5d

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA               Item No.      5d 
ACTION ITEM 
Date of Meeting    November 19, 2013 
DATE:    November 11, 2013 
TO:      Tay Yoshitani, Chief Executive Officer 
FROM:   Michael Ehl, Director, Airport Operations 
Wayne Grotheer, Director, Aviation Program Management Group 
SUBJECT:  South 160th Street Ground Transportation Project (CIP #C101107) 
Amount of This Request:         $667,000   Source of Funds:   Airport Development
Fund and Customer
Est. Total Project Cost:          $3,559,000 
Facility Charges 

ACTION REQUESTED 
Request Commission authorization for the Chief Executive Officer to: (1) proceed with design of
the S. 160th St. Ground Transportation Lot Project for an estimated $667,000; (2) execute utility
agreements with Puget Sound Energy (PSE), Comcast, and CenturyLink to underground utilities;
(3) grant and transfer a utility easement, if necessary, to PSE, Comcast, and CenturyLink on Port
property along the south side of S. 160th St. for the underground utilities; (4) reimburse PSE,
Comcast, and CenturyLink in an amount not to exceed $540,000 for the utility undergrounding
work; and (5) transfer the utility undergrounding scope of work and $973,000 of authorized
budget from the Off-Site Roadway Improvements (ORI) Project to the S. 160th St. Ground
Transportation Lot Project. 
SYNOPSIS 
The Port's S. 160th Ground Transportation Lot serves as a holding area for limousines, buses,
and taxis that serve Airport passengers. An existing building on the lot provides office space and
amenities for taxi drivers; however, it is in sub-standard condition and requires renovation.
Other proposed lot infrastructure improvements include a storm drainage system, lot re-striping,
and curb, gutter, and sidewalk along S. 160th St.
The project also includes undergrounding of existing overhead utility lines along the south side
of S. 160th St. Originally included in the ORI project as part of the Rental Car Facility (RCF) 
Program, undergrounding of the overhead utilities was deferred per agreement between the Port
and City of SeaTac. The undergrounding scope of work must be transferred from the ORI project
and be completed as part of the S. 160th St. Ground Transportation Lot improvements. The
existing overhead utility lines are owned by PSE, Comcast, and Century Link. These companies

Template revised May 30, 2013.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
November 11, 2013 
Page 2 of 7 
will perform the undergrounding design and construction and be reimbursed for their actual costs
by the Port in an amount not to exceed $540,000.
Depending on the alignment of the utility undergrounding determined during the design phase,
the Port may need to grant an easement on Port property along the south side of S. 160th St. The
requested authorization is for the design of the building renovation and lot infrastructure,
entering into agreements with utility companies to perform the design, construction and seek
reimbursement from the Port, grant and transfer, if needed, an easement to the utility companies
for the underground utilities, and transfer of the previously authorized scope and funds from the 
ORI project to the S. 160th St. Ground Transportation Lot project. Staff will return to
Commission for authorization to construct the building and lot improvements in the future. Total
project cost, including the utility undergrounding, is estimated to be $3,559,000. 
This project was included in the 2014  2018 capital budget and plan of finance.
BACKGROUND 
Lot Improvements 
The Port owns and operates the S. 160th St. Ground Transportation Lot located immediately
south of the RCF between Host Road and International Blvd. (see Attachment A). Existing
facilities were constructed in 1991, and vehicle access to and from S. 160th St. was recently
upgraded as part of the ORI project. 
The proposed project will provide a renovated building and other site improvements to support
an existing ground transportation facility. The taxi administration building has endured intense
use during the past 20 years and the interior has reached the end of its useful life. The building is
leased to Yellow Cab as part of their concession agreement. As part of the agreement, the Port is
responsible for building maintenance. Yellow Cab has approximately 700 drivers that use the
building on a regular basis. The renovation provides improvements to the building interior and
resolves habitability problems that can no longer be addressed through maintenance. In addition,
the lot's existing drainage system is not up to standard and does not adequately capture and
convey stormwater runoff. The project will connect the stormwater improvements to the off-site
storage water quality system located under the RCF to prevent erosion and protect Port of Seattle
property. 
Utility Undergrounding 
The ORI project completed the roadway improvements on State Route 518, International Blvd.,
S. 160th St, and Host Road as part of the RCF program. The Port and the City of SeaTac have an
Interlocal Agreement (2005 ILA) that addresses a number of issues associated with land use and
development on Airport property within the City of SeaTac. During the design of the ORI
project, the Port's original position was that the utilities in the area were located on Port of
Seattle property and therefore subject to the 2005 ILA rather than City of SeaTac Municipal
Code; however, after discussion with the City, it was determined that the utilities were located
within city right-of-way and subject to SeaTac Municipal Code. The timing of this discovery
precluded the undergrounding of utilities as part of the ORI project. In order not to delay the

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
November 11, 2013 
Page 3 of 7 
scheduled opening of the RCF, the Port and City agreed that the Port would commit to 
undergrounding the utilities when performing future work in this area (see Attachment B). Staff
has determined the S. 160th St. Ground Transportation Lot project is the appropriate project to
incorporate completion of undergrounding existing overhead utilities and is requesting the
transfer of the scope of work and $973,000 of previously authorized customer facility charge 
funds for this purpose. 
Under an agreement with the Port, PSE will design and construct the undergrounding of the
existing overhead power lines. PSE will relocate electrical service as well as any Comcast and
Century Link services co-located with the power lines. The Port will reimburse these utilities for
their work to convert their communications lines to underground.  Some or all of the alignment
and trench for the utility undergrounding may need to occur on Port property along the south side
of S. 160th St.  Therefore, the Port may need to grant PSE, Comcast, and CenturyLink a
permanent easement to construct and maintain their respective utility lines. 

PROJECT JUSTIFICATION AND DETAILS 
The existing building suffers from overuse of restroom and kitchen facilities resulting in broken
plumbing fixtures, out of service showers, water leaks, water damage, broken tile, and stained
ceilings.  In addition, stormwater runoff on the lot is not adequately captured by a drainage
system. Rainwater often flows directly off the lot causing erosion damage. An expanded
drainage network is required to collect stormwater that flows across the lot and route it to an
existing pipeline and water quality treatment system at the RCF on the north side of S. 160th St. 
Existing aboveground utility lines along S. 160th St. should be undergrounded to meet the
provisions of the City of SeaTac Municipal Code.
Project Objectives 
Objectives of the proposed upgrades are to: 
Provide a renovated building with amenities for drivers 
Provide other site and infrastructure improvements 
Provide an upgraded ground transportation asset with a low total cost of ownership 
Underground utility lines along S. 160th St. 
Scope of Work 
Renovate existing drivers' building interior 
Complete the installation of curbs, gutters, and landscaping along S. 160th St. 
Install site storm drainage system with a connection to the RCF system 
Re-striping the existing lot to create more parking space and more efficient use 
Undergrounding of existing utility lines along S. 160th St. fronting Port property

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
November 11, 2013 
Page 4 of 7 
Schedule 
Design: December 2013  June 2014 
Advertise for bids, award and construct: July 2014  February 2015 
Budget by Area of Work 
Project, Excluding           Utility     Total 
Utility Undergrounding     Undergrounding
Only (Transfer) 
Construction                    $1,800,000          $295,000     $2,095,000 
Soft Costs                       $786,000          $138,000      $924,000 
Reimbursement to Utilities                $0          $540,000      $540,000 
Total                          $2,586,000          $973,000     $3,559,000 
Less expense                     -$50,000         -$687,000     -$737,000 
Net capital costs                   $2,536,000          $286,000     $2,822,000 
Project work, excluding utility undergrounding, includes building renovation, lot storm drainage
system, lot striping, and signage.   Work related to utility undergrounding includes
reimbursement to utility companies for their construction and soft costs trenching and converting
lines from overhead to underground, and Port costs for sidewalks, curbs, landscaping, and
fencing in the undergrounding area. The landscaping and fencing on Port property will be
capitalized. 

Budget/Authorization Summary 
Capital      Expense    Total Project 
Original Budget                      $3,516,000          $0     $3,516,000 
Revised scope                       -$980,000      $50,000     -$930,000 
Budget transfer                        $973,000          $0      $973,000 
Reclassify Budget as public expense         ($687,000)     $687,000          $0 
Revised Budget                     $2,822,000     $737,000     $3,559,000 
Previous Authorizations                      $0          $0           $0 
Authorization transfer                    $286,000      $687,000      $973,000 
Current request for authorization             $667,000          $0      $667,000 
Total Authorizations, including this request      $953,000      $687,000     $1,640,000 
Remaining budget to be authorized         $1,869,000      $50,000     $1,919,000 
Total Estimated Project Cost             $2,822,000     $737,000     $3,559,000 
The original budget included scope to resurface the entire lot and replace the lighting. During
the development of the project notebook, it was determined that these scope items were not
necessary.  A portion of the budget to be transferred for utility undergrounding has been
determined to be public expense.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
November 11, 2013 
Page 5 of 7 
Project Cost Breakdown                     This Request      Total Project 
Construction                                      $0        $1,954,000 
Construction Management                          $0        $147,000 
Design                                    $331,000         $331,000 
Project Management                          $184,000        $184,000 
Other Soft Costs                               $152,000         $262,000 
State & Local Taxes (estimated)                         $0         $141,000 
Utility Undergrounding Reimbursement                   $0         $540,000 
Total                                        $667,000        $3,559,000 
Budget Status and Source of Funds 
The S. 160th St. Ground Transportation project, CIP C101107, is included in the 2014  2018
capital budget and plan of finance. The budget has been modified for scope reductions and
scope additions.  The funding source for the 160th lot improvements will be the Airport
Development Fund. For the $973,000 budget transferred in from the RCF program (C100266),
the funding source will be Customer Facility Charge (CFC) revenues. 
Financial Analysis and Summary 
The below financial analysis does not include the utility undergrounding work. 
CIP Category             Renewal/Enhancement 
Project Type              Life Cycle Extension and Asset Protection 
Risk adjusted discount rate     N/A 
Key risk factors             Unforeseen site conditions could increase design and
construction costs and delay project schedule. 
Project cost for analysis        $2,586,000 (excludes utility undergrounding) 
Business Unit (BU)          Ground Transportation 
Effect on business performance  NOI after depreciation will decrease. 
IRR/NPV             N/A, This is a renewal and replacement project that
increases the life of existing Port of Seattle assets that are
necessary to maintain existing revenues from taxi service. 
CPE Impact             None 
Lifecycle Cost and Savings 
Annual maintenance costs for the building continue to increase. Maintenance costs for 2013
were $15,000 for the restrooms alone. New improvements will significantly reduce the need for
unscheduled maintenance activity and extend the useful life of the building. 
STRATEGIES AND OBJECTIVES 
This project aligns with the Port's Century Agenda to meet the region's air transportation needs
at Sea-Tac Airport for the next 25 years.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
November 11, 2013 
Page 6 of 7 
TRIPLE BOTTOM LINE 
Economic Development 
The project supports economic development by investing in an upgraded ground transportation
lot to serve the public's needs at the Airport. Environmental sustainability principles will be
employed consistent with Port policy. In addition, procedures set forth in the Port's Small
Contractors and Suppliers Program will be used when applicable in the project contracting
process in coordination with the Office of Social Responsibility. 
Environmental Responsibility 
This project will provide the opportunity to apply environmental sustainability principles
associated with the new improvements, including: 
Upgrading the site drainage system to better manage stormwater 
Undergrounding utility lines to improve reliability and visual appearance. 
Utilizing energy efficient light fixtures and water efficient plumbing fixtures in the
building 
Community Benefits 
This project provides infrastructure upgrades and replacement to an Airport asset that provides a
significant service and benefits to passengers. The project also fulfills agreements with the City
of SeaTac to provide underground utilities along S. 160th Street. 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  Do nothing. Under this alternative, the existing ground transportation (GT) lot
facilities will continue to deteriorate. The habitability of the building and the functionality of the
storm drainage system will continue to be sub-standard.  Existing overhead utilities along
S. 160th St. will not be undergrounded. This alternative is not recommended. 
Alternative 2  Invest in the GT lot facility upgrades, but at a reduced scope of work from those
proposed here.  For example, the amount of building renovations could be reduced or an
upgraded storm drainage system could be deleted from the project. As with Alternative 1, the
habitability of the building and the functionality of the storm drainage system will continue to be
sub-standard, although existing overhead utilities along S. 160th St. would be undergrounded.
This alternative is not recommended. 
Alternative 3  Invest in the GT lot facility upgrades and underground existing overhead utilities
along S. 160th St. as proposed.  This will result in a renovated building with improved
habitability and lower maintenance and repair cost. The improved storm drainage system will
collect surface runoff from the lot with conveyance to the Rental Car Facility drainage system.
This is the recommended alternative.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
November 11, 2013 
Page 7 of 7 
ATTACHMENTS TO THIS REQUEST 
Attachment A  Project Site Figure 
Attachment B  April 11, 2011 letter from Mark Reis to the City of SeaTac regarding
the application of the city municipal code to the Port's Rental Car Facility Off-Site Road
Improvement Project 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
December 15, 2009  the Commission authorized an additional $16,334,400 for the
construction of the ORI project, and the execution of construction contracts for
$17,534,400 (including Washington State Department of Transportation's bridge
seismic improvements). 
June 30, 2009  the Commission 1) lifted the suspension and restarted the entire RCF
program, 2) authorized $591,670 in additional design funds for the BMF and ORI
projects, 3) authorized $27,826,000 in additional construction funds for the RCF
project, 4) authorized multiple change orders for a not to exceed value of $16,800,000
and up to 260 calendar days for the construction of the RCF project, and 5) revised the
Commission notification requirements for change orders for the RCF project. 
December 15, 2008  the Commission authorized the suspension of most work under
the contract for construction of the RCF project for an indefinite period, not to exceed
one year. Design for the Bus Maintenance Facility (BMF) and ORI projects would
continue. 
November 11, 2008  the Commission was briefed on the status of the RCF program
and authorized $552,000 for the ORI project for design and advance utility relocations. 
November 9, 2004  the Commission authorized $18,675,000 for the completion of
facility design for the RCF program, and for procurement of a GC/CM for the delivery
of the project. This included $2,019,500 for the ORI project. 
March 27, 2001  the Commission authorized $3,500,000 for the completion of
schematic development for the RCF program. This included $405,600 for the ORI
project.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.