7a supp
Item No. 7a_Supp Date: November 19, 2013 Capital Improvement Projects Third Quarter Report 2013 Commission Briefing Capital Improvement Projects Overall Status of Projects 111 Total Projects in report 61 Projects are within or ahead of target schedule and budget 47 Projects have either target schedule or budget off 3 Projects have both target schedule and budget off 2 Project Status Total CIPs Managed by CDD 100% 90% 80% 70% 60% 50% 40% 30% 20% Project Distribution per Quarter 10% 0% 4Q12 1Q13 2Q13 3Q13 Report Report Report Report Both Schedule and Budget off 2 1 1 3 Either Budget or Schedule off 37 40 40 39 On Schedule/On Budget 51 51 58 57 3 AVIATION PROJECT SUMMARY Eight projects are behind schedule: 8th Floor Weatherproofing (7 months) The weatherproofing failed in portions of sections B and C. The work was rejected and has resulted in a delay of beneficial occupancy. C60 C61 BHS Modifications (6 months) The project team revised the scope to ensure needed baggage make-up capacity, computer replacements, and automatic tag readers replacement, delaying the project delivery. Feeder 101 Tap Replacement (3 months) The slip is due to combining the project with the Fire Station Electrical Upgrade and to some issues accessing the manholes along Air Cargo Road. 4 AVIATION PROJECT SUMMARY, Cont. Eight projects are behind schedule (continued): Vertical Conveyance Modernization Phase 1 (6 months) Additional time needed to resolve change order issues. Vertical Conveyance Modernization Phase 2 (12 months) Replacing mechanical and electrical designers. Also potential loading concerns at site of foundation would add to design delay. Stage 2 Mechanical Energy Implementation (1 month) The schedule delays were due to the broken valves in Central Plant and the addition of ten terminal units to the scope. 5 AVIATION PROJECT SUMMARY, Cont. Eight projects are behind schedule (continued): Security Exit Lane Breach Control Phase 2 (5 months) The Phase 2 project schedule was pushed out to ensure adequate time for Airport Security and TSA testing of the pilot project (completed in Phase 1). South Satellite Concessions (3 months) The delay is partially a result of the late start for the second phase of this project caused by the tenant build out of the new duty free shop. One project is forecasting over budget: Doug Fox Site Improvements (~$1,385,000) Construction bids were opened on September 5 and the low bid exceeded the engineer's estimate by more than 10%. 6 SEAPORT/REAL ESTATE PROJECT SUMMARY One Real Estate project - Fisherman's Terminal C-15 Building HVAC - is reporting both schedule and budget variance in the third quarter One Seaport project T91 Maintenance Dredging is reporting a schedule variance in the third quarter 7 Pier 66 Boilers 8 CORPORATE PROJECT SUMMARY Two projects with a new reportable schedule variance this quarter: Maximo Business resource constraints will delay the implementation of the new interfaces that link the Maximo system to the PeopleSoft Financials system until 2014. All other project components have been delivered. Police Records Management Configuration of the final design took longer than anticipated because of complexity with the procured software. System deployment is scheduled for October 2013. 9 Small Business Contracting SB by SBA Standard 2011 2012 2013 2013 2013 2014 Actual Actual To Date Proposed SCS Goals Major Construction 29% 45% 40.9% 20% 12.4% 50% SW Construction 62% 92% 84.9% 60% 8.7% 90% Goods and Services/ 18% 57% *20.3% 30% *4.9% 12%/ Service Agreements 30% Q1-Q3 2013 YTD Aggregate SB to SBE 29.7% Standard * As of 2Q 2013 G&S includes Expense and Capital work. This is an overall POS # and includes consultants and sub-consultants. 10 Service Agreement Procurement Phase Timelines Procurements Have Four Major Phases Phase times may vary by nature of procurement Procurement Phase Times in Number of Days Development Advertising Evaluation - Negotiation- Total Time Selection Execution 2011 YTD 77 27 85 80 211 2012 YTD 70 28 23 84 202 2013 YTD 71 24 42 87 167 11 ProcurementTeam Approach Many players impact schedule CPO Facilitator Department Representatives Project Manager - Leader Evaluation Committee Port Stakeholders Consultant RFQ procurement schedule establishes target for contract execution. 12 CPI Evaluation Process Evaluation of Proposals "Lean" Workshop in October 2011 Evaluation took average 76 days in 2010-2011 Mapped current process Developed new process Consensus Evaluation Goal for 2012 forward = 36 days Metrics 2012 = 23 days 2013 = 42 days 13 Future Process Improvements Negotiation Assistance to PMs Launched March 2013 Not yet able to measure impact Negotiation Time for IDIQ Evaluating how to improve time May do an accelerate workshop (CPI process) Current Average Time = 71 Days Goal = TBD 14
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.