Item Number:  7b_Report
Meeting Date: September 30, 2014


Commission Staff Brieng
Capital Improvement Projects
Second Quarter Report 2014

This page intentionally left blank









ii  Port of Seattle 2Q 2014 Report

Port of Seattle
Capital Improvement Project Report
Second Quarter 2014
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the status of the Port's capital projects.
Background
During 2014, the Port plans to invest $295,200,000 to expand and upgrade the infrastructure that supports marine and
aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping companies,
airlines, rental car companies, concessionaires and public parking. About 4 percent of the Port's capital budget comes
from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in transportation
facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such, the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes "Project Status" illustrating at a
glance if the project is on schedule, and within budget, and the date Construction authorization was received.
x  Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x  Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x  Budget addresses the total project budget and includes information on the overall budget status, recent
Commission authorizations, forecasted overruns or savings, and scope changes.
x  Change Orders provides information on current quarter's COs and total project COs including justification for CO's for
the reporting period and information on any CO over $200,000 or 10% of the contract value.
x  Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x  Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x  Budget Transfers reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page on the Port of Seattle web site to ask a question, make a comment or
request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 2Q 2014 Report  1

Aviation
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C100266 et al .......Rental Car Facility ............................................... 6-7..........
C101107 ................160th GT Lot ..........................................................8 ...........
C102032 ...............Sanitary Sewer Pump Station Upgrade ................9 ........... ..............................
C102573 ...............Aireld Pavement Replacement ...........................10 .......... .............................. 
C800019 ...............Gate Utilities Improvement ...................................11 .......... ..............................
C800034 ...............North Expressway Relocation ..............................12 ..........
C800061 ...............Main Terminal South Low Voltage ..................... 13-14 ........ ..............................
C800107 ...............C4 UPS System Improvements ............................15 .......... .............................. 
C800168 ...............C60-C61 BHS Modications ................................16 ..........
C800218 ...............Security Exit Lane Breach Control Phase I ..........17 .......... ..............
C800230 ...............Emergency Lighting Parking.................................18 .......... ..............................
C800234 ...............Feeder 101 Tap Replacement ..............................19 .......... ..............................
C800238 ...............Central Plant Pre-Conditioned Air ..................... 20-21 ....... .............. ....................................
C800247 ...............Cargo 2 West Hardstand ......................................22 ..........
C800251 ...............Vertical Conveyance Modernization.....................23 ..........
C800253 ...............Parking System Replacement ..............................24 .......... ..............................
C800254 ...............Aircraft RON Parking Post Ofce Site..................25 ..........
C800267 ...............Port Owned Loading Bridges ...............................26 ..........
C800268 ...............Stage 2 Mechanical Energy Implementation .......27 .......... ..............................
C800274 ...............8th Floor Weather Proong ..................................28 .......... ..............................
C800324 ...............Long-Term Cell Phone Lot .................................29-30 ....... ..............
C800334 ...............Two new CTE Freight Elevators ...........................31 .......... 
C800335 ...............EGSE Electrical Charging Stations ................... 32-33 ....... ..............
C800368 ...............Refurbish Bag Claim Device 8..............................34 ..........
C800382 ...............BHS (C22-C1, MK1 and TC3) ............................35-36 .......
C800390 ...............Cargo 6 Enhancements ........................................37 ..........
C800406 ...............RW 16C/34C Reconstruction ...............................38 ..........
C800426 ...............FIS Improvement - Short Term .............................39 .......... ..............
C800451 ...............Doug Fox Site Improvement .............................. 40-41 ....... ..............
C800461 ...............IWTP Fiber Installation .........................................42 .......... ..............................
C800464 ...............Fiber Infrastructure to Gate Backstands ..............43 .......... ..............................
C800474 ...............Airport Signage .....................................................44 .......... .............................. ....................................
C800475 ...............Miscellaneous Building Improvements - AR.........45 ..........
C800479 ...............Fire Station Electrical Upgrades ...........................46 .......... .............................. ....................................



2  Port of Seattle 2Q 2014 Report

Aviation, cont.
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C800490 ...............New Window Wall Ticket Zone 1 ..........................47 .......... .............................. ....................................
C800495 ...............Facility Monitoring System Renewal ....................48 .......... ..............................
C800497 ...............Airport Wide Mechanical Controls System ..........49 .......... ..............................
C800541 ...............RAC Baggage Claim Renovation .........................50 .......... ..............................
C800543 ...............Replace PLBs at S7, S9, B4 .................................51 ..........
C800544 ...............NorthSTAR Program.............................................52 .......... ..............................
C800545 ...............NorthSTAR Main Terminal Improvements............53 .......... ..............................
C800547 ...............NorthSTAR Concourse C Vertical Circ. ...............54 ..........
C800550 ...............Concourse D Roof Replacement..........................55 ..........
C800551 ...............Grease Interceptor Augmentation ........................56 .......... .............................. 
C800555 ...............NorthSTAR Refurbish Baggage Systems ............57 ..........
C800556 ...............NorthSTAR North Satellite Lobbies ...................58-59 ....... .............................. ....................................
C800557 ...............Snowblower and Deicer Trucks ............................60 ..........
C800560 ...............MT Mezzanine Tenant Relocation ........................61 ..........
C800576 ...............Known Crew Member Employee Bypass .............62 .......... .............................. ....................................
C800581 ...............Parking Garage Lights ..........................................63 ..........
C800583 ...............International Arrivals Facility ................................64 ..........
C800605 ...............Security Exit Lane Breach Control Phase 2 .........65 .......... ..............................
C800609 ...............NSAT - STS Ceiling Leak Repair ..........................66 .......... .............................. 
C800612 ...............Checked Baggage Recapitalization/Optimzation.67 ..........
C800615 ...............Second Floor Mezzanine Infra Upgrade ..............68 .......... ..............................
C800637 ...............2014-15 Roof Replacement ..................................69 ..........
C800651 ...............Town-Country Stormwater Pipe ...........................70 ..........
C800659 ...............North Utility Tunnel Steam Pipe ...........................71 ..........
C800667 ...............Automated Passport Control ................................72 ..........
Other Aviation
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C200007...............Highline School Noise Insulation ..........................73 .......... ..............................
C200042 ...............Highline Community College Noise Insulation .....74 ..........
C200048 ...............Home Insulation Retrot .......................................75 ..........
C200093 ...............Single Family Home Sound Insulation .................76 ..........
C800146 ...............RMU/Kiosk Concession Program ........................77 ..........
C800150 ...............Burien Commercial Property Acquisition .............78 .......... ..............................
C800154 ...............Tenant Reimbursement ........................................79 ..........


Port of Seattle 2Q 2014 Report  3

Seaport
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C102554............... Terminal 46 Development....................................80 ..........
C102858 et al ....... Street Vacations T-5/18/105.................................81 .......... ..............................
C800090 ...............Pier 34 Mooring Dolphins .....................................82 ..........
C800132 ...............T-5 Berth Modernization .......................................83 ..........
C800160 ...............T-91 Lighting Upgrade ..........................................84 .......... .............................. 
C800183 ...............P91 Fender System Upgrade ...............................85 ..........
C800430 ...............T-91 Building C175 Roof Replacement ................86 ..........
C800439 ...............T-91 Station Upgrades..........................................87 ..........
C800516 ...............SEA P-66 Apron Pile Wrap ..................................88 ..........
C800546 ...............Argo Yard Truck Roadway ....................................89 .......... .............................. 
C800603 ...............T-46 Dock Rehabilitation ......................................90 .......... ..............................
C800689 ...............T-115 Stormwater Separation ...............................91 ..........

WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation ..................92 ..........
E104324 ................Viaduct Construction Coordination ......................93 ..........
E104840................T-5, T-18 and T-91 E. Maintenance Dredging ......94 .......... ..............................
U00079 .................Clean Truck Program Truck Scrap & Repl ...........95 ..........
U00099 .................IHI Cranes Removal .............................................96 ..........
Real Estate
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C800088 ...............SBM Central Seawall ............................................97 .......... .............................. 
C800137 ...............FT C15 HVAC Improvements ...............................98 .......... ..............................
C800314 ...............P69 Built-up Roof Replacement ...........................99 ..........
C800344 ...............FT C-2 Nordby Roof and HVAC .........................100 .........
C800527 ...............FT Net Shed 9 Roof Replacement ......................101 .........
C800691 ...............P69 Carpet Replacement ....................................102 ......... .............................. 
WP Number  Project Title           Page
E104838................FT Net Shed Code Compliance ..........................103 .........


4  Port of Seattle 2Q 2014 Report

Corporate
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C800162 ...............ID Badge Replacement .......................................104 ......... .............................. 
C800321 ...............Enterprise Project Cost Management ..................105 ......... ..............................
C800323 ...............Network Switch Replacement ..............................106 .........
C800436 ...............Terrminal 91 Visitor Management ........................107 .........
C800519 ...............Contractor Data System Upgrade........................108 .........
C800520 ...............Computer Dispatch System Upgrade ..................109 .........
C800521 ...............Construction Document Management ................110 .........
C800586 ...............Radio Systems Upgrade...................................... 111 .........
C800693 ...............Noise Monitoring System Replacement ..............113 .........


Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Negative Variance Status
New Variance
Previously Reported
Schedule Completion on the Project Reports refers to:
Benecial Occupancy or Last Asset In-Use date







Port of Seattle 2Q 2014 Report  5

SECOND QUARTER REPORT, 2014
Rental Car Facility
Project Status:
Project:   C100266,     The program will construct a       Schedule: Within or ahead
C102167, C800032     consolidated rental car facility (RCF),  Budget: On or under
Status Reset: 6/30/2009
Budget: $379,407,749   off-site roadway improvements (ORI),
a bus maintenance facility (BMF),     (Commission Construction Auth.)
Phase: Construction
Start: 2/24/1998        improvements at the Main Terminal for
busing (MTI), plus purchase a fleet of
Schedule Completion:
buses.                     Budget/Costs Incurred
Q2 2012
400    396.11
Significant Developments                     395
Millions 390
The RCF program is substantially complete with projects either
385
closed or in closeout. The Contractor claims were settled and         380         378.00
authorized by the Commision August 8, 2014. RCF final closeout will                    373.24
Dollars in  375
begin with claim settlement. BMF and ORI.                    370
365
Schedule                            360
Authorized   Forecasted  Costs Incurred
RCF opened May 17, 2012. Final Contractor claims were authorized
by the Commission August 8, 2014. BMF and ORI are anticiapted to
reach final closeout this year, and RCF next year.
Construction Costs
Budget                             300       264.66
250.74
The RCF program remains under budget with a total program budget    250
of $419,306,000. The total forecasted cost at completion for the      Millions 200
RCF program, not including the payment for negotiated final claims,      150
is $400,506,000.
100
Dollars in 
50         16.35
Change Order
0
Current Quarter   Project Total                Initial  Change  Spent
Orders
Number of COs    1          1,757
Amount of COs    $97,643      $15,654,893
Photo
Justification for COs: $97,643 for dispute settlement. The final
claims change orders will be included next quarter.
Risks
No risks identified for the RCF program.


6  Port of Seattle 2Q 2014 Report

Budget Transfers
Transferred $589,122.22 from capital to expense projects in support of the BMF and ORI close out.
Returned $2,000,000 of previously identified savings to the RCF for claim support. The return of
additional savings for the final claims will occur in the next quarter.
Cost Growth of Construction
RCF Airport Wayfinding Signage and Curbside Modifications - MC-0316968 - This contract is closed
and the final cumulative change order percentage is 21.3%.
Consolidated Rental Car Facility - Small Operator Build Out - MC-0317022 - This contract is closed
with a final cumulative change order percentage of 3.97%.
Consolidated Rental Car Facility Offsite Roadway Improvements and SR99 Bridge Seismic Upgrade
MC-0316568 - This contract is closed with a final cumulative change order percentage of 39.6%.
Bus Maintenance Facility - MC-0316730 - This contract is closed with a final cumulative change order
percentage of 2.29%.
GCCM Final Construction (Phase 3 of 3)  MC-0315405 - The current cumulative change order
percentage through this quarter is 4.91% with one change order executed this quarter. This contract
is active with final claim negotiations underway.
TESC & Early Work (Phase 2 of 3)  MC-0315292 - This contract is closed with a final cumulative
change order percentage of 19.4%.
GCCM Pre-Construction (Phase 1 of 3)  MC-0314280  This contract is closed with a final
cumulative change order percentage of 170.5%.





AIRPORT
Port of Seattle 2Q 2014 Report  7

SECOND QUARTER REPORT, 2014
So. 160th GT Lot Expansion
Project Status:
Project: C101107     Renovate existing building for      Schedule:  within or ahead
Budget: $4,532,000    better functionality, improve lot     Budget:   on or under
Phase: Design      draingage, underground existing    Status Reset: Click here to enter a
overhead utility lines, fencing and
Start: 2/1/2013                                 date.
landscaping.
Schedule Completion:                       (Commission Construction Auth.)
9/30/2015
Significant Developments                   Budget/Costs Incurred
Preparation of 30% design documents for building renovation and
5            4.532
site improvements commenced. Negotiations with utility companies
4
on agreements to underground existing overhead utility lines along
S. 160th are in progress.                                 Millions 3
2
Schedule                            Dollars in    1.064
1
Completion of design and advertisement for bids expected in                         0.146
0
November 2014, followed by construction and beneficial occupancy
Authorized   Forecasted  Costs Incurred
in September 2015.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Unforeseen building or site conditions could increase design and
construction costs. Unforeseen complications in executing
agreements with utilities for undergrounding lines.
Budget Transfers
None

AIRPORT
8  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT,
Sanitary Sewer Pump Station Upgrade
Upgrade the aging control systems   Project Status:
Project:   C102032
of 22 sanitary sewer lift stations.     Schedule: Delayed
Budget: $1,133,000                         Budget: On or under
Phase: Design                            Status Reset: Click here to
Start: 3/1/2013                                   enter a date.
Schedule Completion: 11/30/2014                 (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
Control components have been delivered. Installation has begun.      1.2   1.13    1.13
1
Schedule
0.8
The project is behind schedule due to changes to the control panels    0.6
Millions
and installation challenges.
Dollars in  0.4
0.14
0.2
Budget
0
The project forecast is within the approved budget and authorization.       Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                Not Applicable
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 2Q 2014 Report  9

SECOND QUARTER REPORT, 2014
Airfield Pavement Replacement
Project Status:
Project:   C102573     This is a multi-year program to      Schedule: Late
Budget: $29,896,495    replace distressed pavement and   Budget: On or under
Phase: Construction    joint seal on the airfield.        Status Reset: 4/1/2014
Start: 5/2/2010                                  (Commission Construction Auth.)
Schedule Completion: 12/31/2016
Significant Developments                    Budget/Costs Incurred
The first bid for the 2014 AIP was rejected due to a bid irregularity.      35
29.90
The re-bid had similar results, but the pavement repair was deemed     30   27.68
critical enough to request approval from Commission. Commission     Millions 25
20                    17.74
authorized on August 6th.
15
Schedule                            Dollars in  10
5
NTP scheduled for the second week of September. Schedule has
0
been pushed to very late in the construction season increasing the        Authorized  Forecasted Costs Incurred
risk of weather impacts..
Budget                            2014 AIP Construction
The project forecast is within the approved budget.              Costs
Change Order                         N/A
Current Quarter   Project Total
Number of COs    0          0                2014 Cargo 6 Panel
Amount of COs    $0         0                Construction Costs
2.5   2.26
Justification for COs: N/A this quarter.
2
Risks                                Millions 1.5
Project schedule has been pushed to very late in the construction        1
season increasing the risk of weather impacts..                  Dollars in  0.5
0.00    0.00
0
Budget Transfers                             Initial Change Spent
Orders
$129,000 to C800404 (Aeronautical Allowance)
$137,000 to U00128 (ERL project)


AIRPORT
10  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Gate Utility Improvements
Project Status:
Upgrade the South Satellite Port-       Schedule: Delayed
Project:   C800019    owned loading bridges to the same     Budget: On or under
Budget: $11,694,480   standards, including 400Hz power and  Status Reset: Click here to
Phase: Construction  potable water. This will reduce air     enter a date..
Start: 6/28/2007       emissions, improve energy efficiency    (Commission Construction Auth.)
Schedule Completion:  and save money for the airlines.
8/29/2014
Budget/Costs Incurred
Significant Developments
14    12.69
11.69
The Contractor is working at both the North and South Satellites and    12
Concourse B. Part of South Satellite 400 Hz turned over for airline
Millions 10
7.93
use May 5, 2014.                                    8
6
Schedule                            Dollars in  4
2
Remaining 400 Hz are to be turned over at South Satellite by June 1,
0
2014. North Satellite and Concourse B gate water to be turned over
Authorized   Forecasted  Costs Incurred
for use by July 1, 2014.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
6
5.05           4.80
Change Order                           5
Current Quarter   Project Total           Millions  4
Number of COs    20         20                  3
Amount of COs    $37,345.52    $73,467.00              2
Dollars in               0.73
1
Justification for COs: Changes to existing conditions - designer and       0
owner, and varying site conditions.                               Initial  Change  Spent
Orders
Risks
Airport Operations at certain gates could be impacted during the
construction phase of the project, through June 1, 2014.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 2Q 2014 Report  11

SECOND QUARTER REPORT, 2014
North Expressway Relocation
Project:   C800034                             Project Status:
Reconstruct the Northern Airport
Budget: $102,806,300                        Schedule: Within or ahead
Expressway, support the extension
Phase: Construction                        Budget: On or under
of light rail to the Airport, and
Start: 7/27/2004                                  Status Reset: 2/20/2014
construct improvements to Wall 14.  (Commission Construction Auth.)
Schedule Completion:
11/30/2014
Budget/Costs Incurred
Significant Developments
112    110.23
Reconstruction of the Northern Airport Expressway and the light rail    110
transit components are complete. The Wall 14 improvements were     108
106
advertised for construction bids in April 2014, and the contract was
104            102.81
Millions
executed in June 2014 with Pellco Construction, Inc. The bid was
102                    101.06
$381,000 below the engineer's estimate.                     Dollars in 100
98
Schedule                             96
Authorized   Forecasted  Costs Incurred
The Wall 14 improvements remains on schedule with construction
anticipated to start in August 2014 and be complete by November
2014.                                       Construction Costs
Budget                             120          105.38
98.17
Project forecast is within the approved budget and authorization.       100
The total budget for the Wall 14 improvements is $1,891,000.         80
60
Millions
Change Order
Dollars in  40
Current Quarter   Project Total            20         8.03
Number of COs    N/A        226                 0
Amount of COs    $0         $8,034,558                Initial  Change Order  Spent
Justification for COs: N/A this quarter
Photo
Risks
None identified at this time.
Budget Transfers
None.

AIRPORT
12  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Main Terminal South Low Voltage
Project Status:
Project:   C800061   Renewal and replacement of low      Schedule: Delayed
Budget: $8,530,000   voltage (600 volts and below) electrical  Budget: On or under
Phase: Design      distribution equipment in the southern   Status Reset: Click here to
Start: 6/28/2007       part of the Main Terminal            enter a date.
Schedule Completion: 12/31/2008                 (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
Due to project deferral and the possibility of changes in site           10
8.53
conditions and building codes, the design phase changed from 100%
8
to 0% complete. Finalized Project Notebook to address scope of      Millions 6
work, schedule, and budget, presented to and approved by the
Investment Committee on November 6, 2013. The project will go to      4
Commission in third quarter of 2014.                        Dollars in      1.93
2
0.58
0
Schedule
Authorized   Forecasted  Costs Incurred
Staff has finalized the scope of work, schedule and final design
budget. The 100% design documents for this project scheduled to be
complete by the end of December 2015.                   Construction Costs
Not Applicable
Budget
The project budget was increased. The project forecast is within the   Photo
approved budget. Commission Authorization for design funding will
be requested.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will


Port of Seattle 2Q 2014 Report  13

Risks, cont.
be required to add additional crews to complete work in a timely manner. This area is a 24/7/365
operation. Sequencing of this work is critical and electrical power has to be maintained without
interruptions.
Budget Transfers
None at this time











AIRPORT
14  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
C4 UPS System Improvements
Project Status:
Project:   C800107    Replace existing Uninterruptible Power   Schedule: Delayed Schedule
Budget: $2,336,000   Supply (UPS) System, including      Budget: On or under
Phase: Planning     batteries, with a new system located in  Status Reset: Click here to
Start: 6/28/2007       the Airport Combined Communications   enter a date.
Schedule Completion:  and Command Center (C4).        (Commission Construction Auth.)
TBD
Budget/Costs Incurred
Significant Developments
2.5     2.34       2.34
Due to project deferral and the possibility of changes in site
conditions and building codes, the design phase changed from 100%    2
to 30% complete. Revised scope of work, schedule, and budget is
1.5
being included in the new Project Notebook.
Millions
1
Schedule                            Dollars in             0.50
0.5
The project was reactivated. Staff is in the process of determining      0
the scope of work, schedule and final design budget.                 Authorized  Forecasted Costs Incurred
Budget
The project budget is being evaluated based on delays and scope    Construction Costs
changes.                                    Not Applicable
Change Order                         Photo
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
The C4 center is a 24/7/365 operation. Sequencing of this work is
critical and electrical power has to be maintained without
interruptions. It is not known when the construction will proceed as
this is specialized equipment and due to the complexity the new
system will require rigorous testing during the commissioning phase.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 2Q 2014 Report  15

SECOND QUARTER REPORT, 2014
C60 - C61 BHS Modifications
Project Status:
Project:   C800168    This work represents a critical       Schedule: Within or ahead
Budget: $11,864,825   component to providing improved     Budget: On or under
Phase: Construction   operational baggage in-line screening  Status Reset: 11/5/2013
Start: 6/1/2012        at the South end of the Airport and     (Commission Construction Auth.)
Schedule Completion:  more baggage make-up capacity for
airlines.
12/31/2014
Budget/Costs Incurred
Significant Developments
14
11.86      11.86
MD Moore successfully met the June 1 Beneficial Occupancy date     12
on the makeup. Controls and ATR work is in progress.
Millions 10
8
Schedule                             6           4.92
Dollars in   4
The project is currently on schedule.
2
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Current Quarter   Project Total
6
Number of COs    3          3                      5.16
5
Amount of COs    $14,727      $14,727
Millions   4
2.81
Justification for COs: n/a                                      3
2
Risks                                Dollars in   1     0.15
None                                    0
Initial   Change   Spent
Orders
Budget Transfers
None


AIRPORT
16  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Security Exit Lane Breach Control - Phase 1
Project Status:
Project:   C800218      Procure and install new automated   Schedule: Delayed
Budget: $1,310,000      exit lane breach control equipment  Budget: On or under
Phase: Close Out      at the Concourse B exit.       Status Reset: 4/2/2013
Start: 3/1/2012                                   (Commission Construction Auth.)
Schedule Completion: 6/30/2013
Budget/Costs Incurred
Significant Developments
Equipment was ordered for post-construction work to convert the      1.5   1.31    1.31
twin door lanes to triple door lanes.
Millions                           0.92
1
Schedule
0.5
Construction completed July 2013.                         Dollars in 
0
Budget                               Authorized Forecasted Costs Incurred
Project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
No major risks at this time.
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 2Q 2014 Report  17

SECOND QUARTER REPORT, 2014
Emergency Lighting - Parking
Project Status:
Project:   C800230     Provide electrical infrastructure for a
Schedule: Delayed
Budget: $4,602,717.    new source of emergency power to
Budget: On or under
Phase: Construction   feed the parking garage emergency
Status Reset: Click here to
Start: 7/24/2012        lighting circuits and ensure that code-
enter a date.
Schedule Completion:   required level of egress illumination is
(Commission Construction Auth.)
provided for safety.
7/16/2014
Budget/Costs Incurred
Significant Developments
5    4.60      4.60
Project is to meet substantial completion in July.
4
Schedule                            Millions 3
2.04
Monitoring and verification on the ESCO project will take place next      2
quarter.                                              Dollars in  1
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Current Quarter   Project Total
2
Number of COs    0          0                     1.69
1.56
Amount of COs    $0         $0                  1.5
Millions
1
Justification for COs: n/a
Dollars in   0.5
Risks                                      0.00
0
None                                      Initial Change Spent
Orders
Budget Transfers
None


AIRPORT
18  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Feeder 101 Tap Replacements
Project Scope and description:        Project Status:
Project:   C800234    The project includes replacing the     Schedule: Delayed
Budget: $2,646,000    electrical feeds to 13 locations along Air Budget: On or under
Phase: Design      Cargo Road. Also, the electrical     Status Reset: Click here to
Start: 4/1/2013        transformer and associated switchgear  enter a date.
Schedule Completion:  for Air Cargo #4 will be replaced.     (Commission Construction Auth.)
6/30/2015
Budget/Costs Incurred
Significant Developments
3            2.65
Design is 100% complete. Will be combining project w/ C800479 in     2.5
July 2014.                                         Millions 2
1.5
Schedule                             1
0.50               0.37
Commission to authorize bid/construction in July of 2014. Substantial   Dollars in 0.5
completion scheduled for Q2 of 2015.                        0
Authorized  Forecasted Costs Incurred
Budget
Commission to authorize revised budget in July 2014.            Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Unplanned electrical shut downs could impact the project schedule.
Budget Transfers
None


AIRPORT

Port of Seattle 2Q 2014 Report  19

SECOND QUARTER REPORT, 2014
Central Plant Pre-Conditioned Air
Project:   C800238     Provide a centralized pre-conditioned  Project Status:
Budget: $51,890,000    air (PC-Air) plant (PCAP), associated  Schedule: Delayed
Phase: Construction    heating and cooling piping systems,  Budget: Forecast Overrun
Start: 6/15/2009        and jet bridge terminal air handling    Status Reset: 2/25/2014
Schedule Completion:   units to serve airplanes with heating  (Commission Construction Auth.)
and cooling while at the gates.
8/31/2013
Budget/Costs Incurred
Significant Developments
Contractor's work is complete except for punchlist and warranty        53         51.89
issues. PC-Air is operating at 66 gates. Four gates are remaining,      52
51
but operational needs have delayed work on these until second and    Millions 50   49.05
third quarter of 2014. This work was removed from the General        49
47.73
Contract and will be completed separately.                     48
Dollars in  47
Schedule                             46
45
The original contract completion date for all gates was December 11,       Authorized  Forecasted Costs Incurred
2012. Work was completed in December 2013. The delay was
primarily due to Concourse D redesign, as previously reported. All
but four gates are complete, and will be completed in 2014         Construction Costs
contingent on operational needs.
40               35.20
Budget
30   27.01
Negotiations with the contractor on potential change orders and       Millions
claims risk are in process. As negotiations proceed, identify potential      20
budget issues. Current project forecast including open claims
Dollars in               8.41
10
exceeds approved budget and authorization. Staff will return to
Commission to request additional funding and authorization to          0
execute change orders.                                    Initial  Change  Spent
Orders
Change Order
Current Quarter   Project Total
Number of COs    7          204
Amount of COs    $267,692     $8,410,247
Justification for COs: piping and electrical site conflicts on the
concourse and at the gates.


20  Port of Seattle 2Q 2014 Report

Risks
There is budget risk based on the dollar amount of open potential change orders and claims. There is
schedule risk as completing work at each gate is contingent on gates being available.
Budget Transfers
None this quarter.
Cost of Construction Growth
Cost growth occured due to shortcomings in the bid documents. Current cost of executed Change
Orders is 31% of the base contract price. The trended cost growth projection is currently 33% over
bid price. Approximately 20% are related to error and/or ommissions (owner or designer), 7% are
currently in some form of dispute. The remainder of the cost growth are due to site conditions,
discretionary tenant requests or scope changes and regulatory requirements respectively.









AIRPORT
Port of Seattle 2Q 2014 Report  21

Cargo 2 West Cargo Hardstand            SECOND QUARTER REPORT,
Enlarge the western cargo hardstand
Project:   C800247    in the Cargo 2 area. Includes buyout   Project Status:
Budget: $9,247,875    of two cargo buildings and tenant     Schedule: Within or ahead
Phase: Construction   relocations; relocation of FAA      Budget: On or under
Start: 9/25/2012       antenna, security gate, and guard      Status Reset: 10/8/2013
Schedule Completion:  shack; and installation of 400Hz in-    (Commission Construction Auth.)
11/1/2014           ground power.
Budget/Costs Incurred
Significant Developments
14    12.77
Cargo 2 Hardstand is progressing well with slipform paving
12
continuing as lead-in lanes are complete and fill-in lanes are                     9.25
10
underway.                                     Millions 8
6
Schedule
Dollars in   4
2                    1.09
Construction began 1st quarter of 2014. Partial Beneficial
0
Occupancy is anticipated for the middle of August 2014 with
Authorized  Forecasted Costs Incurred
completion of the hardstand portion of the work. The remaining
items are scheduled to be completed by November 1, 2014.
Budget                            Construction Costs
The project forecast is within approved budget and authorization.        6   4.98
Change Order                          Millions 4
Dollars in 
Current Quarter   Project Total
2
Number of COs    0          0                               0.50
Amount of COs    $0         $0                  0
Initial    Change Order    Spent
Justification for COs: n/a
Risks                               Photo
None identified at this time.
Budget Transfers
$82,000 to U00125 (ERL Project)
$2,500,000 to C800404 (Aeronautical Allowance)

AIRPORT
22  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Vertical Conveyance Modernization Program -
Aeronautical - Phase I
Project Status:
Perform modernization on 9 existing     Schedule: Within or ahead
Project:   C800251   elevators and 4 escalators: SSAF,     Budget: On or under
Budget: $22,823,408  MT-2, MT-3, MT-4, MT-5, MT-6, MT-   Status Reset: 11/11/2013
7, SSB, SSC. Install new elevators
Phase: Construction                        (Commission Construction Auth.)
SSM and SSN. Install cooling
Start: 10/25/2011
packages on 12 existing hydraulic
Schedule Completion: elevators throughout Main Terminal.
10/30/2016
Significant Developments                    Budget/Costs Incurred
Phase I contract awarded to the low bidder. Construction work will      25         22.82
begin in 3rd quarter as scheduled.
20
15.25
Schedule                             15
in Millions
Construction scheduled to begin in the 3rd Quarter of 2014, with        10
construction completion in the 3rd Quarter of 2016.                Dollars  5                1.98
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction has
been requested and bidding is underway.                   Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None
Budget Transfers
None


AIRPORT
Port of Seattle 2Q 2014 Report  23

SECOND QUARTER REPORT, 2014
Parking System Replacement
Project Status:
This project replaces the current   Schedule: Delayed
Project:   C800253       Parking Revenue Control System,  Budget: On or under
Budget: $5,577,364      which manages parking access   Status Reset: 3/8/2011
Phase: Construction     and revenue collection in the    (Commission Construction Auth.)
Start: 4/6/2010           Airport's Main Parking Garage.
Schedule Completion: 8/31/2012
Budget/Costs Incurred
Significant Developments
12
Scheidt & Bachmann (S&B), the system vendor completed final           9.78
10
testing. The system is exhibiting accuracy and availability rates
above 99.99%. The Port continues working with S&B to correct a     Millions 8
5.58
limited number of outstanding issues. Ports' Legal and ICT           6                5.02
departments are also involved.                            Dollars in  4
2
Schedule                             0
Authorized   Forecasted  Costs Incurred
The system is substantially complete and in use. However, PCI
related issues remain to be resolved prior to completion.
Budget                            Construction Costs
None this quarter
The project forecast is within the approved budget and authorization.
Photo
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: Not applicable this quarter
Risks
The Port is working with the contractor to address outstanding PCI
and unique transaction identifier issues.
Budget Transfers
Budget transfer of $499,635 to C800405 (Non-Aeronautical
Allowance).

AIRPORT
24  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Aircraft RON Parking USPS Site
Project Status:
Prepare the site for the construction   Schedule: Within or ahead
Project:   C800254     of hardstands for use as Remain    Budget: On or under
Budget: $45,602,000    Overnight (RON) parking of aircraft at Status Reset: 10/8/2013
Phase: Construction    the Cargo 5 area.           (Commission Construction Auth.)
Start: 8/26/2008
Schedule Completion: 11/1/2014
Budget/Costs Incurred
Significant Developments
60
49.99
Mass excavation is complete. This activity required roughly 10,000     50        45.60
truck loads for approximately 300,000 tons of soil. Nelson stud        Millions 40
installation on the soldier piles is underway.                      30
Dollars in 
20
Schedule                                        8.23
10
Construction began in the 1st quarter of 2014. Cargo 5 is on          0
schedule to be completed by the middle of the 4th quarter of 2014.        Authorized Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
30    27.83
Change Order
Current Quarter   Project Total           Millions 20
Number of COs    0          0
10
Amount of COs    $0         $0
Dollars in                           1.56
0
Justification for COs: n/a                                        Initial  Change Order  Spent
Risks
Photo
There has been a significant amount of contaminated soil at Cargo 5
(approximately 10,000 TN to date). Contract bid quantity is 13,500
total TN's. Any overrun will be managed through construction
contingency.
Budget Transfers
None at this time

AIRPORT
Port of Seattle 2Q 2014 Report  25

SECOND QUARTER REPORT, 2014
Port-Owned Loading Bridge Renewal &
Replacement
Project Status:
Replace or refurbish Port-owned    Schedule: Within or ahead
Project:   C800267      Passenger Loading Bridges (PLBs)  Budget: On or under
Budget: $2,405,000      that have reached the end of their   Status Reset: 2/28/2012
Phase: Construction     service life.              (Commission Construction Auth.)
Start: 2/28/2012
Schedule Completion: 12/31/2014
Budget/Costs Incurred
Significant Developments                      3
2.41       2.41
2.5
The work associated with this CIP has been completed and the                        1.98
project is in closeout. The scope of work at Gate S4 is now being      Millions  2
handled under CIP C800662 - 12th & 13th FIS Widebody Gate        1.5
project.
Dollars in   1
0.5
Schedule                             0
Authorized   Forecasted  Costs Incurred
Work has been completed and bridge is in use.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
0.7
0.58           0.57
Change Order                           0.6
0.5
Current Quarter   Project Total           Millions  0.4
Number of COs    0          5                  0.3
Amount of COs    $0         $-12,385              0.2
Dollars in   0.1           0.01
0
Justification for COs: n/a
0.1   Initial   Change   Spent
Orders
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT
26  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Stage 2 Mechanical Energy Implementation
Project Status:
Project:   C800268      Improve the energy performance of  Schedule: Delayed
Budget: $2,852,900.00    the mechanical infrastructure     Budget: On or under
Phase: Construction     systems at the Airport.        Status Reset: 10/4/2011
Start: 10/1/2011                                  (Commission Construction Auth.)
Schedule Completion: 10/31/2013
Significant Developments                    Budget/Costs Incurred
The project is complete. The project implemented the ILA with
2.86     2.85      2.85
Washington State Department of Enterprise Services ESCO
2.84
program. This will be the final report for this project.
2.82   Millions
Schedule                             2.8          2.79
2.78
Project is complete and being closed out.
2.76   Dollars in 
Budget                             2.74
Authorized  Forecasted Costs Incurred
The project realized budget savings through a deductive change
order to remove the heat recovery after investigation of construction
feasibility. This decision was made in 2012, but savings not realized
Construction Costs
until this quarter.
3
2.48
Change Order
2.5                 2.24
Current Quarter   Project Total            Millions  2
Number of COs    7          18                  1.5
1
Amount of COs    $ (12,643.95)   $(239,374)
Dollars in   0.5
0
Justification for COs: Deductive changes for removing heat recovery
0.5   Initial   Change   Spent
0.24
scope decision from 2012.                                       Orders
Risks
None identified at this time.
Budget Transfers
None this quarter.

AIRPORT
Port of Seattle 2Q 2014 Report  27

SECOND QUARTER REPORT, 2014
8th Floor Weatherproofing                Project Status:
Schedule: Delayed
Project:   C800274      Removal and replacement of the    Budget: On or under
Budget: $13,050,000.     floor covering system on the eighth  Status Reset: 5/27/2014
Phase: Construction     floor of the STIA parking garage    (Commission Construction Auth.)
Start: 3/23/2010          and repair or replacement of
Schedule Completion:    expansion joints and flashings.
7/31/2014                                  Budget/Costs Incurred
14    13.05
Significant Developments
12
9.47
The Port's Contractor, PCL, mobilized during this quarter after
Millions 10                         8.07
Commission authorized contract time extension. During that time,      8
they stripped portions of the 8th floor garage deck that contained        6
defective coating. Moisture readings prevented replacement coating   Dollars in  4
from being applied. PCL has now used up its' contract time           2
extension. The Port has directed PCL to complete the work          0
Authorized   Forecasted  Costs Incurred
immediately.
Schedule
Construction Costs
The Contractor has used up their Commission approved schedule
extension. They have received a letter of forbearance from the Port.     7   6.05           6.07
6
Budget
Millions  5
4
The project forecast is within the approved budget and authorization.
3
2
Change Order                         Dollars in         0.70
1
Current Quarter   Project Total            0
Number of COs    N/A        23                    Initial  Change Order  Spent
Amount of COs    N/A        $69,558
Photo
Justification for COs: N/A
Risks
This project is highly weather sensitive. Materials solutions are
being pursued.
Budget Transfers
None this quarter.

AIRPORT
28  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Long-Term Cell Phone Lot
Project Status:
Schedule: Delayed Schedule
Project:   C800324      Construct a new cell phone waiting
Budget: On or under
Budget: $2,207,100      lot to replace the existing lot that is
Status Reset: 5/6/2014
Phase: Construction     being displaced, and construct a
(Commission Construction Auth.)
Start: 12/11/2012         traffic control roundabout or signal
Schedule Completion:    adjacent to the lot on South 170th
Street.
12/31/2014
Budget/Costs Incurred
2.5
Significant Developments                        2.21   2.21
2                    1.76
Cell phone lot paving, striping, lighting, and drainage system was
completed; 200 parking stalls are now in service. Construction of a     1.5
water line for a lot fire hydrant and a communications line for wi-fi are
Millions
1
in progress. Staff is evaluating the cost and performance of a signal    Dollars in 0.5
compared to a roundabout as the permanent traffic control method.
0
Authorized  Forecasted Costs Incurred
Schedule
A recommendation on the permanent traffic control method is
expected during September 2014, to be followed by a request to     Construction Costs (PCS
Commission for design and construction authorization.           Only)
Budget                              0.5  0.44
On May 6, 2014 Commission increased the authorization for the cell     0.4
phone lot portion of the project to $2,207,100. Staff will request       Millions 0.3
additional authorization for permanent traffic control subsequent to                           0.24
completing the evaluation of options and a recommendation.          0.2
Dollars in 
0.1
Change Order
0.00
Current Quarter   Project Total             0
Initial      Change Order      Spen
Number of COs    0          0
Amount of COs    $0         $0                Photo
Justification for COs: n/a
Budget Transfers
$379,100 from C800404 (Aeronautical Allowance)


Port of Seattle 2Q 2014 Report  29

Risks
Project schedule uncertainties related to the time requirement for evaluating the signal and
roundabout options, design and review, and permit acquisition.













AIRPORT
30  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Two New CTE Freight Elevators
Project Status:
Project:   C800334      Provide two new freight elevators   Schedule: Within or ahead
Budget: $8,290,100.     to support concession operations in  Budget: On or under
Phase: Construction     the Central Terminal/Pacific      Status Reset: Click here to
Start: 8/5/2011          Marketplace.                enter a date.
Schedule Completion: 7/31/2014                  (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
Construction is progressing. First elevator delivery is anticipated in      10
8.29       8.29
early Q3.
8                     6.86
Millions
Schedule                             6
As previously reported, the project is anticipating a one-year delay       4
due to scope changes included in the redesign efforts, and delays in    Dollars in  2
reviews.
0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
5   4.30         4.23
Current Quarter   Project Total
4
Number of COs    1          21
Amount of COs    $5,248       $204,862             Millions  3
Dollars in 
2
Justification for COs: Differing site conditions and code compliance
1
improvements.                                           0.20
0
Initial   Change   Spent
Risks
Orders
No new risks identified this quarter.
Budget Transfers
None at this time


AIRPORT
Port of Seattle 2Q 2014 Report  31

SECOND QUARTER REPORT, 2014
Electrical Ground Support Equipment (EGSE)
Electrical Charge Stations
Project Status:
Schedule: Delayed Schedule
Project:   C800335      Airport-wide electrical charging     Budget: On or under
Budget: $30,198,000     system for electrical ground      Status Reset: 10/23/2012
Phase:             support equipment (EGSE) at the   (Commission Construction
Concourses and the North and     Auth.)
Start: 10/26/2010
South Satellites.
Schedule Completion:
6/30/2016                                  Budget/Costs Incurred
35            30.20
Significant Developments                     30  25.35
Finalizing GSE Phase 1 Project "Record Drawings" (Concourse C,     Millions 25
Concourse D and North Satellite) and continue to fine tune the        20
14.80
15
Automatic GSE data collection, storage and Historical Data Report
generation now that it is operational and collecting data.            Dollars in  10
5
0
Design review continues and is nearing completion and lessons          Authorized  Forecasted Costs Incurred
learned from the GSE Phase 1 project are being incorporated in the
design documents. Resolving design conflicts and coordinating with
IAF and other project teams to minimize construction conflicts.       Construction Costs
Reviewing GSE Phase 2 scope of work and implementation
schedule in order to complete infrastructure requirements within        5               4.28
Concourse A, Concourse B and South Satellite to support the GSE
4    3.58
Phase Charging Corrals once the IAF project defines the various of     Millions 3
work on the Terminal Ramp.
2
Schedule                            Dollars in  1      0.70
Phase 1 construction is complete except for finalizing the Record        0
Drawings and other project related documents. Phase 2 construction        Initial  Change Order  Spent
scheduled for completion mid-2016, was impacted by the IAF
Project.
Budget
The project forecast is within the approved budget. The remaining
authorization for the construction funding and authority to advertise
for construction will be requested when the design and bid
documents are completed for GSE Charger Phase 2 Project.


32  Port of Seattle 2Q 2014 Report

Change Order
Current Quarter   Project Total
Number of COs    3          49
Amount of COs    ($2,156.00)    $701,473.00
Justification for COs: Errors/Omissions - Designer & Owner, Varying Site Conditions, Scope Change,
and Regulatory Requirements.
Risks
Coordinate with other airfield projects and Airline Gate Realignment program. Budget and schedule
may affect project implementation and completion.
Budget Transfers
None this quarter.









AIRPORT
Port of Seattle 2Q 2014 Report  33

SECOND QUARTER REPORT, 2014
Refurbish Bag Claim Device
Project Status:
Project:   C800368     Refurbish Claim Device 8 and      Schedule: Within or ahead
Budget: $303,730      replace the current door to a more   Budget: On or under
Phase: Design       secure type.              Status Reset: Click here to
enter a date.
Start: 6/24/2014
(Commission Construction Auth.)
Schedule Completion: 11/24/2014
Significant Developments                    Budget/Costs Incurred
Commission approved budget In June 2014.
350   303.73    303.73
300
Schedule
Project is on schedule.                                  Millions 250200
150
Budget                            Dollars in 100
50
The project forecast is within the approved budget and authorization.                     7.45
0
Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total
Number of COs    0          0                Construction Costs
Amount of COs    $0         $0                None at this time
Justification for COs: N/A
Risks
None
Budget Transfers
None



AIRPORT
34  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Baggage Handling System (C22-C1, MK1, and
TC3)
Replace the ticket counter (TC3)       Project Status:
conveyors and declines, reroute the
Project:   C800382                             Schedule: Within or ahead
conveyors of the C-22 system and      Budget: On or under
Budget: $5,585,000   connect it to the C-1 screening system,  Status Reset: Click here to
Phase: Close Out    replace the existing makeup (MK1)    enter a date.
Start: 3/1/2011        device, and install a new odd size      (Commission Construction Auth.)
Schedule Completion:  baggage system.
5/31/2013
Budget/Costs Incurred
Significant Developments
8
None                                      6.76
7
6              5.59
5.25
Schedule                              5
in Millions   4
The project forecast is within the approved budget and authorization.
Dollars    3
2
Budget
1
The project forecast is within the approved budget and authorization.      0
Authorized    Forecasted   Costs Inc
Change Order                         Construction Costs
Current Quarter   Project Total
Number of COs    0          44                  2            1.79
1.59
Amount of COs    $0         $202,744.00            1.5
Millions  1
Justification for COs: None this quarter
0.5              0.20
Risks                                Dollars in 
0
None identified at this time.                                      Initial  Change Order  Spent
Budget Transfers
To C800404 (Aeronautical Allowance)          $900,000
Cost of Construction Growth
Three changes represent the majority of the cost growth: 1) removed
the C1-CS1 curbside conveyor since replacement was no longer


Port of Seattle 2Q 2014 Report  35

Cost of Construction Growth, Cont.
required, 2) The contract design to replace make-up device MK1 did not include POS ergonomic
standards for this kind of device; and 3) the original contract design for the conveyors in the C1-CS2
conveyor line created unsafe electrical and mechanical conditions for maintenance works. Several
other smaller changes included fire sprinkler and architectural revisions, including a credit to remove
a small scope of work.












AIRPORT
36  Port of Seattle 2Q 2014 Report

Cargo 6 Enhancements               SECOND QUARTER REPORT, 2014
Project:   C800390    Enlarge the Cargo 6 off-gate        Project Status:
Budget: $6,345,875    hardstand to allow simultaneous     Schedule: Within or ahead
nose-loading of wide-body freight
Phase: Construction                        Budget: On or under
aircraft as well as provide fuel hydrant
Start: 9/25/2012                                  Status Reset: 10/8/2013
and ground power capabilities.
Schedule Completion:                        (Commission Construction Auth.)
12/31/2014
Significant Developments                    Budget/Costs Incurred
Cargo 6 Enhancements has been combined with Cargo Areas 2 and
7    6.35      6.35
5 as a single construction contract and has been successfully bid
6
and awarded.
Millions  5
4
Schedule                             3
Construction of the Cargo 6 hardstand enhancements will begin in     Dollars in  2
3rd quarter 2014. Completion is scheduled for 4th quarter 2014.        1               0.44
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
3.72
Current Quarter   Project Total             4
Number of COs    0          0                  3
Amount of COs    $0         $0
2  Millions
Justification for COs: n/a                                    1
Dollars in 
0
Risks                                   Initial  Change Order Spent
None identified at this time.
Budget Transfers                        Photo
None


AIRPORT
Port of Seattle 2Q 2014 Report  37

SECOND QUARTER REPORT, 2014
RW16C/34C Reconstruction
Project Status:
Project:   C800406    Produce final design and reconstruct   Schedule: Within or ahead
Budget: $99,538,000   the existing RW 16C/34C in its      Budget: On or under
existing location, replace TW C and    Status Reset: Click here to
Phase: Design
N, reconfigure TWs H and J, install     enter a date.
Start: 5/4/2010
FOD detection equipment, and install   (Commission Construction Auth.)
Schedule Completion:   LED lighting system.
11/30/2016
Budget/Costs Incurred
Significant Developments
120
99.54
Project is in design. A revised 90% drawing package has been       100
reviewed. A Foreign Object Debris (FOD) detection system vendor
has been selected.                                   Millions 80
60
40
Schedule                            Dollars in 
20    10.68
Design is scheduled for completion in November of 2014.                           0.59
0
Construction is scheduled to begin in the second quarter of 2015. A
decision was made in the fall of 2013 to advance the construction
from 2016.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
$9,100,000 from C800404 (Aeronautical Allowance)
$90,000,000 from C800058 (RW 16C/34C Reconstruction)

AIRPORT
38  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Federal Inspection Services Short Term
Improvements
Short Term Improvements to the      Project Status:
Project:   C800426    Federal Inspection Service area at S.   Schedule: Delayed
Budget: $1,819,000.    Satellite to improve through put and   Budget: On or under
Phase: Construction   conditions for passengers waiting in   Status Reset: 12/10/2013
the International Corridor prior to       (Commission Construction Auth.)
Start: 4/1/2012
Primary Inspection.
Schedule Completion:
Budget/Costs Incurred
6/23/2014
2    1.82      1.82
Significant Developments
1.5
Major Contract work is nearing completion. Light fixtures, new       Millions
podiums and painting is complete. Plastic laminate panel installation    1               0.80
and guardrail installation on new wayfinding walls is underway. PCS
has completed installation of permanent stanchions in the           Dollars in 0.5
international corridor and is installing new PA system.
0
Authorized  Forecasted Costs Incurred
Schedule
Delivery of the plastic laminate panels was delayed and will prevent
the contractor from completing work on time. The Port and the      Construction Costs
contractor are negotiating a new beneficial occupancy date at this
0.7   0.61
time.
0.6
0.5
Budget                             Millions 0.4
The project forecast is within the increased, approved budget and       0.3
0.16
authorization.                                          Dollars in  0.2
0.1          0.00
Change Order                           0
Initial   Change   Spent
Current Quarter   Project Total                   Orders
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Delayed completion is anticipated to have little impact on the
effectiveness of the new wayfinding walls. The Port and the
contractor are printing large scale temporary paper and foam core
"panels" that will remain on the new walls until work is complete.
Budget Transfers
None at this time.
AIRPORT
Port of Seattle 2Q 2014 Report  39

SECOND QUARTER REPORT, 2014
Doug Fox Lot Service Upgrades           Project Status:
Schedule: Delayed Schedule
Budget: On or under
Project:   C800451    Construct a new drainage system,     Status Reset: Click here to
Budget: $6,453,000   asphalt resurfacing, improved lot     enter a date.
Phase: Construction   lighting, new building, and road signage  (Commission Construction Auth.)
to improve lot appearance, function,
Start: 2/1/2012
and revenue generation.
Schedule Completion:
9/30/2014                                  Budget/Costs Incurred
7    6.45      6.45
6
Millions  5
Significant Developments
4
2.82
Overall project construction is approximately 69% complete. New lot    3
lighting system is operational. Phased lot paving and striping is in     Dollars in  2
progress. State Labor and Industries gave approval for final off-site     1
fabrication by vendor and delivery of the new modular office building.     0
Authorized  Forecasted Costs Incurred
Schedule
Contract project beneficial occupancy date is September 30, 2014.
Construction Costs
This date will be delayed by several weeks due to the time required
to receive State L&I approval of the modular building. Fabrication,       5           4.54
delivery, and installation of the building is the critical path for project          3.99
4
completion.                                        Millions  3
Budget                              2
The project forecast is within the approved budget and authorization.    Dollars in   1
0.10
0
Change Order                             Initial Change Spent
Orders
Current Quarter   Project Total
Number of COs    3          11
Amount of COs    -$16,149     $104,450            Photo
Justification for COs: Changes are primarily related to additional
removal and replacement of existing asphalt in poor condition, and
unforeseen conditions related to construction of sewer and electric
utilities.



40  Port of Seattle 2Q 2014 Report

Risks
Additional delays in fabrication, delivery, installation, and final site inspection of the modular building,
which are the project critical path, will delay project completion. Wet weather conditons may delay
asphalt paving and striping.
Budget Transfers
None











AIRPORT

Port of Seattle 2Q 2014 Report  41

SECOND QUARTER REPORT, 2014
Industrial Waste Treatment Plant (IWTP) Fiber
Installation
Project Status:
Install new Single Mode Fiber cable  Schedule: Delayed Schedule
Project:   C800461      from Main Terminal to IWTP and    Budget: On or under
Gate E-45.
Budget: $514,000                          Status Reset: Click here to
Phase: Construction                        enter a date.
Start: 3/1/2012                                   (Commission Construction Auth.)
Schedule Completion: 10/30/2014
Budget/Costs Incurred
Significant Developments
0.6
Construction is stopped until the summer construction season (July-         0.51     0.51
September). Fiber Optic Cable has been installed from the Main      0.5
Terminal to the new equipment termination cabinet near the Alaska    Millions 0.4
Hangar and Gate E-45. Due to a change in FAA Policy/Personnel,     0.3
0.21
the original FAA controled conduit to complete the project was        0.2
deemed full and permisison to use it was denied. An alternate route    Dollars in 
0.1
was designed and accepted by the FAA.                     0
Authorized   Forecasted  Costs Incurred
Schedule
The remaining construction work is scheduled for completion in
September 2014.                               Construction Costs
Not Applicable
Budget
Forecast is currently within the approved budget and authorization.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Additional schedule delays due to physical constraints, the work is to
be completed during the dry summer months. The new route
requires trenching within the Aircraft Active Movement Area and is
subject to strict operational guidelines and requirements.
Budget Transfers
None this quarter.
AIRPORT
42  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Fiber Infrastructure to Gate Backstands
Extend airport provided            Project Status:
Project:   C800464
communications infrastructure and wifi  Schedule: Delayed
Budget: $3,284,000    antennas to additional gates on     Budget: On or under
Phase: Design       Concourses A, B and C.         Status Reset: Click here to
Start: 7/9/2013                                   enter a date.
Schedule Completion: 10/31/2015                 (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
The Concourse C scope and budget was removed from this project.
3.5                   3.28
It will be now under the Terminal Wide Wi-Fi project. Project budget
3
was reduced by $955,000 to a total of $2,329,000.
2.5     Millions
2
Schedule                            Dollars in 
1.5
Project schedule delayed due to a delay in Wi-Fi audit. The project      1   0.79
sponsors agree that the project should not proceed until completion      0.5                0.17
of the Wi-Fi audit. Wi-Fi audit complete and 90% design is             0
Authorized       Forecasted      Costs Incurred
underway.
Budget
Construction Costs
The project forecast is within the approved budget. Commission     Not Applicable
Authorization for construction funding and authority to advertise for
construction will be requested when the bid documents are
completed.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None
Budget Transfers
None

AIRPORT
Port of Seattle 2Q 2014 Report  43

SECOND QUARTER REPORT, 2014
Airport Signage (Airline Realignment)
Project Status:
Project:   C800474      Provide airport directional signage   Schedule: Delayed
Budget: $646,000       for the airline realignment program.  Budget: On or under
Phase: Close Out                          Status Reset: 06/04/2012
Start: 06/01/2011                                 (Commission Construction Auth.)
Schedule Completion: 06/30/2013
Budget/Costs Incurred
Significant Developments
0.7     0.65       0.65
Project complete. This will be the last Quarterly report.
0.6                         0.51
0.5
Schedule                            Millions 0.4
As previously reported, the change in schedule was based on the      0.3
overall Airline Realignment Program Schedule. Airline relocations     Dollars in  0.2
were delayed.                                     0.1
0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget.
Construction Costs
Change Order
Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

44  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Miscellaneous Building Improvements (Airline
Realignment)
Project Status:
Schedule: Within or ahead
Associated with UA Relocation the
Project:   C800475                             Budget: On or under
buildout of existing empty shelled
Budget: $2,172,000                         Status Reset: Click here to
space within Concourse A Ramp
Phase: Close Out                          enter a date.
space.
Start: 11/1/2011                                  (Commission Construction Auth.)
Schedule Completion: 7/31/2013
Significant Developments                    Budget/Costs Incurred
The project is complete and in closeout. This will be the last
5
Quarterly report.
3.82
4
Schedule                            Millions 3  2.66
1.95
Project was completed on schedule.                         2
Dollars in   1
Budget
0
Project forecast is within the approved budget and authorization.          Authorized  Forecasted Costs Incurred
Reimbursements to the United Airlines Group still remain.
Change Order                         Construction Costs
Current Quarter   Project Total          Not Applicable
Number of COs    0          55
Amount of COs    $0         $527,587
Justification for COs: For scope, unforeseen conditions and design
Risks
None identified at this time.
Budget Transfers



AIRPORT
Port of Seattle 2Q 2014 Report  45

SECOND QUARTER REPORT, 2014
Fire Station Electric Upgrades
Project Status:
Project:   C800479    Rreplace the existing 208V         Schedule: Delayed
Budget: $2,157,000.    transformer and 12.47 KV feeder, and  Budget: Forecast Overrun
Phase: Design       add a 500 KV generator and a      Status Reset: Click here to
Start: 4/1/2013         1000kVA transformer.            enter a date.
Schedule Completion: 6/30/2015                  (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Design is 100% complete. Will be combining project w/ C800234 in
2.5
July 2014.                                                    2.16
2
Schedule                            Millions 1.5
Commission to authorize bid/construction in July 2014. Substantial      1
completion scheduled for Q2 of 2015.                       Dollars in 0.5   0.27          0.17
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is $398,700 higher than the approved budget
due to increased electrical equipment costs. Authorization of
construction funding and authority to advertise for construction will
Construction Costs
be requested in July of 2014.
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Unplanned electrical shut downs could impact the project schedule.
Budget Transfers
Budget Transfer of $96,400 from C800404  Aeronautical Allowance
Budget Transfer of $422,300 from C800234  Feeder Taps 101


AIRPORT
46  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
New Window Wall Ticket Zone 1
Project Status:
Project:   C800490      Install new common use ticket
Schedule: Delayed Schedule
Budget: $4,810,000     counters and new baggage system
Budget: On or under
Phase: Close Out      along the window wall and
Status Reset: 5/13/2014
baggage system renovation.
Start: 7/1/2012                                   (Commission Construction Auth.)
Schedule Completion: 2/17/2014
Budget/Costs Incurred
Significant Developments                     6
4.81      4.81
Project is complete and in use. This will be the last Quarterly report.     5
Millions  4                        3.30
3
Dollars in 
Schedule
2
The project schedule was delayed due to unforeseen structural and
1
design issues.
0
Authorized  Forecasted Costs Incurred
Budget
Additional funding was approved by the Commision on May 13,
2014.                                       Construction Costs
Change Order                           4 3.43
Current Quarter   Project Total              3
Number of COs    0          20                 Millions           2.20
Amount of COs    $0         $178,215.61             2
Dollars in    1
Justification for COs: Due to the accelerated nature of the project, a              0.18
number of design issues required addressing during construction.        0
Initial   Change   Spent
Orders
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 2Q 2014 Report  47

SECOND QUARTER REPORT, 2014
Facility Monitoring System Renewal
Project Status:
Project:   C800495     Provide a system upgrade that will
Schedule: Delayed
Budget: $3,420,180     allow the system to maintain and
expand monitoring of critical systems   Budget: On or under
Phase: Construction
such as elevators, escalators, moving   Status Reset: 12/10/2013
Start: 1/22/2013
Schedule Completion:   walks, passenger boarding bridges    (Commission Construction Auth.)
and baggage systems.
8/31/2015
Budget/Costs Incurred
Significant Developments
4
3.42       3.42
The FMS network upgrade and Baggage Reporting Software will be
completed next quarter. The major construction work will be          3
Millions
advertised next quarter.
2
0.99
Schedule                            Dollars in  1
As previously reported, the project is currently behind schedule.
0
Further design changes were required after initial submittal to the         Authorized  Forecasted Costs Incurred
Building Department per Sponsor's request.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
Transfer of $2500 to C800555 NS Refurbish Baggage Systems

AIRPORT
48  Port of Seattle 2Q 2014 Report

Airportwide Mechanical Controls System      SECOND QUARTER REPORT, 2014
Project Scope and description:
Project:   C800497       Upgrade the HVAC Controls     Project Status:
Budget: $2,157,000.      System for the Airport. This    Schedule: Delayed
Phase: Design         includes adding a wireless     Budget: On or under
Start: 5/1/2013            connection to the Logistics area to  Status Reset: Click here to
the south of the Airport.         enter a date.
Schedule Completion:
(Commission Construction Auth.)
4/30/2015
Significant Developments                    Budget/Costs Incurred
Completed 90% design; however, scope was added after we were      3
informed that replacement parts for existing control panels will no                  2.43
2.5
longer be available in 2015.
2
1.5
Schedule                            in Millions
1                    0.70
100% design is on hold waiting for the next MII ballot and            Dollars      0.35
0.5
Commission authorization to increase budget and authorize bidding.
0
Plan to request Commission authorization in Q3 of 2014.               Authorized  Forecasted Costs Incurred
Budget
The budget will increase to $3,500,000 with the added scope. The    Construction Costs
increase will be presented at the August MII meeting first and then to  Not Applicable
Commission.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Unplanned electrical shut downs could impact the project schedule.
Increased control component costs. An allowance was added to the
estimate.
Budget Transfers
None this quarter.

AIRPORT
Port of Seattle 2Q 2014 Report  49

SECOND QUARTER REPORT, 2014
RAC Baggage Claim Renovation
Project:   C800541      Renovation of both rental car      Project Status:
Budget: $1,318,200      counter locations in baggage claim  Schedule: Delayed Schedule
Phase: Closeout       into new waiting areas with vending  Budget: On or under
Start: 10/1/2012          machines and other facilities for     Status Reset: 4/2/2013
Schedule Completion:    special operations           (Commission Construction Auth.)
12/31/2013
Budget/Costs Incurred
Significant Developments
1.5
Five change orders were completed this quarter and the project is          1.32    1.32
1.09
now in closeout.
Millions  1
Schedule
0.5
Beneficial Occupancy occurred on January 24, 2014, one month      Dollars in 
later than originally intended. The project is now in closeout.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
0.7              0.62
Current Quarter   Project Total
0.6
Number of COs    5          12
Amount of COs    $3,025       $62,052              Millions 0.50.4
0.30
0.3     0.26
Justification for COs: Errors and omissions - approximately $500;      Dollars in 0.2
changed site conditions - $900; scope changes - $300; and          0.1
regulatory requirements - $1,300.                            0
Initial    Change Order    Spent
Risks
Only a minor risk remains - the restoration of the master clock       Photo
system in Baggage Claim. We anticipate that this can be addressed
within the approved budget and authorization.
Budget Transfers
None this quarter.

AIRPORT
50  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Replace PLBs at S7, S9 & B4
Project Status:
Project:   C800543      Replace the Passenger Loading    Schedule: Within or ahead
Budget: $2,950,000      Bridges at S7 & S9 and install a    Budget: On or under
Phase: Construction     new bridge At B4           Status Reset: 1/21/2014
Start: 1/21/2014                                  (Commission Construction Auth.)
Schedule Completion:
12/31/2014
Budget/Costs Incurred
Significant Developments
3.5
B4 and S7 are in use. S9 will be installed in October 2014.               2.95    2.95
3
2.5
Schedule                            Millions 2
B-4 and S-7 were available for operations on June 1, 2014. S7 is      1.5
scheduled for installation in the 3rd Quarter.                      Dollars in  1
0.48
0.5
0
Budget
Authorized  Forecasted Costs Incurred
No issues
Change Order                         Construction Costs
Current Quarter   Project Total          Not Applicable
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Schedule risk for installation of B-4 and S-7 were mitigated and
installation occurred on time.
Budget Transfers
None


AIRPORT

Port of Seattle 2Q 2014 Report  51

SECOND QUARTER REPORT, 2014
NorthSTAR Program
Project Status:
Project:   C800544   Includes programmatic project
Schedule: Delayed
management and project controls costs
Budget: $15,400,000                         Budget: On or under
for the NorthSTAR program, consisting
Phase: Design                            Status Reset: Click here to
of 5 capital projects that represents a
Start: 4/5/2012                                   enter a date.
unique partnership between the Port
Schedule Completion:                        (Commission Construction Auth.)
and Alaska Airlines.
8/27/2020
Budget/Costs Incurred
Significant Developments
20
Accomplished transition of AAG program to lead, Greg Smith.
15.40
Completed NSAT expansion Commission Briefing July 2014.        15
MillionsDollars in 
Schedule                             10
Prepare 2nd Qtr NorthSTAR Program Commission Update for August    5   3.60
2.34
presentation. Continue programmatic linkage coordination reviews to
assure airport-wide gate availability is not compromised during         0
Authorized  Forecasted Costs Incurred
construction.
Budget
Construction Costs
The project forecast is within the approved budget.              Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Communication and coordination across multiple teams and
stakeholders along with identification/monitoring of all "linked"
Capital projects outside of NorthSTAR.
Budget Transfers
None

AIRPORT
52  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
NorthSTAR Main Terminal Improvements
Project Status:
Project:   C800545    Renovate the North Main Terminal     Schedule: Delayed
Budget: $29,200,000   security checkpoint, curbside and     Budget: On or under
Phase: Design      ticketing lobby areas incorporate self-   Status Reset: Click here to
Start: 12/3/2013       operated technologies and improve     enter a date.
Schedule Completion:  aesthetics.                 (Commission Construction Auth.)
9/18/2018
Budget/Costs Incurred
Significant Developments
40
Selected Landrum & Brown for the Facility Determination Analysis.
29.20
Scope to address space requirements and preliminary configurations    30
for the north security checkpoint and ticket lobby/curbside uses.       Millions
20
Completed rate analysis and level of effort negotiations are
underway.                                    Dollars in  10
1.50               0.07
0
Schedule                              Authorized Forecasted Costs Incurred
Schedule has been re-baselined to reflect approach of conducting
facility determination analysis prior to project notebook/design
phases. Anticipate project notebook submittal Q1 2016.           Construction Costs
Not Applicable
Budget
Project forecast is within the approved budget. Commission
Authorization for construction funding and authority to advertise for
construction is anticipated Q1 2017 when the bid documents are
completed.
Change Order
Current Quarter   Project Total
Number of COs    n/a         n/a
Amount of COs    n/a         n/a
Justification for COs: n/a
Risks
Project scope definiton could increase scope and budget.
Budget Transfers
None
AIRPORT
Port of Seattle 2Q 2014 Report  53

SECOND QUARTER REPORT, 2014
NorthSTAR Concourse C Vertical Circulation
Construct exterior, weather protected    Project Status:
Project:   C800547
sloped walkways with elevators at      Schedule: Within or ahead
Budget: $18,600,000   Gates C2/4, C10/12, and C14 to     Budget: On or under
Phase: Construction   provide enhanced access from      Status Reset: 10/22/2013
Start: 11/6/2012       concourse to aircraft ramp for        (Commission Construction Auth.)
Schedule Completion:  Alaska/Horizon regional operations.
4/17/2015
Budget/Costs Incurred
Significant Developments
20    18.60     18.60
Forma Construction Co. has begun activity at C2, C10 & C16.
15
Underground grease interceptor piping scope and funds were        Millions
transferred into the project to minimize distruptions to airline. EGSE     10
chargers removed from C2 and relocation design at 90%.
Dollars in   5                        2.84
Schedule                             0
Authorized  Forecasted Costs Incurred
The project schedule was re-baselined after receipt and acceptance
of Forma construction schedule. The project is currently within 2
weeks of the original March 2015 completion date. Coordination with
Construction Costs
AAG construction on their adjacent ground level walkways is ongoing
to minimize impact on AS/QX operations.
10   8.72
Budget                              8
The project forecast is within the approved budget and authorization.      6   Millions
4
Change Order                          Dollars in  2
0.51
0.00
Current Quarter   Project Total              0
Number of COs    1          n/a                    Initial Change Spent
Orders
Amount of COs    n/a         n/a
Justification for COs: n/a
Risks
Potential for underground utility conflicts during construction.
Budget Transfers
$75,000 for underground grease interceptor piping

AIRPORT
54  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Concourse D Roof Replacement
Project Status:
Project:   C800550     Remove and replace the roofing     Schedule: Within or ahead
Budget: $3,371,800    systems on Concourse D of the     Budget: On or under
Airport; install ladders, stairs and
Phase: Design                            Status Reset: Click here to
fall protection on the penthouse
Start: 7/1/2013                                   enter a date.
sections; and make repairs and
Schedule Completion:                        (Commission Construction Auth.)
where required, replacements to
10/31/2014           the Kal Wall window system.
Budget/Costs Incurred
Significant Developments
4
Roofing scheduled to be complete on time. Window resurfacing will         3.37     3.37
3.5
be complete by mid-August. Complete window replacements in
3
September as scheduled.                            MillionsDollars in 
2.5
2
Schedule                             1.5
1
This project is currently on schedule.                           0.5                 0.12
0
Authorized       Forecasted      Costs Incurred
Budget
The project forecast is within the approved budget.
Change Order                         Construction Costs
Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Stair manufacturing takes longer than anticipated. Additional
windows require replacement.
Budget Transfers
None at this time.


AIRPORT
Port of Seattle 2Q 2014 Report  55

SECOND QUARTER REPORT, 2014
Grease Interceptor Augmentation
Project Status:
Project:   C800551     Install two underground 9,000 gallon   Schedule: Delayed
Budget: $1,484,200.    grease interceptors to service the    Budget: On or under
Phase: Permitting     Concourse C and South Satellite.    Status Reset: Click here to
Start: 5/1/2013                                   enter a date.
Schedule Completion: 3/6/2015                   (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Design flaw discovered prior to bid. Grease Interceptor at S.
2
Satellite location is being revised. It is currently under review by
1.48      1.48
Ops.
1.5
Millions
Schedule                             1
0.50
Design revision has caused project schedule to slip.               Dollars in 0.5
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Construction impacts Delta Operations at S. Satellite.
Budget Transfers
$75,000 transferred to C800547 Concourse C Vertical Circulation on
June 6, 2014.


AIRPORT
56  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
NorthSTAR Refurbish Baggage Systems
Project Status:
Project:   C800555    Refurbish existing baggage systems   Schedule: Within or ahead
Budget: $21,502,500    in support of AAG operation at North   Budget: On or under
Phase: Construction   Satellite and Concourse D. The work  Status Reset: 9/24/2013
will extend the service life of part of
Start: 11/6/2012                                  (Commission Construction Auth.)
the C92 systems, C88 North Satellite
Schedule Completion:
systems, and C88 tunnel systems.
5/15/2015
Budget/Costs Incurred
Significant Developments                     25  21.50   21.50
Advertised, awarded and executed construction contract. NTP        20
issued June 2014. Central Equipment Room power is under        Millions 15
construction.
10
Dollars in   5
Schedule                                        1.19
0
Began resolution of Motor Control Panel issue. Beneficial              Authorized  Forecasted Costs Incurred
Occupancy May 15, 2015.
Budget                            Construction Costs
The project forecast is within the approved budget.              Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Motor Control Panel room may need relocation to avoid future
conflicts with seismic improvements. NSAT expansion decision may
impact system refurbishment requirements.
Budget Transfers
$2,500 scope/funds transferred in for permanent power for baggage
controls and FMS in central equipment room

AIRPORT
Port of Seattle 2Q 2014 Report  57

SECOND QUARTER REPORT, 2014
NorthSTAR North Satellite Renovation and
NSTS Lobbies
Project Status:
Project:   C800556     Renovation of the North Satellite     Schedule: Delayed
Budget: $399,732,944   (NSAT) terminal, including North    Budget: On or under
Phase: Design       Satellite Transit System (STS)     Status Reset: Click here to
Start: 7/24/2012        stations "refresh", ramp level,       enter a date.
Concourse level, and new rooftop    (Commission Construction Auth.)
Schedule Completion:
airline lounge.
2/13/2020
Budget/Costs Incurred
Significant Developments
Received Commission approval of NSAT expansion to 20 gates,
vertical circulation to facilitate dual door aircraft boarding/deplaning     500
and use of GC/CM alternative public works contracting methodology    Millions          399.73
400
on August 5th. Began 30% design review process. Completed
analysis of STS North Loop passenger capacity validating that        300
system can handle NSAT facility expansion. Completed analysis of    Dollars in 200
future NSAT baggage system capacity.
100    32.99
5.44
Schedule                             0
Authorized  Forecasted Costs Incurred
Thirty percent design and cost estimate reviews in process
culminating with AAG concurrence of scope and budget on        Construction Costs
September 30th. Continue preparation of acquisition documents for   Not Applicable
GC/CM and finalize sustainability analysis for presentation to
Port/AAG Steering Committees.
Budget
Commission has authorized $48,714,800 to date for design, testing
and inspection, safety services, procurement support, gate planning
and utilization analysis and advertise for GC/CM contractor. Total
project cost approved by the Commission is $405,532,944 inclusive
of $5,800,000 RMM expense funds.
Change Order
Current Quarter   Project Total
Number of COs   0          0
Amount of COs   $0         $0
Justification for COs: n/a

58  Port of Seattle 2Q 2014 Report

Risks
Existing baggage system capacity and NSAT mechanical and electrical infrastructure may not be
adequate for NSAT expansion.
Budget Transfers
None












AIRPORT
Port of Seattle 2Q 2014 Report  59

SECOND QUARTER REPORT, 2014
Snow Blower and Deicer Trucks
Project Status:
Project:   C800557      Purchase 1 Deicer Truck and      Schedule: Within or ahead
Budget: $2,200,000      2 Snow Blower Trucks        Budget: Choose an item
Status Reset: Click here to
Phase: Implementation
enter a date.
Start: 4/4/2014
(Commission Construction Auth.)
Schedule Completion: Deicer - 1/30/2015
Snow Blowers  1/30/2016
Budget/Costs Incurred
Significant Developments
2.5     2.20       2.20
Project split out:
2
(1) Deicer Truck Project #105068 to be purchased in 2014, and
(2) Snow Blower Trucks both to be purchased in 2015.             Millions 1.5
1
Schedule                            Dollars in 0.5
0.00
Not Applicable                                       0
Authorized  Forecasted Costs Incurred
Budget
$400,000 - 2014
$1,800,000 - 2015                                 Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
None
Budget Transfers
None


AIRPORT
60  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Main Terminal Mezzanine Tenant Relocations
Project Status:
Project:   C800560    Construct new tenant leased spaces in  Schedule: Within or ahead
Budget: $2,025,000    order to move existing tenants and    Budget: On or under
Phase: Construction   provide new leasable office space for  Status Reset: 11/19/2013
Start: 3/26/2013        airlines on the mezzanine of the main   (Commission Construction Auth.)
Schedule Completion:   terminal.
3/30/2015
Budget/Costs Incurred
2.5
Significant Developments                        2.03   2.03
2
Received five good bids, the contract was awarded to low bidder      Millions 1.5
Regency NW Construction Inc. on August 4, 2014.
Dollars in 
1
Schedule                             0.5          0.30
On schedule                                     0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None at this time.



AIRPORT
Port of Seattle 2Q 2014 Report  61

SECOND QUARTER REPORT, 2014
Known Crewmember Employee Bypass
Project Status:
Construct new Known          Schedule: Delayed Schedule
Project:   C800576      Crewmember Bypass and        Budget: Forecast Overrun
Budget: $650,000       Employee Bypass locations at the   Status Reset: 12/11/2012
Airport.
Phase: Construction                        (Commission Construction Auth.)
Start: 12/11/2012
Schedule Completion: 10/31/2014
Budget/Costs Incurred
0.65      0.65
Significant Developments                     0.7
0.6
New Portal vendor for the Employee Bypass will start fabrication
0.5                        0.45
August 11, 2014.                                    Millions 0.4
0.3
Schedule                            Dollars in 0.2
0.1
Schedule delayed on delivery of portals to end of October pushing
0
the schedule out to November 2014.
Authorized  Forecasted Costs Incurred
Budget
The project forecast is beyond the approved budget and          Construction Costs
authorization due to several changes, mainly the need to procure a   Not Applicable
new portal vendor after the original vendor went bankrupt before
delivery of the portals.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Budget forecast overrun due to changes in locations and in portal
vendors.
Budget Transfers
None this quarter.

AIRPORT
62  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Parking Garage Lights (CA)
Use current technology to replace all   Project Status:
Project:   C800581     normal lighting in the Airport Parking   Schedule: Within or ahead
Budget: $6,235,700     Garage on all 8 floors and in the    Budget: On or under
helices. This will reduce energy      Status Reset: Click here to
Phase: Design
Start: 1/31/2014        consumption over 60%.           enter a date.
(Commission Construction Auth.)
Schedule Completion: 12/31/2019
Significant Developments                    Budget/Costs Incurred
Received Commission Authorization for Design.
7            6.24
6
Schedule
Millions  5
The project is on schedule.                                4
3
Budget                            Dollars in  2  1.28
1
The project forecast is within the approved budget and authorization.                     0.10
0
Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total
Number of COs    0                          Construction Costs
Amount of COs    $0                          None at this time
Justification for COs:
Risks
No risks at this time.
Budget Transfers
None



AIRPORT

Port of Seattle 2Q 2014 Report  63

SECOND QUARTER REPORT, 2014
International Arrivals Facility (IAF)
Project Status:
Project:   C800583    Planning, Design, Construction of new  Schedule: Within or ahead
Budget: $344,000,000   Federal Inspection Services (FIS)    Budget: On or under
Phase: Planning     facility, including connector between   Status Reset: Click here to
Start: 6/25/2013        South Satellite and FIS and sterile     enter a date.
Schedule Completion:   corridors and walkways within      (Commission Construction Auth.)
Concourse A.
6/30/2018
Significant Developments                    Budget/Costs Incurred
Planning and Repogramming effort completed. Preparing project for
400
344.00
turnover to AVPMG to refine scope, schedule and budget. Advancing    350
RFQ for issue in Q3 2014.
Millions  300
250
Schedule                             200
Dollars in   150
The project is currently on schedule.                          100
50      8.50                    1.69
Budget                              0
Authorized      Forecasted     Costs Incurred
The project forecast indicates a budget increase may be required.
Change Order                         Construction Costs
Current Quarter   Project Total          Not Applicable
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Additional technical analysis of the South Satellite to Concourse A
connector will delay bridge or tunnel decision and advertisement of
RFP. Program budget may increase due to new scope being added
to the IAF, such as airline relocations.
Budget Transfers
None this quarter.


AIRPORT
64  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Security Exit Lane Breach Control-Phase 2
Project:   C800605    This project will procure and install new  Project Status:
automated breach control equipment at   Schedule: Delayed
Budget: $6,407,000
four security exits in the airport terminal.  Budget: On or under
Phase: Construction                        Status Reset: 9/10/2013
Start: 10/1/2012                                  (Commission Construction Auth.)
Schedule Completion: 11/30/2014

Significant Developments                    Budget/Costs Incurred
The construction contract was terminated by convenience by the
7    6.41     6.41
Port and the project suspended due to an inability to reach a funding     6
agreement with TSA.
Millions  5
4
Schedule                             3          2.35
2
The project has been suspended by the Port.                   Dollars in  1
0
Budget                               Authorized Forecasted Costs Incurred
Project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Current Quarter   Project Total
2
Number of COs    0          0                     1.76
Amount of COs    $0         $0
Millions  1.5
Justification for COs: n/a                                     1
Dollars in   0.5
Risks
0   0.074909
The project could resume if a funding agreement can be reached        0
Initial   Change   Spent
with TSA.
Orders
Budget Transfers
None this quarter.


AIRPORT
Port of Seattle 2Q 2014 Report  65

SECOND QUARTER REPORT, 2014
North Satellite - STS Ceiling Leak Repair
Eliminate ceiling leaks at the North   Project Status:
Project:   C800609
Satellite (NSAT) that occur        Schedule: Delayed
Budget: $1,750,000      between the satellite transit station  Budget: On or under
Phase: Design         (STS) and the elevators.       Status Reset: Click here to
Start: 5/1/2013                                   enter a date.
Schedule Completion: 10/4/2015                  (Commission Construction Auth.)
Significant Developments
Budget/Costs Incurred
The project was advertised and received a single, irregular bid. The
project will be re-advertised next year.                           2   1.75     1.75
1.5
Schedule                            Millions
The project construction schedule has been delayed by one year.       1
Dollars in 0.5                        0.20
Budget
0
The project forecast is within the approved budget. Commission
Authorized  Forecasted Costs Incurred
Authorized funding for construction and authority to advertise on
April 1, 2014.
Change Order                         Construction Costs
Not Applicable
Current Quarter   Project Total
Number of COs    0          0                Photo
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Single high bid was previously received and that could occur again.
Need driest time of the year for construction.
Budget Transfers
None this quarter.


AIRPORT
66  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT,
Checked Baggage Recapitalization/Optimization
Project:   C800612    TSA approached the Airport in 2012    Project Status:
Budget: $317,000,000   with plan to replace all federally owned  Schedule: Within or ahead
Phase: Design      and operated baggage scanning     Budget: On or under
Start: 2/26/2013       equipment, known as Explosive       Status Reset: Click here to
Schedule Completion:  Detection System (EDS) equipment.   enter a date.
The EDS equipment is approaching
12/31/2024                                 (Commission Construction Auth.)
the end of its life.
Significant Developments                    Budget/Costs Incurred
Design work continues to progress towards 70% design. The team is
25
looking to have the 70% design complete by 2ndquarter 2015. The         19.85
project team continues to define project phasing for the overall ten-      20
year program. We are evaluating and refining overall global project      15
schedule. The team is coordinating with all other programs within the     Millions
10
capital program.                                      Dollars in
5                    3.10
0.32
Schedule
0
The project is currently on schedule. Overall schedule will be refined        Authorized  Forecasted Costs Incurred
to reflect a ten-year program.
Budget                            Construction Costs
The project forecast is within the approved budget. Commission     Not Applicable
Authorization for construction funding and authority to advertise for
construction will be requested when the bid documents are
completed.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter
AIRPORT
Port of Seattle 2Q 2014 Report  67

SECOND QUARTER REPORT, 2014
Second Floor Mezzanine Infrastructure Upgrade
Project:   C800615    Upgrade and extend the infrastructure  Project Status:
(HVAC, Communications, Electrical,
Budget: $2,545,000                         Schedule: Delayed Schedule
Plumbing, WiFi) to 14,000sq ft of future  Budget: On or under
Phase: Construction
lease space on the 2nd floor, including  Status Reset: Click here to
Start: 8/1/2013         7,000 sq ft for a new USO.          enter a date.
Schedule Completion:                        (Commission Construction Auth.)
2/13/2015
Significant Developments                    Budget/Costs Incurred
A contract was executed with Regency NW Construction Inc. on
3
2.55      2.55
August 5, 2014. NTP is expected by October 3, 2014.
2.5
Schedule                            Millions 2
1.5
Current project is to complete construction in February 2015.          1
The delay is due to design challenges existing from the second floor    Dollars in                  0.47
0.5
to meet egress code requirements and to determine the routing of
0
the infrastructure, primarily HVAC.                               Authorized  Forecasted Costs Incurred
Budget
The forecast is within the approved budget and authorization..       Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
The risks are to ensure that the USO infrastructure and utility line up
with the Infrastructure project tie-ins.
Budget Transfers
None.

AIRPORT
68  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
2014-2015 Roof Replacement
Project Status:
Remove and replace the current
Project:   C800637                             Schedule: Within or ahead
roofing system on the Alaska Hangar
Budget: $4,785,000                         Budget: On or under
One and associated maintenance    Status Reset: Click here to
Phase: Design       building, the Air Cargo 6 facility, and  enter a date.
Start: 4/1/2014         the former United Cargo Building.     (Commission Construction Auth.)
Schedule Completion:
10/31/2015
Budget/Costs Incurred
Significant Developments
6
Commission authorized design on June 10, 2014.                         4.79
5
4
Schedule
3
Millions
Project is currently on schedule.
Dollars in   2
1    0.45
Budget                                        0.21
0
Project forecast is within the approved budget.                      Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                None at this time
Amount of COs    $0         $0
Justification for COs: N/A
Risks
No risks identified at this time.
Budget Transfers
None at this time.



AIRPORT

Port of Seattle 2Q 2014 Report  69

SECOND QUARTER REPORT, 2014
Town & Country Stormwater Pipe
Project Status:
Project:   C800651      Stormwater Pipe             Schedule: Within or ahead
Budget: $350,000                          Budget: On or under
Phase: Construction                        Status Reset: 9/3/2014
Start: 1/1/2014                                   (Commission Construction Auth.)
Schedule Completion: 9/30/2014
Budget/Costs Incurred
Significant Developments
Pipe is now installed but several pipe joints need repair kits to enable    0.4   0.35     0.35
passage of pressure test.
0.3
Schedule                            Millions           0.19078
0.2
On schedule
Dollars in 0.1
Budget
0
Project is within budget and forecast.                             Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total          Construction Costs
Number of COs    0          0                Not Applicable
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Further pressure testing setbacks or delays in procuring or installing
repair kits may cause budget or schedule overruns
Budget Transfers
None



AIRPORT
70  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
North Utlity Tunnel Steam Pipe
Project Status:
Project:   C800659      Replace 45 year old steam piping   Schedule: Within or ahead
Budget: $1,250,000      expansion joints in the North Utility  Budget: On or under
Phase: Construction     Tunnel.                Status Reset: Click here to
Start: 3/18/2014                                  enter a date.
Schedule Completion: 10/8/2014                  (Commission Construction Auth.)
Significant Developments
Project was out to bid on May 22, 2014. NTP issued July 23, 2014   Budget/Costs Incurred
and construction is underway.
1.4     1.25       1.25
1.2
Schedule
1
Project is on schedule to complete October 8, 2014.               Millions 0.8
Dollars in 
0.6
Budget                             0.4
0.12
0.2
Currently on budget.
0
Authorized  Forecasted Costs Incurred
Change Order
Current Quarter   Project Total
Number of COs    0          0                Construction Costs
Amount of COs    $0         $0
Justification for COs: N/A
Risks
None
Budget Transfers
None




AIRPORT
Port of Seattle 2Q 2014 Report  71

SECOND QUARTER REPORT, 2014
Automated Passport Control
Install fourteen (14) Automated     Project Status:
Project:   C800667
Passport Control (APC) kiosks in    Schedule: Within or ahead
Budget: $2,207,000      the existing FIS at the South     Budget: On or under
Phase: Construction     Satellite.               Status Reset: Click here to
Start: 10/31/2013                                 enter a date.
Schedule Completion: 12/31/2013                 (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
Project is in close out. PCS is completing a few remaining            2.5   2.21     2.21
adjustments to the queuing stanchions.
2
Schedule                            Millions 1.5           1.16
Currently on schedule for close out.                           1
Dollars in  0.5
Budget
0
Project forecast is currently under budget due to the                  Authorized  Forecasted Costs Incurred
acceleration.Commission Authorized construction on November 8,
2013.
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT
72  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Highline School Noise Insulation
Project Status:
Project:   C200007      Highline School Insulation        Schedule: Delayed
Budget: $101,797,000    Agreement will provide funding for  Budget: On or under
Phase: Construction     sound mitigation for 15 schools that  Status Reset: Click here to
Start: 3/23/1999          are impacted by aircraft noise from   enter a date.
Schedule Completion:    Sea-Tac Airport.            (Commission Construction Auth.)
11/30/2021

Significant Developments                    Budget/Costs Incurred
Port funds authorized for availability when the FAA, the State of       120
102.14     101.80
Washington, and the Highline School District provide matching
100
funds.
80
60                    52.04
Schedule                            in Millions
40
The schedule for state funds is unknown. The district's schedule is    Dollars 
20
dependent on obtaining general election bonds at various intervals.
0
FAA grant received for Olympic Elementary. Construction may          Authorized  Forecasted Costs Incurred
resume in 2015, if a voter approval bond is secured in the Fall of
2014.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Project delayed due to funding issues with the Highline School
District. There is a risk if no bonds are passed in the general
election. There is a risk if FAA Airport Improvement Program (AIP)
Grant funding is not available.
Budget Transfers
None this quarter
AIRPORT
Port of Seattle 2Q 2014 Report  73

SECOND QUARTER REPORT, 2014
Highline Community College Noise Insulation
Project Status:
Project:   C200042      Highline Community College      Schedule: Within or ahead
Budget: $32,050,000     Insulation Agreement will provide   Budget: On or under
Phase: Construction     funding for up to 22 eligible      Status Reset: Click here to
Start: 1/11/2005          buildings that are impacted by      enter a date.
Schedule Completion:    aircraft noise from Sea-Tac Airport.  (Commission Construction Auth.)
12/31/2013
Significant Developments                    Budget/Costs Incurred
Fourteen of the original 22 eligible buildings have been sound         8.3
insulated by the college. The College sound insulation program has         8.19
8.2
been dependent on receiving funding from FAA grants. The FAA      Millions
notified the Port that the Highline Community College Campus is no    8.1
Dollars in 
longer located within the 65 DNL Noise Contour and therefore is not     8         7.97     7.96
eligible for any further grant funding. Without the FAA's approval and
7.9
funding the remainder of the college buildings cannot be sound
insulated.                                             7.8
Authorized   Forecasted  Costs Incurred
Schedule
The construction is complete on the last building (Building #4) and    Construction Costs
the Noise Office is working with FAA to Close Grant AIP 127. Once   Not Applicable
the FAA sends Final Grant Closure documents, the project will be
closed.
Budget
The project forecast is within the approved budget. No further
authorization is anticipated with this project.
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
The FAA will not allocate future grant funds to this project.
Budget Transfers
None at this time
AIRPORT
74  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Home Insulation Retrofit
Project Status:
Project:   C200048      This project includes storm window
Schedule: Within or ahead
Budget: $5,344,000      retrofit of previously insulated
Budget: On or under
Phase: Construction     homes.
Status Reset: Click here to
Start: 1/11/2005                                  enter a date.
Schedule Completion: 12/31/2015                 (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
The Port has identified eligible homes and notified homeowners of      6   5.34
their eligibility. The Port is continuing with storm window retrofit.
5
4.06
Project budget was reduced by $1,300,000 due to being unable to
identify additional eligible homes.                            Millions 4                 3.44
3
2
Schedule                            Dollars in 
1
The Port is reviewing other potential homes for eligibility. The project
0
has encountered additional delay due to non-responsive
Authorized   Forecasted  Costs Incurred
homeowners willing to participate in the program.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
The ability to accomplish the retrofit is dependent on homeowner's
schedules, and structural integrity of the home.
Budget Transfers
None at this time


AIRPORT
Port of Seattle 2Q 2014 Report  75

SECOND QUARTER REPORT, 2014
Single Family Home Sound Insulation
Project Status:
Project:   C200093      Sound insulate remaining homes    Schedule: Within or ahead
Budget: $13,747,395     that are within the 1998 65 decibel  Budget: On or under
Phase: Construction     day night level (DNL) noise      Status Reset: Click here to
Start: 3/27/2007          contour.                   enter a date.
Schedule Completion: 12/31/2015                 (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Forty-six homes are complete; and 35 homes are in the process of
15    13.75     13.75
receiving sound insulation.
Schedule                            Millions 10
Project is on schedule. Anticipate completion by 4th quarter 2015.                       4.46
5
Dollars in 
Budget
0
The project forecast is within approved budget and authorization to        Authorized  Forecasted Costs Incurred
complete all homes currently in progress.
Change Order                         Construction Costs
Current Quarter   Project Total
3.8
4
Number of COs    0          0
Amount of COs    $0         $0                  3
Millions                            1.78
Justification for COs:                                      2
Risks                                Dollars in  1
0
The ability to accomplish the insulation is dependent on the           0
Initial    Change Order    Spent
homeowner's schedules, willingness to sign an aviation easement,
obtain a subordination agreement from their lender, and structural
integrity of the home. If more eligible homes than anticipated are
identified in the future, then additional funding may be needed.
Budget Transfers
None this quarter


AIRPORT
76  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
RMU/Kiosk Concession Program
Design and fabrication of Retail        Project Status:
Project:   C800146
Merchandising Units (RMUs); power,    Schedule: Delayed
Budget: $879,146
communications, and data to RMU     Budget: On or under
Phase: Construction  locations; and install floor-mounted    Status Reset: Click here to
Start: 11/20/2007      receptacles for the utilities to allow easy  enter a date.
Schedule Completion:  connection points as well as flexibility for  (Commission Construction Auth.)
2/5/2014           future utilization.

Budget/Costs Incurred
Significant Developments
Communication boxes were installed in June. We are working with     1.4
1.21
the vendor to complete punchlist items.                       1.2
1             0.88
0.75
Schedule                             0.8
in Millions
0.6
Punchlist items are pending and tentatively scheduled for September
Dollars  0.4
16, 2014.
0.2
Budget                             0
Authorized   Forecasted  Costs Incurred
The project forecast is currently within the approved budget and
authorization.
Construction Costs
Change Order
Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
None at this time.
Budget Transfers
None this quarter.

AIRPORT

Port of Seattle 2Q 2014 Report  77

SECOND QUARTER REPORT, 2014
Burien Commercial Property Acquisition
Project Status:
Project:   C800150     Acquire commercial properties along  Schedule: Delayed
Budget: $2,703,616     Des Moines Memorial Drive, and    Budget: On or under
Phase: Implementation  vacate one street in the City of Burien  Status Reset: Click here to
Start: 5/31/2007        that is surrounded by Port-owned     enter a date.
Schedule Completion:   properties.                (Commission Construction Auth.)
3/31/2014
Budget/Costs Incurred
Significant Developments                        2.79
2.8
2.78
The remaining acquisition was the street vacation of 12th Place S. in
2.76
Burien, Washington, completed in the 2nd quarter. This CIP can be    2.74
2.71
closed                                         2.72         2.70
Millions
2.7
Schedule                            Dollars in 2.68
2.66
Acquisition was completed in the second quarter of 2014.           2.64
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget.              Construction
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
$300,000 reduction based on Q4 2013 cash flows


AIRPORT
78  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Tenant Reimbursement
Build-out of spaces for new and       Project Status:
Project:   C800154    existing tenants. If more than a "basic   Schedule: Within or ahead
Budget: $4,709,577    finish" condition space is built for the   Budget: On or under
Phase: Construction   tenant, the tenant is required to      Status Reset: Click here to
Start: 8/14/2007       reimburse the Port for the cost of the    enter a date.
Schedule Completion:  work beyond this "basic finish".      (Commission Construction Auth.)
TBD          Reimbursements allowed under the
guidelines in the "Tenant Reimb
Policy".                        Budget/Costs Incurred
5    4.69      4.71
Significant Developments                      4
Airport Management Services' office build-out on the ramp level of     Millions 3
Dollars in 
baggage claim in review. Anticipate payment in Q3 or Q4 2014.
2                     1.30
Schedule                             1
Schedules vary to meet the tenant's needs.                     0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 2Q 2014 Report  79

SECOND QUARTER REPORT, 2014
T-46 Lease Improvements
Project: C102554       Construct stormwater treatment     Project Status:
Budget: $8,000,000     system to comply with Ecology     Schedule: Within or ahead
Phase: Design        order. Terminal pavement overlay   Budget: On or under
Start: 4/12/2013         to fulfill lease obligation.          Status Reset: Click here to
Schedule Completion: 2020                     enter a date.
(Commission Construction Auth.)
Significant Developments
Executed construction contract with ICON Materials on April 28,     Budget/Costs Incurred
2014. Stormwater treatment vaults and manholes have been
10
installed for Basin 5 and 6. Sheetpile shoring removed.                  8      8
8
Schedule                            Millions 6
Installation of the three treatment vaults projected to be complete by     4
December 2014. The fourth treatment will be installed once       Dollars in                1.71
2
Washington State Department of Transportation (WSDOT) vacates
the lease area.                                        0
Authorized   Forecasted  Costs Incurred
Budget
$8,000,000 for Stormwater Treatment System. Currently within
budget.                                       Construction Costs
None at this time
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Construction impact on terminal operation due to unforeseen
condition.
Budget Transfers
Not Applicable

SEAPORT
80  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Street Vacations T5,18,105
Project Status:
Street vacation related real estate      Schedule: Delayed Schedule
Project: C102858,
C102875, E104366    negotiations and agreements --T5,    Budget: On or under
T18, and T105 (complete).          Status Reset: Click here to
Budget: $1,500,000                         enter a date.
Phase: Permitting                         (Commission Construction Auth.)
Start: 6/1/2010
Schedule Completion: 2014
Budget/Costs Incurred
1.55
Significant Developments                         1.5    1.5
1.5
Draft Easement and Utility transfer documents have been prepared    Millions 1.45
by the City and are under Port Legal Department review for Terminal
18 (T-18). Discussion and Title work has begun for Terminal 5.        1.4                1.378
Dollars in 1.35
Schedule
1.3
Current schedule has T-18 completed by the end of 2014 (City           Authorized  Forecasted Costs Incurred
Council action by end of March 2015) and T-5 by the end of 2015 or
early 2016.
Construction Costs
Budget                            Not Applicable
The budget has been revised for 2014 and beyond.             Photo
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Not applicable
Budget Transfers
Not applicable


SEAPORT
Port of Seattle 2Q 2014 Report  81

SECOND QUARTER REPORT, 2014
Pier 34 Mooring Dolphins
Project Status:
Project:   C800090      Replacement of four existing failed   Schedule: Within or ahead
Budget: $1,800,000      timber mooring dolphins with four   Budget: On or under
Phase: Design        new steel dolphin structures     Status Reset: Click here to
Start: 4/1/2014          located at Pier 34 at the head of    enter a date.
Schedule Completion:    the East waterway by March 2015   (Commission Construction Auth.)
for $1.8M
3/30/2015
Budget/Costs Incurred
Significant Developments                      2   1.8
1.611
Final design underway, permit notification submitted.
1.5
Millions
Schedule                             1
Design complete by August 2014.                        Dollars in  0.5
Construction complete by March 2015                                      0.055
0
Authorized   Forecasted  Costs Incurred
Budget
Project is within approved budget.
Construction Costs
Change Order                         None at this time
None this quarter
Risks
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Budget Transfers
None


SEAPORT
82  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
T-5 Berth Modernization
Improvements to support larger    Project Status:
Project: C800132      vessels at T5, including crane rail   Schedule:  within or ahead
Budget: $5,000,000    strengthening, berth deepening,   Budget:   on or under
Phase: Design      and electrical upgrades.       Status Reset: 6/3/2014
Start: 6/3/2014                                (Commission Construction Auth.)
Schedule Completion: 6/30/2018
Budget/Costs Incurred
Significant Developments
Commission authorization received on June 3, 2014 to begin         6
5 5
design and permitting.                                   5
4
Schedule
Millions
3
The team completed 15% level design and will be selecting and      Dollars in 
2
negotiating a consultant agreement to provide design support
1
0.257
services in Q3.
0
Authorized      Forecasted     Costs Incurred
Budget
Budget is currently $5,000,000, which will cover 30% level design
and initiation of environmental review and permit process.         Construction Costs
None at this time
Change Order
Current Quarter   Project Total         Photo
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
Scope of work is subject to change depending on tenant selection
and lease negotiation.
Budget Transfers
None



SEAPORT                          Port of Seattle 2Q 2014 Report  83

SECOND QUARTER REPORT, 2014
T91 Lighting Upgrade
Lighting upgrade at Terminal 91      Project Status:
Project: C800160
Schedule:  delayed
Budget: $1,035,000
Budget:   on or under
Phase: Construction                       Status Reset: 3/4/2014
Start: 6/23/2014                                 (Commission Construction Auth.)
Schedule Completion: 10/17/2014
Budget/Costs Incurred
Significant Developments
1.2
We are in the process of installing the fixtures and will soon be able         1.035    1.035
1
to demonsrate the improved lighting characteristics and begin
0.8
working with the controls to further improve performance.           Millions
0.6                         0.46
Schedule                            Dollars in 0.4
Installation began the week of August 4th and will continue through     0.2
September with controls and commissioning.                   0
Authorized   Forecasted  Costs Incurred
Budget
The project is anticipated to complete on budget.
Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    2          2
Amount of COs    ($23,000)     ($23,000)
Justification for COs: Resulting from coordination of fixture positions
and selected fixtures; fewer flood lights will be required and
mounting requirements have been simplified. The result is a net
reduction in the materials purchase of approximately -$23,000.
Risks
Because of a later start date, the work must be coordinated around
the cruise schedule and arrival of the Northern Fleet.
Budget Transfers
None


SEAPORT
84  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
P91 Fender System Upgrade
Project Status:
Project:   C800183      Upgrades to the vessel berths to    Schedule: Within or ahead
Budget: $5,700,000      better accommodate cruise ships   Budget: On or under
Phase: Construction     and serve the other industrial     Status Reset: 6/14/2011
Start: 1/31/2010          customers who utilize the berths    (Commission Construction Auth.)
Schedule Completion:    and adjacent dock/apron areas for
less than $5.7M.
6/1/2014
Budget/Costs Incurred
5.7
6
Significant Developments                                  4.83
5                 4.6
Camel barges fabricated and delivered for use during the 2014       Millions  4
cruise season. This will be the final project update.                3
Dollars in     2
Schedule                             1
0
All work complete.
Authorized      Forecasted     Costs Incurred
Budget
Project is within approved budget.                         Construction Costs
Change Order                           2.5
2.083              2.083
None this quarter                                        2
Millions
1.5
Dollars in 
Risks
1
Current Quarter   Project Total
0.5
Number of COs    0          0
Amount of COs    $0         $0                   0
Initial     Change     Spent
Orders
Justification for COs: n/a
Budget Transfers
None


SEAPORT

Port of Seattle 2Q 2014 Report  85

SECOND QUARTER REPORT, 2014
T-91, Bldg C175 Roof Replacement
Project Status:
Schedule: Within or ahead
Project:   C800430      Replace roof on the C175 building   Budget: On or under
Budget: $2,450,000      at Terminal 91.            Status Reset: 1/14/2014
Phase: Construction                        (Commission Construction Auth.)
Start: 7/26/2011
Schedule Completion: Q4 2014                  Budget/Costs Incurred
3
2.45
Significant Developments                     2.5       2.2
Construction is underway and is 75% complete. Project is          Millions 2
anticipated to be completed on schedule.                     1.5
1                    0.81
Schedule                            Dollars in 
0.5
Project remains on schedule for completion 2014.                 0
Authorized  Forecasted Costs Incurred
Budget
On budget
Construction Costs
Change Order
2
1.65
Current Quarter   Project Total
1.5
Number of COs    0          0                 Millions
Amount of COs    $0         $0                   1
0.47
Dollars in   0.5
Justification for COs: n/a
0
0
Initial   Change   Spent
Risks
Orders
None at this time
Photo
Budget Transfers
None



SEAPORT
86  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
T-91 Station Upgrades
Project Status:
Schedule: Within or ahead
Project:   C800439      Upgrade/replace existing        Budget: On or under
Budget: $424,000       substations/equipment at       Status Reset: 3/11/2014
Phase: Design        Substation Nos. 1, 14 and 15.     (Commission Construction Auth.)
Start: 11/4/2013
Schedule Completion: 12/31/2015
Budget/Costs Incurred
Significant Developments                     0.5
0.424      0.424
Developed design scope of work and fees with design consultant.      0.4
Started design development phase.                        Millions 0.3
Schedule                             0.2
Dollars in 
On Schedule                                  0.1             0.066
0
Budget                               Authorized Forecasted Costs Incurred
On Budget
Change Order                         Construction Costs
Not Applicable
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    0          0
Justification for COs: n/a
Risks
None for the early design stage.
Budget Transfers
None



SEAPORT
Port of Seattle 2Q 2014 Report  87

SECOND QUARTER REPORT, 2014
SEA P66 Apron Pile Wrap
Project Status:
Project:   C800516      Design and install a pile wrap      Schedule: Within or ahead
Budget: $3,010,000      system for corrosion protection of   Budget: On or under
Phase: Construction     steel structural pilings associated   Status Reset: 11/6/2012
Start: 3/6/2012          with Seaport structures at Pier 66.   (Commission Construction Auth.)
Schedule Completion: 12/31/2014
Budget/Costs Incurred
Significant Developments
4
Port issued substantial completion letter to our contractor KC
3.01
Equipment on May 13, 2014, one week ahead of the scheduled        3
contractual completion date. Lessons learned session was held and   Millions            1.9
2
project has transitioned into the Close-Out Phase. This will be the                       1.409
last report on this project.                                   Dollars in   1
Schedule                             0
Authorized   Forecasted  Costs Incurred
Construction is complete and project is in close-out.
Budget                            Construction Costs
Project is on budget.
1.2                1.128
1.04
Change Order                           1
Millions  0.8
Current Quarter   Project Total
0.6
Number of COs    5          9
0.4
Amount of COs    $19,440      $110,728             Dollars in  0.2     0.088
0
Justification for COs: Reconciliation of bid items.
Initial   Change   Spent
Orders
Risks
None. Construction is complete with no outstanding claims.       Photo
Budget Transfers
None


SEAPORT

88  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Argo Yard Truck Roadway
Project Status:
Schedule: Delayed
Project:   C800546,      New Port of Seattle owned truck    Budget: On or under
E104751, E104754       roadway between East Marginal    Status Reset: 4/22/2014
Budget: $7,750,000      Way and Colorado Avenue South   (Commission Construction Auth.)
Phase: Design        right-of-way.
Start: 3/11/2012
Schedule Completion: 12/31/2014
Significant Developments                    Budget/Costs Incurred
Required project permits received. Project construction documents     10
advertised for bid and contract executed with Gary Merlino               7.75     7.75
8
Construction.
6  Millions
Schedule                             4
Construction now expected to be completed by early 2015 due to     Dollars in  2               1.086
October construction start and likelihood of inclement weather
0
November thru January.
Authorized   Forecasted  Costs Incurred
Budget
Project authorized budget is $7,750,000 (including $600,000 from    Construction Costs
FMSIB for roadway construction by Port and $3,750,000 pass-thru    None at this time
funding from FMSIB for Argo Yard upgrades by UPRR).
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
No significant known risks at this time
Budget Transfers
None

SEAPORT
Port of Seattle 2Q 2014 Report  89

SECOND QUARTER REPORT, 2014
T-46 Dock Rehabilitation
Project Status:
Project:   C800603      Terminal 46 Dock Rehabilitation    Schedule: Delayed Schedule
Budget: $1,854,000      Project                Budget: On or under
Phase: Design                            Status Reset: Click here to
Start: 11/6/2012                                  enter a date.
Schedule Completion: Q4 2023                   (Commission Construction Auth.)
Significant Developments
The project is at 90% design and is on hold as previoulsy reported    Budget/Costs Incurred
due to the focused effort at Terminal 5. This project has been
2    1.854
posponed and is scheduled to resume design in 2020. At this time
this is the last report until the project is resumed.                   1.5
Millions                  1.023
Schedule                             1
The project has been postponed for five years due to the Terminal 5    Dollars in                  0.412
0.5
redevelopment project. Construction is anticipated to start in 2021
0
Authorized   Forecasted  Costs Incurred
Budget
The project is on budget
Construction Costs
Change Order
None at this time
Current Quarter   Project Total
Number of COs    0          0                Photo
Amount of COs    $0         $0
Justification for COs: n/a
Risks
None at this time
Budget Transfers
None


SEAPORT

90  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Terminal 115 Stormwater Separation
Project Status:
Project:   C800689      Separate stormwater originating    Schedule: Within or ahead
Budget: $548,000       from the Port leased area and the   Budget: On or under
Phase: Construction     Common Use Area on T-115 from   Status Reset: 5/6/2014
Start: 1/27/2014          the area exclusively used by       (Commission Construction Auth.)
Schedule Completion:    Northland Services.
9/30/2014
Budget/Costs Incurred
0.6     0.548      0.548
Significant Developments
0.5
Design complete, construction underway by PCS crews to meet       0.4
deadline of September 30, 2014.                          0.3
Millions
0.2
Schedule                            Dollars in 0.1           0.044
Construction complete by September 30, 2014.                  0
Authorized   Forecasted  Costs Incurred
Budget
Project is within approved budget.                         Construction Costs
Port Self Perform
Change Order
Construction
None this quarter
Risks
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Budget Transfers
None


SEAPORT

Port of Seattle 2Q 2014 Report  91

SECOND QUARTER REPORT, 2014
East Marginal Way Grade Separation
FAST Corridor funded project;      Project Status:
Project:   E102007     FHWA, State, City with Port       Schedule: Delayed Schedule
Budget: $56,256,171    commitment of $22,480,807. Scope  Budget: On or under
Phase: Close Out      is to construct grade separation in   Status Reset: 4/22/2014
Start: 5/1/2006          vicinity of T5 and T18 to minimize    (Commission Construction Auth.)
Schedule Completion:    truck traffic/rail conflicts.
Q4 2015
Budget/Costs Incurred
56.4    56.25      56.25
Significant Developments                     56.2
Effort for properties conveyance to City in conjunction with recently      56
55.8
approved MOA has begun.
55.6
Millions
55.4                        55.3
Schedule                            Dollars in 55.2
Anticipate final acceptance by Seattle Department of Transportation     55
54.8
(SDOT) 2nd Quarter 2015.
Authorized   Forecasted  Costs Incurred
Budget
An additional $800,000 authorized by Commission for project       Construction Costs
construction completion and conveyance of properties and
easements to City.                                     25   22        22
20
Change Order                          Millions 15
Current Quarter   Project Total
10
Number of COs    0          97
Dollars in 
Amount of COs    $0         $1,922,967              5      1.992
0
Justification for COs: N/A this quarter                               Initial  Change  Spent
Orders
Risks
None at this time.                                     Photo
Budget Transfers
None

SEAPORT

92  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Viaduct Construction Coordination
Participate in the design &          Project Status:
Project:   E104324,     construction of the bored tunnel, N. &  Schedule: Within or ahead
E104535-38         S. portals, Holgate to King St, Central  Budget: On or under
Budget: $2,900,000     Waterfront surface streets, & related  Status Reset: Click here to
Phase: Implementation  projects to ensure adequate      enter a date.
Start: 1/1/2009         connection to port facilities.         (Commission Construction Auth.)
Schedule Completion: 12/31/2018
Budget/Costs Incurred
Significant Developments
3.5
Repair plans for the SR 99 tunnel boring machine were received in          2.9
3
June and crews are implementing. Seawall construction is
Millions 2.5
restricted to the south end of waterfront during summertime. Mercer
2             1.75
and Roy Streets opened to two-way traffic following the closure of
1.5                         1.14
Broad Street from Dexter to 5th Ave.
Dollars in   1
0.5
Schedule
0
Tunnel boring machine expected to resume operation in late March        Authorized  Forecasted Costs Incurred
2015. Mercer West construction to continue through mid-2015.
Seawall Phase I construction to be completed in mid-2016. Central
Waterfront completion depends on Viaduct demolition in 2017.      Construction Costs
Not Applicable
Budget
Port staff costs were within anticipated 2014 spending.            Photo
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Project delays due to repairs to the tunneling machine.
Budget Transfers
None

SEAPORT
Port of Seattle 2Q 2014 Report  93

SECOND QUARTER REPORT, 2014
T-5 and T-91 Maintenance Dredging
Project Status:
Project:   E104840 &     Maintenance Dredge at T-5 all     Schedule: Delayed Schedule
U00067            three berths and at T-91 East     Budget: On or under
Budget: $4,800,000      cruise berth.             Status Reset: Click here to
Phase: Design                            enter a date.
Start: 8/14/2012                                  (Commission Construction Auth.)
Schedule Completion: 2/28/2016
Budget/Costs Incurred
Significant Developments
6
T-5 construction finished in February 2014 and is in closeout. There         4.8     4.8
5
will be no more updates on T-5. Due to complications and delays in
permitting, T-91 construction is delayed with Phase I scheduled for     Millions 4
3
January 2015 and Phase II late 2015--early 2016--all contingent on                      1.99
2
permits. The team is in discussion with the permitting agencies       Dollars in  1
regarding alternatives to traditional dredging. The preferred
0
alternative is under-water regrading to minimize environmental
Authorized   Forecasted  Costs Incurred
impact and reduce costs.
Schedule                           Construction Costs
T-5 Maintenance Dredging completion was on schedule. T-91 E.    None at this time
Cruise Berth delayed due to permitting complications.
Photo
Budget
Project is on budget.
Change Order
Current Quarter   Project Total
Number of COs    2          2
Amount of COs    $20,390.33    $20,390.33
Justification for COs: Additional sand covers per Permit requirements
Risks
Environmental permitting may cause further delays, scope change,
and cost impact to the T-91 East Cruise Berth Dredging project.
Budget Transfers
None

SEAPORT
94  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Clean Truck Program Truck Scrapping and
Replacement Project
Project Status:
Scrap or retrofit at least 220 trucks   Schedule: Within or ahead
Project: U00079; U00134
with pre-2007 engines currently     Budget: On or under
Budget: $4,727,000
operating at the Port of Seattle.      Status Reset: Click here to
Phase: Implementation                       enter a date.
Start: 12/10/2013                                 (Commission Construction Auth.)
Schedule Completion: 11/30/2015
Budget/Costs Incurred
Significant Developments
4.727     4.727
5
The Clean Truck program provides incentive vouchers to truckers
4
who operate at the Port of Seattle and who commit to scrapping
trucks with 2007 or older engines in order to purchase trucks with      Millions 3
2007 or newer engines. The truck scrapping center at T-5 opened on    2
May 27th. Currently, 111 voucher applications have been pre-        Dollars in  1
approved, and 30 trucks scrapped and replaced. The program will                     0.12
continue through November 2015.                         0
Authorized  Forecasted    Costs
Incurred
Schedule
On schedule                                  Construction Costs
Not Applicable
Budget
On budget                                   Photo
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
Due to multiple funding sources, the project needs to be compliant
with funding agencies' requirements. A consultant has been retained
to provide grant administration services.
Budget Transfers
None

SEAPORT
Port of Seattle 2Q 2014 Report  95

SECOND QUARTER REPORT, 2014
IHI Crane Removal
Project: U00099      Remove three IHI Cranes from      Project Status:
Terminal 18                  Schedule:  within or ahead
Budget: $1,500,000                        Budget:   on or under
Phase: Construction                       Status Reset: 9/11/2012
Start: 9/11/2012                                 (Commission Construction Auth.)
Schedule Completion: 1/23/2015
Budget/Costs Incurred
Significant Developments
At the time the cranes were surplused in September 2012, staff       1.6   1.5
made two unsuccessfull attempts to sell them. During the Second      1.4
Quarter plans and specifications were developed for the crane       Millions 1.2
1
removal and the project was advertised. Favorable bids were
0.8
received in August and the project is currently in the process of       Dollars in  0.6
being executed.                                     0.4
0.2                                0.046
Schedule                             0
Authorized      Forecasted     Costs Incurred
All the cranes to be removed from the terminal by January 23, 2014.
The contract completion date is a function of the award date and
currently estimated to be March 5, 2015                    Construction Costs
None at this time
Budget
The project is within budget                              Photo
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
none beyond standard construction risk
Budget Transfers
none

SEAPORT
96  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Shilshole Bay Marina Central Seawall
Project Status:
Project:   C800088      Rehabilitation of the timber step    Schedule: Delayed
Budget: $915,000       wall section of the central seawall   Budget: On or under
Phase: Construction     at Shilshole Bay Marina        Status Reset: Click here to
Start: 7/9/2013                                   enter a date.
Schedule Completion: 10/31/2015                 (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
Design is complete. Permit approval complete. Material ordered and    1   0.915    0.915
stockpiled for installation next year. This is the last report until         0.8
project begins again next year.                             Millions 0.6
0.4
Schedule
Dollars in  0.2                        0.0782
In-water work delayed one year due to tidal constraints. Site work
will begin June 1, 2015. Complete construction by October 31, 2015.    0
Authorized   Forecasted  Costs Incurred
Budget
Project is within approved budget.                         Construction Costs
None at this time
Change Order
None this quarter
Risks
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Budget Transfers
None


REAL ESTATE
Port of Seattle 2Q 2014 Report  97

SECOND QUARTER REPORT, 2014
FT C15 HVAC Improvements
Project:   C800137     Provide the preliminary planning,
Project Status:
Budget: $4,887,000     design, and construction to replace
Schedule: Delayed Schedule
Phase: Construction    the existing HVAC systems within
Budget: On or under
Start: 5/1/2010         Building C-15 that are at the end of
Status Reset: 10/8/2013
their service life.
Schedule Completion:                        (Commission Construction Auth.)
6/30/2014
Budget/Costs Incurred
Significant Developments
6
Construction activities concentrated on the west side of the               4.887    4.887
5
Fishermen's Center Building, both inside tenant spaces and in the
mechanical well. Work within the mechanical well remains extremely   Millions 4                3.2
challenging due to space limitations.                           3
2
Schedule                            Dollars in 
1
Contractor is behind schedule by approximately two and half months.    0
Authorized   Forecasted  Costs Incurred
Budget
Project is on track to be within the October 8, 2013 Commission
funding authorization.                                  Construction Costs
3.5
Change Order                             2.97
3
Current Quarter   Project Total             2.5           2.2
Number of COs    1          1                  Millions  2     1.52
Amount of COs    -$1,218      -$1,218               1.5
Dollars in    1
0.5
Justification for COs: Credit for weekend callout of tenant contractor.
0
Initial   Change   Spent
Risks                                      Orders
Construction related access to existing mechanical wells is extremely
difficult and some work will be within areas currently concealed from
view. Contractor performance/safety issues resulted in the removal
of their superintendent and a 2-week construction pause. Some cost
trend items have been identified by the contractor and likely would
result in claims/dispute resolution.
Budget Transfers
None

REAL ESTATE
98  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
P-69 Built-up Roof Replacement
Project Status:
Project:   C800314      Replace 32,000SF of the 65,000SF  Schedule: Within or ahead
Budget: $3,418,000      Built-Up Roof at the P-69       Budget: On or under
Phase: Construction     Headquarters Office Building     Status Reset: 2/25/2014.
Start: 2/26/2012                                  (Commission Construction Auth.)
Schedule Completion: 10/30/2014
Significant Developments                    Budget/Costs Incurred
Construction in progress. Demolition and replacement activities are
4
3.418      3.418
almost complete with on going installation. Sawtooth valleys are       3.5
being worked on with a liquid applied membrane. The facility roof      3
developed a leak along the south side of the building during the        2.5
recent rainstorm, the facility was immediately cleaned with water        2
Millions
1.5
damage being repaired by the contractor.                     Dollars in  1
0.5                         0.279
Schedule                             0
Authorized   Forecasted  Costs Incurred
Completion date scheduled for Q4 2014.
Budget
Construction Costs
The project is currently below budget.
3.5    3.13
Change Order                           3
2.5
None                                  Millions  2
1.5
Risks                                 1
Dollars in                      0.356
0.5
Current Quarter   Project Total
0
Number of COs    2          2                  0.5  Initial Change0.014  Spent
Amount of COs    -$14,240     -$14,240                     Orders
Justification for COs: A cumlative credit of -$14,240 as a result of
deleting Wood nailers and Fire retardent for the project.
Budget Transfers
None

REAL ESTATE

Port of Seattle 2Q 2014 Report  99

SECOND QUARTER REPORT, 2014
FT C-2 Nordby HVAC and Roof Replacement
Project Status:
Project:   C800344      Replace 23,000SF of existing      Schedule: Within or ahead
Budget: $2,338,600      Roofing and roof top HVAC units   Budget: On or under
Phase: Construction                        Status Reset: 1/7/2014
Start: 2/26/2012                                  (Commission Construction Auth.)
Schedule Completion: 10/30/2014
Significant Developments                    Budget/Costs Incurred
The project is currently under construction. Construction demolition
3    2.74      2.74
activities are progressing from south to north with HVAC demolition
2.5
ongoing. Installation is ongoing from east to west with HVAC units
2
also being installed. The facility roof developed a leak during the      Millions
recent rainstorm, the facility was immediately cleaned with water       1.5
damage being repaired by the contractor.                     Dollars in  1
0.5                         0.301
Schedule                             0
Authorized   Forecasted  Costs Incurred
The project is scheduled for completion in Q4 2014
Budget
Construction Costs
The project is currently below budget.
2.5   2.17
Change Order
2
Current Quarter   Project Total            Millions 1.5
Number of COs    0          0
Amount of COs    $0         $0                   1
Dollars in   0.5
0 0
Justification for COs: n/a                                      0
Initial   Change   Spent
Risks                                      Orders
None
Budget Transfers
$100,000 transferred to the FT NS 9 Roof Replacement Project (CIP
#C800527).


REAL ESTATE
100  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
FT Net Shed #9 Roof Overlay
Project Status:
Project:   C800527      Overlay 12,000SF of existing      Schedule: Within or ahead
Budget: $401,400       corrugated Roof at the FT Net     Budget: On or under
Phase: Construction     Shed Building            Status Reset: 1/7/2014
Start: 2/26/2012                                  (Commission Construction Auth.)
Schedule Completion: 10/30/2014
Budget/Costs Incurred
Significant Developments
0.35
The project is currently in construction. Construction concerns, with         0.301    0.301
0.3
Seattle City Light (SCL) and Labor and Industries (L&I), with the
0.25
26Kv high power lines terminating near the Net Shed building are     Millions 0.2                0.153
resolved. Construction will begin shortly.
0.15
Dollars in  0.1
Schedule
0.05
With the SCL and L&I delay, the project is still scheduled for           0
completion in Q4 2014                                   Authorized  Forecasted Costs Incurred
Budget
Construction Costs
The project is currently at budget.
0.3   0.268
Change Order
0.25
Current Quarter   Project Total           Millions  0.2
Number of COs    0          0                  0.15
Amount of COs    $0         $0
0.1
Dollars in 
0.05
Justification for COs: N/A                                            0   0.003
0
Initial   Change   Spent
Risks                                      Orders
None
Budget Transfers
$100,000 was received from C-2 Nordby C800344.


REAL ESTATE

Port of Seattle 2Q 2014 Report  101

SECOND QUARTER REPORT, 2014
P69 Carpet Replacement
Project Status:
Project: C800691      Replace carpet flooring at
Corporate Headquarters Building     Schedule: Delayed Schedule
Budget: $1,200,000
on the second and third floors.       Budget: On or under
Phase: Construction                       Status Reset: 2/4/2014
Start: 7/7/2014                                 (Commission Construction Auth.)
Schedule Completion: 9/30/2014
Budget/Costs Incurred
Significant Developments
1.4
1.2
The Port has approved carpet and trim materials. Materials have      1.2
been ordered.
Millions  1
0.8
Schedule                            0.6
Working with the contractor on establishing the exact start date for     Dollars in  0.4
carpet installation. Installation is anticipated to take place October      0.2                 0.047
0
2014.
Authorized   Forecasted  Costs Incurred
Budget
The project should complete within the allotted budget.           Construction Costs
Not Applicable
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: N/A
Risks
None at this time
Budget Transfers
None



REAL ESTATE
102  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
FT Net Shed Code Compliance
Project Status:
Project:   E104838      FT Net Sheds 3-11: Improvements   Schedule: Within or ahead
Budget: $2,950,000      required per City of Seattle building  Budget: On or under
Phase: Construction     & fire codes             Status Reset: 6/25/2013
Start: 5/1/2012                                   (Commission Construction Auth.)
Schedule Completion: 6/30/2015
Significant Developments                    Budget/Costs Incurred
Net Shed 10 work is complete and crew began working on Net Shed
3.5
11 improvements. Additional building permits received.                 2.95     2.95
3
2.5
Schedule
2  Millions
Overall construction completion is still scheduled by the end of 2nd      1.5
quarter 2015.                                       Dollars in  1               0.721
0.5
Budget                             0
Authorized   Forecasted  Costs Incurred
Project budget is on track.
Change Order
Construction Costs
Current Quarter   Project Total          Port Self Perform
Number of COs    0          0                Construction
Amount of COs    $0         $0
Photo
Justification for COs: n/a
Risks
It is difficult to forecast the amount of stored materials that needs to
be moved out and moved back into the netlockers since tenant
storage habits vary significantly. In addition, the amount of work
required in each unit is difficult to assess until some stored materials
are cleared and locker conditions are more visible. These would
impact the overall project budget.
Budget Transfers
None

REAL ESTATE
Port of Seattle 2Q 2014 Report  103

SECOND QUARTER REPORT, 2014
ID Badge System Replacement
Project Status:
Project: C800162        Procurement and replacement of   Schedule: Delayed Schedule
Budget: $2,500,000      the Portwide ID Badge system     Budget: On or under
Phase:Implementation    including software, hardware, and   Status Reset: Click here to
Start: 5/1/2012           equipment.                 enter a date.
Schedule Completion: 7/30/2015                   (Commission Construction Auth.)
Significant Developments                    Budget/Costs Incurred
Testing is in progress for an October 2014 delivery of the new ID
Badge system. A 2nd deployment to add mobile functionality and       3
2.50       2.50
authorized signer efficiencies will be scheduled following the main
2.5
system deployment.
2
1.30
Schedule                             Millions 1.5 Dollars in 1
Resource availability and system complexity have delayed project
0.5
completion.
0
Authorized   Forecasted  Costs Incurred
Budget
On Budget
Construction Costs
Change Order                         Not Applicable
Current Quarter   Project Total
Number of COs    1          1
Amount of COs    $108,497     $108,497
Justification for COs: With an additional module for the new ID
Badge system, we had an opportunity to more seamlessly integrate
the Transportation Worker Identification Card (TWIC) registration
creating a more efficient process for Credential Specialists and
Tenants.
Risks
Resource availability may continue to delay the second phase mobile
deliverables.
Budget Transfers
None

CORPORATE
104  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Enterprise Project Cost Management
Project Status:
Project: C800321        Replace the current construction    Schedule: Delayed Schedule
Budget: $1,525,000      costing systems with a common    Budget: On or under
Phase:Implementation    enterprise project cost         Status Reset: Click here to
Start: 4/21/2008          management system.           enter a date.
Schedule Completion: 12/30/2014                  (Commission Construction Auth.)

Significant Developments                    Budget/Costs Incurred
The first phase deployment has been completed and the software is
1.55    1.525      1.525
in-use by the Project Management Groups. Next phase deliverables
1.5
such as trend logs and cash flows are in test and scheduled for
delivery in 3rd Quarter 2014.                               1.45  Millions                  1.4
1.4
Schedule                            1.35 Dollars in 
Prior Report: Availability of resources is impacting the completion of     1.3
Authorized  Forecasted Costs Incurred
the remaining components. These include features such as cash
flows and trend logs as well as additional interfaces that require
resources currently focused on the Peoplesoft Financials Upgrade
project. We are in the process of procuring additional configuration    Construction Costs
assistance and expect to deliver in phases over the next several     Not Applicable
months.
Budget
None
Change Order
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0
Justification for COs: n/a
Risks
Availability of Port resources may delay next phase deliverables.
Budget Transfers
None

CORPORATE
Port of Seattle 2Q 2014 Report  105

SECOND QUARTER REPORT, 2014
Network Switch Replacement
Project Status:
Project: C800323        Upgrade the Network switch      Schedule: Within or ahead
Budget: $1,500,000      infrastructure hardware and      Budget: On or under
Phase: Design         software                Status Reset: Click here to
Start: 12/15/2013                                enter a date.
Schedule Completion: 3/31/2015                   (Commission Construction Auth.)

Significant Developments
Budget/Costs Incurred
Design, procurement, and site improvements are in progress.
2
Schedule
1.50       1.50
1.5
On schedule.                                    Millions
1
Budget
On budget.                                     Dollars in 0.5              0.35
0
Change Order                            Authorized Forecasted Costs Incurred
Current Quarter   Project Total
Number of COs    0          0
Amount of COs    $0         $0                Construction Costs
Not Applicable
Justification for COs: n/a
Risks
Port resource availability may impact schedule.
Budget Transfers
None



CORPORATE
106  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Terminal 91 Visitor Management
Project Status:
Project: C800436        Upgrade of the Radio System Core  Schedule: Within or ahead
Budget: $520,000       Hardware and Software and      Budget: On or under
Phase: Planning        Dispatch Consoles           Status Reset: Click here to
Start: 7/1/2013                                   enter a date.
Schedule Completion: 5/1/2016                    (Commission Construction Auth.)
Significant Developments
Planning and Procurement in Process                     Budget/Costs Incurred
Schedule                             0.6  0.52  0.52
On Schedule                                    0.5
Millions  0.4
Budget                              0.3
On Budget                                    0.2
Dollars in   0.1
0
Change Order                           0
Authorized Forecasted   Costs
Current Quarter   Project Total                         Incurred
Number of COs    0          0
Amount of COs    $0         $0
Construction Costs
Justification for COs: n/a                                 Not Applicable
Risks
No signfiicant risks at this time.
Budget Transfers
None




CORPORATE
Port of Seattle 2Q 2014 Report  107

SECOND QUARTER REPORT, 2014
Contractor Data System Upgrade
Project Status:
Project: C800519        Upgrade of the Contractor Data    Schedule: Within or ahead
Budget: $1,500,000      System used by Engineering and   Budget: On or under
Phase: Planning        other groups to track contracts for   Status Reset: Click here to
Start: 7/1/2013           construction projects.           enter a date.
Schedule Completion: 2/28/2016                   (Commission Construction Auth.)
Significant Developments
Planning is in progress                                 Budget/Costs Incurred
Schedule                              2
1.5       1.5
On Schedule                                    1.5
Budget                              Millions  1
On Budget                                   Dollars in  0.5
0
Change Order                            0
Authorized Forecasted   Costs
Current Quarter   Project Total                           Incurred
Number of COs    0          0
Amount of COs    $0         $0                Construction Costs
Not Applicable
Justification for COs: n/a
Risks
No signfiicant risks at this time.
Budget Transfers
None




CORPORATE
108  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Computer Dispatch System Upgrade
Project Status:
Project: C800520        Upgrade Computer Dispatch      Schedule: Within or ahead
Budget: $790,000       System used by 911 and        Budget: On or under
Phase: Planning        Emergency Responders        Status Reset: Click here to
Start: 4/1/2013                                   enter a date.
Schedule Completion: 8/31/2015                   (Commission Construction Auth.)
Significant Developments
Procurement and Planning in process                     Budget/Costs Incurred
Schedule                              1
0.79     0.79
On Schedule                                    0.8
Millions   0.6
Budget
0.4
On Budget                                   Dollars in  0.2
0.05
Change Order                            0
Authorized Forecasted   Costs
Current Quarter   Project Total                          Incurred
Number of COs    0          0
Amount of COs    $0         $0
Construction Costs
Justification for COs: n/a                                 Not Applicable
Risks
No signfiicant risks at this time.
Budget Transfers
None




CORPORATE
Port of Seattle 2Q 2014 Report  109

SECOND QUARTER REPORT, 2014
Construction Document Management
Replacement of the Construction     Project Status:
Project: C800521       Document Management System    Schedule: Within or ahead
Budget: $900,000       used by Construction Management   Budget: On or under
Phase: Planning       to accept, review, and distribute    Status Reset: Click here to
Start: 9/10/2013         critical documentation.           enter a date.
Schedule Completion: 3/31/2015                   (Commission Construction Auth.)
Significant Developments
Bid proposals are currently being evaluated.                  Budget/Costs Incurred
Schedule                              1  0.9   0.9
On Schedule                                    0.8
Millions  0.6
Budget
0.4
On Budget                                   Dollars in  0.2
0.005
Change Order                           0
Authorized Forecasted   Costs
Current Quarter   Project Total                         Incurred
Number of COs    0          0
Amount of COs    $0         $0
Construction Costs
Justification for COs: n/a                                 Not Applicable
Risks
Procurement schedule has been extended which may impact the
overall project schedule.
Budget Transfers
None



CORPORATE
110  Port of Seattle 2Q 2014 Report

SECOND QUARTER REPORT, 2014
Radio System Upgrade
Project Status:
Project: C800586        Upgrade of the Radio System Core  Schedule: Within or ahead
Budget: $6,750,000      Hardware and Software and      Budget: On or under
Phase: Close Out       Dispatch Consoles           Status Reset: Click here to
Start: 6/9/2013                                   enter a date.
Schedule Completion: 5/31/2014                   (Commission Construction Auth.)
Significant Developments
Radio system upgrade was successfully completed in 2nd Quarter.    Budget/Costs Incurred
The close out process will address small items that remain inprocess.
This will be the last report on the project.                    8
6.75     6.75
6
Schedule                            Millions            3.9
On Schedule                                     4
2
Budget                             Dollars in 
We are estimating a budget underrun of approximately $1,000,000.       0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter   Project Total
Number of COs    0          0                Construction Costs
Amount of COs    $0         $0                Not Applicable
Justification for COs: n/a
Risks
No signfiicant risks at this time.
Budget Transfers
None



CORPORATE
Port of Seattle 2Q 2014 Report  111

SECOND QUARTER REPORT, 2014
Noise Monitoring System Replacement
Project Status:
Project: C800693        Upgrade or Replacement of the    Schedule: Within or ahead
Budget: $1,900,000      Airport Noise Monitoring System    Budget: On or under
Phase: Planning                            Status Reset: Click here to
Start: 4/1/2014                                   enter a date.
Schedule Completion: 8/31/2015                   (Commission Construction Auth.)
Significant Developments
Planning and Procurement in Process                     Budget/Costs Incurred
1.9      1.9
Schedule                              2
On Schedule
1.5
Millions
Budget                              1
On Schedule                                  Dollars in  0.5
0.01
Change Order                            0
Authorized Forecasted   Costs
Current Quarter   Project Total                          Incurred
Number of COs    0          0
Amount of COs    $0         $0
Construction Costs
Justification for COs: n/a                                 Not Applicable
Risks
No signfiicant risks at this time.
Budget Transfers
None




CORPORATE
112  Port of Seattle 2Q 2014 Report

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.