 5/6/2014
Start: 1/27/2014          the area exclusively used by       (Commission Construction Auth.)
Schedule Completion:    Northland Services.
12/31/2014
Significant Developments                    Budget/Costs Incurred
Design is complete and construction is underway by PCS.          0.6   0.548    0.548
Unanticipated King County Metro 96" sewer line discovered in vault     0.5
alignment. Design revised to accommodate and revised vaults       Millions 0.4
ordered.                                          0.3               0.235
0.2
One hundred percent of stormwater flow diverted to new outfall using   Dollars in  0.1
temporary pumps as of September 30, 2014.
0
Authorized   Forecasted  Costs Incurred
Schedule
Complete construction by December 31, 2014.
Construction Costs
Budget                            Port Self Perform
Construction
Project is within approved budget.
Change Order
None this quarter
Risks
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Budget Transfers
None

SEAPORT
Port of Seattle 3Q 2014 Report  91

THIRD QUARTER REPORT, 2014
East Marginal Way Grade Separation
FAST Corridor funded project;      Project Status:
Project:   E102007     FHWA, State, City with Port       Schedule: Within or ahead
Budget: $56,256,171    commitment of $22,480,807. Scope  Budget: On or under
Phase: Close Out      is to construct grade separation in   Status Reset: 4/22/2014
Start: 5/1/2006          vicinity of T5 and T18 to minimize    (Commission Construction Auth.)
Schedule Completion:    truck traffic/rail conflicts.
Q4 2015
Budget/Costs Incurred
Significant Developments
56.4    56.25      56.25
Coordination underway with consultant surveyor, POS Real Estate     56.2
and SDOT for properties and easements conveyance to City.         56
Millions55.8
55.6
Schedule
55.4                        55.3
Anticipate final acceptance by Seattle Department of Transportation    Dollars in 55.2
(SDOT) 2nd Quarter 2015.                             55
54.8
Authorized   Forecasted  Costs Incurred
Budget
Project is on track within 4/22/14 Commission authorization.
Construction Costs
Change Order
25   22          22
Current Quarter   Project Total
Number of COs    0          97                  20
Amount of COs    $0         $1,922,967            Millions 15
10
Justification for COs: N/A this quarter
Dollars in    5          1.992
Risks                                 0
Initial   Change   Spent
None at this time.                                                Orders
Budget Transfers
Photo
None


SEAPORT
92  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Viaduct Construction Coordination
Participate in the design &          Project Status:
Project:   E104324,     construction of the bored tunnel, N. &  Schedule: Within or ahead
E104535-38         S. portals, Holgate to King St, Central  Budget: On or under
Budget: $2,900,000     Waterfront surface streets, & related  Status Reset: Click here to
Phase: Implementation  projects to ensure adequate      enter a date.
Start: 1/1/2009         connection to port facilities.         (Commission Construction Auth.)
Schedule Completion: 12/31/2018
Budget/Costs Incurred
Significant Developments
3.5
Contractor is implementing repair plans for the SR 99 tunnel boring          2.9
3
machine. Season 2 of Seawall construction began in October.
Mercer corridor construction continued.                       Millions 2.5
2             1.75
1.5                         1.14
Schedule
Dollars in   1
Tunnel boring machine expected to resume operation in late March     0.5
2015. Mercer West construction to continue through mid-2015.       0
Seawall Phase I construction to be completed in mid-2016. Central        Authorized  Forecasted Costs Incurred
Waterfront completion depends on Viaduct demolition in 2017.
Budget                            Construction Costs
Not Applicable
Port staff costs were within anticipated 2014 spending.
Change Order                         Photo
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Project delays due to repairs to the tunneling machine.
Budget Transfers
None

SEAPORT

Port of Seattle 3Q 2014 Report  93

THIRD QUARTER REPORT, 2014
T-5 and T-91 Maintenance Dredging
Project Status:
Project:   E104840 &     Maintenance Dredge at T-5 all     Schedule: Delayed Schedule
U00067            three berths and at T-91 East     Budget: On or under
Budget: $4,800,000      cruise berth.             Status Reset: Click here to
Phase: Design                            enter a date.
Start: 8/14/2012                                  (Commission Construction Auth.)
Schedule Completion: 2/28/2016
Budget/Costs Incurred
Significant Developments
6
T-5 Maintenance Dredging was completed earlier in 2014.               4.8     4.8
5
T-91 East Cruise Berth: The Port is in discussion with the permitting
Millions  4
agencies regarding alternatives to traditional dredging. The preferred
3
alternative is under-water regrading to minimize environmental                         2.05
2
impact and reduce costs. Under-water regrading is a new          Dollars in  1
construction method in the Puget Sound area; therefore, permitting
0
agencies requested additional studies delaying the project further.
Authorized   Forecasted  Costs Incurred
Constuction in the 2014-16 in-water construction window is unlikely.
Schedule                           Construction Costs
T-91 East Cruise Berth is delayed due to permitting complications.    None at this time
Budget                            Photo
Project is on budget.
Change Order
Current Quarter   Project Total
Number of COs    0          2
Amount of COs    $0         $20,390.33
Justification for COs: None this quarter
Risks
Environmental permitting may cause further delays, scope change,
and cost impact to the T-91 East Cruise Berth Dredging project.
Budget Transfers
None

SEAPORT
94  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Clean Truck Program Truck Scrapping and
Replacement Project
Project Status:
Scrap or retrofit at least 220 trucks   Schedule: Within or ahead
Project: U00079; U00134
with pre-2007 engines currently     Budget: On or under
Budget: $6,327,000
operating at the Port of Seattle.      Status Reset: Click here to
Phase: Implementation                       enter a date.
Start: 12/10/2013                                 (Commission Construction Auth.)
Schedule Completion: 11/30/2015
Budget/Costs Incurred
Significant Developments
The Clean Truck program provides incentive vouchers to truckers
7    6.327     6.327
who operate at the Port of Seattle and who commit to scrapping       6
trucks with--depending on the grant source--either 2004 or 2006 or      5
older engines in order to purchase trucks with either 2007 or 2010 or   Millions 4
newer engines. Currently, 111 voucher applications have been pre-     3
approved, and 45 trucks scrapped and replaced. The program will     Dollars in  2              1.244
continue through December                            1
0
Authorized  Forecasted    Costs
Schedule                                       Incurred
On schedule
Construction Costs
Budget                            Not Applicable
On budget
Photo
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
Due to multiple funding sources, the project needs to be compliant
with funding agencies' requirements. A consultant has been retained
to provide grant administration services.
Budget Transfers
None

SEAPORT
Port of Seattle 3Q 2014 Report  95

THIRD QUARTER REPORT, 2014
IHI Crane Removal
Project Status:
Project: U00099      Remove three IHI Cranes from
Budget: $1,500,000    Terminal 18               Schedule: Within or ahead
Budget: On or under
Phase: Construction                       Status Reset: 9/11/2012
Start: 9/11/2012                                 (Commission Construction Auth.)
Schedule Completion: 1/23/2015
Significant Developments                   Budget/Costs Incurred
The project wasbid in August and the contract has been awarded
1.6       1.5
and executed. The contractor is developing and submitting the       1.4
required submittal documents. The project team is working on plans   Millions 1.2
1
to maintain labor harmony between the unions on the terminal.
0.8
Dollars in    0.6
Schedule
0.4
0.2                                0.085
All the cranes will be removed from the terminal by January 23,
0
2015. The contract completion date is a function of the award date
Authorized      Forecasted     Costs Incurred
and is currently estimated to be March 5, 2015
Budget
Construction Costs
The project is within budget                              Not Applicable
Change Order                        Photo
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
Anticipate additional project costs and added duration associated
with resolving labor harmony
Budget Transfers
none

SEAPORT
96  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
FT C15 HVAC Improvements
Project Status:
Project:   C800137     Provide the preliminary planning,
Schedule: Delayed Schedule
Budget: $4,887,000     design, and construction to replace
Budget: On or under
Phase: Construction    the existing HVAC systems within
Status Reset: 10/8/2013
Start: 5/1/2010         Building C-15 that are at the end of
(Commission Construction Auth.)
their service life.
Schedule Completion:
6/30/2014
Budget/Costs Incurred
Significant Developments                      6
4.887      4.887
5
All major HVAC equipment has been installed. Testing and
3.62
balancing work is underway. Some training and commissining work    Millions 4
has been completed.                                 3
2
Schedule                            Dollars in 
1
Contractor is behind schedule by approximately four months. Notice     0
of forbearance has been issued.                              Authorized  Forecasted Costs Incurred
Budget
Project is currently on track to be within the October 8, 2013        Construction Costs
Commission funding authorization.
3.5
2.97
3
Change Order                                   2.4
2.5
Current Quarter   Project Total            Millions  2
Number of COs    7          8                   1.5
Dollars in    1
Amount of COs    $111,219     $110,001
0.5          0.11
0
Justification for COs: Mostly varying site conditions and some design         Initial  Change  Spent
error and omission.                                             Orders
Risks
Some significant cost items have been raised by the contractor but
Port disagrees with their merits. These likely would result in claims
and dispute resolution/mediation may be necessary.
Budget Transfers
None

REAL ESTATE
Port of Seattle 3Q 2014 Report  97

THIRD QUARTER REPORT, 2014
P-69 Built-up Roof Replacement
Project Status:
Project:   C800314      Replace 32,000SF of the 65,000SF  Schedule: Within or ahead
Budget: $3,418,000      Built-Up Roof at the P-69       Budget: On or under
Phase: Construction     Headquarters Office Building     Status Reset: 2/25/2014.
Start: 2/26/2012                                  (Commission Construction Auth.)
Schedule Completion: 11/10/2014
Significant Developments                    Budget/Costs Incurred
Construction is in progress. Final installation of metal coping is in
4
3.418      3.418
progress. Sawtooth valleys are close to being complete with the      3.5
installation of the liquid applied membrane.                      3
Millions 2.5
Schedule                             2
1.5                         1.18
Completion date scheduled for Q4 2014.                     Dollars in  1
0.5
Budget                             0
Authorized   Forecasted  Costs Incurred
The project is currently below budget.
Change Order
Construction Costs
None
3.5    3.13
3
Risks
2.5
Current Quarter   Project Total           Millions  2           1.585
Number of COs    0          2                  1.5
1
Amount of COs    $0         -$14,240
Dollars in   0.5
0
Justification for COs: None this quarter                         0.5  Initial  Change0.014  Spent
Orders
Budget Transfers
None



REAL ESTATE
98  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
FT C-2 Nordby HVAC and Roof Replacement
Project Status:
Project:   C800344      Replace 23,000SF of existing      Schedule: Within or ahead
Budget: $2,338,600      Roofing and roof top HVAC units   Budget: On or under
Phase: Construction                        Status Reset: 1/7/2014
Start: 2/26/2012                                  (Commission Construction Auth.)
Schedule Completion: 11/21/2014
Significant Developments                    Budget/Costs Incurred
The project is currently under construction; finalizing the HVAC units
2.5     2.338      2.338
and Roof replacement installations. Currently the final punch list is
2
being prepared along with preparation to Test and Balance the
HVAC system including Commissioning.                    Millions 1.5
1
Schedule                            Dollars in             0.454
0.5
The project is scheduled for completion in Q4 2014
0
Authorized   Forecasted  Costs Incurred
Budget
The project is currently below budget.
Construction Costs
Change Order
Current Quarter   Project Total             2.5  2.170
Number of COs    0          0                   2
Amount of COs    $0         $0                 Millions 1.5
Justification for COs: n/a                                      1
Dollars in   0.5                0.257
0.000
Risks
0
An area over the warehouse has approximately 3200 SQ/FT of wet         Initial Change Spent
Orders
installation that must be removed and replaced in order to keep and
obtain the Soprema 25 year warranty. The contractor will continue
the progress as the weather permits.
Budget Transfers
None this quarter


REAL ESTATE
Port of Seattle 3Q 2014 Report  99

THIRD QUARTER REPORT, 2014
FT Net Shed #9 Roof Overlay
Project Status:
Project:   C800527      Overlay 12,000SF of existing      Schedule: Within or ahead
Budget: $401,400       corrugated Roof at the FT Net     Budget: On or under
Phase: Construction     Shed Building            Status Reset: 1/7/2014
Start: 2/26/2012                                  (Commission Construction Auth.)
Schedule Completion: 11/21/2014
Budget/Costs Incurred
Significant Developments
0.5
The project is currently in construction. Previous concerns with             0.401    0.401
Seattle City Light (SCL) and Labor and Industries (L&I) involving the    0.4
26Kv high power lines terminating near the Net Shed building have    Millions 0.3
been resolved. Construction will begin shortly with weather
0.2                         0.169
permitting.                                            Dollars in  0.1
Schedule                             0
With the SCL and L&I delay, the project is still scheduled for             Authorized  Forecasted Costs Incurred
completion in Q4 2014
Budget                            Construction Costs
The project is currently at budget.                              0.3  0.268
0.25
Change Order
Millions  0.2
0.146
Current Quarter   Project Total            0.15
Number of COs    1          1
0.1
Amount of COs    $0         $0                 Dollars in 
0.05
0
0
Justification for COs: Nesting Seagulls, Seattle City Light Powerline
Initial   Change   Spent
and Time extention due to contract execution date.                        Orders
Risks
None
Budget Transfers
None this quarter

REAL ESTATE
100  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
P69 Carpet Replacement               Project Status:
Schedule: Within or ahead
Project: C800691      Replace carpet flooring at         Budget: On or under
Corporate Headquarters Building     Status Reset: 2/4/2014
Budget: $1,200,000
on the second and third floors.       (Commission Construction Auth.)
Phase: Construction
Start: 7/7/2014
Schedule Completion: 9/30/2014
Budget/Costs Incurred
Significant Developments
1.4
The project is progressing as planned and the contractor is               1.2     1.2
1.2
completing work per the approved schedule.
Millions  1
0.8
Schedule
0.6                         0.433
The contractor began work on October 22 and is working to remove   Dollars in  0.4
and install carpet in the designated areas. The contractor is currently    0.2
maintaining work flow as scheduled.                         0
Authorized   Forecasted  Costs Incurred
Budget
The project is anticipated to complete within the allotted budget.
Construction Costs
Change Order                        Not Applicable
Current Quarter   Project Total
Number of COs    2          2
Amount of COs    $3,300       $3,300
Justification for COs: CO-01 was issued for contract extension; no
cost. CO-02 was issued for design correction to identify custom
base material; total cost of $3,300.
Risks
None at this time
Budget Transfers
None


REAL ESTATE
Port of Seattle 3Q 2014 Report  101

THIRD QUARTER REPORT, 2014
P69 Beam Rehabilitation Project
Project Status:
Project: C800698         Rehabilitate five rows of       Schedule: Within or ahead
Budget: $2,300,00-       concrete beams supporting    Budget: On or under
$3,300,000             top of clerestory windows at    Status Reset: Click here to
Phase: Design         P69.               enter a date.
(Commission Construction Auth.)
Start: 7/1/2014
Schedule Completion: 10/30/2015
Significant Developments                   Budget/Costs Incurred
Commission authorization to proceed with design and preparation of
0.35      0.33          0.33
bid documents received on July 1, 2014.
0.3
Schedule                            Millions 0.25
Dollars in 
0.2
Sixty percent Design Documents submitted for review.
0.15
0.1
Budget
0.05                              0.026235
Design phase budget authorization is $330,000. Total project costs      0
Authorized      Forecasted     Costs Incurred
are expected to be between $2,300,000 and $3,300,000.
Change Order
Construction Costs
Current Quarter   Project Total
Not Applicable
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
Scope of work and costs may escalate as design work and
investigations proceed.
Budget Transfers
Project preliminary design work began under Expense project
#105048  P69 Roof Beam Repair. Cost transferred to this project.
Approx. $31,000 (SP 105146)


SEAPORT
102  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
FT Net Shed Code Compliance
Project Status:
Project:   E104838      FT Net Sheds 3-11: Improvements   Schedule: Within or ahead
Budget: $2,950,000      required per City of Seattle building  Budget: On or under
Phase: Construction     & fire codes             Status Reset: 6/25/2013
Start: 5/1/2012                                   (Commission Construction Auth.)
Schedule Completion: 6/30/2015
Significant Developments                    Budget/Costs Incurred
Port Construction Services completed code compliance
3.5
improvements to Netsheds 11 (Netsheds 9 and 10 completed ealier).        2.95    2.95
3
Work within Netshed 5 is more than 50% complete.
Millions 2.5
2
Schedule                             1.5           1.084
Overall construction completion is scheduled by the end of 2nd        Dollars in  1
quarter 2015.                                       0.5
0
Authorized   Forecasted  Costs Incurred
Budget
Project budget is on track.
Construction Costs
Change Order
Port Self Perform
Current Quarter   Project Total          Construction
Number of COs    0          0
Amount of COs    $0         $0                Photo
Justification for COs: n/a
Risks
It is difficult to forecast the amount of stored materials that needs to
be moved out and moved back into the netlockers since tenant
storage habits vary significantly. In addition, the amount of work
required in each unit is difficult to assess until some stored materials
are cleared and locker conditions are more visible. These would
impact the overall project schedule and budget.
Budget Transfers
None

REAL ESTATE
Port of Seattle 3Q 2014 Report  103

THIRD QUARTER REPORT, 2014
ID Badge System Replacement
Project Status:
Project: C800162        Procurement and replacement of   Schedule: Delayed Schedule
Budget: $2,500,000      the Portwide ID Badge system     Budget: On or under
Phase:Implementation    including software, hardware, and   Status Reset: Click here to
Start: 5/1/2012           equipment.                 enter a date.
Schedule Completion: 7/30/2015                   (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
The first phase of the new Badge System was deployed on
November 5th. A 2nd deployment to add mobile functionality and      3
2.50      2.50
authorized signer efficiencies is in the planning stage.
2.5
2                    1.60
Schedule
Millions 1.5
Prior Report: Resource availability and system complexity have
Dollars in  1
delayed project completion.
0.5
0
Budget
Authorized  Forecasted    Costs
On Budget                                                Incurred
Change Order                         Construction Costs
Current Quarter   Project Total          Not Applicable
Number of COs    0          1
Amount of COs    $0         $108,497
Justification for COs: None this quarter.
Risks
Resource availability may continue to delay the second phase mobile
deliverables.
Budget Transfers
None


CORPORATE
104  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Enterprise Project Cost Management
Project Status:
Project: C800321        Replace the current construction    Schedule: Delayed Schedule
Budget: $1,525,000      costing systems with a common    Budget: On or under
Phase:Implementation    enterprise project cost         Status Reset: Click here to
Start: 4/21/2008          management system.           enter a date.
Schedule Completion: 12/30/2014                  (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
The first phase deployment has been completed and the software is
1.54    1.525    1.525
in-use by the Project Management Groups. Next phase deliverables
1.52
such as trend logs and cash flows are in test and scheduled for
delivery in 4th Quarter 2014.                               1.5 Millions               1.48
1.48
Schedule                            1.46 Dollars in 
Prior Report: Availability of resources is impacting the completion of    1.44
Authorized Forecasted   Costs
the remaining components. These include features such as cash
Incurred
flows and trend logs as well as additional interfaces that require
resources currently focused on the Peoplesoft Financials Upgrade
project. We are in the process of procuring additional configuration    Construction Costs
assistance and expect to deliver in phases over the next several     Not Applicable
months.
Budget
None
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Availability of Port resources may delay next phase deliverables.
Budget Transfers
None

CORPORATE
Port of Seattle 3Q 2014 Report  105

THIRD QUARTER REPORT, 2014
Network Switch Replacement
Project Status:
Project: C800323        Upgrade the Network switch      Schedule: Within or ahead
Budget: $1,500,000      infrastructure hardware and      Budget: On or under
Phase: Implementation    software                Status Reset: Click here to
Start: 12/15/2013                                enter a date.
Schedule Completion: 3/31/2015                   (Commission Construction Auth.)

Significant Developments
Budget/Costs Incurred
Implementation is in progress.
2
Schedule
1.50       1.50
1.5
On schedule.                                    Millions
1
Budget                                        0.68
On budget.                                     Dollars in 0.5
0
Change Order                            Authorized Forecasted Costs Incurred
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0                Construction Costs
Not Applicable
Justification for COs: n/a
Risks
Port resource availability may impact schedule.
Budget Transfers
None



CORPORATE
106  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Terminal 91 Visitor Management
Project Status:
Project: C800436        Upgrade of the Radio System Core  Schedule: Within or ahead
Budget: $520,000       Hardware and Software and      Budget: On or under
Phase: Planning        Dispatch Consoles           Status Reset: Click here to
Start: 7/1/2013                                   enter a date.
Schedule Completion: 5/1/2016                    (Commission Construction Auth.)
Significant Developments
Planning and Procurement in Process                     Budget/Costs Incurred
Schedule                              0.6  0.52   0.52
0.5
On Schedule
Millions   0.4
Budget                              0.3
0.2
On Budget                                   Dollars in               0.083
0.1
Change Order                            0
Authorized  Forecasted   Costs
Current Quarter   Project Total                           Incurred
Number of COs    0          0
Amount of COs    $0         $0                Construction Costs
Not Applicable
Justification for COs: n/a
Risks
Grant extensions necessary to complete project may not be
approved. Evaluation is in progress to determine appropriate risk
mitigation.
Budget Transfers
None



CORPORATE
Port of Seattle 3Q 2014 Report  107

THIRD QUARTER REPORT, 2014
Contractor Data System Upgrade
Project Status:
Project: C800519        Upgrade of the Contractor Data    Schedule: Within or ahead
Budget: $1,500,000      System used by Engineering and   Budget: On or under
Phase: Implementation    other groups to track contracts for   Status Reset: Click here to
Start: 7/1/2013           construction projects.           enter a date.
Schedule Completion: 2/28/2016                   (Commission Construction Auth.)
Significant Developments
Development is in progress                            Budget/Costs Incurred
Schedule                              2
1.5      1.5
On Schedule                                    1.5
Budget                              Millions 1
On Budget                                   Dollars in 0.5
0.034
Change Order                           0
Authorized Forecasted  Costs
Current Quarter   Project Total                         Incurred
Number of COs    0          0
Amount of COs    $0         $0                Construction Costs
Not Applicable
Justification for COs: n/a
Risks
No signfiicant risks at this time.
Budget Transfers
None




CORPORATE
108  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Computer Dispatch System Upgrade
Project Status:
Project: C800520        Upgrade Computer Dispatch      Schedule: Within or ahead
Budget: $790,000       System used by 911 and        Budget: On or under
Phase: Planning        Emergency Responders        Status Reset: Click here to
Start: 4/1/2013                                   enter a date.
Schedule Completion: 8/31/2015                   (Commission Construction Auth.)
Significant Developments
Procurement and Planning in process                     Budget/Costs Incurred
Schedule                              1
0.79     0.79
On Schedule                                    0.8
Millions  0.6
Budget
0.4
On Budget                                   Dollars in  0.2
0.05
Change Order                           0
Authorized Forecasted  Costs
Current Quarter   Project Total                         Incurred
Number of COs    0          0
Amount of COs    $0         $0                Construction Costs
Not Applicable
Justification for COs: n/a
Risks
No signfiicant risks at this time.
Budget Transfers
None




CORPORATE
Port of Seattle 3Q 2014 Report  109

THIRD QUARTER REPORT, 2014
Construction Document Management
Replacement of the Construction     Project Status:
Project: C800521       Document Management System    Schedule: Within or ahead
Budget: $900,000       used by Construction Management   Budget: On or under
Phase: Planning       to accept, review, and distribute    Status Reset: Click here to
Start: 9/10/2013         critical documentation.           enter a date.
Schedule Completion: 3/31/2015                   (Commission Construction Auth.)
Significant Developments
Vendor has been selected and design is in progress             Budget/Costs Incurred
Schedule                              1  0.9   0.9
On Schedule                                    0.8
Millions  0.6
Budget
0.4
On Budget                                   Dollars in  0.2
0.01
Change Order                           0
Authorized Forecasted  Costs
Current Quarter   Project Total                         Incurred
Number of COs    0          0
Amount of COs    $0         $0                Construction Costs
Not Applicable
Justification for COs: n/a
Risks
Procurement schedule has been extended which may impact the
overall project schedule.
Budget Transfers
None



CORPORATE
110  Port of Seattle 3Q 2014 Report

THIRD QUARTER REPORT, 2014
Radio System Upgrade
Project Status:
Project: C800586        Upgrade of the Radio System Core  Schedule: Within or ahead
Budget: $6,750,000      Hardware and Software and      Budget: On or under
Phase: Implementation    Dispatch Consoles           Status Reset: 11/4/2014
Start: 6/9/2013                                   (Commission Construction Auth.)
Schedule Completion: 3/31/2015
Significant Developments                    Budget/Costs Incurred
Radio system upgrade was successfully completed in 2nd Quarter.
The following phase will address King County integration and small       8
6.75     6.75
enhancements that will improve availability.
6
4.3
Schedule                              4
in Millions
On Schedule
Dollars     2
Budget                              0
Authorized Forecasted   Costs
We are estimating a budget underrun of approximately $1,500,000.                   Incurred
Change Order
Construction Costs
Current Quarter   Project Total          Not Applicable
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
No signfiicant risks at this time.
Budget Transfers
None



CORPORATE
Port of Seattle 3Q 2014 Report  111

THIRD QUARTER REPORT, 2014
Noise Monitoring System Replacement
Project Status:
Project: C800693        Upgrade or Replacement of the    Schedule: Within or ahead
Budget: $1,900,000      Airport Noise Monitoring System    Budget: On or under
Phase: Implementation                        Status Reset: Click here to
Start: 4/1/2014                                   enter a date.
Schedule Completion: 8/31/2015                   (Commission Construction Auth.)
Significant Developments
Vendor has been selected and contract negotiations are in process.   Budget/Costs Incurred
1.9      1.9
Schedule                              2
On Schedule                                    1.5
Millions
Budget                              1
On Schedule                                  Dollars in  0.5
0.02
Change Order                           0
Authorized Forecasted   Costs
Current Quarter   Project Total                         Incurred
Number of COs    0          0
Amount of COs    $0         $0                Construction Costs
Not Applicable
Justification for COs: n/a
Risks
No signfiicant risks at this time.
Budget Transfers
None




CORPORATE
112  Port of Seattle 3Q 2014 Report

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.