7c attach

Item Number:  7c_Report
Meeting Date: March 11, 2014


Commission Staff Brieng
Capital Improvement Projects
Fourth Quarter Report 2013

This page intentionally left blank









ii  Port of Seattle 4Q 2013 Report

Port of Seattle
Capital Improvement Project Report
)RXUWK Quarter 2013
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the status of the Port's capital projects.
Background
During 2013 the Port plans to invest over $225,500,000 to expand and upgrade the infrastructure that supports marine
and aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping
companies, airlines, rental car companies, concessionaires and public parking. About 4 percent of the Port's capital
budget comes from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in
transportation facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes a "Status Snapshot" illustrating at a
glance if the project is on schedule, within budget, the total number of change orders to date, and the total value of
executed change orders.
x Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x Budget addresses the total project budget and includes things like overall budget status, recent Commission
authorizations, forecasted overruns or savings, and scope changes.
x Change Orders provides a description of CO for the reporting period and information on any CO over $200,000 or
10% of the contract value.
x Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x Budget Transfers reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page and select the Audit/Accountability button. Use the form to ask a
question, make a comment or request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 4Q 2013 Report  1

Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C000683 et al .......3rd Runway Program .............................................6 ........... 
C100266 et al .......Rental Car Facility ............................................... 7-8..........
C102032 ...............Sanitary Sewer Pump Station Upgrade ................9 ...........
C102334 ...............Water System Isolation Valve Upgrade ................10 ..........
C102573 ...............Aireld Pavement Replacement ...........................11 ..........
C800019 ...............Gate Utilities Improvement ...................................12 ..........
C800034 ...............North Expressway Relocation ..............................13 ..........
C800061 ...............Main Terminal South Low Voltage ........................14 ..........
C800105 ...............Airport Owned Gate Infrastructure .......................15 ..........
C800107 ...............C4 UPS System Improvements ............................16 ..........
C800112................Runway 16C/34C Panel/Joint Sealant .................17 .......... ................. ............................................
C800168 ...............C60-C61 BHS Modications ................................18 ..........
C800174................FIS - New Primary Inspection Booths ..................19 ..........
C800218 ...............Security Exit Lane Breach Control Phase I ..........20 ..........
C800230 ...............Emergency Lighting Parking.................................21 ..........
C800234 ...............Feeder 101 Tap Replacement ..............................22 ..........
C800237 ...............Terminal Escalators Modernization ......................23 .......... ................. ............................................
C800238 ...............Central Plant Pre-Conditioned Air ..................... 24-25 ....... ................. ............................................
C800247 ...............Cargo 2 West Hardstand ......................................26 ..........
C800251 ...............Vertical Conveyance Modernization.....................27 ..........
C800253 ...............Parking System Replacement ..............................28 ..........
C800254 ...............Aircraft RON Parking Post Ofce Site..................29 ..........
C800267 ...............Port Owned Loading Bridges ...............................30 ..........
C800268 ...............Stage 2 Mechanical Energy Implementation .......31 ..........
C800274 ...............8th Floor Weather Proong ..................................32 ..........
C800276 ...............Common Use Equipment Expansion (CUSE) ......33 ..........
C800324 ...............Long-Term Cell Phone Lot ....................................34 .......... ................. ............................................
C800334 ...............Two new CTE Freight Elevators ...........................35 .......... 
C800335 ...............EGSE Electrical Charging Stations ...................36-37 .......
C800374 ...............Claim Device 14 and Lower Inland .......................38 ..........
C800376 ...............South Satellite HVAC, Lights, and Ceiling Repl. ..39 ..........
C800382 ...............BHS (C22-C1, MK1 and TC3) ............................ 40-41 .......
C800390 ...............Cargo 6 Enhancements ........................................42 ..........
C800406 ...............RW 16C/34C Reconstruction ...............................43 ..........




2  Port of Seattle 4Q 2013 Report

Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule Budget
C800412 ...............South Satellite Concessions Project ....................44 ..........
C800414 ...............Access Control Door Additions ............................45 ..........
C800415 ...............ALCMS Upgrade...................................................46 ..........
C800417 ...............Lagoon 3 Bird Wires .............................................47 ..........
C800426 ...............FIS Improvement - Short Term .............................48 ..........
C800451 ...............Doug Fox Site Improvement .................................49 ..........
C800455 ...............Concourse D Common Use Environment ............50 ..........
C800459 ...............2011-2013 Roof Replacement Program ...............51 .......... .................................. ............................................
C800461 ...............IWTP Fiber Installation .........................................52 ..........
C800464 ...............Fiber Infrastructure to Gate Backstands ..............53 ..........
C800466 ...............South Satellite - Additional Gate Lobby ................54 ..........
C800467 ...............PLB Replacement .................................................55 ..........
C800473 ...............CUSE at Ticket Counters/Gates - AR ..................56 ..........
C800474 ...............Airport Signage .....................................................57 ..........
C800475 ...............Miscellaneous Building Improvements - AR.........58 ..........
C800479 ...............Fire Station Electrical Upgrades ...........................59 .......... .............................. 
C800484 ...............Laptop Power In Concourses ...............................60 .......... .............................. 
C800490 ...............New Window Wall Ticket Zone 1 ..........................61 ..........
C800491 ...............Convert Ticket Zone 2 Pusback ...........................62 ..........
C800492 ...............Convert Ticket Zone 3 Flow Thru .........................63 ..........
C800495 ...............Facility Monitoring System Renewal ....................64 ..........
C800497 ...............Airport Wide Mechanical Controls System ..........65 .......... .............................. 
C800541 ...............RAC Baggage Claim Renovation .........................66 ..........
C800544 ...............NorthSTAR Program.............................................67 .......... .............................. 
C800547 ...............NorthSTAR Concourse C Vertical Circ. ...............68 ..........
C800550 ...............Concourse D Roof Replacement..........................69 ..........
C800551 ...............Grease Interceptor Augmentation ........................70 ..........
C800555 ...............NorthSTAR Refurbish Baggage Systems ............71 ..........
C800556 ...............NorthSTAR North Satellite Lobbies ................... 72-73........ .............................. 
C800560 ...............MT Mezzanine Tenant Relocation ........................74 .......... .............................. 
C800576 ...............Known Crew Member Employee Bypass .............75 .......... .............................. 
C800583 ...............International Arrivals Facility ................................76 ..........
C800605 ...............Security Exit Lane Breach Control Phase 2 .........77 ..........
C800609 ...............NSAT - STS Ceiling Leak Repair ..........................78 ..........
C800611 ...............Passenger Bridge & Walkway S16 Repl ..............79 ..........
C800612 ...............Checked Baggage Recapitalization/Optimzation.80 ..........
C800615 ...............Second Floor Mezzanine Infra Upgrade ..............81 .......... .............................. 
C800667 ...............Automated Passport Control ................................82 .......... ..............................  ........................................


Port of Seattle 4Q 2013 Report  3

Other Aviation ..........................................................................
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C200007...............Highline School Noise Insulation ..........................83 ..........
C200042 ...............Highline Community College Noise Insulation .....84 ..........
C200048 ...............Home Insulation Retrot .......................................85 .......... .............................. 
C200093 ...............Single Family Home Sound Insulation .................86 .......... .............................. 
C800146 ...............RMU/Kiosk Concession Program ........................87 .......... .............................. 
C800150 ...............Burien Commercial Property Acquisition .............88 ..........
C800154 ...............Tenant Reimbursement ........................................89 ..........
C800498 ...............Snow Removal Equipment ...................................90 ..........

Seaport
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C102554............... Terminal 46 Development....................................91 ..........
C102858 et al ....... Street Vacations T-5/18/105.................................92 ..........
C800183 ...............P91 Fender System Upgrade ...............................93 ..........
C800430 ...............T-91 Building C175 Roof Replacement ................94 ..........
C800516 ...............SEA P-66 Apron Pile Wrap ..................................95 ..........
C800546 ...............Argo Yard Truck Roadway .................................96-97 .......
C800603 ...............T-46 Dock Rehabilitation ......................................98 ..........
U00079 .................Clean Truck Program Truck Scrap & Repl ...........99 ..........
WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation .................100 .........
E104324 ................Viaduct Construction Coordination .....................101 .........
E104840................T-5, T-18 and T-91 E. Maintenance Dredging .....102 .........
Real Estate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800137 ...............FT C15 HVAC Improvements ..............................103 .........
C800313 ...............P69 N Apron Corrosion Control ..........................104 .........
C800314 ...............P69 Built-up Roof Replacement ..........................105 .........



4  Port of Seattle 4Q 2013 Report

Real Estate, cont.
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800344 ...............FT C-2 Nordby Roof and HVAC .........................106 .........
C800527 ...............FT Net Shed 9 Roof Replacement ......................107 .........
C800571 ...............MIC Built-up Roof Replacement ..........................108 .........
C800625 ...............Pier 66 Steam Replacement................................109 .........
E104838................FT Net Shed Code Compliance ..........................110 .........
Corporate

Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C101117 ................Flight Information Systems (FIMS) II ................... 111 .........
C800003 ...............Maximo Enterprise Implementation .....................112 .........
C800162 ...............ID Badge Replacement .......................................113 .........
C800222 ...............Airline Activity Management ................................114 .........
C800321 ...............Enterprise Project Cost Management ..................115 .........
C800323 ...............Network Switch Replacement ..............................116 .........
C800387 ...............Time Clock System ..............................................117 .........
C800393 ...............Police Records Management System .................118 .........
C800521 ...............Construction Document Management ................119 .........
C800558 ...............Access Control Network Refresh ........................120 .........
C800586 ...............Radio Systems Upgrade......................................121 .........


Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Variance Status
Variance Since Last Report



Port of Seattle 4Q 2013 Report  5

FOURTH QUARTER REPORT, 2013
3rd Runway Program
Status Snapshot
On Schedule
Project: C000683,       The 3rd Runway Program
On Budget
C001138, C001175,      constructed a new 8,500 foot long
0 Change Orders
C001331, C001751,      runway, connecting taxiways, and
Total Change Orders Amount:
C001760, C100172      related infrastructure.
$0.00
Budget: $914,744,759
Phase: Construction                       Budget/Costs Incurred
Start: 05/27/1997
1150
Completion: 12/31/2011
1100
1050
Significant Developments                    1000 Millions
950
Remaining funds in CIP C001760 is to be transferred to Aviation
900
Division's Environmental Department's Expense for the removal of     Dollars in 850
contaminated soils at the RST Property Site in the first quarter of      800
2014 so that expense work to be done by Port Construction            Authorized Forecasted Costs Incurred
Services can be started in the spring of 2014.
Schedule                           Construction Costs
None.                                    Not Applicable
Budget                           Photo
The project forecast is within the approved budget and authorization.
Change Order
No change orders executed this quarter.
Risks
None
Budget Transfer
To Savings                       $255,618


AIRPORT
6  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Rental Car Facility                       Status Snapshot Prior Report
Delayed Schedule 3Q 12
Project:   C100266,     The program will construct a       Under Budget        1Q 13
C102167, C800032     consolidated rental car facility (RCF)  1,755 Change Orders
Budget: $378,014,414   for all rental car companies at the    Total Change Orders Amount:
Phase: Construction    airport, a bus maintenance facility    $15,492,533
Start: 02/24/1998        (BMF), and mitigation with the off-site
roadway improvements (ORI), plus
Completion: Spring 2012
purchase a fleet of buses.
Significant Developments                    Budget/Costs Incurred
The RCF is substantially complete with projects either closed or in
closeout. A binding Arbitration Agreement has been executed to       400
resolve the final claims on the RCF project which are in dispute. The    395
390
FAA approved the transfer of Port property to WSDOT and the City
385
of SeaTac on December 5, 2013 for the ORI project.               Millions 380
Schedule                            Dollars in 375
370
RCF opened May 17, 2012. Resolution of the final claims for the      365
RCF project via the Arbitration Agreement are expected to continue     360
Authorized   Forecasted  Costs Incurred
through 2014.
Budget                            Construction Costs
The RCF program remains under budget with a total program budget
of $419,306,000. The total forecasted cost at completion for the        300
RCF program, not including funding for any claims, is $392,306,000.      250
Millions  200
Change Order                           150
Four change orders were issued this quarter for the RCF project for      100
Dollars in 
a total value of $1,514,768. They are as follows:                    50
1) $1,580,884 - Undisputed portion of claim                       0
2) $0 - Unidentified Trade Damage Corrections                       Initial  Change  Spent
Orders
3) -$66,116 - Light Fixture Credit
4) $0 - Reconciliation change order
Photo
No change orders were issued this quarter for the other projects.
Risks
Resolution of the pending claims for the RCF project. No other risks
were identified for the other projects.

Port of Seattle 4Q 2013 Report  7

Budget Transfers
Transferred $973,000 to the S. 160th St Ground Transportation Lot Improvement projects. Reduced
$368,029 from the budget and transferred it out as Government Expense work. Increase the project
budget by $650,000 (previously identified savings) for payment of undisputed portion of claim.
Cost Growth of Construction
RCF Airport Wayfinding Signage and Curbside Modifications - MC-0316968 - This contract is closed
with a final cumulative change order percentage is 21.3%.
Consolidated Rental Car Facility - Small Operator Build Out - MC-0317022 - This contract is closed
with a final cumulative change order percentage is 3.97%.
Consolidated Rental Car Facility Offsite Roadway Improvements and SR99 Bridge Seismic Upgrade
MC-0316568 - The final payment was made to the Contractor and the contract is in closeout. The
cumulative change order value through this quarter is $3,017,296 (39.6%) with no activity this quarter.
Bus Maintenance Facility - MC-0316730 - Final payment was made to the Contractor and the contract
is in closeout. The cumulative change order value is $300,190 (2.29%) with no activity this quarter.
GCCM Final Construction (Phase 3 of 3)  MC-0315405 - The current cumulative change order
percentage through this quarter is 4.86% with four change orders executed this quarter. This contract
is active with final claim negotiations underway.
TESC & Early Work (Phase 2 of 3)  MC-0315292 - This contract is closed with a final cumulative
change order percentage of 19.4%.
GCCM Pre-Construction (Phase 1 of 3)  MC-0314280  This contract is closed with a final
cumulative change order percentage of 170.5%.




AIRPORT

8  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Sanitary Sewer Pump Station Upgrade
Project:   C102032      This project upgrades the aging    Status Snapshot
Budget: $1,133,000      control systems of 22 sanitary     On Schedule
Phase: Design        sewer lift stations at Seattle-     On Budget
Start: 03/01/2013         Tacoma International Airport.      0 Change Orders
Completion: 5/31/2014                        Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
1.2
Control components have been ordered. Pre-construction meeting
1
for electrical field work was held.
Millions 0.8
0.6
Schedule
0.4
The project is currently on schedule.                         Dollars in 0.2
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT
Port of Seattle 4Q 2013 Report  9

FOURTH QUARTER REPORT, 2013
Water System Isolation Valve Upgrade-non AF
Status Snapshot Prior Report
Delayed Schedule 3Q 12
Project:   C102334      This project replaces isolation     On Budget
Budget: $882,000       valves on the aging water       0 Change Orders
Phase: Close Out      distribution system, necessary for   Total Change Orders Amount:
Start: 10/01/2010         isolating portions of the system in    $0
Completion: 02/28/2013   the event of breaks, leaks, or tieins
, in non-airfield (AF) locations.    Budget/Costs Incurred
0.98
0.96
Significant Developments                     0.94
Millions   0.92
Construction is complete and project is in closeout. This will be the      0.9
last quarterly report.                                       Dollars in   0.88
0.86
0.84
Schedule                             0.82
0.8
Construction is complete.                                 0.78
Authorized       Forecasted      Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
None
Risks
None identified at this time
Budget Transfers
From C800404 (Aeronautical Allowance)          $75,000




AIRPORT
10  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Airfield Pavement Replacement
Status Snapshot
On Schedule
Project:   C102573      The project is intended to be a     On Budget
Budget: $30,162,035     multi-year pavement replacement   2 Change Orders
Phase: Construction     program to replace distressed     Total Change Orders Amount:
Start: 05/02/2010         pavement and joint seal on the     -$4,027.27
Completion: 12/31/2016   airfield.
Budget/Costs Incurred
Significant Developments                     35
30
All contractor work for 2013 has been completed.
Millions 25
20
Schedule                             15
The 60% design for the fourth phase in 2014 will be distributed in      Dollars in  10
early January 2014.                                   5
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Commission
Authorization for construction funding and authority to advertise for    2013 Construction Costs
construction will be requested when the bid documents are
completed.
6000
5000
Change Order
Two change orders were executed this quarter. They are for         Millions  4000
3000
Reconciling Bid items on the major contract in the amount of -
2000
$4,027.27.                                        Dollars in  1000
0
Risks
Initial     Change     Spent
1000
None identified at this time.                                             Orders
Budget Transfers                        2014 Cargo 6 Panel
None this quarter.                                    Construction Costs
2500
2000
Millions 1500
Dollars in 
1000
500
0
Initial   Change   Spent
AIRPORT                              Orders
Port of Seattle 4Q 2013 Report  11

FOURTH QUARTER REPORT, 2013
Gate Utility Improvements
Status Snapshot Prior Report
Project:   C800019   This project will upgrade the South      Delayed Schedule     3Q 12
Satellite Port-owned loading bridges to
Budget: $11,744,480                         On Budget
the same standards, including 400Hz
Phase: Construction                        0 Change Orders
power and potable water. This will
Start: 06/28/2007                                 Total Change Orders Amount:
reduce air emissions, improve energy
Completion: 8/29/2014                        $0
efficiency and save money for the
airlines.
Budget/Costs Incurred
Significant Developments                     15
The Contractor is working at both the North and South Satellite.
Millions 10
Schedule
5
As previously reported, the project was delayed.                 Dollars in 
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
None
6
Risks                                  5
Airport Operations at certain gates could be impacted during the       Millions  4
construction phase of the project. Shutdown of South Satellite           3
Power being scheduled for Feb 11, 2014.                       2
Dollars in    1
Budget Transfers                           0
Initial   Change   Spent
None this quarter.                                              Orders



AIRPORT

12  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
North Expressway Relocation
Project:   C800034
The project reconstructs the North   Status Snapshot
Budget: $102,213,605    Airport Expressway and supports   Delayed Schedule
Phase: Construction     the extension of light rail to the    On Budget
Start: 07/27/2004         Airport. It also includes          226 Change Orders
Completion: 11/30/2014   improvements to Wall 14.       Total Change Orders Amount:
$8,295,574
Significant Developments
Budget/Costs Incurred
Reconstruction of the North Airport Expressway and the light rail
transit components are complete. Delay in Wall 14 improvements      115
project until 2014.
110
Millions
Schedule                             105
There is a delay in the final design and construction of the Wall 14
Dollars in 100                                                                            Improvements project until 2014.
95
Budget                               Authorized Forecasted Costs Incurred
Project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
No change orders issued this quarter.
120
100
Risks
Millions 80
None identified at this time.                                  60
40
Budget Transfers                          Dollars in  20
None.                                       0
Initial    Change Order    Spent

Photo



AIRPORT
Port of Seattle 4Q 2013 Report  13

FOURTH QUARTER REPORT, 2013
Main Terminal South Low Voltage
Project:   C800061   This project covers the renewal and     Status Snapshot Prior Report
Budget: $8,530,000   replacement of low voltage (600 volts   Delayed Schedule 1Q 08
On Budget
Phase: Design      and below) electrical distribution
0 Change Orders
Start: 06/28/2007      equipment in the southern part of the
Completion:        Main Terminal.               Total Change Orders Amount:
$0
01/31/2016
Budget/Costs Incurred
Significant Developments
Due to project deferral and the possibility of changes in site           10
conditions and building codes, the design phase changed from 100%
8
to 90% complete. Finalized Project Notebook to address scope of      Millions 6
work, schedule, and budget, presented to, and approved by the
Investment Committee on November 6, 2013. The project will go to      4
Commission in second quarter of 2014.                      Dollars in  2
0
Schedule                               Authorized Forecasted Costs Incurred
Staff has finalized the scope of work, schedule and final design
budget. The 100% design documents for this project are scheduled
to be complete by the end of August 2014.                   Construction Costs
Not Applicable
Budget
The project budget was increased. The project forecast is within the   Photo
approved budget. Commission Authorization for construction funding
and authority to advertise for construction will be requested when the
bid documents are completed.
Change Order
None
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will
be required to add additional crews to complete work in a timely
manner. This area is a 24/7/365 operation. Sequencing of this work
is critical and electrical power has to be maintained without
interruptions.
Budget Transfers
From C800404 (Aeronautical Allowance)         $4,274,000
AIRPORT
14  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Airport Owned Gate Infrastructure
Status Snapshot Prior Report
Project:   C800105      This project purchases and
Budget: $6,072,461      replaces passenger loading bridges  Delayed Schedule 3Q 12
(PLB) at gates throughout the      On Budget
Phase: Close Out                          0 Change Orders
Start: 07/24/2007         airport. The project is being
performed in phases.           Total Change Orders Amount:
Completion: 06/30/2013                       $0
Significant Developments
Budget/Costs Incurred
The project is complete and in closeout. This will be the last
quarterly report.                                          6.6
6.4
Schedule
Millions 6.2
The project is complete.                                   6
5.8
Budget                             Dollars in 5.6
5.4
The project forecast is within the approved budget and authorization.
Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT
Port of Seattle 4Q 2013 Report  15

FOURTH QUARTER REPORT, 2013
C4 UPS System Improvements
Project:   C800107    Project will replace existing          Status Snapshot Prior Report
Budget: $2,336,000   Uninterruptible Power Supply (UPS)    Delayed Schedule 1Q 09
Phase: Construction  System, including batteries, with a new  On Budget
Start: 06/28/2007      new system located in the Airport      0 Change Orders
Completion: TBD     Combined Communications and      Total Change Orders Amount:
Command Center (C4).           $0
Significant Developments                    Budget/Costs Incurred
Due to project deferral and the possibility of changes in site
2.5
conditions and building codes, the design phase changed from 100%
to 90% complete. Revised scope of work, schedule, and budget is      2
being included in the new Project Notebook.                    Millions 1.5
1
Schedule                            Dollars in 0.5
The project was reactivated. Staff is in the process of determining
0
the scope of work, schedule and final design budget.
Authorized  Forecasted Costs Incurred
Budget
The project budget is being evaluated based on delays and scope    Construction Costs
changes.                                    Not Applicable
Change Order                         Photo
None
Risks
The C4 center is a 24/7/365 operation, sequencing of this work is
critical and electrical power has to be maintained without
interruptions. It is not known when the construction will proceed as
this is specialized equipment and due to the complexity the new
system will require rigorous testing during the commissioning phase.
Budget Transfers
None this quarter


AIRPORT

16  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Runway 16C/34C Panel/Joint Sealant
Replacement
Status Snapshot
The scope of work will remove and   On Schedule
Project:   C800112      replace the pavement and joint seal  Under Budget
in areas on Runway 16C-34C.
Budget: $3,461,623                         0 Change Orders
Phase: Close Out                          Total Change Orders Amount:
Start: 02/26/2008                                 $0.00
Completion: 09/01/2012
Budget/Costs Incurred
Significant Developments
6
All contractor work has been completed for 2013. This will be the       5
last quarterly report for this project.                             Millions 4
3
Schedule
2
There are eleven runway panels scheduled for replacement in 2014,    Dollars in  1
which will be expensed.                                  0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Anticipated savings will be returned to the overall program in the first  Construction Costs
quarter of 2014.                                     Not Applicable
Change Order                         Photo
No change orders were executed this quarter.
Risks
No risks have been identified at this time.
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 4Q 2013 Report  17

FOURTH QUARTER REPORT, 2013
C60 - C61 BHS Modifications
Status Snapshot
On Schedule
Project:   C800168      The work planned under this      On Budget
Budget: $11,864,825     project represents a critical      0 Change Orders
Phase: Design        component in providing improved   Total Change Orders Amount:
Start: 06/01/2012         operational baggage in-line       $0
Completion: 12/31/2014   screening at the south end of the
Airport and provide more baggage  Budget/Costs Incurred
make-up capacity for airlines.
14
12
10
Significant Developments                     Millions 8
Design document were completed. Project team requested          6
Dollars in   4
Commission authorization to advertise and award a major contract in
2
November. The project was advertised and bids were opened
0
December 19. MD Moore Company was the apparent low bidder.        Authorized  Forecasted Costs Incurred
Schedule
The project is currently on schedule.                        Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
Completion of baggage make-up device to support Delta Airlines
added flights.
Budget Transfers
To C800404 (Aeronautical Allowance)        $1,404,176


AIRPORT

18  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Federal Inspection Services - New Primary
Inspection Booths
This project will replace existing     Status Snapshot  Prior Report
Project:   C800174      primary inspection booths for      Delayed Schedule 4Q 12
Customs and Border Protection in   On Budget
Budget: $1,849,000
the International Arrivals Federal    0 Change Orders
Phase: Construction     Inspection Services (FIS) facility in  Total Change Orders Amount:
Start: 07/27/2010         the South Satellite.             $0
Completion: 09/08/2011
Budget/Costs Incurred
Significant Developments
New signs have been delivered to the airport. Installation will begin      2.5
after Automated Passport Control (APC) Kiosk project is complete (in     2
the first quarter of 2014).                                    Millions 1.5
1
Schedule
Dollars in 0.5
The project is substantially complete. The current schedule for
completion of the replacement signs is now the first quarter of 2014.      0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Not Applicable
Change Order
None                                 Photo
Risks
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT
Port of Seattle 4Q 2013 Report  19

FOURTH QUARTER REPORT, 2013
Security Exit Lane Breach Control - Phase 1
Project:   C800218      This project will procure and install   Status Snapshot Prior Report
Budget: $1,310,000      new automated exit lane breach    Delayed Schedule 2Q 13
Phase: Construction     control equipment at the       On Budget
Start: 3/1/2012          Concourse B exit.             0 Change Orders
Completion: 06/30/2013                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
1.5
Equipment was ordered for post-construction work to convert the
twin door lanes to triple door lanes.
Millions  1
Dollars in 
Schedule
0.5
As previously reported, Port Construction Services completed
construction late due to additional commissioning of new equipment     0
needed in the field.                                          Authorized  Forecasted Costs Incurred
Budget
Project forecast is within the approved budget and authorization.     Construction Costs
Not Applicable
Change Order
None
Risks
No major risks at this time.
Budget Transfers
None this quarter.



AIRPORT

20  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Emergency Lighting - Parking
Project:   C800230      The purpose of this project is to    Status Snapshot Prior Report
Budget: $4,683,370      provide electrical infrastructure for   Delayed Schedule 4Q 12
Phase: Design        a new source of emergency power  On Budget
Start: 07/24/2012         to feed the parking garage        0 Change Orders
Completion: 07/31/2014   emergency lighting circuits and    Total Change Orders Amount:
ensure that code-required level of    $0
egress illumination is provided for
safety.                      Budget/Costs Incurred
5
Significant Developments
4
Awarded contract to Regency Northwest.
Millions  3
The ESCO contract with McKinstry was successfully completed. We     2
received the Department of Commerce rebate of $384,450 and BPA    Dollars in  1
rebate of $231,000.
0
Authorized  Forecasted Costs Incurred
Schedule
The infrastructure portion of the contract has been delayed due to
constructablity issues that were caught after the 100% design was    Construction Costs
complete, as previously reported. The design was going to require
major shutdowns that would significantly impact operations therefore      2
redesign of portions of the project is required.
1.5
1
The ESCO contract recevied substantial completion in December      Millions
2013. The work has been completed.                       0.5
Dollars in    0
Budget                                Initial Change Spent
0.5          Orders
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
The biggest challenge has been parked cars that are in the way.
Budget Transfers
None this quarter.

AIRPORT
Port of Seattle 4Q 2013 Report  21

FOURTH QUARTER REPORT, 2013
Feeder 101 Tap Replacements
Project:   C800234      Project Scope and description:     Status Snapshot Prior Report
Budget: $2,646,000      The project includes replacing the   Delayed Schedule 3Q 13
Phase: Design        electrical feeds to 13 locations    On Budget
Start: 04/01/2013         along Air Cargo Road. Also, the    0 Change Orders
Completion: 2/28/2015    electrical transformer and       Total Change Orders Amount:
associated switchgear for Air Cargo  $0
#4 will be replaced.
Budget/Costs Incurred
Significant Developments                     3
Design is 90% complete.                              2.5
Millions  2
Schedule                            1.5
1
Design is currently behind schedule due to additional scope, as       Dollars in 0.5
previously reported. Design is now scheduled to be complete in
0
March 2014. Plan to request authorization from Commission to bid        Authorized Forecasted Costs Incurred
the project in the second quarter of 2014.
Budget                            Construction Costs
The project forecast is within the approved budget. Authorization of   Not Applicable
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
None.
Risks
Unplanned electrical shut downs could impact the project schedule.
Budget Transfers
None.


AIRPORT
22  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Terminal Escalators Modernization
Project:   C800237
Budget: $30,610,979     This project will replace 42      Status Snapshot
Phase: Close Out      escalators in the Main Terminal,    On Schedule
Concourse B, and South Satellite.    Under Budget
Start: 11/02/2007
In addition, two new escalators will   130 Change Orders
Completion: 07/01/2013
be installed at the South Satellite.    Total Change Orders Amount:
$6,025,111
Significant Developments
Escalator installation is complete. Close out of activities are
continuing. This is the last quarterly report.                     Budget/Costs Incurred
60
Schedule
50
The project is in close out.                                  Millions 40
30
Budget
20
The project is within the approved budget and authorization. Savings   Dollars in  10
are being returned at closeout.
0
Authorized  Forecasted    Costs
Change Order                                     Incurred
Construction contract completion letter issued. There are no further
change orders.                                   Construction Costs
25
Risks
20
None identified at this time.
Millions 15
Budget Transfers                          10
None this quarter.                                     Dollars in  5
0
Cost of Construction Growth                      Initial Change Order Spent
Circumstances contributing to cost growth: differing site conditions
encountered at the South Satellite during the installation of the two
new escalators resulted in revisions to the architectural and
structural designs, increased cost of construction, acceleration of
operationally critical units, and impacted the critical path of the
project circumstances contributing to cost growth. Cost increases
also experienced due to state inspector imposed requirement for a
hard barrier between escalators during construction.
AIRPORT
Port of Seattle 4Q 2013 Report  23

FOURTH QUARTER REPORT, 2013
Central Plant Pre-Conditioned Air
Status Snapshot Prior Report
Delayed Schedule 1Q 13
Project:   C800238     This project will provide a centralized  Forecast Overrun
Budget: $51,890,000    pre-conditioned air (PC-Air) plant    190 Change Orders
Phase: Construction    (PCAP), associated heating and    Total Change Orders Amount:
Start: 06/15/2009       cooling piping systems, and jet bridge  $7,604,291
Completion: 08/31/2013  terminal air handling units to serve
airplanes with heating and cooling
while at the gates.
Budget/Costs Incurred
Significant Developments
PC-Air is operating at 62 gates. Four gates are remaining, but         54
operational needs have delayed work on these until first quarter of      52
2014. This work was removed from the General Contract and will be   Millions 50
completed separately.                                  48
46
Schedule                            Dollars in 44
The original contract completion date for all gates was December 11,    42
Authorized  Forecasted Costs Incurred
2012. The delay was primarily due to Concourse D redesign, as
previously reported. All but four gates are complete, and will be
completed in first quarter of 2014 contingent on operational needs.
Construction Costs
Budget
40
Negotiations with the contractor on potential change orders and
claims risk are in process. As negotiations proceed, identify potential      30
budget issues. Current project forecast including open claims
20
exceeds approved budget and authorization. Staff will return to
Millions
Commission to request additional funding and authorization to        Dollars in   10
execute change orders.
0
Initial   Change   Spent
Change Order                                Orders
Twenty change orders issued this quarter. Issued change orders for
piping and electrical site conflicts on the concourse and at the gates.
Risks
There is budget risk based on the dollar amount of open potential
change orders and claims. There is schedule risk as completing work
at each gate is contingent on gates being available.


24  Port of Seattle 4Q 2013 Report

Budget Transfers
None this quarter.
Cost of Construction Growth
Cost growth is still occuring due to shortcomings in the bid documents. Current cost of executed
Change Orders is 36% of the base contract price. The trended cost growth projection is currently 32%
over bid price. Approximately 20% are related to error and/or ommissions (owner or designer), 7%
are currently in some form of dispute. The remainder of the cost growth are due to site conditions,
discretionary tenant requests or scope changes and regulatory requirements respectively. The
current projections do not include any cost trending for potential claims due to late project completion
due to owner caused delay.










AIRPORT

Port of Seattle 4Q 2013 Report  25

FOURTH QUARTER REPORT, 2013
Cargo 2 West Cargo Hardstand
Project:   C800247      This project will enlarge the       Status Snapshot Prior Report
Budget: $11,830,000     western cargo hardstand in the    Delayed Schedule 3Q 12
Phase: Construction     Cargo 2 area, it includes buyout of  On Budget
Start: 09/25/2012         two cargo buildings and tenant     0 Change Orders
Completion: 12/31/2014   relocations; relocation of FAA     Total Change Orders Amount:
antenna, security gate, and guard    $0
shack; and installation of 400Hz inground
power.              Budget/Costs Incurred
15
Significant Developments
Cargo 2 Hardstand project is combined with Cargos 5 and 6 into a
Millions 10
single construction contract which has been successfully bid and
awarded.
5
Dollars in 
Schedule
0
Construction is scheduled to begin the first quarter of 2014 and to be       Authorized  Forecasted Costs Incurred
completed in second quarter. Demolition of Building #2 is scheduled
for the second quarter. FAA's antenna will be relocated during the
second quarter.                                    Construction Costs
Budget                             5000
The project forecast is within approved budget and authorization.      4000
3000  Millions
Change Order
2000
None
1000  Dollars in 
Risks                                 0
Initial    Change Order    Spent
None identified at this time.
Budget Transfers
Photo
None this quarter.


AIRPORT

26  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Vertical Conveyance Modernization Program -
Aeronautical - Phase I
Perform modernization on 7       Status Snapshot  Prior Report
Project:   C800251      existing elevators: SSAF, MT-2,    Delayed Schedule 3Q 13
MT-3, MT-4, MT-5, MT-6, MT-7,    On Budget
Budget: $22,823,408
plus install cooling packages on 12   0 Change Orders
Phase: Design        existing hydraulic elevators      Total Change Orders Amount:
Start: 10/25/2011         throughout Main Terminal and 4    $0
Completion: 06/30/2016   escalators at skybridge 6.
Significant Developments
Budget/Costs Incurred
Changing priorities concerning failure of existing Main Terminal
elevators has prompted further review of project scopes, and the
25
consolidation of all Main Terminal elevators to Phase I, and two new
20
South Satellite elevators to Phase II. Also added to the scope was
the design of one additional hydraulic oil cooling package for         Millions 15
Elevator Q; this elevator is experiencing overheating time-outs to       10
serve United Airlines' club associated with airline relocation to         Dollars in  5
Concourse A.
0
Authorized  Forecasted Costs Incurred
Schedule
The construction is scheduled to begin in the third quarter of 2014,
with construction completion in the third quarter of 2016.           Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction has
been requested and bidding is underway.
Change Order
None
Risks
Final determination of scope and priorities could cause delays.
Budget Transfers
From C800375 (Vertical Convey Modn Aero Ph2)   $8,834,408
From C800404 (Aeronautical Allowance)          $486,789

AIRPORT
Port of Seattle 4Q 2013 Report  27

FOURTH QUARTER REPORT, 2013
Parking System Replacement
Status Snapshot Prior Report
Project:   C800253      This project replaces the current    Delayed Schedule 2Q 12
Budget: $6,076,999.30    Parking Revenue Control System,   On Budget
Phase: Construction     which manages parking access    9 Change Orders
Start: 04/06/2010         and revenue collection in the      Total Change Orders Amount:
Completion: 08/31/2012   Airport's Main Parking Garage.    $195,780
Budget/Costs Incurred
Significant Developments
12
Scheidt & Bachmann (S&B), the system vendor completed final
10
testing. The vendor's software has experienced a number of failures,
leading to reporting and operational issues. The Port is working with    Millions 8
6
S&B to correct the outstanding issues.
4
Dollars in   2
Schedule
0
The system is substantially complete. However, service outages of        Authorized  Forecasted Costs Incurred
the vendor's system have led to delays in system commissioning.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  None this quarter
Change Order                         Photo
No new change orders occurred during the reporting period.
Risks
The Port is actively engaging the Contractor at the executive level to
address system issues.
Budget Transfers
None this quarter.



AIRPORT

28  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Aircraft RON Parking USPS Site
Status Snapshot Prior Report
Delayed Schedule     1Q 11
Project: C800254        This project will prepare the site for
On Budget
Budget: $46,040,000     the construction of hardstands for
0 Change Orders
Phase: Construction    use as Remain Overnight (RON)
Total Change Orders Amount:
Start: 08/26/2008        parking of aircraft at the Cargo 5
$0.00
area.
Completion: 12/31/2014
Significant Developments                    Budget/Costs Incurred
A single construction contract with three cargo areas (Cargo Area's     60
2, 5 and 6) has been bid and awarded.                       50
Millions 40
Schedule                             30
Contract execution will be in the first quarter of 2014. Construction      20
will begin in the first quarter of 2014. Cargo 5 is scheduled to be       Dollars in  10
completed by the end of the third quarter of 2014.                 0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
25000
None this quarter.
20000
Risks
15000   Millions
None identified at this time.
10000
Dollars in 
Budget Transfers
5000
None this quarter.
0
Initial      Change Order      Spen
Photo



AIRPORT
Port of Seattle 4Q 2013 Report  29

FOURTH QUARTER REPORT, 2013
Port-Owned Loading Bridge Renewal &       Status Snapshot
Replacement                     On Schedule
On Budget
0 Change Orders
Project:   C800267      This project will allow the Airport to
replace or refurbish Port-owned     Total Change Orders Amount:
Budget: $2,405,000
Passenger Loading Bridges (PLBs)  $0
Phase: Construction     that have reached the end of their
Start: 02/28/2012         service life.
Completion: 12/31/2014
Budget/Costs Incurred
Significant Developments                      3
The work at S3 and S12 has been completed. The work at S4 will     2.5
be transferred to the 12th & 13th FIS Gate project (C800662).         Millions 2
1.5
Schedule                             1
Dollars in 0.5
The remainder of work programmed for this project is currently on
0
hold.
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Change Order
0.8
None                                   0.6
Millions  0.4
Risks
0.2
None identified at this time.
Dollars in    0
Initial   Change   Spent
Budget Transfers                           0.2    Orders
None this quarter.



AIRPORT

30  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Stage 2 Mechanical Energy Implementation
Status Snapshot Prior Report
Project:   C800268      This project will improve the energy  Delayed Schedule 3Q 13
Budget: $2,852,900.00    performance of the mechanical    On Budget
Phase: Construction     infrastructure systems at the     0 Change Order
Start: 10/01/2011         Airport.                    Total Change Orders Amount:
Completion: 10/31/2013                       $0
Budget/Costs Incurred
Significant Developments                     2.9
The project is substantially complete.                          2.8
Millions 2.7   Dollars in 
Schedule
2.6
Closed major construction and entering energy savings verification.     2.5
2.4
Budget
Authorized  Forecasted Costs Incurred
The forecast is within the approved budget and authorization.
Change Order                         Construction Costs
None
3
Risks                                 2.5
2
None identified at this time.
1.5
Millions
Budget Transfers                           1
Dollars in   0.5
None this quarter.
0
Initial   Change   Spent
Orders



AIRPORT

Port of Seattle 4Q 2013 Report  31

FOURTH QUARTER REPORT, 2013
8th Floor Weatherproofing
Status Snapshot Prior Report
Delayed Schedule 3Q 13
Project:   C800274      This project includes removal and   On Budget
Budget: $9,474,000      replacement of the floor covering   22 Change Orders
Phase: Construction     system on the eighth floor of the   Total Change Orders Amount:
Start: 03/23/2010         STIA parking garage and repair or   $69,558
Completion: 07/31/2014   replacement of expansion joints
and flashings.
Budget/Costs Incurred
Significant Developments                     15
The Port's contractor, PCL Construction, stripped and replaced old
weatherproofing, and performed crack repair on the eighth floor       Millions 10
garage deck. Weatherproofing failed in portions of sections B and C.
The work was rejected and will be repaired June 2014 at contractor's     5
expense.                                      Dollars in 
0
Schedule                               Authorized Forecasted Costs Incurred
Defective work has resulted in a delay of beneficial occupancy. The
new end date is expected to be July 31, 2014, which was previously
reported.                                          Construction Costs
8
Budget
The project forecast is within the approved budget and authorization.     6
4
Change Order
Millions
Executed one change order this quarter for railing modifications.       Dollars in  2
0
Risks                                   Initial Change Order Spent
This is a weather-dependent project.
Budget Transfers                        Photo
None this quarter.


AIRPORT

32  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Common Use Equipment Expansion (CUSE)
Project:   C800276      This project installs flexible       Status Snapshot
Budget: $1,461,000      passenger processing         On Schedule
Phase: Close Out      infrastructure and equipment at the  On Budget
Start: 09/01/2009         airline gates at some South       25 Change Orders
Completion: 09/30/2012   Satellite gates.            Total Change Orders Amount:
-$11.926
Budget/Costs Incurred
Significant Developments
3
Project close out is complete. This will be the last quarterly report.
2.5

2
Schedule
MillionsDollars in     1.5
The project is complete.
1
Budget                             0.5
0
The project forecast is within the approved budget and authorization.        Authorized    Forecasted   Costs Incurred
Change Order
None                                 Construction Costs
Risks                                 0.7
0.6
None identified at this time.
Millions    0.5
0.4
Budget Transfers                         Dollars in  0.3
0.2
None this quarter.                                       0.1
0
Initial        Change Orders        Spent
0.1




AIRPORT

Port of Seattle 4Q 2013 Report  33

FOURTH QUARTER REPORT, 2013
Long-Term Cell Phone Lot
Status Snapshot Prior Report
Project:   C800324      Construct a new cell phone waiting  Delayed Schedule 1Q 13
Budget: $1,435,000      lot to replace the existing lot that is  Forecast Overrun
Phase: Construction     being displaced, and construct a   0 Change Orders
Start: 12/11/2012         traffic control roundabout adjacent   Total Change Orders Amount:
Completion: 12/31/2014   to the lot on South 170th Street.    $0
Budget/Costs Incurred
Significant Developments                     2
Design of the cell phone lot is complete and construction has started.    1.5
Design of the roundabout is at 60%. Design of the temporary traffic    Millions
1
signal has started. The project team is working collaboratively to
develop a plan to construct the cell phone lot and be operational      Dollars in 0.5
before existing lot is demolished due to construction.
0
Authorized  Forecasted Costs Incurred
Schedule
The cell phone lot is to be constructed ahead of the roundabout due
to longer time needed for design and permitting. Cell phone lot      Construction Costs (PCS
beneficial occupancy is scheduled for April 1. Roundabout         Only)
construction starts third quarter of 2014 with completion in fourth
quarter of 2014.                                       0.5
0.4
Budget                             Millions 0.3
Roundabout construction cost is being developed. Early estimate      0.2
exceeds Commission Authorization for roundabout construction. If     Dollars in 0.1
necessary, additional authorization will be requested.
0
Initial    Change Order    Spent
Change Order
None
Photo
Budget Transfers
To C800404 (Aeronautical Allowance)          $333,000
To C800405 (Non-Aeronautical Allowance )       $753,000
Risks
Schedule uncertainties related to roundabout design review and
permit acquisition time requirement. There is potential wet/winter
construction-related delay to cell phone lot construction that could
result in no cell phone lot for up to a few weeks.

AIRPORT
34  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Two New CTE Freight Elevators
Status Snapshot Prior Report
Delayed Schedule 2Q 12
Project:   C800334      Provide two new freight elevators   On Budget
Budget: $8,302,648      to support concession operations in  5 Change Orders
Phase: Construction     the Central Terminal/Pacific      Total Change Orders Amount:
Start: 08/05/2011         Marketplace.                $49,535
Completion: 07/31/2014
Budget/Costs Incurred
Significant Developments
The contract was awarded in April to Pease Construction. Notice To     10
Proceed was issued in June. The contractor commenced sawcutting     8
concrete pavement for North Freight elevator pit & installation of new    Millions 6
grease Interceptor.
4
Schedule                            Dollars in  2
As previously reported, the project is anticipating a one-year delay       0
Authorized  Forecasted Costs Incurred
due to scope changes included in the redesign efforts, and delays in
reviews.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.
5
4
Change Order
Millions   3
Four (4) change orders executed this quarter.
2
Risks                                Dollars in   1
No new risks identified this quarter.                              0
Initial   Change   Spent
Orders
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 4Q 2013 Report  35

FOURTH QUARTER REPORT, 2013
Electrical Ground Support Equipment (EGSE)
Electrical Charge Stations                Status Snapshot Prior Report
Delayed Schedule 1Q 13
On Budget
Airport-wide electrical charging     25 Change Orders
Project:   C800335      system for electrical ground       Total Change Orders Amount:
Budget: $30,198,000     support equipment (EGSE) at the   $103,135
Phase: Design        Concourses and the North and
Start: 10/26/2010         South Satellites.
Completion: 12/31/2015
Significant Developments                    Budget/Costs Incurred
Beneficial Occupancy received for the installation of 40
demonstration charge stations on Concourse C2 for Horizon Airlines.     35
Phase 1 includes balance of charge stations at Concourse C, D and     30
North Satellite. Contractor has issued partial Beneficial Occupancy    Millions  25
20
for charge corrals at Concourse C, D and at North Satellite.         Dollars in   15
Beneficial Occupancies are completed and Assets were completed
10
and submitted to accounting.
5
0
Authorized       Forecasted      Costs Incurred
Consultant issued GSE Charger Phase 2 Project 100% bid design
documents for review that includes Concourse A, B and South
Satellite. Review is nearing completion. FAA approved 2013 VALE
grant for $3,547,527. A second application was submitted to FAA for  Construction Costs
an additional $9,161,233 2014. A request for exemption to the
Washington Sales Tax was submitted for the GSE Charger Phase 2     4
Project.
3
Millions
Schedule                             2
Phase 1 construction is basically complete except for some punch     Dollars in  1
list items not in the major contract; Phase 2 construction scheduled
0
for completion in late 2015.
Initial    Change Order    Spent
Budget
The project forecast is within the approved budget. The remaining
authorization for the construction funding and authority to advertise
for construction will be requested when the design and bid
documents are completed for GSE Charger Phase 2 Project.
Change Order
Twenty-five change orders issued.

36  Port of Seattle 4Q 2013 Report

Risks
Coordinate with other airfield projects and Airline Gate Realignment program. Budget and schedule
may affect project implementation and completion.
Budget Transfers
None this quarter.












AIRPORT
Port of Seattle 4Q 2013 Report  37

FOURTH QUARTER REPORT, 2013
Claim Device 14 & Lower Inbound
Status Snapshot Prior Report
Project:   C800374      This project will replace the slope-   Delayed Schedule 4Q 12
Budget: $1,897,000      plate bag claim device 14 and     On Budget
Phase: Close Out      associated controls, in addition to   23 Change Orders
Start: 04/01/2011         removing the lower feed conveyor   Total Change Orders Amount:
Completion: 3/31/2013    and replacing it with a new      $129,002
overhead feed.
Budget/Costs Incurred
5
Significant Developments
4
The project is currently in close-out. This will be the last quarterly      Millions 3
report.
2
Schedule                            Dollars in  1
As previously reported, the project was delayed due to Hurricane       0
Sandy. Equipment was on the dock at the Port of New York the day       Authorized  Forecasted Costs Incurred
of the hurricane. The Port worked with the contractor to come up
with a recovery schedule. The construction was completed in March.
Construction Costs
Budget
1.2
The project forecast is within the approved budget and authorization.
1
Change Order                          Millions 0.8
0.6
None
0.4
Dollars in   0.2
Risks
0
None identified at this time.                                      Initial  Change  Spent
Orders
Budget Transfers
None this quarter.



AIRPORT
38  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
South Satellite HVAC, Lights, and Ceiling
Replacement
This project will replace the heating   Status Snapshot
Project:   C800376      ventilation, lighting and ceiling     On Schedule
systems in the South Satellite.      On Budget
Budget: $34,011,000
0 Change Orders
Phase: Design                            Total Change Orders Amount:
Start: 7/24/2012                                  $0
Completion: 07/31/2016
Budget/Costs Incurred
Significant Developments
Thirty percent design delayed pending the finalization of mechanical     40
equipment room locations and review of seismic requirements.
30
Design is scheduled to resume in the first quarter of 2014.           Millions
Completed negotiation of the service directive modification to          20
address a revised scope of work.
Dollars in  10
Schedule
0
Thirty percent design is scheduled to be completed second quarter        Authorized Forecasted Costs Incurred
of 2014. The project will then be evaluated prior to proceeding.
Budget
The project forecast is within the approved budget. Authorization of   Construction Costs
construction funding and authority to advertise for construction will    Not Applicable
be requested when the bid documents are completed.
Change Order
none
Risks
South Satellite siesmic analysis and strategy may impact project
costs and schedule. Seismic upgrade is not currently in the design
scope of work.
Budget Transfers
None this quarter

AIRPORT

Port of Seattle 4Q 2013 Report  39

FOURTH QUARTER REPORT, 2013
Baggage Handling System (C22-C1, MK1, and
Status Snapshot
TC3)                          On Schedule
This project will replace the ticket    On Budget
Project:   C800382      counter (TC3) conveyors and      42 Change Orders
declines, reroute the conveyors of   Total Change Orders Amount:
Budget: $5,861,000
the C-22 system and connect it to    $181,179
Phase: Close Out      the C-1 screening system, replace
Start: 03/01/2011         the existing makeup (MK1) device,  Budget/Costs Incurred
Completion: 05/31/2013   and install a new odd size baggage
8
system.
6
Millions
Significant Developments                     4
The original project is currently in closeout, which is associated to      Dollars in  2
this project as part of the International Window Wall Ticket Counters
0
and Bag Belt system. This included the connection between belts        Authorized Forecasted  Costs
C60 and C61. The ticket counters and belt system will open on                      Incurred
February 20, 2014 with ANA Airlines.
Construction Costs
Schedule
2
The project is currently on schedule.
1.5
Budget                             Millions
1
The project forecast is within the approved budget and authorization.
Dollars in   0.5
Change Order
0
There are currently 42 change orders executed on this contract.            Initial  Change  Spent
Orders
Risks
None identified at this time.
Budget Transfers
To C800404 (Aeronautical Allowance)          $900,000
Cost of Construction Growth
Three changes represent the majority of the cost growth: 1) removed
the C1-CS1 curbside conveyor since replacement was no longer
required, 2) The contract design to replace make-up device MK1 did


40  Port of Seattle 4Q 2013 Report

Cost of Construction Growth (Cont.)
not include POS ergonomic standards for this kind of device; and 3) the original contact design for the
conveyors in the C1-CS2 conveyor line created unsafe electrical and mechanical conditions for
maintenance works. Several other smaller changes included fire sprinkler and architectural revisions,
including a credit to remove a small scope of work.












AIRPORT
Port of Seattle 4Q 2013 Report  41

FOURTH QUARTER REPORT, 2013
Cargo 6 Enhancements
Project:   C800390      This project will enlarge the Cargo   Status Snapshot Prior Report
Budget: $6,428,000      6 off-gate hardstand to allow     Delayed Schedule 4Q 12
Phase: Construction     simultaneous nose-loading of wide-  On Budget
Start: 09/25/2012         body freight aircraft as well as      0 Change Orders
Completion: 12/31/2014   provide fuel hydrant and ground    Total Change Orders Amount:
power capabilities.              $0
Budget/Costs Incurred
Significant Developments
8
Cargo 6 Enhancements has been combined with Cargo Areas 2 and
5 as a single construction contract and has been successfully bid       6
and awarded.                                   Millions
4
Schedule                            Dollars in  2
Construction of the Cargo 6 hardstand enhancements will begin in
0
third quarter of 2014. Completion is scheduled for fourth quarter of         Authorized  Forecasted Costs Incurred
2014.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.
3500
Change Order                          3000
2500
None this quarter                                     2000  Millions
1500
Risks                                1000 Dollars in 500
None identified at this time.
0
Initial    Change Order    Spent
Budget Transfers
None this quarter
Photo



AIRPORT
42  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
RW16C/34C Reconstruction
Status Snapshot
On Schedule
Project:   C800406      This project will produce the 60%   On Budget
Budget: $669,000       design for the runway 16C/34C    0 Change Orders
Phase: Design        reconstruction. The design will    Total Change Orders Amount:
Start: 05/04/2010         include utilities, runway status      $0
Completion: 11/30/2016   lights, and other scope items
related to the project.            Budget/Costs Incurred
Significant Developments                     0.8
The decision has been made to advance the reconstruction of        0.6
Runway 16C/34C by one year to begin construction in 2015.         Millions
0.4
Schedule                            Dollars in 0.2
Staff will return to Commission for authorization of the remaining
0
design funds in the first quarter of 2014. The construction is              Authorized  Forecasted Costs Incurred
scheduled to begin in the second quarter of 2015.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 4Q 2013 Report  43

FOURTH QUARTER REPORT, 2013
South Satellite Concessions Project
Project:   C800412      This project demolished and      Status Snapshot
Budget: $1,777,400      relocated the old duty free shop,   Delayed Schedule
Phase: Construction     electric/communications to support  On Budget
Start: 01/01/2011         a temporary duty free location were  0 Change Orders
Completion: 12/31/2013   installed and construct a new food   Total Change Orders Amount:
and beverage shell space in the     $0
South Satellite at Sea-Tac Airport
was completed.
Budget/Costs Incurred
1.8
Significant Developments
1.7
The project is substantially complete.                         Millions 1.6
Schedule                             1.5
The contractor will complete all work associated with this project in     Dollars in 1.4
early November. The delay is partially a result of the late start for the     1.3
second phase of this project caused by the tenant build out of the          Authorized  Forecasted Costs Incurred
new duty free shop.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT
44  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Access Control Door Additions
Status Snapshot Prior Report
Project:   C800414      This project will provide biometric   Delayed Schedule 3Q 12
Budget: $1,543,444      access controls and security     On Budget
Phase: Close Out      cameras at airport terminal doors.   4 Change Orders
Start: 09/27/2011                                 Total Change Orders Amount:
Completion: 08/30/2013                       $23,123
Significant Developments                    Budget/Costs Incurred
The project is complete. This will be the last quarterly report.          2
1.5
Schedule                            Millions 1
Construction was completed in August.
0.5
Budget                             Dollars in 
0
Project forecast is within the approved budget and authorization.          Authorized Forecasted Costs Incurred
Change Order
None this quarter.                                    Construction Costs
0.6
Risks
0.5
None identified at this time
Millions  0.4
0.3
Budget Transfers
0.2
None this quarter.                                      Dollars in  0.1
0
Initial   Change   Spent
Orders



AIRPORT

Port of Seattle 4Q 2013 Report  45

FOURTH QUARTER REPORT, 2013
Airfield Lighting Control and Monitoring System
(ALCMS) Upgrades                  Status Snapshot
Provide modifications to the Airfield   On Schedule
Project:   C800415      Lighting Control and Monitoring    On Budget
System to update, enhance and    1 Change Orders
Budget: $1,732,144
stabilize the system to meet the     Total Change Orders Amount:
Phase: Close Out      latest FAA specifications.       $17,989
Start: 01/01/2011
Completion: 07/31/2013
Budget/Costs Incurred
Significant Developments
Liberty Airport Systems was operational on July 12, 2013. The        2.5
project is in closeout.                                        2
Millions 1.5
Schedule
1
The project was completed on schedule.                     Dollars in 0.5
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Change Order 1 was issued for FAA ALCMS Training workstation.    Not Applicable
Risks
None identified at this time.
Budget Transfers
From C800404 (Aeronautical Allowance)          $50,000




AIRPORT
46  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Lagoon 3 Bird Wires
Status Snapshot
On Schedule
Project:   C800417      This project will reduce access by   On Budget
Budget: $1,563,000      waterfowl to the industrial       19 Change Orders
Phase: Construction     wastewater system Lagoon 3,     Total Change Orders Amount:
Start: 10/11/2011         which is located near the south end  $117,370.30
Completion: 10/31/2012   of the airfield.
Budget/Costs Incurred
2
Significant Developments
1.5
The major construction work is complete.
1
Millions
Schedule                            Dollars in 0.5
Some minor work remains by Port Construction Services to improve
0
post stability. One-year warranty period ended in November 2013.          Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Change Order                           1
No change orders were executed this quarter.                   0.8
Millions  0.6
Risks                                 0.4
No risks have been identified at this time.                       Dollars in   0.2
0
Budget Transfers                             Initial Change Spent
Orders
None this quarter.
Cost of Construction Growth                  Photo
The contractor was compensated for additional costs for revisions to
access gate framing and ramp posts. This change order was the
result of a design error or omission.


AIRPORT

Port of Seattle 4Q 2013 Report  47

FOURTH QUARTER REPORT, 2013
Federal Inspection Services Short Term
Status Snapshot Prior Report
Improvements                    Delayed Schedule 1Q 13
Short Term Improvements to the    On Budget
Project:   C800426      Federal Inspection Service area at   0 Change Orders
the South Satellite to improve      Total Change Orders Amount:
Budget: $1,141,000
through put and improve conditions  $0
Phase: Design        for passengers waiting in the
Start: 04/01/2012         International Corridor prior to
Completion: 02/28/2014   Primary Inspection.
Budget/Costs Incurred
Significant Developments                     1.2
1
Project scope was refined at 90% design to split work between small
works and major contract to faciliate faster completion. Bid docs for     Millions 0.8
0.6
major contract work are being developed for an early January 2014
0.4
advertisement.                                     Dollars in 0.2
Schedule                             0
Authorized  Forecasted Costs Incurred
Advertisement and construction completion for major contract work
has been accelerated to recover time lost during 60% design
development. Goal is to complete construction work prior to the
Construction Costs
busy summer 2014 travel season.
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
Although additional funding has been secured for 90% design,
budget remains tight and design is not yet final.
Budget Transfers
From C800404 (Aeronautical Allowance)        $100,000

AIRPORT

48  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Doug Fox Lot Service Upgrades
Project:   C800451      Construct a new drainage system,   Status Snapshot Prior Report
Budget: $6,453,000      asphalt resurfacing, improved lot   Delayed Schedule 1Q 13
Phase: Construction     lighting, new building, and road    On Budget
Start: 02/01/2012         signage to improve lot appearance,  1 Change Orders
Completion: 09/30/2014   function, and revenue generation.   Total Change Orders Amount:
$10,000.00
Budget/Costs Incurred
Significant Developments
8
Construction bids opened on September 5th, and the low bid
6
exceeded the engineer's estimate by more than 10%. Commission     Millions
authorized additional budget and the contract was awarded.           4
Schedule                            Dollars in  2
Project schedule was delayed to resolve the bid irregularity. Pre-        0
construction submittals are in progress and notice to proceed is           Authorized  Forecasted Costs Incurred
expected in early January 2014.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.
5
The budget was increased to the bid irregularity and additional
construction contingency.                                 4
3
Change Order
Millions
2
One change order was executed this quarter for "Valley View         Dollars in  1
Sewer/City of Seatac Right of Way Use Permit Conditions and
0
Potholing" in the amount of $10,000.00.
Initial    Change Order    Spent
Risks
Wet/winter construction could cause additional delays to completion   Photo
of the work.
Budget Transfers
From C800405 (Non-Aeronautical Allowance )    $1,335,000

AIRPORT
Port of Seattle 4Q 2013 Report  49

FOURTH QUARTER REPORT, 2013
Concourse D Common Use Environment
Status Snapshot Prior Report
Delayed Schedule 3Q 11
Project:   C800455      This project installs a common-use  On Budget
Budget: $4,100,000      environment at all gates on      14 Change Orders
Phase: Close Out      Concourse D. Scope includes new  Total Change Orders Amount:
Start: 03/01/2011         communications infrastructure,     $111,155
Completion: 04/30/2013   casework built to a new Airport
standard, new carpet, wall        Budget/Costs Incurred
coverings and task lighting.
5
4
Significant Developments
Millions  3
Project is in close out.
2
Schedule                            Dollars in  1
Contractor completed non-essential project work prior to contract        0
end date of August 2013.                                  Authorized Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Change Order                           1.5
None
1
Risks
Millions
0.5
None identified at this time.                                  Dollars in 
0
Budget Transfers                             Initial Change Spent
Orders
None this quarter.



AIRPORT
50  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
2011-2013 Roof Replacement Program
Status Snapshot
On Schedule
Project:   C800459      This project will remove and      Under Budget
Budget: $4,659,000      replace the roofing systems on the  0 Change Orders
Phase: Close Out      fire station and north end of the    Total Change Orders Amount:
Start: 07/01/2011         main terminal.                $0
Completion: 10/31/2013
Budget/Costs Incurred
5
Significant Developments
4
This project received beneficial occupancy on October 31, 2013.
Millions  3
Dollars in 
Schedule                             2
The project was completed on schedule.                      1
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Savings will be returned at closeout.
Construction Costs
Change Order
None                                    2
1.5
Risks                                Millions
1
None identified at this time.
Dollars in   0.5
Budget Transfers
0
None this quarter.                                          Initial  Change  Spent
Orders




AIRPORT

Port of Seattle 4Q 2013 Report  51

FOURTH QUARTER REPORT, 2013
Industrial Waste Treatment Plant (IWTP) Fiber
Installation
Install new Single Mode Fiber cable
Project:   C800461      from Main Terminal to IWTP and    Status Snapshot Prior Report
Gate E-45.                 Delayed Schedule 1Q 13
Budget: $514,000
On Budget
Phase: Construction                        0 Change Orders
Start: 03/01/2012                                 Total Change Orders Amount:
Completion: 10/31/2014                       $0
Significant Developments                    Budget/Costs Incurred
The Fiber Optic Cable has been installed from Main Terminal to the
new equipment termination cabinet near the Alaska Hangar and       0.6
Gate E-45. Selected new routing for conduits for remaining portion     0.5
of the route since co-use of existing conduits from E-45 to the IWTP     0.4
with FAA fiber optic cable is not permitted. Completed final design      Millions 0.3
for submission to FAA.                                  0.2
Dollars in 0.1
Schedule                             0
Authorized  Forecasted Costs Incurred
The schedule delay is due to a change in the FAA policy/personnel.
The original FAA conduit for the project was deemed full and
permission to use it was denied. A new route was developed, but
requires trenching and installation of new conduit in the aircraft      Construction Costs
movement area. Construction will be done in the summer months.    Not Applicable
Budget
The project forecast is currently within the approved budget and
authorization.
Change Order
None
Risks
The project may require additional budget and authorization. When
the design for the revised route is completed, revised scope and
costs will be developed.
Trenching adjacent to taxiways for new proposed routing.
Budget Transfers
None this quarter.
AIRPORT
52  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Fiber Infrastructure to Gate Backstands
Project:   C800464      This project extends airport       Status Snapshot
Budget: $3,284,000      provided communications       On Schedule
Phase: Design        infrastructure and wifi antennas to   On Budget
Start: 07/09/2013         additional gates on Concourses A,   0 Change Orders
Completion: 04/01/2015   B and C.                Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
4
Design is currently underway.
3
Millions
Schedule
2
The project schedule has been delayed due to contract negotiations.
Dollars in   1
The project team is determining if the delay will affect the overall
schedule.                                         0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Commission
Authorization for construction funding and authority to advertise for    Construction Costs
construction will be requested when the bid documents are        Not Applicable
completed.
Change Order
None at this time.
Risks
The design has been delayed during the negotiations process, which
may affect the overall delivery schedule.
Budget Transfers
None.


AIRPORT

Port of Seattle 4Q 2013 Report  53

FOURTH QUARTER REPORT, 2013
South Satellite - Additional Gate Lobby
Project:   C800466      Demolition of glass partitions,      Status Snapshot Prior Report
Budget: $1,965,000      restrooms, relocation of gate     Delayed Schedule 3Q 12
Phase: Close Out      podiums new flooring, ceilings and  On Budget
Start: 11/01/2010         infrastucture to provide additional    14 Change Orders
Completion: 09/15/2013   gate lobby in the South Satellite.   Total Change Orders Amount:
$141,934
Significant Developments
This project is complete and in closeout.
Budget/Costs Incurred
Schedule
As previously reported, the project delay was caused by delayed
2
design negotiations and contracting. Additionally, a longer design
1.95
period is required due to dependency on the South Satellite
Concessions Project (C800412).                          Millions 1.9
1.85
Budget                             Dollars in 1.8
The project forecast is within the approved budget and authorization.
1.75
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks
None identified at this time.                                   2.5
2
Budget Transfers                          Millions 1.5
None this quarter.                                        1
Dollars in   0.5
0
Initial   Change   Spent
Orders


AIRPORT
54  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Passenger Loading Bridge Replacement -
Airline Realignment                    Status Snapshot
This project entails Passenger      On Schedule
Project:   C800467      Loading Bridge (PLB)          On Budget
replacements associated with the    31 Change Orders
Budget: $7,847,539
one-time airline realignment (AR).    Total Change Orders Amount:
Phase: Close Out      The work will take place at      $168,886
Start: 04/12/2011         Concourse D and Concourse B.
Completion: 09/30/2013
Budget/Costs Incurred
10
Significant Developments
Project is complete and in closeout.                           8
Millions  6
Schedule
4
The project was completed on schedule.                     Dollars in  2
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
None
2.5
Risks                                  2
None identified at this time.                                  Millions 1.5
1
Budget Transfers
Dollars in   0.5
None this quarter.
0
Initial   Change   Spent
Orders



AIRPORT
Port of Seattle 4Q 2013 Report  55

FOURTH QUARTER REPORT, 2013
CUSE at Gates & Ticket Counters- Airline
Realignment
Provide common use equipment,    Status Snapshot Prior Report
Project:   C800473      casework and infrastructure at     Delayed Schedule 3Q 12
gates and ticket counters for the     On Budget
Budget: $1,293,000
Airline Realignment program.      0 Change Orders
Phase: Close Out                          Total Change Orders Amount:
Start: 04/02/2012                                 $0
Completion: 05/01/2013
Budget/Costs Incurred
Significant Developments
Project is complete and in closeout.                           2.5
2
Schedule
1.5
Completed project construction and post-construction work.           Millions
1
Budget                             Dollars in 0.5
0
Project forecast is within the approved budget and authorization.
Authorized  Forecasted Costs Incurred
Reimbursements to the United Airlines Group still remain.
Change Order
Construction Costs
None                                 Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT
56  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Airport Signage (Airline Realignment)
Project:   C800474      The project will provide airport     Status Snapshot Prior Report
Budget: $646,000       directional signage for the airline   Delayed Schedule 1Q 13
Phase: Close Out      realignment program.         On Budget
Start: 06/01/2011                                 0 Change Orders
Completion: 06/30/2013                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Completed signage changes for all airline relocations. Completed      0.8
replacement of old and damaged signs. Project close-out has
begun.                                       0.6
Millions
0.4
Schedule
Dollars in 0.2                                                                               As previously reported, the change in schedule was based on the
overall Airline Realignment Program Schedule. Airline relocations       0
were delayed.                                        Authorized Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.              Construction Costs
Not Applicable
Change Order
None this quarter
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 4Q 2013 Report  57

FOURTH QUARTER REPORT, 2013
Miscellaneous Building Improvements (Airline
Realignment)
Status Snapshot
Project:   C800475      This project will install a new ramp   On Schedule
for passenger access to regional    On Budget
Budget: $2,172,000
aircraft on Concourse A for the     0 Change Orders
Phase: Close Out      Airline Realignment program.     Total Change Orders Amount:
Start: 11/01/2011                                 $0
Completion: 07/31/2013
Budget/Costs Incurred
Significant Developments
2.5
The project is complete and in closeout.
2
Schedule                            Millions 1.5
1
Project was completed on schedule.
Dollars in 0.5
Budget                              0
Authorized  Forecasted Costs Incurred
Project forecast is within the approved budget and authorization.
Reimbursements to the United Airlines Group still remain.
Change Order                         Construction Costs
None                                 Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
58  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Fire Station Electric Upgrades
Project:   C800479      This project will replace the existing  Status Snapshot
Budget: $2,033,000      208V transformer and 12.47 KV    Delayed Schedule
Phase: Design        feeder, and add a 500 KV       On Budget
Start: 04/01/2013         generator and a 1000kVA        0 Change Orders
Completion: 02/28/2015   transformer.              Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Design is 90% complete.                               2.5
2
Schedule
Millions 1.5
Design is currently behind schedule due to additional scope,
including adding a cabinet for data equipment to keep the length of      1
cables below the maximum allowed. Design is now scheduled to be    Dollars in 0.5
completed in March 2014. Plan to request authorization from          0
Commission to bid the project in the second quarter of 2014.             Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of   Construction Costs
construction funding and authority to advertise for construction will    Not Applicable
be requested when the bid documents are completed.
Change Order
None
Risks
Unplanned electrical shut downs could impact the project schedule.
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 4Q 2013 Report  59

FOURTH QUARTER REPORT, 2013
Laptop Power in Concourses
Project:   C800484      This project includes additional     Status Snapshot
Budget: $1,937,050      charging opportunities for personal  Delayed Schedule
Phase: Construction     electronic devices at several     On Budget
Start: 06/26/2012         strategic locations throughout the    0 Change Orders
Completion: 02/28/2014   airport terminal.            Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
2.5
Construction is complete on Concourse A and work has begun on
Concourse B.                                    2
1.5
Schedule
Millions
1
Construction completion has been delayed two months due to       Dollars in 0.5
descretionary changes made during casework mock-up review that
0
require additional casework fabrication time. This delayed
Authorized  Forecasted Costs Incurred
completion date includes some "no concourse work" blackout dates
due to the holidays.
Construction Costs
Budget
The project forecast is within the approved budget and authorization.     1.2
1
Change Order                          Millions 0.8
None                                   0.6
0.4
Risks                                Dollars in  0.2
0
No risks identified at this time.
Initial   Change   Spent
Orders
Budget Transfers
To Expense                      $82,950



AIRPORT
60  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
New Window Wall Ticket Zone 1
Project:   C800490      This project will install new       Status Snapshot
Budget: $4,810,000      common use ticket counters and   Delayed Schedule
Phase: Construction     new baggage system along the    On Budget
Start: 07/01/2012         window wall and baggage system   2 Change Orders
Completion: 2/17/2014    renovation.              Total Change Orders Amount:
Budget/Costs Incurred
Significant Developments
6
Project is in it's finishing stages for the ticket counters to open mid -
5
February, 2014.
Millions  4
3
Schedule
2
The project schedule is delayed due to unforeseen structural and      Dollars in  1
design issues.                                        0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
4
None
3
Risks                                Millions
2
None identified at this time.
Dollars in    1
Budget Transfers                           0
Initial   Change   Spent
None this quarter.
Orders




AIRPORT
Port of Seattle 4Q 2013 Report  61

FOURTH QUARTER REPORT, 2013
Convert Ticket Zone 2 Pushback
Project:   C800491      The scope of the project is to      Status Snapshot
Budget: $3,982,540      renovate the Ticket counters and   On Schedule
Phase: Close Out      Airline Ticket Office (ATO) spaces  On Budget
Start: 12/11/2012         into a pushback configuration.      0 Change Orders
Completion: 11/30/2013                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
5
Project was completed on schedule for United Airlines (UA) to
4
relocate their Ticketing counters from Zone 7 to Zone 2; counters
opened on May 22, 2013. Phase 2 of this project moved Air Canada    Millions 3
(AC), All Nippon Airways (ANA), among others to temporary ticket      2
counters, demolished the remaining counters and completed the UA   Dollars in  1
pushback ticket counters, these were completed on time and were
0
occupied and operational mid-November 2013.                   Authorized Forecasted Costs Incurred
Schedule
The ticket counters are all operational.                       Construction Costs
Not Applicable
Budget
The project forecast is within approved budget and authorization.
Change Order
We are presently working through change orders associated with the
UA Pushback.
Risks
None identified at this time
Budget Transfers
None this quarter.


AIRPORT
62  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Convert Ticket Zone 3 Flow Through
Status Snapshot
On Schedule
Project:   C800492      This project will convert the Zone 3  On Budget
Budget: $10,659,000     Ticketing Area to a flow through    0 Change Orders
Phase: Close Out      concept.               Total Change Orders Amount:
Start: 08/07/2012                                 $0
Completion: 10/31/2013
Budget/Costs Incurred
12
Significant Developments
11.5
The project is substantially complete. Tenant reimbursement to       Millions
11
Delta was processed before the end of 2013. One final
reimbursement request remains which will likely be received during    10.5  Dollars in 
first quarter 2014.
10
Authorized  Forecasted Costs Incurred
Schedule
The project was completed on schedule.
Construction Costs
Budget
The project forecast is within the approved budget and authorization.     0.6
0.5
Change Order                          Millions 0.4
None                                   0.3
0.2
Risks                                Dollars in  0.1
0
None identified at this time.
Initial   Change   Spent
Orders
Budget Transfers
None this quarter.



AIRPORT

Port of Seattle 4Q 2013 Report  63

FOURTH QUARTER REPORT, 2013
Facility Monitoring System Renewal
Status Snapshot Prior Report
Project:   C800495      This project will provide a system   Delayed Schedule 1Q 13
Budget: $3,422,680      upgrade that will allow the system   On Budget
Phase: Construction     to maintain and expand monitoring  0 Change Orders
Start: 01/22/2013         of critical systems such as        Total Change Orders Amount:
Completion: 08/31/2015   elevators, escalators, moving     $0
walks, passenger boarding bridges
and baggage systems.
Budget/Costs Incurred
Significant Developments
4
Completed 60% design on the passenger loading bridges portion of
3
the work. The network upgrade is progressing well. The Information   Millions
and Communications Technology (ICT) Architecture Committee has     2
approved the project's network architecture and the project can begin
1
purchase of equipment.                               Dollars in 
0
Schedule                              Authorized Forecasted Costs Incurred
As previously reported, the project is currently behind schedule.
Scope reduction has occurred due to code changes that would
Construction Costs
significantly increase cost without much benefit and also due to other
Not Applicable
project impacts.
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT
64  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Airportwide Mechanical Controls System
Project:   C800497      Project Scope and description:     Status Snapshot
Budget: $2,157,000      Upgrade the HVAC Controls     Delayed Schedule
Phase: Design        System for the Airport. This     On Budget
Start: 05/01/2013         includes adding a wireless        0 Change Orders
Completion: 02/28/2015   connection to the Logistics area to  Total Change Orders Amount:
the south of the Airport.           $0
Budget/Costs Incurred
Significant Developments
2.5
60% design is complete.
2
Millions 1.5
Schedule
1
Design is currently behind schedule due to additional scope,
including adding automatic valve actuators to five valves in the        Dollars in 0.5
Cooling Towers and added controls to two pressurization fans in the     0
Parking Garage stair wells. Design is now scheduled to be              Authorized  Forecasted Costs Incurred
completed in March 2014. Plan to request authorization from
Commission to bid the project in the second quarter of 2014.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
None.
Risks
Unplanned electrical shut downs could impact the project schedule.
Budget Transfers
None this quarter.


AIRPORT
Port of Seattle 4Q 2013 Report  65

FOURTH QUARTER REPORT, 2013
RAC Baggage Claim Renovation
Project:   C800541      Renovation of both rental car      Status Snapshot Prior Report
Budget: $1,318,200      counter locations in baggage claim  Delayed Schedule 2Q 13
Phase: Construction     into new waiting areas with vending  On Budget
Start: 10/01/2012         machines and other facilities for     0 Change Orders
Completion: 02/21/2014   special operations           Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
1.5
On November 1, 2013 issued Notice to Proceed to Neeley
Construction & Cabinet Company. Construction is underway and is
1
70% complete.                                  Millions
0.5
Schedule                            Dollars in 
Construction remains on schedule with a substantial completion date    0
of February 21, 2014.                                     Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
0.3
Change Order
0.25
No change orders issued this quarter.                        Millions 0.2
0.15
Risks
0.1
A number of unknown conditions have arisen that will need to be      0.05  Dollars in 
addressed as part of the project. We anticipate that they can be        0
addressed within the approved budget and authorization.                Initial  Change Order  Spent
Budget Transfers
To U00010 (Special Ops Counters)             $8,500

.


AIRPORT
66  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
NorthSTAR Program
Status Snapshot
Delayed Schedule
Project:   C800544      This project includes the         On Budget
Budget: $15,400,000     programmatic project management  0 Change Orders
Phase: Design        and project controls costs for the   Total Change Orders Amount:
Start: 04/05/2012         NorthSTAR program, consisting of   $0
Completion: 12/31/2019   five capital projects that represents
a unique partnership between the   Budget/Costs Incurred
Port and Alaska Airlines.
20
Significant Developments                     15
The NorthSTAR programmatic Project Labor Agreement (PLA) has    Millions 10
been signed. Executed contract with GluMac for Commissioning and
finalized negotiations with Heery for Construction Management       Dollars in  5
Support.                                         0
Authorized Forecasted   Costs
Schedule                                      Incurred
Continuing to define specific NorthSTAR program performance
Construction Costs
metrics and develop programmatic public relations communication
Not Applicable
plan. Preparing MII NorthSTAR project ballot for AAAC review and
vote. Update Program master schedule to the most current baseline
assumptions due to changes in design durations and scope.
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
None
Risks
Communication and coordination across multiple teams and
stakeholders along with identification/monitoring of all "linked"
Capital projects outside of NorthSTAR.
Budget Transfers
To C800556 (NS NSAT Renov NSTS Lobbies)   $900,000

AIRPORT

Port of Seattle 4Q 2013 Report  67

FOURTH QUARTER REPORT, 2013
NorthSTAR Concourse C Vertical Circulation
Project:   C800547      Construct exterior, weather       Status Snapshot
Budget: $18,525,000     protected sloped walkways with    On Schedule
Phase: Construction     elevators at Gates C2/4, C10/12,   On Budget
Start: 11/07/2012         and C14 to provide enhanced      0 Change Orders
Completion: 03/31/2015   access from concourse to aircraft   Total Change Orders Amount:
ramp for Alaska/Horizon regional    $0
operations.
Budget/Costs Incurred
Significant Developments
20
Commission authorized Construction and the project was advertised
for bids on December 3. Addressing bidder questions. Bid opening    15
scheduled for January 14, 2014. The 90% design review underway    Millions
10
for removal of C10, C12, C14 and C16 passenger loading bridges to
accommodate new walkways. Removal of C16 was added to project
Dollars in   5
due to conflict with Alaska Airlines Group (AAG) installed walkways.
0
Authorized  Forecasted Costs Incurred
Schedule
The project is currently on schedule. Bid opening in January with
award in February. Working on AAG/Port cost sharing agreement    Construction Costs
for temporary passenger walkways and C16 loading bridge removal.  Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
Construction phasing to minimize impact on airline operations and
potential for underground utility conflicts during construction.
Budget Transfers
To Expense                       $775,000


AIRPORT

68  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Concourse D Roof Replacement
Project:   C800550      This project will remove and      Status Snapshot
Budget: $3,252,800      replace the roofing systems on    On Schedule
Phase: Design        Concourse D of the Airport; install   On Budget
Start: 07/01/2013         ladders, stairs and fall protection on  0 Change Orders
Completion: 10/31/2014   the penthouse sections; and make  Total Change Orders Amount:
repairs and where required        $0
replacments to the KalWall window
system.
Budget/Costs Incurred
Significant Developments
4
Ninety percent design is complete
3
Schedule
Millions  2
This project is currently on schedule.
Dollars in  1
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Commission
Authorization for construction funding and authority to advertise for
construction will be requested when the bid documents are
completed.                                     Construction Costs
Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT

Port of Seattle 4Q 2013 Report  69

FOURTH QUARTER REPORT, 2013
Grease Interceptor Augmentation
Project:   C800551      This project will install two        Status Snapshot
Budget: $1,559,200      underground 9,000 gallon grease   On Schedule
Phase: Design        interceptors to service the       On Budget
Start: 05/01/2013         Concourse C and South Satellite.    0 Change Orders
Completion: 10/31/2014                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The 60% design is complete.                             2
Schedule                             1.5
Millions
The project is currently on schedule.                           1
Budget                             Dollars in 0.5
The project forecast is within the approved budget. Authorization of      0
construction funding and authority to advertise for construction will         Authorized  Forecasted Costs Incurred
be requested when the bid documents are completed.
Change Order                         Construction Costs
None                                 Not Applicable
Risks
Design may run longer than anticipated due to conflicts with other
projects.
Budget Transfers
None this quarter.



AIRPORT

70  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
NorthSTAR Refurbish Baggage Systems
Status Snapshot
This project will refurbish existing
Project:   C800555                             On Schedule
baggage systems in support of
Budget: $22,000,000                         On Budget
AAG operation at North Satellite
Phase: Construction                        0 Change Orders
and Concourse D. The work will
Start: 11/6/2012                                  Total Change Orders Amount:
extend the service life of part of the
Completion: 12/31/2015                       $0
C92 systems, C88 North Satellite
systems, and C88 tunnel systems.
Budget/Costs Incurred
Significant Developments
25
Commission authorized construction. Completed independent
technical design review and received AAG concurrence of project      20
scope and budget. Submitted bid documents for review. Submitted    Millions 15
for building permit.                                        10
Dollars in   5
Schedule
0
Commission Memo is being prepared to request additional funds for       Authorized Forecasted Costs Incurred
$6,200,000. Bid opening scheduled January 2014 with anticipated
construction start second quarter of 2014. Design schedule has
slipped slightly due to designer performance and finalizing scope     Construction Costs
decisions. Construction schedule is extended due to construction    Not Applicable
sequencing and scope increases.
Budget
The project forecast is within the approved budget. Prior $6,500,000
savings cover additional refurbishment scope and incidental
Regulated Material abatement. Authorization is being sought to
utilize savings to incorporate added scope.
Change Order
None
Risks
NSAT scope changes may impact baggage handling system
refurbishment requirements due to forecasted baggage volume and
speed. TSA's recapitalization may impact scope and schedule of the
baggage project.
Budget Transfers
None

AIRPORT
Port of Seattle 4Q 2013 Report  71

FOURTH QUARTER REPORT, 2013
NorthSTAR North Satellite Renovation NSTS
Status Snapshot
Lobbies
Delayed Schedule
Renovation of the North Satellite    Forecast Overrun
Project:   C800556      (NSAT) terminal, including Satellite  0 Change Orders
Transit System (STS) station
Budget: $383,548,000                        Total Change Orders Amount:
"refresh", ramp level, Concourse
Phase: Design                           $0
level, and new rooftop airline
Start: 7/24/2012          lounge.
Completion: 05/31/2019
Budget/Costs Incurred
Significant Developments
Port and AAG agreed to expand NSAT to 20 gates based upon
500
airport wide gating analysis. Received Commission concurrence to
proceed with design while preparing the formal authorization memo.    Millions 400
300
Conceptual options for dual door aircraft enplanement and          Dollars in 200
deplanement were presented to AAG steering committee and will be
100
incorporated into NSAT scope.
0
Authorized  Forecasted Costs Incurred
Received confirmation that PCB abatement can occur during
construction phase. NSAT project registered with USGBC for       Construction Costs
potential LEED certification.                               Not Applicable
Schedule
Start of 30% design has been delayed with the decision to expand
NSAT and for AAG to finalize the dual door concept. Continued
development of construction phasing strategy to maximize gate
availability and utililzation during NSAT renovation.
Budget
Commission has authorized $32,933,556 to date for design effort.
The current budget does not include the cost of facility expansion. A
pending request is being prepared for Commission approval for
additional authorization.
Change Order
None.



72  Port of Seattle 4Q 2013 Report

Risks
Airlines operational requirements and availability of Airport gates may require changes to the
preliminary two-phased construction approach.
Budget Transfers
To RMM Expense                   $5,000,000
NorthSTAR Decrease                 $14,850,037
NorthSTAR Increase                  $195,051,680
From C800544                      $900,000










AIRPORT

Port of Seattle 4Q 2013 Report  73

FOURTH QUARTER REPORT, 2013
Main Terminal Mezzanine Tenant Relocations
Project:   C800560      This project will construct new     Status Snapshot
Budget: $2,025,000      tenant leased spaces in order to   Delayed Schedule
Phase: Design        move existing tenants and provide  On Budget
Start: 3/26/2013          new leasable office space for      0 Change Orders
Completion: 3/30/2015    airlines on the mezzanine of the    Total Change Orders Amount:
main terminal.                $0
Budget/Costs Incurred
Significant Developments
2.5
The scope has been increased to include the widening of the
2
Mezzanine by the central annex to allow for an increased number of    Millions 1.5
tenants in that area. The 90% design will begin in January 2014.
1
Schedule                            Dollars in 0.5
This project schedule has been revised due to the additional scope.      0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
None this quarter
Risks
None identified at this time.
Budget Transfers
From C800404 (Aeronautical Allowance)          $275,000



AIRPORT

74  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Known Crewmember Employee Bypass
Project:   C800576      This project will construct new     Status Snapshot
Budget: $650,000       Known Crewmember Bypass and   Delayed Schedule
Phase: Construction     Employee Bypass locations at the   On Budget
Start: 12/11/2012         Airport.                    0 Change Orders
Completion: 06/30/2014                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Known Crewmember Bypass is up and running at both Concourse A
and Concourse D.                                 0.8
Schedule                             0.6
Millions
Installation of the Employee Bypass at North and South will be        0.4
delayed until at least the second quarter of 2014. The portals were
Dollars in 0.2                                                                               supposed to be shipped first week of January, however the vendor
has been unresponsive.                                0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
None this quarter
Risks
If the portal issue does not get resolved, we will need to issue a new
purchase order to another vendor.
Budget Transfers
None this quarter.



AIRPORT

Port of Seattle 4Q 2013 Report  75

FOURTH QUARTER REPORT, 2013
International Arrivals Facility (IAF)
Project:   C800583       Pre-design and acquisition      Status Snapshot
Budget: $344,000,000     planning for a new international   On Schedule
Phase: Planning        arrivals facility for Seat-Tac     On Budget
Start: 06/25/2013          International Airport, including a    0 Change Orders
Completion: 06/30/2018    new Federal Inspection Services   Total Change Orders Amount:
Area.                    $0

Budget/Costs Incurred
Significant Developments
A Project Management (PM) Consultant Team has been selected      400
and service agreement is being negotiated. Decision has been
300
made to build a single IAF facility landside of Concourse A with a      Millions
connector to the South Satellite instead of split FIS facilities at both      200
Concourse A and the South Satellite.
Dollars in 100
Schedule
0
The project is currently on schedule.                             Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the current budget.                Construction Costs
Not Applicable
Change Order
None
Risks
The current budget includes construction of a bridge to connect the
South Satellite to the new Concourse A facility. The project team
anticipates an increase to the total IAF program costs if a decision is
made to include a tunnel as the connector instead of a bridge. This
decision will be made in the first or second quarter of 2014.
Budget Transfers
None this quarter.


AIRPORT
76  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Security Exit Lane Breach Control-Phase 2
Project:   C800605      This project will procure and install   Status Snapshot Prior Report
Budget: $6,407,000      new automated breach control    Delayed Schedule 3Q 13
Phase: Design        equipment at four security exits in   On Budget
Start: 10/1/2012          the airport terminal.            0 Change Orders
Completion: 11/30/2014                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The construction bidding process was completed.
8
Schedule
6
Phase 2 project schedule was pushed out later to ensure that there
was adequate time for Airport Security and TSA testing of the pilot       4
in Millions
project (completed in Phase 1), as previously reported.
2  Dollars 
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
None
2
Risks
1.5
No major risks identified at this time.
1
Millions
Budget Transfers
None this quarter.                                      Dollars in 0.5
0
Initial    Change Order    Spent



AIRPORT
Port of Seattle 4Q 2013 Report  77

FOURTH QUARTER REPORT, 2013
North Satellite - STS Ceiling Leak Repair
Project:   C800609      This project will eliminate ceiling    Status Snapshot
Budget: $1,750,000      leaks at the North Satellite (NSAT)  On Schedule
Phase: Design         that occur between the satellite    On Budget
Start: 05/28/2013         transit station (STS) and the       0 Change Orders
Completion: 09/30/2014   elevators.               Total Change Orders Amount:
$0

Budget/Costs Incurred
Significant Developments
The project is currently in design.                              2
Schedule                             1.5
The project schedule has been updated to reflect change in           Millions 1
design from Port led to Consultant led. This change will not affect
the overall schedule for construction completion.                  Dollars in 0.5
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget. Commission
Authorization for construction funding and authority to advertise for
construction will be requested when the bid documents are        Construction Costs
completed.                                     Not Applicable
Change Order                         Photo
None.
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT

78  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Passenger Bridge and Walkway S16
Replacement                     Status Snapshot
Replace existing Passenger       On Schedule
Project:   C800611      Loading Bridge (PLB) and Fixed    On Budget
Walkway at Gate S16. Upgrade    0 Change Orders
Budget: $1,000,000
existing foundations and install      Total Change Orders Amount:
Phase: Construction     infrastructure to support new Wi-Fi  $0
Start: 06/03/2013         capabilities
Completion: 12/31/2013                       Budget/Costs Incurred
Significant Developments                     1.2
The project is substantially complete and the bridge is operational.       1
Some remaining communication and Preconditioned Air work will      Millions 0.8
take place around the operational schedule for the bridge. Project is    0.6
in closeout.                                            0.4
Dollars in 0.2
Schedule                             0
Authorized  Forecasted Costs Incurred
The project was completed on schedule.
Budget
Construction Costs
Project forecast is within the approved budget and authorization.
Not Applicable
Change Order
None.
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT

Port of Seattle 4Q 2013 Report  79

FOURTH QUARTER REPORT, 2013
Checked Baggage Recapitalization/Optimization
Project:   C800612      TSA approached the Airport in     Status Snapshot
Budget: 317,000,000     2012 with plan to replace all      On Schedule
Phase: Design        federally owned and operated     On Budget
Start: 2/26/2013          baggage scanning equipment,     0 Change Orders
Completion: 12/31/2017   known as Explosive Detection     Total Change Orders Amount:
System (EDS) equipment. The     $0
EDS equipment is approaching the
end of its life.                    Budget/Costs Incurred
400
Significant Developments
300
The Port and TSA have executed an Other Transaction Agreement    Millions
(OTA). The design started in February 2013 and 30% design of the     200
TSA component was completed in June, per the OTA.
Dollars in 100                                                                            The TSA 30% design component was approved and the project team
is working to address TSA's formal comments. The Port and TSA       0
have executed an Other Transaction Agreement (OTA) for just over        Authorized Forecasted Costs Incurred
$93,000,000. The 30% overall airport design was completed this
quarter.
Construction Costs
Schedule                           Not Applicable
The project is currently on schedule. Overall schedule will be refined
to reflect a ten-year program.
Budget
The project forecast is within the approved budget. Commission
Authorization for construction funding and authority to advertise for
construction will be requested when the bid documents are
completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter.

AIRPORT
80  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Second Floor Mezzanine Infrastructure Upgrade
Status Snapshot
Project:   C800615      This project will upgrade and      Delayed Schedule
Budget: $2,545,000      extend the infrastructure (HVAC,   On Budget
Phase: Design        Communications, Electrical,      0 Change Orders
Start: 08/01/2013         Plumbing, WiFi) to 14,000sq ft of    Total Change Orders Amount:
Completion: 12/30/2014   future lease space on the second   $0
floor, including 7,000 sq ft for a new
USO.                Budget/Costs Incurred
3
Significant Developments
2.5
The project is currently in design. After design started it became       Millions 2
evident that the infrastructure project design could not start until after    1.5
the United Services Organization (USO) design was complete, due      1
to exiting requirements and utility requirements changing. The USO     Dollars in 0.5
Tenant build-out will be completed prior to the Infrastructure buildout.
0
Authorized  Forecasted Costs Incurred
Schedule
Current project is to complete construction in December 2014.
Construction Costs
The delay is due to many design challenges exiting from the second   Not Applicable
floor to meet egress code requirements and determining the routing
of the infrastructure, primarily HVAC.
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
The risks are to ensure that the USO infrastructure and utility line up
with the Infrastructure project tie-ins.
Budget Transfers
None

AIRPORT
Port of Seattle 4Q 2013 Report  81

FOURTH QUARTER REPORT, 2013
Automated Passport Control
Project:   C800667      Install fourteen (14) Automated     Status Snapshot
Budget: $2,207,000      Passport Control (APC) kiosks in   Ahead of Schedule
Phase: Construction     the existing FIS at the South     Under Budget
Start: 10/13/2013         Satellite.                   0 Change Orders
Completion: 12/31/2013                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
Project was originally scheduled to complete at the end of the first      2.5
quarter of 2014, but was accelerated to get the kiosks installed by       2
mid-December 2013. Commission approved funding in the fourth     Millions 1.5
quarter of 2013. Kiosks were advertised for bid and purchased. Port
Construction Services installed the electrical and communications       1
infrastructure and the kiosks were placed and put into service.        Dollars in 0.5
0
Schedule                               Authorized Forecasted Costs Incurred
Accelerated project at the request of Delta Airlines to get APCs
installed prior to the busy holiday season. Installation of the kiosks is
complete. Some queue stanchions are still on order and will be      Construction Costs
installed in the next several weeks.                         Not Applicable
Budget
This project forecast is currently under budget due to the
accelleration.
Change Order
None.
Risks
None identified at this time.
Budget Transfers
None this quarter.

AIRPORT
82  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Highline School Noise Insulation
Status Snapshot Prior Report
Project:   C200007      Highline School Insulation        Delayed Schedule 4Q 10
Budget: $101,797,000    Agreement will provide funding for  On Budget
Phase: Construction     sound mitigation for 15 schools that  0 Change Orders
Start: 03/23/1999         are impacted by aircraft noise from   Total Change Orders Amount:
Completion: 11/30/2021   Sea-Tac Airport.            $0
Budget/Costs Incurred
Significant Developments
120
Port funding is authorized and will become available when the FAA,
100
the State of Washington, and the Highline School District provide
matching funds.                                     Millions 80
60
Schedule                             40
Dollars in  20
The schedule for state funding is not known. The district's schedule
0
is dependent on obtaining general election bonds at various
Authorized  Forecasted Costs Incurred
intervals. FAA grant received for Olympic Elementary. Construction
may resume in 2015 if a voter approval bond is secured in 2014.
Budget                            Construction Costs
Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
Not applicable
Risks
Project delayed due to funding issues with the Highline School
District. There is a risk if no bonds are passed in the general
election. Obtain FAA Airport Improvement Program (AIP) Grant
funding.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 4Q 2013 Report  83

FOURTH QUARTER REPORT, 2013
Highline Community College Noise Insulation
Project:   C200042      Highline Community College      Status Snapshot Prior Report
Budget: $32,050,000     Insulation Agreement will provide   Delayed Schedule 4Q 10
Phase: Construction     funding for up to 22 eligible      On Budget
Start: 01/11/2005         buildings that are impacted by      0 Change Orders
Completion: 12/31/2013   aircraft noise from Sea-Tac Airport.  Total Change Orders Amount:
$0
Significant Developments
Fourteen of the original 22 eligible buildings have been sound       Budget/Costs Incurred
insulated by the college. The College sound insulation program has
40
been dependent on receiving funding from FAA grants. The FAA
notified the Port that the Highline Community College Campus is no     30
longer located within the 65 DNL Noise Contour and therefore is not
20
eligible for any further grant funding. Without the FAA's approval and    in Millions
funding the remainder of the college buildings cannot be sound       Dollars  10
insulated.
0
Authorized  Forecasted Costs Incurred
Schedule
The construction is complete on the last building (Building #4) and
the Noise Office is working with the College on final invoicing. The
Construction Costs
project is also FAA Grant funded and cannot be closed out until the
Not Applicable
appropriate grant revenues are received from the FAA.
Budget
The project forecast is within the approved budget. No further
authorization is anticipated with this project.
Change Order
Not Applicable
Risks
The FAA will not allocate future grant funds to this project.
Budget Transfers
None this quarter.

AIRPORT
84  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Home Insulation Retrofit
Project:   C200048      This project includes storm window  Status Snapshot
Budget: $5,344,000      retrofit of previously insulated     Delayed Schedule
Phase: Construction     homes.                On Budget
Start: 01/11/2005                                 0 Change Orders
Completion: 04/30/2014                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The Port has identified eligible homes and notified homeowners of
their eligibility. The Port is continuing with storm window retrofit.          6
5
Schedule                             4
The Port is reviewing other potential homes for eligibility. The project     3
in Millions
has encountered additional delay due to non-responsive             2
homeowners willing to participate in the program.                 Dollars  1
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable
None.
Risks
The ability to accomplish the retrofit is dependent on homeowner's
schedules, and structural integrity of the home.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 4Q 2013 Report  85

FOURTH QUARTER REPORT, 2013
Single Family Home Sound Insulation
Project:   C200093      Sound insulate remaining homes    Status Snapshot
Budget: $13,747,395     that are within the 1998 65 decibel  Delayed Schedule
Phase: Construction     day night level (DNL) noise      On Budget
Start: 03/27/2007         contour.                   2 Change Orders
Completion: 12/31/2015                       Total Change Orders Amount:
$942
Budget/Costs Incurred
Significant Developments
Forty homes are complete; 22 homes are in the process of receiving     15
sound insulation. Approximately 41 additional homes have been
identified as eligible.                                         Millions 10
Schedule                             5
Dollars in 
The Single Family Insulation project encountered delays due to
0
issues with identifying eligible parcels. Homeowners also are
Authorized  Forecasted Costs Incurred
experiencing difficulties in getting the required paperwork signed by
their mortgage companies.
Budget                            Construction Costs
The project forecast is within approved budget and authorization to      4
complete all homes currently in progress.
3
Change Order                          Millions
2
Change orders were for city permits
Dollars in   1
Risks                                 0
Initial    Change Order    Spent
The ability to accomplish the insulation is dependent on the
homeowner's schedules, willingness to sign an aviation easement,
and obtain a subordination agreement from their lender, and
structural integrity of the home. If more eligible homes than
anticipated are identified in the future, then additional funding may be
needed.
Budget Transfers
None this quarter.

AIRPORT
86  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
RMU/Kiosk Concession Program
Status Snapshot Prior Report
Delayed Schedule 4Q 10
Project:   C800146    The project will provide design and     On Budget
Budget: $879,146     fabrication of Retail Merchandising    1 Change Orders
Phase: Construction   Units (RMUs); provide power,       Total Change Orders Amount:
Start: 11/20/2007      communications, and data to RMU     $13,574.00
Completion: 02/05/14  locations; and install floor-mounted
receptacles for the utilities to allow easy
connection points as well as flexibility   Budget/Costs Incurred
for future utilization.
1.5
Significant Developments                     Millions 1
RMU utilities have been installed at the Concourse C location. The
0.5
procurement of the casework has been awarded and the contract      Dollars in 
was executed in June 2013. We are finalizing the design of the
0
casework and installation is scheduled for late January 2014.
Authorized  Forecasted Costs Incurred
Schedule
The casework is scheduled for installation 10 weeks from the final    Construction Costs
design approval; anticipate late January 2014.                 Not Applicable
Budget
The project forecast is currently within the approved budget and
authorization.
Change Order
One for expense of casework, possibly a second for installation
labor.
Risks
The additional units on Concourse C may exceed the proposed
budget.
Budget Transfers
None this quarter.

AIRPORT

Port of Seattle 4Q 2013 Report  87

FOURTH QUARTER REPORT, 2013
Burien Commercial Property Acquisition
Project:   C800150      Acquire commercial properties     Status Snapshot Prior Report
Budget: $3,000,000      along Des Moines Memorial Drive,  Delayed Schedule    2Q 10
Phase: Implementation   and vacate one street, in the City of  On Budget
Start: 05/31/2007         Burien that is surrounded by Port-   0 Change Orders
Completion: 03/31/2014   owned properties.           Total Change Orders Amount:
$0
Budget/Costs Incurred
4
Significant Developments
The remaining anticipated acquisitions will be street vacation of 12th      3
Place S. in Burien, Washington; possibly the 757 Convenience store;    Millions
2
Dollars in 
and a small upholstery shop on the Lora Lake site.
1
Schedule
0
It is anticipated that the acquisitions will occur in the first quarter of          Authorized  Forecasted Costs Incurred
2014.
Budget                            Construction
The project forecast is within the approved budget.              Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
88  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Tenant Reimbursement
Status Snapshot
Project:   C800154    Build out of spaces for new and      On Schedule
Budget: $4,709,577    existing tenants. If more than a "basic  On Budget
finish" condition space is built for the    0 Change Orders
Phase: Construction
tenant, the tenant is required to       Total Change Orders Amount:
Start: 08/14/2007
reimburse the Port for the cost of the   $0
Completion: TBD
work beyond this "basic finish". These
reimbursements are allowed under
the guidelines described in the
"Tenant Reimbursement Policy".     Budget/Costs Incurred
5
Significant Developments
4
No activity in the fourth quarter of 2013, although anticipate a         Millions 3
reimbursement for Hudson during first quarter of 2014.
2
Schedule                            Dollars in  1
Schedules vary to meet the tenant's needs.                     0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 4Q 2013 Report  89

FOURTH QUARTER REPORT, 2013
Snow Removal Equipment - 2013
Project:   C800498      This project will purchase four     Status Snapshot
Budget: $2,000,000      pieces of runway snow removal    On Schedule
Phase: Implementation   equipment.              On Budget 1Q 13
Start: 02/14/2012                                 0 Change Orders
Completion: 01/22/2013                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
All work is complete. This will be the last quarterly report for this
project.                                                2.02
2
Schedule
1.98
Equipment delivered on schedule.
1.96   in Millions
Budget                             1.94 Dollars 
The project forecast is within the approved budget and authorization.    1.92
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT

90  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
T-46 Lease Improvements
Construct stormwater treatment     Status Snapshot
Project: C102554
system to comply with Ecology     On Schedule
Budget: $6,000,000
order by 09/30/2014. Terminal     On Budget
Phase: Design                           0 Change Orders
Start: 04/12/2013        pavement overlay to fulfill lease
obligation.                     Total Change Orders Amount:
Completion: 2020                          0
Significant Developments                   Budget/Costs Incurred
Pilot testing of the selected stormwater treatment systems is
7
complete. Engineering Report and Alternatives evaluation report       6
submitted to Department of Ecology for approval. Submitted time       5
extension request to Ecology for the installation of the treatment       Millions 4
system. Completed 90% design of the Stormwater improvements      3
project.                                                Dollars in  2
1
Schedule                             0
Authorized  Forecasted Costs Incurred
Stormwater treatment system to be completed by September 30,
2014. Request extension to complete two treatment vaults by
December 2013, and the third by June 2014. The fourth treatment
Construction Costs
will be installed once WSDOT vacates the lease area.
None
Budget
$10,000,000 for Stormwater Treatment System. Currently within
budget.
Change Order
Not Applicable
Risks
Complete stormwater treatment system within budget by
September 30, 2014
Budget Transfers
Not Applicable

SEAPORT

Port of Seattle 4Q 2013 Report  91

FOURTH QUARTER REPORT, 2013
Street Vacations T5,18,105
Status Snapshot
Delayed Schedule 4Q 11
Project: C102858,     Street vacation related real estate     On Budget
C102875, E104366    negotiations and agreements --T5,    0 Change Orders
Budget: $1,500,000   T18, and T105 (complete).        Total Change Orders Amount:
Phase: Permitting                         $0
Start: June 2010
Completion: 2014                          Budget/Costs Incurred
2
Significant Developments                     1.5
Millions
Draft Easement and Utility transfer documents have been prepared      1
by the City and are under Port review for Terminal 18 (T-18).
Discussion and Title work has begun for Terminal 5.               Dollars in 0.5
0
Schedule                               Authorized Forecasted Costs Incurred
Current schedule has T-18 completed by the end of 2014 and T-5 by
the end of 2015.                                    Construction Costs
Not Applicable
Budget
The budget has been revised for 2014 and beyond.             Photo
Change Order
Not applicable
Risks
Not applicable
Budget Transfers
Not applicable



SEAPORT
92  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
P91 Fender System Upgrade
Project:   C800183      Upgrades to the vessel berths of    Status Snapshot
Budget: $5,700,000      P91 to better accommodate cruise  On Schedule
Phase: Construction     ships and also serve the other    On Budget
Start: 01/31/10          industrial customers who utilize the   0 Change Orders
Completion: 8/1/2013    berths and adjacent dock/apron    Total Change Orders Amount:
areas on P91 for less than $6M by   $0
spring 2011.
Budget/Costs Incurred
Significant Developments
6
Fabrication of 7 camel barges complete. Camels completed service
for the remainder of 2013 cruise season.
Millions  4
Option exercised to purchase 3 additional barges under existing
purchase and within project budget. These barges will be delivered
2
for the start of the 2014 cruise season.
Dollars in 
0
Schedule                               Authorized Forecasted Costs Incurred
Full Fender replacement completed April 2012.
Camel Barge replacement completed by July 2013.
Additional barges delivered May 2014.                     Construction Costs
Budget                              2.5
Project is within approved budget.                             2
Millions  1.5
Change Order
1
None this quarter                                     Dollars in  0.5
Risks                                  0
Initial   Change   Spent
None this quarter                                              Orders
Budget Transfers
None



SEAPORT
Port of Seattle 4Q 2013 Report  93

FOURTH QUARTER REPORT, 2013
T-91, Bldg C175 Roof Replacement
Status Snapshot Prior Report
Project:   C800430      Replace roof on the C175 building
Budget: $240,000       at Terminal 91.            Delayed Schedule 3Q 11
Phase: Design                            On Budget
Start: 7/26/11                                    0 Change Orders
Completion: Q4 2014                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Ninety percent submittal was completed and reviewed during the
quarter. Preparations were made to present the project to
0.3
Commission for construction funding in January 2014 as well as
0.25
advertise for construction bids.
0.2
0.15
Schedule                             Millions
0.1
Project remains on schedule for installation during 2014.
0.05   Dollars in
0
Budget                               Authorized Forecasted Costs Incurred
On budget
Change Order                         Construction Costs
None                                 Not Applicable
Risks                               Photo
None at this time
Budget Transfers
None




SEAPORT
94  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
SEA P66 Apron Pile Wrap
Status Snapshot
Project:   C800516      Design and install a pile wrap
Budget: $3,010,000      system for corrosion protection of   On Schedule
Phase: Construction     steel structural pilings associated   On Budget
Start: 3/6/12            with Seaport structures at Pier 66.   4 Change Orders
Completion: 12/31/14                         Total Change Orders Amount:
$91,288
Significant Developments                    Budget/Costs Incurred
Construction continues and progressing well. Work is being           4
completed in conjunction with the P69 North Apron Corrosion Control
3
Project (CIP C800313).                                Millions 2
Schedule
Dollars in   1
Projected construction completion date remains at the end of March
2014.                                          0
Authorized  Forecasted Costs Incurred
Budget
Project is on budget.                                   Construction Costs
Not Applicable
Change Order
Total Change Order cost is $91,288                       Photo
Risks
Installation of pile wraps is tide and weather dependent.
Construction duration may lengthen due to unfavorable conditions.
Budget Transfers
None



SEAPORT

Port of Seattle 4Q 2013 Report  95

FOURTH QUARTER REPORT, 2013
Argo Yard Truck Roadway
Status Snapshot
Project:   C800546,      New Port of Seattle owned truck    On Schedule
E104751, E104754       roadway between SR 99 and     On Budget
Budget: $6,600,000      Colorado Way Avenue right-of-way.  0 Change Orders
Phase: Design                            Total Change Orders Amount:
Start: 03/11/12                                   $
Completion: 12/31/2014
Significant Developments                    Budget/Costs Incurred
MOU Supplemental Agreement approval and easement negotiations
8
with stakeholders are in its final stage. Property appraisals for the
Roadway and Stormwater easement areas are complete and         6
awaiting approval by Prologis. 90% engineering design nearly        Millions 4
complete for review by City in early 2014.
Dollars in   2
Schedule
0
Complete design and permitting by late spring 2014. Construction is       Authorized  Forecasted Costs Incurred
to be completed in 2014.
Budget                            Construction Costs
Project authorized budget is $2,800,000 (including $600,000 from    Not Applicable
FMSIB).
Change Order
None
Risks
Additional funding approval expected to be required when
authorization to advertise for construction bids is requested in April
2014. Current preliminary project estimate is $3,400,000. The actual
start of utilization of the proposed Argo Yard truck roadway is
dependent upon the completion of separate off-site projects - EMW
Phase II (East Marginal Way surface street improvements) and
WSDOT's SR 99 timber trestle replacement scheduled for
construction completion by spring 2014. The EMW Phase II
improvements will also require timely approval by Union Pacific
Railroad and the Ash Grove Cement Co. in order to be completed
within 2014.

96  Port of Seattle 4Q 2013 Report

Budget Transfers
None













SEAPORT
Port of Seattle 4Q 2013 Report  97

FOURTH QUARTER REPORT, 2013
T-46 Dock Rehabilitation
Project:   C800603      Terminal 46 Dock Rehabilitation    Status Snapshot Prior Report
Budget: $1,854,000      Project                Delayed Schedule
Phase: Design                            On Budget
Start: November 6, 2012                            0 Change Orders
Completion: Q1 2016                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
There are no new developments on the project since the last report.
The remaining design effort from 90% to Final Design remains on       2
hold. The project will resume once the conflicting construction
project has advanced sufficiently to avoid a conflicting delay.          1.5
Millions
1
Schedule
As noted in the previous report, the construction schedule was        Dollars in 0.5
delayed a year, from 2014 to 2015, to avoid conflicting construction
0
projects on the terminal.                                      Authorized  Forecasted Costs Incurred
Budget
The project is on budget                               Construction Costs
Not Applicable
Change Order
None                                 Photo
Risks
None at this time
Budget Transfers
None



SEAPORT

98  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Clean Truck Program Truck Scrapping and
Replacement Project                  Status Snapshot
Scrap or retrofit at least 180 trucks
Project:   U00079       and replace them with 2007 modelyear
or newer trucks.            0 Change Orders
Budget: 4,727,000
Total Change Orders Amount:
Phase: Design                            $0
Start: December 10, 2013
Completion: May 4, 2014                      Budget/Costs Incurred
Significant Developments                      5
Commission authorized $4,727,000 in funding on June 25, 2013 and     4
December 10, 2013. Two grants received from the Federal Highway   Millions 3
Administration and Washington State Department of Ecology. Inter-
2
local agreement (ILA) executed to implement the Clean Truck
Program with the Puget Sound Clean Air Agency.               Dollars in  1
0
Schedule                               Authorized Forecasted Costs Incurred
Project is on schedule to finish program design by April 2014 and to
open the truck center by May 4, 2014.
Construction Costs
Budget                            Not Applicable
On budget
Photo
Change Order
None
Risks
Due to multiple funding sources involved, the project needs to be
compliant with funding agencies' requirements. A consultant is being
retained to provide grant administration services.
Budget Transfers
None


SEAPORT

Port of Seattle 4Q 2013 Report  99

FOURTH QUARTER REPORT, 2013
East Marginal Way Grade Separation        Budget/Costs Incurred
Status Snapshot Prior Report
Project:   E102007      FAST Corridor funded project;      Delayed Schedule
Budget: $55,456,171     FHWA, State, City with Port      On Budget
Phase: Construction     commitment of $20,437,841. Scope  97 Change Orders
Start: 5/2006            is to construct grade separation in    Total Change Orders Amount:
Completion: Q2 2014     vicinity of T5 and T18 to minimize   $1,922,967
truck traffic/rail conflicts.
53.6
53.58
Significant Developments
53.56
Final landscaping improvements installed and are now under a       53.54  Millions
3-year maintenance period before final acceptance by City. Other     53.52
miscellaneous construction loose ends are in process of being        53.5  Dollars in 
completed. Final project Memo of Agreement (MOA) is in process    53.48
with the City. As-built drawings are in progress.                   53.46
Authorized  Forecasted Costs Incurred
Schedule
Anticipate final acceptance by SDOT 2nd Quarter 2014
Construction Costs
Budget
25
Current construction costs, part of project closeout, are based on unit
20
line items and cost reconciliation. Preliminary investigation indicates     Millions  15
potential overrun.
10
Change Order                          Dollars in  5
Executed change orders for a total net amount of $1,922,967.           0
Initial   Change   Spent
Orders
Risks
Anticipate need for additional POS funding in early 2014 to complete
final project loose ends.                                  Photo
Budget Transfers
None


SEAPORT
100  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Viaduct Construction Coordination
Project:   E104324,      Participate in the design &       Status Snapshot
E104535-38          construction of the bored tunnel,   On Schedule
Budget: $2.9M        north & south portals, Holgate to   On Budget 4Q 13
Phase: Implementation   King St, Central Waterfront surface  0 Change Orders
Start: 1/1/2009          streets, and related projects to     Total Change Orders Amount:
ensure adequate connection to port  $0
Completion: 12/31/2018
facilities.
Budget/Costs Incurred
Significant Developments
3.5
SR 99 tunnel boring machine made significant progress, mining        3
1,019 ft. out of total 9,720 ft. Tunneling stopped in December and
Millions 2.5                                                                                further investigation is needed before tunneling can resume. Mercer        2
West construction continued. Seawall utility relocations and roadway    1.5
detours were completed.                               Dollars in  1
0.5
Schedule                             0
Authorized  Forecasted Costs Incurred
Construction of Atlantic St. Overpass to be completed by the end of
January. Tunneling stopped due to mechanical problems. Related
City projects are making steady progress: Mercer West construction
Construction Costs
is underway; Seawall Phase I construction is underway; Central
Not Applicable
Waterfront design is at 30% level.
Photo
Budget
Port staff costs were within anticipated 2013 spending.
Change Order
Not applicable
Risks
Project delays due to repairs to the Tunneling machine.
Budget Transfers
None


SEAPORT
Port of Seattle 4Q 2013 Report  101

FOURTH QUARTER REPORT, 2013
T-5 and T-91Maintenance Dredging
Status Snapshot
Project:   E104840 &     Maintenance Dredge at T-5 all     Delayed Schedule
U00067            three berths and at T-91 East     On Budget
Budget: $4,800,000      cruise berth.             0 Change Orders
Phase: Design                            Total Change Orders Amount:
Start: 08/14/12                                   $
Completion: 02/28/2015                       Budget/Costs Incurred
6
Significant Developments
T-5 Phase II maintenance dredging construction began in December    Millions 4
2013. T18 Maintenance Dredging is no longer part of the scope and
T-91 East Cruise Berth dredging was added to the scope as per        2
Commission action on September 10, 2013. Due to complications     Dollars in 
and delays in permitting, T91maintenance dredging construction is      0
Authorized  Forecasted Costs Incurred
now delayed for construction in late 2014--early 2015.
Schedule
Construction Costs
T-5 Phase II maintenance dredging construction is expected to be    Not Applicable
completed by February 2014, and T-91 East Cruise Berth
maintenance dredging to be completed by February 2015.         Photo
Budget
Project is on budget.
Change Order
None
Risks
Environmental permitting may cause major delays, scope change,
and cost impact to the T-91 East Cruise Berth dredging project.
Budget Transfers
None

SEAPORT

102  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
FT C15 HVAC Improvements
Status Snapshot
Project:   C800137                             On Schedule
Budget: $4,887,000    Provide the preliminary planning,    On Budget
Phase: Construction   design, and construction to replace    0 Change Orders
Start: 05/01/10         the existing HVAC systems within     Total Change Orders Amount:
Building C-15 that are at the end of
Completion: 6/30/2014                        $0
their service life.
Budget/Costs Incurred
Significant Developments
6
Construction contract awarded to Kassel & Associates, Inc.
5
Reviewing preconstruction submittals. The contractor conducted site
Millions  4
verification walk-through to identify potential issues that could impact
3
construction and only minor issues were found.
2
Dollars in 
Schedule                             1
0
Contractor is still projecting construction complete by the end of June
Authorized  Forecasted Costs Incurred
2014.
Budget
Construction Costs
Project is on track to be within the October 8, 2013 Commission     Not Applicable
funding authorization.
Change Order
None
Risks
Construction related access to existing infrastructure will be difficult
and some work will be within areas currently concealed from view.
Challenges may arise and could impact construction costs and
schedule. However, contractor has conducted site verification
walkthrough in December and the issues identified are relatively
minor.
Budget Transfers
None

REAL ESTATE
Port of Seattle 4Q 2013 Report  103

FOURTH QUARTER REPORT, 2013
P69 N Apron Corrosion Control
Status Snapshot
Project:   C800313      Install a corrosion control system    On Schedule
Budget: $5,100,000      for the steel pilings, pile caps, and   On Budget
Phase: Construction     beams under the North Apron.    0 Change Orders
Start: 03/06/12                                   Total Change Orders Amount:
Completion: 12/31/2013                       $0
Budget/Costs Incurred
Significant Developments
6
Construction is complete. Project is proceeding to closeout. This
will be the last report.                                        Millions 4
Schedule                             2
Construction completed on schedule.                       Dollars in 
0
Authorized  Forecasted Costs Incurred
Budget
Project is under budget.
Construction Costs
Change Order                         Not Applicable
None
Photo
Risks
None.
Budget Transfers
None.




REAL ESTATE
104  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
P-69 Built-up Roof Replacement
Project:   C800314      Replace 32,000SF of the 65,000SF  Status Snapshot
Budget: $445,000       Built-Up Roof at the P-69       On Schedule
Phase: Design        Headquarters Office Building     On Budget
Start: 2/26/12                                    0 Change Orders
Completion: 10/30/2014                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The project is in the 100% design phase. Expect Commission
authorization for construction in Q1 2014.                        4
Schedule                             3
Millions
The project is scheduled to be completed in Q4 2014               2
Budget                             Dollars in  1
The project is currently below budget.                          0
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
None
Budget Transfers
None




REAL ESTATE
Port of Seattle 4Q 2013 Report  105

FOURTH QUARTER REPORT, 2013
FT C-2 Nordby HVAC and Roof Replacement
Project:   C800344      Replace 23,000SF of existing      Status Snapshot
Budget: $298,000       Roofing and roof top HVAC units   On Schedule
Phase: Design                            On Budget
Start: 2/26/12                                    0 Change Orders
Completion: 10/30/2014                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The project is in the 100% design phase. Projects FT C-2 Nordby
HVAC and FT Net Shed 9 Roof Overlay projects are to be combined     3
together for funding authorization and bid as one (1) package with      2.5
separate CIP's. Expect Commission authorization for construction in
Q1 2014.                                     Millions 2
Dollars in 
1.5
1
Schedule
0.5
The project is scheduled for completion in Q4 2014
0
Authorized  Forecasted Costs Incurred
Budget
The project is currently below budget.
Construction Costs
Change Order                         Not Applicable
None
Risks
None
Budget Transfers
None



REAL ESTATE
106  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
FT Net Shed #9 Roof Overlay
Project:   C800527      Overlay 12,000SF of existing      Status Snapshot
Budget: $130,000       corrugated Roof at the FT Net     On Schedule
Phase: Design        Shed Building             On Budget
Start: 2/26/12                                    0 Change Orders
Completion: 10/30/2014                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The project is in the 100% design phase. This project will be
combined with the FT C-2 Nordby HVAC and Roof Replacement      0.35
project for funding authorization and bid as one (1) package with       0.3
separate CIP's. Expect Commission authorization for construction in    0.25
Q1 2014                                   Millions 0.2
0.15
Schedule                            Dollars in 0.1
0.05
The project is scheduled for completion in Q4 2014
0
Authorized  Forecasted Costs Incurred
Budget
The project is currently below budget.
Construction Costs
Change Order                         Not Applicable
None
Risks
None
Budget Transfers
None



REAL ESTATE

Port of Seattle 4Q 2013 Report  107

FOURTH QUARTER REPORT, 2013
Maritime Industrial Center Built-up Roof
Replacement
Replace the 21,000SF Roof at the   Status Snapshot
Project:   C800571      MIC Office Building            On Schedule
On Budget
Budget: $1,456,000
4 Change Orders
Phase: Construction                        Total Change Orders Amount:
Start: 9/30/12                                    $48,390
Completion: 10/30/2013
Budget/Costs Incurred
Significant Developments
The project is completed. Final closeout is scheduled.              2
1.5
Schedule                            Millions
The project is scheduled for completion in Q4 2013                1
0.5
Budget                             Dollars in 
The project is currently on budget.                             0
Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
None
Budget Transfers
None




REAL ESTATE
108  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Pier 66 Steam Replacement
Status Snapshot
Project: C800625        Install new boilers to provide
adequate heat and hot water      On Schedule
Budget: 1,560,000
service for both the conference     On Budget
Phase: Construction                           Change Orders
Start: 6/2/2013          center and CTA operations.
Total Change Orders Amount:
Completion: 12/31/13
Significant Developments                    Budget/Costs Incurred
Construction complete. System fully operational. This will be the
final report.
1.5
Schedule
1
Seattle Steam delayed cutoff of steam service from September 2nd
in Millions
to October 31st due to delay of City of Seattle seawall project. Crews
0.5
completed cutover to new system before this deadline. Remaining     Dollars 
control work and fine tuning now complete.
0
Authorized  Forecasted Costs Incurred
Budget
Project is within budget
Construction Costs
Change Order                        Not applicable
None
Risks
None
Budget Transfers
None



REAL ESTATE
Port of Seattle 4Q 2013 Report  109

FOURTH QUARTER REPORT, 2013
FT Net Shed Code Compliance
Project:   E104838      FT Net Sheds 3-11: Improvements   Status Snapshot
Budget: $2,950,000      required per City of Seattle building  On Schedule
Phase: Construction     & fire codes             On Budget
Start: May 2012                                  0 Change Orders
Completion: June 2015                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Received master/standard plan building permit for rack installation.
Applied individual net locker permits for units within Net Shed 9.        3.5
Netlocker improvements to the upper level of Net Shed 9 is complete     3
as of the end of December 2013.                          Millions 2.52
Schedule                             1.5
1
Despite additional permit process required by the City of Seattle,       Dollars in 
0.5
overall construction completion is still scheduled to be completed by
0
the end of 2nd quarter 2015.                                  Authorized  Forecasted Costs Incurred
Budget
Project budget is on track.                               Construction Costs
Not Applicable
Change Order
None                                 Photo
Risks
It is difficult to project the amount of stored materials that needs to be
moved out and moved back since tenant storage habit could vary
significantly. In addition, the amount of work required in each unit is
difficult to assess until stored materials are removed. These would
impact the overall project budget.
Budget Transfers
None


REAL ESTATE
110  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013 
Flight Information System (FIMS) II 
Project: C101117      Procure, develop, and implement a    Status Snapshot
Budget: $8,220,000     FIMS system that includes        On Schedule
Phase:Implementation   replacement monitors, an airport     On Budget
Start: 5/4/2010         resource management system, and    5 Change Orders
Completion: 12/30/2014  a flexible digital signage system      Total Change Orders Amount:
capable of displaying flight           $395,223
information, visual paging, and
notifications.
Budget/Costs Incurred 
9
Significant Developments
8
The first phase deployment of the Flight Information Display (FIDS)      7
Dollars in Millions   6
software was completed on-schedule in November 2012.
5
Deployment of the Resource Management System (RMS) was        4
deployed on-schedule in June 2013 with no major issues. This fully      3
2
replaces the previous FIMS software.
1
0
Authorized     Forecasted    Costs Incurred
New signage construction will continue through 2013 and small
enhancements to benefit airlines and Port operations will be
deployed through 2014. Planned integration with the Airport Breach
Notification System is no longer required and will not be delivered.    Construction Costs
2.5
Schedule
2
On Schedule
1.5
Budget                              1
On Budget                                   Dollars in Millions 0.5
0
Change Order                             Initial  Change  Spent
Orders
Prior report: Additional signage replacement was approved resulting
in a contract change order for construction design.
.
Risks
No significant risks.
Budget Transfers
None

CORPORATE 
Port of Seattle 4Q 2013 Report  111

FOURTH QUARTER REPORT, 2013
Maximo Enterprise Implementation
Project:   C800003      Implement latest version of       Status Snapshot Prior Report
Budget: $3,680,000      Maximo, merge Aviation and Real   Delayed Schedule
Phase: Implementation   Estate applications onto one     On Budget
Start: 11/25/2007         platform, and add service desk     0 Change Orders
Completion: 6/30/2014    module and wireless handheld    Total Change Orders Amount:
capabilities.                    $0

Significant Developments                    Budget/Costs Incurred
Major components of the program have been delivered, including the
4
deployment of Service Management software for the ICT Service
Desk in December 2008 and the upgrade and consolidation of         3
Marine Maintenance and Aviation Maintenance Maximo systems in     2
Millions
September 2010. Mobility enhancements were deployed for Aviation
1
and Marine Maintenance personnel in 2013.                   Dollars in
0
Schedule                              Authorized Forecasted  Costs
Incurred
Business resource constraints will delay the implementation of the
new interfaces that link the Maximo system to the Peoplesoft
Construction Costs
Financials system until 2014.
Not Applicable
Budget
On Budget
Change Order
None
Risks
Resource constraints may continue to delay the implementation of
the interfaces.
Budget Transfers
None


CORPORATE
112  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013 
ID Badge System Replacement 
Project: C800162        Procurement and replacement of   Status Snapshot Prior Report 
Budget: $2,500,000      the Portwide ID Badge system     Delayed Schedule
Phase:Implementation     including software, hardware, and   On Budget
Start: 5/1/2012           equipment.                 0 Change Orders
Completion: 9/30/2014                         Total Change Orders Amount:
$0
Significant Developments
Testing is in progress for an early April 2014 delivery of the new ID    Budget/Costs Incurred 
Badge system.
3
Schedule
Dollars in Millions 2
Complexity of the data migration and resource availability has
delayed project completion.                               1
Budget                             0
Authorized Forecasted   Costs
On Budget                                               Incurred
Change Order
Construction Costs
None                                 Not Applicable
Risks
Resource availability may continue to delay the second phase mobile
deliverables.
Budget Transfers
None




CORPORATE
Port of Seattle 4Q 2013 Report  113

FOURTH QUARTER REPORT, 2013
Airline Activity Management
Project: C800222        Development of an airline activity   Status Snapshot
Budget: $500,000       management system that       Delayed Schedule
Phase:Close Out       integrates with several Port      On Budget
Start: 6/19/2011          systems to replace aging reporting   0 Change Orders
Completion: 3/31/2014    system and supply data for airline   Total Change Orders Amount:
activity fees.                    $0

Budget/Costs Incurred
Significant Developments
0.6
The first phase delivery, that includes replacement of the aging
activity reporting system, has been delivered according to schedule.
0.4
Part of the original scope included a web portal that would be used to     Millions
0.2
collect flight activity from the airlines. This collection process was not    Dollars in
included in the final SLOA Agreement; however, so the web portal is
0
no longer a valid requirement and will not be delivered.                Authorized Forecasted  Costs
Incurred
Schedule
Implementing final requirements based on new SLOA Agreement    Construction Costs
terms.                                          Not Applicable
Budget
On Budget
Change Order
None
Risks
None
Budget Transfers
None


CORPORATE
114  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Enterprise Project Cost Management
Project: C800321        Replace the current construction    Status Snapshot
Budget: $1,525,000      costing systems with a common    Delayed Schedule
Phase:Implementation    enterprise project cost         On Budget
Start: 4/21/2008          management system.           0 Change Orders
Completion: 12/30/2014                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The first phase deployment has been completed and the software is
in-use by the Project Management Groups. Next phase deliverables     2
such as trend logs and cash flows are in test and scheduled for
1.5
delivery in 1st quarter 2014.
1
Millions
Schedule
Dollars in 0.5
Prior Report: Availability of resources is impacting the completion of
0
the remaining components. These include features such as cash
Authorized  Forecasted   Costs
flows and trend logs as well as additional interfaces that require                       Incurred
resources currently focused on the Peoplesoft Financials Upgrade
project. We are in the process of procuring additional configuration    Construction Costs
assistance and expect to deliver in phases over the next several     Not Applicable
months.
Budget
None
Change Order
None
Risks
Availability of Port resources may delay next phase deliverables.
Budget Transfers
None


CORPORATE
Port of Seattle 4Q 2013 Report  115

FOURTH QUARTER REPORT, 2013
Network Switch Replacement
Project: C800323        Upgrade the Network switch      Status Snapshot
Budget: $1,500,000      infrastructure hardware and      On Schedule
Phase: Design         software                On Budget
Start: 12/15/2013                                0 Change Orders
Completion: 3/31/2015                         Total Change Orders Amount:
$0

Significant Developments                    Budget/Costs Incurred
Planning and design are in progress.                          2
1.5
Schedule                            Millions  1
On schedule.
0.5
Dollars in    0
Budget
Authorized  Forecasted   Costs
On budget.                                                   Incurred
Change Order                         Construction Costs
Not Applicable
None
Risks
Port resource availability may impact schedule.
Budget Transfers
None





CORPORATE
116  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Time Clock System
Project: C800387        Procure and implement a Time    Status Snapshot Prior Report
Budget: $380,000       Clock System to accurately capture  Delayed Schedule
Phase: Implementation    and track time and attendance for   On Budget
Start: 6/8/2010           approximately 230 employees in    0 Change Orders
Completion: 4/30/2014    Aviation Security and Airport      Total Change Orders Amount:
Operations organizations.         $0

Significant Developments                    Budget/Costs Incurred
The new system rolled out to two organizations with two remaining
0.4
for the 1st Quarter 2014.
0.3
Prior Report: Vendor was unable to deliver software that functioned
in our environment per the contract so the project evaluated options      Millions  0.2
and elected to move forward with the procurement and            Dollars in 0.1
implementation of a simpler time clock system from another vendor.
The scope of the implementation will not include a PeopleSoft           0
Authorized Forecasted   Costs
interface as originally planned.
Incurred
Schedule
Construction Costs
Completion of new system rollout is scheduled for April 2014.
Not Applicable
Budget
$75,500 of the $240,000 spent to date on the project was directly
related to the previous vendor solution and will not contribute to the
value of a new product implementation. This was expensed against
the ICT Operations Budget in 2012. The new solution can be
delivered within the approved budget.
Change Order
None
Risks
No signfiicant risks at this time.
Budget Transfers
None

CORPORATE
Port of Seattle 4Q 2013 Report  117

FOURTH QUARTER REPORT, 2013
Police Records Management System
Project: C800393        Procure and implement a       Status Snapshot Prior Report
Budget: $1,300,000      replacement Police Records      Delayed Schedule
Phase:Close Out       Management System         On Budget
Start: 10/10/10                                   0 Change Orders
Completion: 4/1/2014                          Total Change Orders Amount:
$0
Significant Developments
The system was delivered for the Police Department in October     Budget/Costs Incurred
2013. Closeout activities are in progress.
1.4
Schedule                            1.2
1
Prior Report - Configuration of the final design took longer than
0.8
anticipated because of complexity in the procured software.           Millions
0.6
Dollars in0.4
Prior Report - A change request was approved to implement         0.2
additional software that will better meet business process for field       0
reporting. Technical problems installing the new software will delay        Authorized Forecasted  Costs
Incurred
the implementation until August 2013.
Prior Report - Contract negotiations took significantly longer than
anticipated delaying project completion by 8 months.             Construction Costs
Not Applicable
Budget
On Budget
Change Order
None
Risks
Continued issues with the software configuration could delay the
October delivery.
Budget Transfers
None

CORPORATE
118  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Construction Document Management
Project: C800521        Replacement of the Construction   Status Snapshot
Budget: $900,000       Document Management System    On Schedule
Phase: Planning        used by Construction Management  On Budget
Start: 9/10/2013          to accept, review, and distribute    0 Change Orders
Completion: 3/31/2015    critical documentation.         Total Change Orders Amount:
$0

Significant Developments                    Budget/Costs Incurred
Bid proposals are currently being evaluated.
1
Schedule                              0.8
On Schedule                                    0.6
Millions
0.4
Budget                             Dollars in 0.2
On Budget
0
Authorized Forecasted   Costs
Change Order                                    Incurred
None
Construction Costs
Risks                               Not Applicable
No signfiicant risks at this time.
Budget Transfers
None




CORPORATE
Port of Seattle 4Q 2013 Report  119

FOURTH QUARTER REPORT, 2013 
Access Control Network Refresh
Project: C800558        Upgrade the Access Control      Status Snapshot
Budget: $1,500,000      Network switch infrastructure     On Schedule
Phase: Design          hardware and software         On Budget
Start: 3/26/2013                                 0 Change Orders
Completion: 3/31/2014                         Total Change Orders Amount:
$0

Significant Developments                    Budget/Costs Incurred 
Data Center site improvements, equipment configuration, and virtual      2
infrastructure design is in progress.
1.5
Schedule                            Dollars in Millions 1
0.5
On schedule.
0
Authorized Forecasted   Costs
Budget                                       Incurred
On budget.
Construction Costs
Change Order
Not Applicable
None
Risks
Port resource availability may impact schedule.
Budget Transfers
None




CORPORATE
120  Port of Seattle 4Q 2013 Report

FOURTH QUARTER REPORT, 2013
Radio System Upgrade
Project: C800586        Upgrade of the Radio System Core  Status Snapshot
Budget: $6,750,000      Hardware and Software and      On Schedule
Phase: Implementation    Dispatch Consoles           On Budget
Start: 6/9/2013                                   0 Change Orders
Completion: 5/31/2014                         Total Change Orders Amount:
$0

Significant Developments                    Budget/Costs Incurred
Procurements have been completed and system configuration is in
8
progress.
6
Schedule
Millions    4
On Schedule
Dollars in    2
Budget
0
On Budget                                       Authorized Forecasted  Costs
Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
No signfiicant risks at this time.
Budget Transfers
None




CORPORATE
Port of Seattle 4Q 2013 Report  121

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.