7a attach

Item Number:   _Report
Meeting Date: Nov 19, 2013


Commission Staff Brieng
Capital Improvement Projects
Third Quarter Report 2013

This page intentionally left blank









ii  Port of Seattle 3Q 2013 Report

Port of Seattle
Capital Improvement Project Report
7KLUG Quarter 2013
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the status of the Port's capital projects.
Background
During 2013 the Port plans to invest over $225,500,000 to expand and upgrade the infrastructure that supports marine
and aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping
companies, airlines, rental car companies, concessionaires and public parking. About 4 percent of the Port's capital
budget comes from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in
transportation facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes a "Status Snapshot" illustrating at a
glance if the project is on schedule, within budget, the total number of change orders to date, and the total value of
executed change orders.
x Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x Budget addresses the total project budget and includes things like overall budget status, recent Commission
authorizations, forecasted overruns or savings, and scope changes.
x Change Orders provides a description of CO for the reporting period and information on any CO over $200,000 or
10% of the contract value.
x Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x Budget Transfers reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page and select the Audit/Accountability button. Use the form to ask a
question, make a comment or request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 3Q 2013 Report  1

Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C000683 et al .......3rd Runway Program .............................................6 ........... 
C100266 et al .......Rental Car Facility ............................................... 7-8..........
C102032 ...............Sanitary Sewer Pump Station Upgrade ................9 ...........
C102334 ...............Water System Isolation Valve Upgrade ................10 ..........
C102573 ...............Aireld Pavement Replacement ...........................11 ..........
C800019 ...............Gate Utilities Improvement ...................................12 ..........
C800034 ...............North Expressway Relocation ..............................13 ..........
C800061 ...............Main Terminal South Low Voltage ........................14 ..........
C800105 ...............Airport Owned Gate Infrastructure .......................15 ..........
C800107 ...............C4 UPS System Improvements ............................16 ..........
C800112................Runway 16C/34C Panel/Joint Sealant .................17 ..........
C800148 ...............GML Arrivals Hall Concessions ...........................18 ..........
C800168 ...............C60-C61 BHS Modications ................................19 .......... ...............
C800174................FIS - New Primary Inspection Booths ..................20 ..........
C800218 ...............Security Exit Lane Breach Control Phase I ..........21 ..........
C800230 ...............Emergency Lighting Parking.............................. 22-23........
C800234 ...............Feeder 101 Tap Replacement ..............................24 ..........
C800237 ...............Terminal Escalators Modernization ......................25 ..........
C800238 ...............Central Plant Pre-Conditioned Air ..................... 26-27 .......
C800247 ...............Cargo 2 West Hardstand ......................................28 ..........
C800251 ...............Vertical Conveyance Modernization.....................29 .......... ...............
C800253 ...............Parking System Replacement ..............................30 ..........
C800254 ...............Aircraft RON Parking Post Ofce Site..................31 ..........
C800267 ...............Port Owned Loading Bridges ...............................32 ..........
C800268 ...............Stage 2 Mechanical Energy Implementation .......33 .......... ...............
C800274 ...............8th Floor Weather Proong ..................................34 .......... ...............
C800276 ...............Common Use Equipment Expansion (CUSE) ......35 ..........
C800324 ...............Long-Term Cell Phone Lot .................................36-37 .......
C800334 ...............Two new CTE Freight Elevators ...........................38 .......... 
C800335 ...............EGSE Electrical Charging Stations ...................39-40 .......
C800374 ...............Claim Device 14 and Lower Inland .......................41 ..........
C800375 ...............Vertical Conveyance Modernization.....................42 .......... ...............
C800376 ...............South Satellite HVAC, Lights, and Ceiling Repl. ..43 ..........
C800382 ...............BHS (C22-C1, MK1 and TC3) ............................44-45 .......
C800390 ...............Cargo 6 Enhancements ........................................46 ..........
C800406 ...............RW 16C/34C Reconstruction Design ...................47 ..........



2  Port of Seattle 3Q 2013 Report

Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule Budget
C800412 ...............South Satellite Concessions Project ....................48 .......... .............................. 
C800414 ...............Access Control Door Additions ............................49 ..........
C800415 ...............ALCMS Upgrade...................................................50 ..........
C800417 ...............Lagoon 3 Bird Wires .............................................51 ..........
C800426 ...............FIS Improvement - Short Term .............................52 ..........
C800451 ...............Doug Fox Site Improvement .................................53 .......... ................. ............................................
C800455 ...............Concourse D Common Use Environment ............54 ..........
C800459 ...............2011-2013 Roof Replacement Program ...............55 ..........
C800461 ...............IWTP Fiber Installation .........................................56 ..........
C800464 ...............Fiber Infrastructure to Gate Backstands ..............57 ..........
C800466 ...............South Satellite - Additional Gate Lobby ................58 ..........
C800467 ...............PLB Replacement .................................................59 ..........
C800473 ...............CUSE at Ticket Counters/Gates - AR ..................60 ..........
C800474 ...............Airport Signage .....................................................61 ..........
C800475 ...............Miscellaneous Building Improvements - AR.........62 ..........
C800479 ...............Fire Station Electrical Upgrades ...........................63 ..........
C800484 ...............Laptop Power In Concourses ...............................64 ..........
C800490 ...............New Window Wall Ticket Zone 1 ..........................65 ..........
C800491 ...............Convert Ticket Zone 2 Pusback ...........................66 ..........
C800492 ...............Convert Ticket Zone 3 Flow Thru .........................67 ..........
C800495 ...............Facility Monitoring System Renewal ....................68 ..........
C800497 ...............Airport Wide Mechanical Controls System ..........69 ..........
C800541 ...............RAC Baggage Claim Renovation .........................70 ..........
C800544 ...............NorthSTAR Program.............................................71 ..........
C800547 ...............NorthSTAR Concourse C Vertical Circ. ...............72 ..........
C800550 ...............Concourse D Roof Replacement..........................73 ..........
C800551 ...............Grease Interceptor Augmentation ........................74 ..........
C800555 ...............NorthSTAR Refurbish Baggage Systems ............75 ..........
C800556 ...............NorthSTAR North Satellite Renovations ..............76 ..........
C800560 ...............MT Mezzanine Tenant Relocation ........................77 ..........
C800576 ...............Known Crew Member Employee Bypass .............78 ..........
C800583 ...............International Arrivals Facility ................................79 ..........
C800605 ...............Security Exit Lane Breach Control .......................80 .......... .............................. 
C800609 ...............NSAT - STS Ceiling Leak Repair ..........................81 ..........
C800611 ...............Passenger Bridge & Walkway S16 Repl ..............82 ..........
C800612 ...............Checked Baggage Recapitalization/Optimzation.83 ..........
C800615 ...............Second Floor Mezzanine Infra Upgrade ..............84 ..........



Port of Seattle 3Q 2013 Report  3

Other Aviation ..........................................................................
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C200007...............Highline School Noise Insulation ..........................85 ..........
C200042 ...............Highline Community College Noise Insulation .....86 ..........
C200048 ...............Home Insulation Retrot .......................................87 ..........
C200093 ...............Single Family Home Sound Insulation .................88 ..........
C800146 ...............RMU/Kiosk Concession Program ........................89 ..........
C800150 ...............Burien Commercial Property Acquisition .............90 ..........
C800154 ...............Tenant Reimbursement ........................................91 ..........
C800498 ...............Snow Removal Equipment ...................................92 ..........

Seaport
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C102554............... Terminal 46 Development....................................93 ..........
C102858 et al ....... Street Vacations T-5/18/105.................................94 ..........
C800183 ...............P91 Fender System Upgrade ...............................95 ..........
C800430 ...............T-91 Building C175 Roof Replacement ................96 ..........
C800516 ...............SEA P-66 Apron Pile Wrap ..................................97 ..........
C800546 ...............Argo Yard Truck Roadway .................................98-99 .......
C800596 ...............P66 Security Camera Upgrade ...........................100 .........
C800603 ...............T-46 Dock Rehabilitation .....................................101 .........

WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation .................102 .........
E104324 ................Viaduct Construction Coordination .....................103 .........
E104840................T-5, T-18 and T-91 E. Maintenance Dredging .....104 ......... .............................. 
Real Estate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800137 ...............FT C15 HVAC Improvements ..............................105 ......... ..............................  ........................................
C800313 ...............P69 N Apron Corrosion Control ..........................106 .........

4  Port of Seattle 3Q 2013 Report

Real Estate, cont.
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800344 ...............FT C-2 Nordby Roof and HVAC .........................108 .........
C800527 ...............FT Net Shed 9 Roof Replacement ......................109 .........
C800571 ...............MIC Built-up Roof Replacement ..........................110 .........
C800625 ...............Pier 66 Steam Replacement................................ 111 .........
E104838................FT Net Shed Code Compliance ..........................112 .........
Corporate

Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C101117 ................Flight Information Systems (FIMS) II ...................113 .........
C800003 ...............Maximo Enterprise Implementation .....................114 ......... .............................. 
C800162 ...............ID Badge Replacement .......................................115 ......... .............................. 
C800222 ...............Airline Activity Management ................................116 .........
C800321 ...............Enterprise Project Cost Management ..................117 .........
C800322 ...............Records and Document Management .................118 .........
C800387 ...............Time Clock System ..............................................119 .........
C800392 ...............PeopleSoft Financial Upgrade .............................120 .........
C800393 ...............Police Records Management System .................121 .........
C800521 ...............Construction Document Management ................122 .........
C800558 ...............Access Control Network Refresh ........................123 .........
C800586 ...............Radio Systems Upgrade......................................124 .........


Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Variance Status
Variance Since Last Report



Port of Seattle 3Q 2013 Report  5

THIRD QUARTER REPORT, 2013
3rd Runway Program
Status Snapshot
On Schedule
Project: C000683,       The 3rd Runway Program
On Budget
C001138, C001175,      constructed a new 8,500 foot long
0 Change Orders
C001331, C001751,      runway, connecting taxiways, and
Total Change Orders Amount:
C001760, C100172      related infrastructure.
$0.00
Budget: $914,744,759
Phase: Construction                       Budget/Costs Incurred
Start: 05/27/1997
1150
Completion: 12/31/2011
1100
1050
Significant Developments                    1000 MillionsDollars in 
950
None.                                     900
850
Schedule                            800
Authorized  Forecasted    Costs
The remaining construction work includes RST property site                        Incurred
restoration. Impervious surfaces are to be removed from the site.
Budget                           Construction Costs
Not Applicable
The project forecast is within the approved budget and authorization.
Additional savings is anticipated.
Photo
Change Order
No change orders were executed this quarter.
Risks
None
Budget Transfer
To Savings                      $4,250,000



AIRPORT
6  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Rental Car Facility                       Status Snapshot Prior Report
Delayed Schedule 3Q 12
Project:   C100266,     The program will construct a       Under Budget        1Q 13
C102167, C800032     consolidated rental car facility (RCF)  1,751 Change Orders
Budget: $378,791,752   for all rental car companies at the    Total Change Orders Amount:
Phase: Construction    airport, a bus maintenance facility    $13,977,765
Start: 02/24/1998        (BMF), and mitigation with the off-site
roadway improvements (ORI), plus    Budget/Costs Incurred
Completion: Spring 2012
purchase a fleet of buses.
400
Significant Developments                     390
The Consolidated Rental Car Facility is substantially complete.        Millions 380
Project is in closeout. Final claims negotiations are pending.
370
Dollars in 
The ORI project is in closeout. The FAA continues working on the       360
transfer of Port property to WSDOT and the City of SeaTac.
350
Authorized  Forecasted Costs Incurred
The BMF project is in closeout.
Schedule
Construction Costs
RCF opened May 17, 2012. Project closeout is substantially
complete except for RCF (2014 pending final claim resolution).         300
250
Budget                             Millions 200
150
The total forecasted cost at completion, not including funding for
100
claims settlement, is $392,306,000 (capital and expense budgets).
The current forecast represents a total estimated program savings of    Dollars in   50
$27,000,000 based upon the total program budget of $419,306,000.      0
Initial   Change   Spent
Orders
Change Order
None this quarter.                                    Photo
Risks
x For RCF: in closeout, claims resolution.
x For ORI: none identified.
x For BMF: none identified.



Port of Seattle 3Q 2013 Report  7

Budget Transfers
Reduced $17,111,099 from the budget and transferred it out as Government Expense work.
Returned an additional $1,327,000 to savings.
Cost Growth of Construction
RCF Airport Wayfinding Signage and Curbside Modifications - MC-0316968 - Cumulative change
order percentage is 21.3% with no activity this quarter. This contract is closed.
Consolidated Rental Car Facility - Small Operator Build Out - MC-0317022 - Cumulative change
order percentage is 3.97% with minimal activity this quarter. This contract is closed.
Consolidated Rental Car Facility Offsite Roadway Improvements and SR99 Bridge Seismic Upgrade
MC-0316568 - no change orders executed this quarter. The cumulative change order value
through this quarter is $3,017,296 (39.6%). Final payment made to the Contractor. This contract is in
closeout.
Bus Maintenance Facility - MC-0316730 - The cumulative change order value is $300,190 (2.29%).
Final payment made to the Contractor. This contract is in closeout.
GCCM Final Construction (Phase 3 of 3)  MC-0315405 - On June 30, Commission authorized the
$32,000,000 suspension impact including a $6,973,300 budget increase and an increase in change
order limit from 10% to 18% requiring Commission notification. The current cumulative change order
percentage through this quarter is 4.2% with no change orders executed this quarter. Final claim
negotiations are underway. This contract is active.
TESC & Early Work (Phase 2 of 3)  MC-0315292 - Cumulative change order percentage is 19.4%
due primarily to removal of contaminated soils and associated impacts. This work and the final
contract reconciliation is complete and the contract is closed.
GCCM Pre-Construction (Phase 1 of 3)  MC-0314280  The cumulative change order percentage of
170.5% is the result of changes for additional contractor management and support beyond the extent
of the original scope to validate project costs and support the rental car companies and the Port on
final approval of the project. This work and the final contract reconciliation is complete and the
contract is closed.


AIRPORT
8  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Sanitary Sewer Pump Station Upgrade
Project:   C102032      This project upgrades the aging    Status Snapshot
Budget: $1,133,000      control systems of 22 sanitary     On Schedule
Phase: Design        sewer lift stations at Seattle-     On Budget
Start: 03/01/2013         Tacoma International Airport.      0 Change Orders
Completion: 5/31/2014                        Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
1.2
Control components have been ordered. Project-specific electrical
1
contractor has been selected.
Millions 0.8
0.6
Schedule
0.4
The project is currently on schedule.                         Dollars in 0.2
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT
Port of Seattle 3Q 2013 Report  9

THIRD QUARTER REPORT, 2013
Water System Isolation Valve Upgrade-non AF
Status Snapshot Prior Report
Delayed Schedule 3Q 12
Project:   C102334      This project replaces isolation     On Budget
Budget: $807,000       valves on the aging water       0 Change Orders
Phase: Close Out      distribution system, necessary for   Total Change Orders Amount:
Start: 10/01/2010         isolating portions of the system in    $0
Completion: 2/28/2013    the event of breaks, leaks, or tieins
, in non-airfield (AF) locations.    Budget/Costs Incurred
1.2
Significant Developments                      1
Millions    0.8
Construction is complete and project is in closeout.
Dollars in     0.6
Schedule                             0.4
0.2
Construction is complete.
0
Authorized       Forecasted      Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time
Budget Transfers
To C800404 (Aeronautical Allowance)          $147,000




AIRPORT
10  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Airfield Pavement Replacement
Status Snapshot
Project:   C102573      The project is intended to be a     On Schedule
Budget: $30,162,035     multi-year pavement replacement   On Budget
Phase: Construction     program to replace distressed     0 Change Orders
Start: 05/02/2010         pavement and joint seal on the     Total Change Orders Amount:
Completion: 12/31/2016   airfield.                $0.00
Budget/Costs Incurred
Significant Developments
35
All work has been completed except for Thermoplastic marking and
30
painting. This work is weather dependent.
Millions 25
20
Schedule                             15
The 2013 construction work should be complete by the end of        Dollars in  10
October. Preliminary engineering for the fourth phase in 2014 has      5
begun.                                        0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.              2013 Construction Costs
Change Order
6
No change orders were executed this quarter.                     5
Millions   4
Risks                                  3
None this quarter.                                        2
Dollars in    1
Budget Transfers                           0
Initial   Change   Spent
To Expense                      $50,000
Orders
To 800404 (Aeronautical Allowance)          $50,000




AIRPORT
Port of Seattle 3Q 2013 Report  11

THIRD QUARTER REPORT, 2013
Gate Utility Improvements
Status Snapshot Prior Report
Delayed Schedule     3Q 12
Project:   C800019   This project will upgrade the South      On Budget
Satellite Port-owned loading bridges to
Budget: $11,744,480                         0 Change Orders
the same standards, including 400Hz
Phase: Construction                        Total Change Orders Amount:
power and potable water. This will
Start: 06/28/2007                                 $0
reduce air emissions, improve energy
Completion: 8/29/2014 efficiency and save money for the     Budget/Costs Incurred
airlines.
15
Significant Developments                     Millions 10
The Contractor is working at both the North and South Satellite.
5
Schedule                            Dollars in 
After the design completion in December, the current schedule has      0
Authorized  Forecasted Costs Incurred
the construction starting in third quarter of 2013 and being completed
in one year.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.
6
5
Change Order
Millions   4
None                                    3
2
Risks                                Dollars in   1
Airport Operations at certain gates could be impacted during the         0
construction phase of the project.                                 Initial  Change  Spent
Orders
Budget Transfers
None this quarter.



AIRPORT
12  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
North Expressway Relocation
Project:   C800034
The project reconstructs the North   Status Snapshot  Prior Report
Budget: $102,213,605    Airport Expressway and suports the  Delayed Schedule 2Q 11
Phase: Construction     extension of light rail to the Airport.  On Budget
Start: 07/27/2004         It also includes improvements to    226 Change Orders
Completion: 07/31/2012   Wall 14.                Total Change Orders Amount:
$8,295,574
Significant Developments
Budget/Costs Incurred
The main contracts for reconstruction of the North Airport
Expressway and the light rail transit components are complete.        115
110
Schedule                            Millions
The original schedule for the Wall 14 Improvements included the       105
completion of design by April 2013, and the completion of
construction by October 2013. The final design and construction of     Dollars in 100
this project has been delayed until 2014 given the construction traffic     95
impacts to Air Cargo Road and to Cell Phone Lot operations.            Authorized Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
120
Change Order
100
One change order was issued this quarter.
Millions 80
60
Risks
40
None identified at this time.                                 Dollars in  20
0
Budget Transfers                             Initial  Change Order Spent
To C102066 (Art Pool)                    $3,000
Photo



AIRPORT
Port of Seattle 3Q 2013 Report  13

THIRD QUARTER REPORT, 2013
Main Terminal South Low Voltage
Project:   C800061   This project covers the renewal and     Status Snapshot Prior Report
Budget: $1,925,000   replacement of low voltage (600 volts   Delayed Schedule 1Q 08
Phase: Design      and below) electrical distribution      On Budget
0 Change Orders
Start: 06/28/2007      equipment in the southern part of the
Total Change Orders Amount:
Completion: TBD    Main Terminal.
$0
Significant Developments
Budget/Costs Incurred
Due to project deferral and the possibility of changes in site
conditions and building codes, the design phase changed from 100%     5
to 90% complete. Project Notebook is being finalized to address
4
scope of work, schedule, and budget. Project Definition section of     Millions 3
the notebook has been presented to the Investment Committee(IC)
and the updated Project Notebook is scheduled to be presented to      2
IC on November 6, 2013.                              Dollars in  1
0
Schedule                               Authorized Forecasted Costs Incurred
Staff has finalized the scope of work, schedule and final design
budget. The 100% design documents for this project are scheduled
to be complete by the end of June 2014.                    Construction Costs
Not Applicable
Budget
The project budget is being evaluated based on delays and scope    Photo
changes.
Change Order
None
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will
be required to add additional crews to complete work in a timely
manner. This area is a 24/7/365 operation. Sequencing of this work
is critical and electrical power has to be maintained without
interruptions.
Budget Transfers
None this quarter.

AIRPORT
14  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Airport Owned Gate Infrastructure
Project:   C800105      This project purchases and       Status Snapshot Prior Report
replaces passenger loading bridges  Delayed Schedule 3Q 12
Budget: $6,072,461
On Budget
Phase: Close Out      (PLB) at gates throughout the
airport. The project is being        0 Change Orders
Start: 07/24/2007
performed in phases.           Total Change Orders Amount:
Completion: 06/30/2013                       $0
Significant Developments                    Budget/Costs Incurred
All work has been completed and this CIP is in closeout.            6.6
6.4
Schedule
Millions 6.2
6
Dollars in 
The work is complete and the project is in closeout.
5.8
Budget                             5.6
5.4
The project forecast is within the approved budget and authorization.
Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
To C800404 (Aeronautical Allowance)          $323,000





AIRPORT
Port of Seattle 3Q 2013 Report  15

THIRD QUARTER REPORT, 2013
C4 UPS System Improvements
Project:   C800107    Project will replace existing          Status Snapshot Prior Report
Budget: $2,336,000   Uninterruptible Power Supply (UPS)    Delayed Schedule 1Q 09
Phase: Construction  System, including batteries, with a new  On Budget
Start: 06/28/2007      new system located in the Airport      0 Change Orders
Completion: TBD     Combined Communications and      Total Change Orders Amount:
Command Center (C4).           $0
Significant Developments                    Budget/Costs Incurred
Due to project deferral and the possibility of changes in site
2.5
conditions and building codes, the design phase changed from 100%
to 90% complete. Progressing with new Project Notebook to include     2
a revised address scope of work, schedule, and budget.            Millions 1.5
1
Schedule                            Dollars in 0.5
The project was reactivated. Staff is in the process of determining
0
the scope of work, schedule and final design budget.
Authorized  Forecasted Costs Incurred
Budget
The project budget is being evaluated based on delays and scope    Construction Costs
changes.                                    Not Applicable
Change Order                         Photo
None
Risks
The C4 center is a 24/7/365 operation and sequencing of this work is
critical and electrical power has to be maintained without
interruptions. It is not known when the construction will proceed as
this is specialized equipment and due to the complexity the new
system will require rigorous testing during the commissioning phase.
Budget Transfers
None this quarter


AIRPORT
16  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Runway 16C/34C Panel/Joint Sealant
Replacement
Status Snapshot
The scope of work will remove and   On Schedule
Project:   C800112      replace the pavement and joint seal  On Budget
in areas on Runway 16C-34C.
Budget: $3,461,623                         0 Change Orders
Phase: Construction                        Total Change Orders Amount:
Start: 02/26/2008                                 $0.00
Completion: 09/01/2012
Budget/Costs Incurred
Significant Developments
6
Gary Merlino Construction was the low bidder. The intent of the        5
contract was to coordinate this work with an apron panel             4
replacement project.                                   Millions
3
2
Schedule                            Dollars in  1
The 2013 replacement of runway panels is complete. Currently        0
there are no runway panels scheduled for replacement in 2014.          Authorized Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
No change orders were executed this quarter.
Photo
Risks
No risks have been identified at this time.
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 3Q 2013 Report  17

THIRD QUARTER REPORT, 2013
Gina Marie Lindsey (GML) Arrivals Hall
Concessions
This project will provide a new      Status Snapshot  Prior Report
Project:   C800148      retail-merchandising corridor in the  Delayed Schedule 1Q 11
Gina Marie Lindsey Arrivals Hall.    On Budget
Budget: $459,000
The project includes installing three   0 Change Orders
Phase: Design        Retail Merchandizing Units (RMUs)  Total Change Orders Amount:
Start: 11/20/2007         and providing utilities to a new      $0
Completion: TBD       approximate 25-seat restaurant
and bar.
Budget/Costs Incurred
Significant Developments                     1.2
1
Scope of this project is being deleted from the capital project and
0.8
redeveloped as a small works project to support minimal utilities for     Millions
0.6
the restaurant and bar. This will be the final quarterly report for this
0.4
project.                                                Dollars in 0.2
Schedule                             0
Authorized  Forecasted Costs Incurred
As previously reported, the project schedule delay was due to the
pending decision by the Business Development Group to proceed
with the concessionaire.                                Construction Costs
Not applicable
Budget
The project forecast is within the approved budget and authorization.  Photo
Change Order
None
Risks
Due to delay in schedule, bidding climate may change when the
project is bid and additional budget may be required.
Budget Transfers
To C800405 (Non-Aeronautical Allowance)          $574,000


AIRPORT

18  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
C60 - C61 BHS Modifications
Status Snapshot
Project:   C800168      The work planned under this      Delayed Schedule
Budget: $13,269,000     project represents a critical      On Budget
Phase: Design        component in providing improved   0 Change Orders
Start: 06/01/2012         operational baggage in-line       Total Change Orders Amount:
Completion: 10/31/2014   screening at the south end of the   $0
Airport and provide more baggage
make-up capacity for airlines.      Budget/Costs Incurred
14
12
Significant Developments
Millions 10
Design is 70% complete. TSA has removed funding from the project.    8
The project team revised the project scope to ensure Airport receives    6
4
needed baggage make-up capacity, computer replacements, and     Dollars in 
2
automatic tag readers replacement. Team is coordinating with the
0
Optimization project to reduce any redundant work. Plan to bid           Authorized  Forecasted Costs Incurred
project 4th quarter 2013.
Schedule                           Construction Costs
The project is currently delayed due to TSA funding issues and      Not Applicable
revised scope.
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
From C800404 (Aeronautical Allowance)        $2,300,000
Note: $1,404,176 will be returned to C800404 in forth quarter to
reflect current scope of work

AIRPORT
Port of Seattle 3Q 2013 Report  19

THIRD QUARTER REPORT, 2013
Federal Inspection Services - New Primary
Inspection Booths
This project will replace existing     Status Snapshot  Prior Report
Project:   C800174      primary inspection booths for      Delayed Schedule 4Q 12
Customs and Border Protection in   On Budget
Budget: $2,000,000
the International Arrivals Federal    0 Change Orders
Phase: Construction     Inspection Services (FIS) facility in  Total Change Orders Amount:
Start: 07/27/2010         the South Satellite.             $0
Completion: 09/08/2011
Budget/Costs Incurred
Significant Developments
New sign procurement underway to replace the defective signs.       2.5
2
Schedule                            Millions 1.5
The project is substantially complete. The current schedule for
1
completion of the replacement signs is now the 4th quarter of 2013.     Dollars in 0.5
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
None                                 Not Applicable
Risks
None identified at this time.                                Photo
Budget Transfers
None this quarter.




AIRPORT

20  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Security Exit Lane Breach Control - Phase 1
Project:   C800218      This project will procure and install   Status Snapshot Prior Report
Budget: $1,310,000      new automated exit lane breach    Delayed Schedule 2Q 13
Phase: Construction     control equipment at the       On Budget
Start: 3/1/2012          Concourse B exit.             0 Change Orders
Completion: 06/30/2013                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
1.5
The breach control equipment successfully passed testing by Airport
Security and TSA.
Millions  1
Schedule
0.5
The project construction by Port Construction Services was         Dollars in 
completed late due to additional commissioning of new equipment      0
needed in the field, as previously reported.                         Authorized  Forecasted Costs Incurred
Budget
Project forecast is within the approved budget and authorization.     Construction Costs
Not Applicable
Change Order
None
Risks
No major risks at this time.
Budget Transfers
From C800404 (Aeronautical Allowance)          $640,000



AIRPORT

Port of Seattle 3Q 2013 Report  21

THIRD QUARTER REPORT, 2013
Emergency Lighting - Parking
Project:   C800230      The purpose of this project is to
Budget: $1,157,081      provide electrical infrastructure for   Status Snapshot Prior Report
Phase: Design        a new source of emergency power  Delayed Schedule 4Q 12
Start: 07/24/2012         to feed the parking garage        On Budget
Completion: 07/31/2014   emergency lighting circuits and    0 Change Orders
ensure that code-required level of    Total Change Orders Amount:
egress illumination is provided for    $0
safety.
Budget/Costs Incurred
Significant Developments
5
The Service Directive with Casne for design was executed on
4
September 24, 2012. The Building Deptarment permit has been
issued. During final review a constructability issue was raised and     Millions 3
some redesign work was required. The anticipated IFB documents      2
are expected from the Consultant in September.                 Dollars in  1
0
The ESCO contract with McKinstry was delayed due to design
Authorized  Forecasted Costs Incurred
deficiencies. The Port worked closely with McKinstry to assist in
developing acceptable design documents. Construction Notice to
Proceed was issued on July 17. Construction has been going well.
Construction Costs
Schedule
1.5
The infrastructure portion of the contract has been delayed due to
constructablity issues that were caught after the 100% design was        1
complete. The design was going to require major shutdowns that      Millions
0.5
would significantly impact operations therefore redesign of portions
of the project is required.                                    Dollars in   0
Initial   Change   Spent
0.5          Orders
The ESCO contract was delayed due to design deficiencies,
however they are making it up in Construction.
Budget
The project forecast is within the approved budget. Authorization of
design and construction of emergency lighting through State ESCO
contract was approved by the Commission.
Change Order
None

22  Port of Seattle 3Q 2013 Report

Risks
The biggest challenge has been parked cars that are in the way.
Budget Transfers
To C800405 (Non-Aeronautical Allowance)  $586,230












AIRPORT

Port of Seattle 3Q 2013 Report  23

THIRD QUARTER REPORT, 2013
Feeder 101 Tap Replacements
Project:   C800234      Project Scope and description:     Status Snapshot
Budget: $500,000       The project includes replacing the   Delayed Schedule
Phase: Design        electrical feeds to 13 locations    On Budget
Start: 04/01/2013         along Air Cargo Road. Also, the    0 Change Orders
Completion: 10/31/2014   electrical transformer and       Total Change Orders Amount:
associated switchgear for Air Cargo  $0
#4 will be replaced.
Budget/Costs Incurred
Significant Developments                     3
The design is 60% complete.                            2.5
Millions  2
Schedule                            1.5
1
The project is currently on schedule. Design is anticipated to be      Dollars in 0.5
complete November 2013. Construction is scheduled from January
0
2014 to October 2014.                                   Authorized Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of   Construction Costs
construction funding and authority to advertise for construction will    Not Applicable
be requested when the bid documents are completed.
Change Order
None.
Risks
Unplanned electrical shut downs could impact the project schedule.
Budget Transfers
None.



AIRPORT
24  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Terminal Escalators Modernization

Project:   C800237      This project will replace 42        Status Snapshot
Budget: $30,610,979     escalators in the Main Terminal,    On Schedule
Phase: Close Out      Concourse B, and South Satellite.   On Budget
In addition, two new escalators will   130 Change Orders
Start: 11/02/2007
be installed at the South Satellite.    Total Change Orders Amount:
Completion: 07/01/2013                       $6,025,111
Significant Developments
Budget/Costs Incurred
Escalator installation is complete. Close out activities are continuing.
60
Schedule                             50
The project is in close out.                                  Millions 40
30
Budget                             20
Dollars in 
The project is within the approved budget and authorization.          10
0
Change Order                            Authorized Forecasted  Costs
Incurred
Construction contract completion letter issued. There are no further
change orders.
Construction Costs
Risks                                25
None identified at this time.                                 20
Millions 15
Budget Transfers
10
To C800404 (Aeronautical Allowance)          $5,000,000
Dollars in   5
Cost of Construction Growth                   0
Initial   Change Order   Spent
Circumstances contributing to cost growth: differing site conditions
encountered at the South Satellite during the installation of the two
new escalators resulted in revisions to the architectural and
structural designs, increased cost of construction, acceleration of
operationally critical units, and impacted the critical path of the
project circumstances contributing to cost growth. The project also
experienced cost increases due to state inspector imposed
requirement for a hard barrier between escalators during
construction.

AIRPORT
Port of Seattle 3Q 2013 Report  25

THIRD QUARTER REPORT, 2013
Central Plant Pre-Conditioned Air
Status Snapshot Prior Report
Delayed Schedule 1Q 13
Project:   C800238     This project will provide a centralized  On Budget
Budget: $47,235,000    pre-conditioned air (PC-Air) plant    170 Change Orders
Phase: Construction    (PCAP), associated heating and    Total Change Orders Amount:
Start: 06/15/2009       cooling piping systems, and jet bridge  $6,493,110
Completion: 08/31/2013  terminal air handling units to serve
airplanes with heating and cooling
while at the gates.               Budget/Costs Incurred
Significant Developments                     48
PC-Air is operating at 39 gates. Concourse A began operations in
47
July. Most of the gates at South Satellite and 1/2 of the gates at        Millions
Concourse B were added in August and September.              46
45
Schedule                            Dollars in 
The original contract completion date was December 11, 2012.        44
Authorized  Forecasted Costs Incurred
The delay is primarily due to Concourse D redesign, as previously
reported. Current completion to occur mid 4th Quarter 2013
contingent on scheduling gate shutdowns without impacting
operations.                                        Construction Costs
40
Budget
Negotiations with the contractor on potential change orders and         30
claims risk are in process. As negotiations proceed, potential budget    Millions
20
issues will be identified. Current project forecast including open
claims exceeds approved budget and authorization by approximately    Dollars in   10
32%. Staff will return to Commission to request additional funding
0
and authorization to execute change orders.
Initial   Change   Spent
Orders
Change Order
Nine change orders issued this quarter. The change orders were
issued for piping and electrical site conflicts on the concourse and at
the gates.
Risks
There is budget risk based on the dollar amount of open potential
change orders and claims. There is schedule risk as completing work
at each gate is contingent on gates being available.
Budget Transfers
To C800404 (Aeronautical Allowance)          $600,000
26  Port of Seattle 3Q 2013 Report

Cost of Construction Growth
Cost growth is still occuring due to shortcomings in the bid documents. Current cost of executed
Change Orders is 26% of the base contract price. The trended cost growth projection is currently 32%
over bid price. Approximately 20% are related to error and/or ommissions (owner or designer), 7%
are currently in some form of dispute. The remainder of the cost growth are due to site conditions,
discretionary tenant requests or scope changes and regulatory requirements respectively. The
current projections do not include any cost trending for potential claims due to late project completion
due to owner caused delay.











AIRPORT
Port of Seattle 3Q 2013 Report  27

THIRD QUARTER REPORT, 2013
Cargo 2 West Cargo Hardstand
Project:   C800247      This project will enlarge the       Status Snapshot Prior Report
Budget: $11,830,000     western cargo hardstand in the    Delayed Schedule 3Q 12
Phase: Design        Cargo 2 area, it includes buyout of  On Budget
Start: 09/25/2012         two cargo buildings and tenant     0 Change Orders
Completion: 12/31/2014   relocations; relocation of FAA     Total Change Orders Amount:
antenna, security gate, and guard    $0
shack; and installation of 400Hz inground
power.              Budget/Costs Incurred
15
Significant Developments
Cargo 2 will be combined with Cargos 5 and 6 as a single
10
construction contract. FAA antenna relocation agreement was        Millions
completed.
5
Dollars in 
Schedule
0
100% Design has been completed. Building acquisition,              Authorized Forecasted Costs Incurred
Commission Authorization for Construction, Contract Bid and Award
will be completed in the 4th quarter of 2013. Demolition of Building
#2 is scheduled for the 1st quarter of 2014 with hardstand completion  Construction Costs
scheduled for the 2nd quarter of 2014. The current schedule reflects   Not Applicable
the combining of Cargo 2, 5, and 6 projects.
Photo
Budget
The project forecast is within approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None.

AIRPORT
28  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Vertical Conveyance Modernization Program -
Aeronautical - Phase I                   Status Snapshot
Perform modernization on 7       Delayed Schedule
Project:   C800251      existing elevators: SSAF, MT-2,    On Budget
MT-3, MT-4, MT-5, MT-6, MT-7,    0 Change Orders
Budget: $13,502,211
plus install cooling packages on 12   Total Change Orders Amount:
Phase: Design        existing hydraulic elevators      $0
Start: 10/25/2011         throughout Main Terminal and 4
Completion: 06/30/2016   escalators at skybridge 6.
Significant Developments                    Budget/Costs Incurred
Changing priorities concerning failure of existing Main Terminal
15
elevators has prompted further review of project scopes, and the
consolidation of all Main Terminal elevators to Phase I, and two new
10
South Satellite elevators to Phase II. Also added to the scope was
the design of one additional hydraulic oil cooling package for         in Millions
5
Elevator Q; this elevator is experiencing overheating time-outs to       Dollars 
serve United Airlines' club associated with airline relocation to
0
Concourse A.
Authorized  Forecasted Costs Incurred
Schedule
The construction is scheduled to begin in the 2nd Quarter of 2014,    Construction Costs
with construction completion in the 2nd Quarter of 2016.           Not Applicable
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
None
Risks
Final determination of scope and priorities could cause delays.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 3Q 2013 Report  29

THIRD QUARTER REPORT, 2013
Parking System Replacement
Status Snapshot Prior Report
Delayed Schedule 2Q 12
Project:   C800253      This project replaces the current    On Budget
Budget: $6,076,999.30    Parking Revenue Control System,   9 Change Orders
Phase: Construction     which manages parking access    Total Change Orders Amount:
Start: 04/06/2010         and revenue collection in the      $195,780
Completion: 08/31/2012   Airport's Main Parking Garage.
Budget/Costs Incurred
12
Significant Developments
10
Scheidt & Bachmann (S&B), the system vendor, experienced several
8
reporting and system issues, corrected them and began final testing.    Millions
6
The vendor's software has experienced a number of failures, leading
4
to reporting and operational issues. The Port has hired a Systems     Dollars in  2
Software Auditor to analyze the system.
0
Authorized  Forecasted Costs Incurred
Schedule
The system is substantially complete. However, repeated service
outages of the vendor's system have led to delays in system        Construction Costs
commissioning.                                  None this quarter
Budget                            Photo
The project forecast is within the approved budget and authorization.
Change Order
No new change orders occurred during the reporting period.
Risks
The Port is actively engaging the Contractor at the executive level to
address system issues.
Budget Transfers
None this quarter.


AIRPORT

30  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Aircraft RON Parking USPS Site
Status Snapshot Prior Report
Delayed Schedule     1Q 11
Project: C800254        This project will prepare the site for
On Budget
Budget: $46,040,000     the construction of hardstands for
4 Change Orders
Phase: Design        use as Remain Overnight (RON)
Total Change Orders Amount:
Start: 08/26/2008        parking of aircraft at the Cargo 5
-$150,211
area.
Completion: 12/31/2014
Significant Developments                    Budget/Costs Incurred
Demolition of the USPS building is complete and the project is        50
closed out. With the design authorization of Cargo 2 and 6
40
approved by the Commission on September 25, 2012, they will be
added to Cargo 5 to produce a single construction contract with 3      Millions 30
cargo areas.                                        20
Dollars in  10
Schedule
0
100% Design has been completed. Final Design, Commission          Authorized Forecasted Costs Incurred
Authorization for Construction, Contract Bid and Award will be
completed in the 4th quarter of 2013. Construction is scheduled to
begin the 1st quarter of 2014. Cargo 5 is scheduled to be completed  Construction Costs
by the end of the 3rd quarter of 2014.                       Not Applicable
Budget                           Photo
The project forecast is within the approved budget.
Change Order
None this quarter.
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT
Port of Seattle 3Q 2013 Report  31

THIRD QUARTER REPORT, 2013
Port-Owned Loading Bridge Renewal &       Status Snapshot
Replacement                     On Schedule
On Budget
0 Change Orders
Project:   C800267      This project will allow the Airport to
replace or refurbish Port-owned     Total Change Orders Amount:
Budget: $2,405,000
Passenger Loading Bridges (PLBs)  $0
Phase: Design        that have reached the end of their
Start: 02/28/2012         service life.
Completion: 12/31/2014
Budget/Costs Incurred
Significant Developments                      3
The PLB and fixed walkway removal and replacement at S3 was      2.5
completed in February 2013. The S12 PLB and fixed walkway       Millions 2
refurbishment work was completed and the bridge returned to         1.5
service as scheduled on October 9, 2013. The design for the S4       1
Dollars in 
refurbishment is currently on hold due to potential conflicts with the      0.5
upgrades planned for the new International Arrivals Facility.           0
Authorized  Forecasted Costs Incurred
Schedule
The remainder of work programmed for this project is currently on
hold.                                              Construction Costs
0.8
Budget
0.6
The project forecast is within the approved budget and authorization.
Millions  0.4
Change Order                           0.2
None                                  Dollars in   0
Initial   Change   Spent
0.2          Orders
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
32  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Stage 2 Mechanical Energy Implementation
Project:   C800268      This project will improve the energy  Status Snapshot
Budget: $2,872,900.00    performance of the mechanical    Delayed Schedule
Phase: Construction     infrastructure systems at the     On Budget
Start: 10/01/2011         Airport.                    0 Change Order
Completion: 10/31/2013                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
3
Additional costs are being incurred due to broken valves in Central
2.5
Plant which slowed schedule and had cost impact. Evaluating cost
2
of adding scope deleted from South Mezzanine terminals and North    Millions
1.5
Bridge Level.
1
Dollars in 
Schedule                             0.5
0
Major construction is now anticipated to be complete in October          Authorized  Forecasted Costs Incurred
2013. The schedule delays were due to the broken valves and the
addition of ten terminal units to the sope
Construction Costs
Budget
The forecast is within the approved budget and authorization.           3
2.5
Change Order                          Millions 2
None                                   1.5
1
Risks                                Dollars in  0.5
None identified at this time.                                    0
Initial   Change   Spent
Orders
Budget Transfers
None



AIRPORT
Port of Seattle 3Q 2013 Report  33

THIRD QUARTER REPORT, 2013
8th Floor Weatherproofing
Status Snapshot
Delayed Schedule
Project:   C800274      This project includes removal and   On Budget
Budget: $9,474,000      replacement of the floor covering   14 Change Orders
Phase: Construction     system on the eighth floor of the   Total Change Orders Amount:
Start: 03/23/2010         STIA parking garage and repair or   $65,182
Completion: 07/31/2014   replacement of expansion joints
and flashings.
Budget/Costs Incurred
Significant Developments                     15
The Port's contractor, PCL Construction, stripped and replaced old
weatherproofing, and performed crack repair on sections A and B of    Millions 10
the eighth floor garage deck. Expansion joints throughout those
sections were also replaced. Weatherproofing failed in portions of       5
sections B and C. The work was rejected and will be repaired June    Dollars in 
2014 at contractor's expense.                              0
Authorized  Forecasted Costs Incurred
Schedule
Defective work has resulted in a delay of beneficial occupancy. The
new end date is expected to be July 31, 2014                 Construction Costs
8
Budget
The project forecast is within the approved budget and authorization.     6
Millions
4
Dollars in 
Change Order
2
Executed four change orders this quarter.
0
Risks                                   Initial Change Order Spent
This is a weather-dependent project.
Budget Transfers                        Photo
To C800405 (Non-Aeronautical Allowance)        $576,000


AIRPORT

34  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Common Use Equipment Expansion (CUSE)
Project:   C800276      This project installs flexible       Status Snapshot
Budget: $1,461,000      passenger processing         On Schedule
Phase: Close Out      infrastructure and equipment at the  On Budget
Start: 09/01/2009         airline gates at some South       25 Change Orders
Completion: 09/30/2012   Satellite gates.            Total Change Orders Amount:
-$11.926
Budget/Costs Incurred
Significant Developments
3
Project close out is nearing completion.
2.5
Millions    2
Schedule
Dollars in     1.5
The project is in close out.
1
Budget                             0.5
0
The project forecast is within the approved budget and authorization.        Authorized    Forecasted   Costs Incurred
Change Order
None                                 Construction Costs
Risks                                 0.7
0.6
None identified at this time
Millions    0.5
0.4
Budget Transfers                         Dollars in  0.3
0.2
To C800404 (Aeronautical Allowance)          $1,120,000       0.1
0
Initial        Change Orders        Spent
0.1




AIRPORT

Port of Seattle 3Q 2013 Report  35

THIRD QUARTER REPORT, 2013
Long-Term Cell Phone Lot
Project:   C800324      Construct a new cell phone waiting  Status Snapshot Prior Report
Budget: $2,521,000      lot to replace the existing lot that is  Delayed Schedule 1Q 13
Phase: Design        being displaced, and construct a   On Budget
Start: 12/11/2012         traffic control roundabout adjacent   0 Change Orders
Completion: 12/31/2014   to the lot on South 170th Street.    Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
3
Design of the cell phone lot was completed to the 90% level. The
2.5
traffic engineering analysis and 30% design of the roundabout was
completed. Working collaboratively with project sponsor, Port       Millions 2
1.5
Construction Services, Air Cargo 5 Team and Engineering to
1
develop plan to construct Lot and be operational before existing Cell    Dollars in 0.5
Lot is demolished due to construction.
0
Authorized  Forecasted Costs Incurred
Schedule
The cell phone lot is planned to be constructed ahead of the
roundabout, which is expected to require a longer time for design     Construction Costs
and permit acquisition. Cell phone lot design planned to be        Not Applicable
completed in the 4th quarter of 2013 followed by construction in 4th
quarter 2013 and 1st quarter 2014. Roundabout construction will     Photo
start in the 3rd quarter of 2014 with completion in the 4th quarter of
2014.
Budget
The project forecast is within the approved budget. Commission
Authorization for construction funding and authority to advertise for
construction will be requested when the bid documents are
completed.
Change Order
None
Budget Transfers
From C800405 (Non-Aeronautical Allowance)      $753,000


36  Port of Seattle 3Q 2013 Report

Risks
Schedule uncertainties related to roundabout design review and permit acquisition time requirement.
There is potential wet/winter construction-related delay to cell phone lot construction that could result
in no cell phone lot for up to a few weeks.













AIRPORT
Port of Seattle 3Q 2013 Report  37

THIRD QUARTER REPORT, 2013
Two New CTE Freight Elevators
Status Snapshot Prior Report
Delayed Schedule 2Q 12
Project:   C800334      Provide two new freight elevators   On Budget
Budget: $8,318,000      to support concession operations in  5 Change Orders
Phase: Construction     the Central Terminal/Pacific      Total Change Orders Amount:
Start: 08/05/2011         Marketplace.                $49,535
Completion: 07/31/2014
Budget/Costs Incurred
Significant Developments
The contract was awarded in April to Pease Construction. Notice To     10
Proceed was issued in June. The contractor commenced sawcutting     8
concrete pavement for North Freight elevator pit & installation of new    Millions 6
grease Interceptor.
4
Schedule                            Dollars in  2
As previously reported, the project is anticipating a one-year delay       0
Authorized  Forecasted Costs Incurred
due to scope changes included in the redesign efforts, and delays in
reviews.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.
5
4
Change Order
Millions   3
Executed four (4) change orders this quarter.
2
Risks                                Dollars in   1
No new risks identified this quarter.                              0
Initial   Change   Spent
Orders
Budget Transfers
None this quarter


AIRPORT

38  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Electrical Ground Support Equipment (EGSE)
Electrical Charge Stations                Status Snapshot Prior Report
Delayed Schedule 1Q 13
On Budget
Airport-wide electrical charging     25 Change Orders
Project:   C800335      system for electrical ground       Total Change Orders Amount:
Budget: $30,198,000     support equipment (EGSE) at the   $103,135
Phase: Design        Concourses and the North and
Start: 10/26/2010         South Satellites.
Completion: 12/31/2015
Significant Developments                    Budget/Costs Incurred
Received Beneficial Occupancy for installation of 40 demonstration
charge stations on Concourse C2 for Horizon Airlines. Phase 1        35
includes balance of charge stations at Concourse C, D and North       30
Satellite. Contractor has issued partial Beneficial Occupancy for        25   Millions
20
charge corrals at Concourse C, D and at North Satellite. Beneficial    Dollars in   15
Occupancies are scheduled to be issued by September 30, 2013.
10
5
The consultant is scheduled to issue GSE Charger Phase 2 Project      0
Authorized       Forecasted      Costs Incurred
100% bid design documents for review that includes Concourse A, B
and South Satellite. Working to secure FAA VALE grant and for
Washington Sales Tax exemption for the GSE Charger Phase 2
Project.                                             Construction Costs
Schedule                             4
Phase 1 construction is scheduled for completion on September 30,     3
2013; Phase 2 construction scheduled for completion in late 2015.     Millions
2
Budget                             Dollars in  1
The project forecast is within the approved budget. The remaining
0
authorization for the construction funding and authority to advertise          Initial  Change Order  Spent
for construction will be requested when the design and bid
documents are completed for GSE Charger Phase 2 Project.
Change Order
Twenty-five change orders issued.


Port of Seattle 3Q 2013 Report  39

Risks
Coordinate with other airfield projects and Airline Gate Realignment program. Budget and schedule
may affect project implementation and completion.
Budget Transfers
None this quarter.












AIRPORT
40  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Claim Device 14 & Lower Inbound
Status Snapshot Prior Report
Delayed Schedule 4Q 12
Project:   C800374      This project will replace the slope-   On Budget
Budget: $1,897,000      plate bag claim device 14 and     23 Change Orders
Phase: Close Out      associated controls, in addition to   Total Change Orders Amount:
Start: 04/01/2011         removing the lower feed conveyor   $129,002
Completion: 3/31/2013    and replacing it with a new
overhead feed.              Budget/Costs Incurred
5
4
Significant Developments
Millions  3
The project is currently in close-out.
Dollars in 
2
Schedule                             1
As previously reported, the project was delayed due to Hurricane       0
Sandy. Equipment was on the dock at the Port of New York the day       Authorized  Forecasted Costs Incurred
of the hurricane. The Port worked with the contractor to come up
with a recovery schedule. The construction was completed in March.
Construction Costs
Budget
1.2
The project forecast is within the approved budget and authorization.
1
Change Order                          Millions 0.8
0.6
None
0.4
Dollars in   0.2
Risks
0
None identified at this time.                                      Initial  Change  Spent
Orders
Budget Transfers
To C800404 (Aeronautical Allowance)          $1,003,000



AIRPORT

Port of Seattle 3Q 2013 Report  41

THIRD QUARTER REPORT, 2013
Vertical Conveyance Modernization Aero Ph 2
Status Snapshot
Delayed Schedule
Project:   C800375      Perorm modernization of 2       On Budget
Budget: $8,834,408      elevators: SSB and SSC, construct  0 Change Orders
Phase: Design        2 new elevators at South Satellite.  Total Change Orders Amount:
Start: 12/11/2012                                 $0
Completion: 12/31/2016
Budget/Costs Incurred
10
9
Significant Developments                      8
Millions    7
Dollars in 
Final siting of new elevators will require relocation of 20 electrical        6
5
conduits, including main electrical feeders to South Satellite.           4
Developing electrical power relocation scope.                    3
2
1
Schedule                             0
Authorized       Forecasted      Costs Incurred
Construction is scheduled to begin in 3rd Quarter 2014 with
construction completion in 4th Quarter 2016.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
None
Risks
Relocation of existing main electrical power to South Satelitte.
Budget Transfers
None this quarter.



AIRPORT
42  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
South Satellite HVAC, Lights, and Ceiling
Status Snapshot
Replacement                     On Schedule
This project will replace the Heating  On Budget
Project:   C800376      Ventilation, lighting and ceiling     0 Change Orders
systems in the South Satellite.      Total Change Orders Amount:
Budget: $6,500,000
$0
Phase: Design
Start: 7/24/2012
Completion: 07/31/2016                       Budget/Costs Incurred
40
Significant Developments
30
Thirty percent design was delayed pending the finalization of         Millions
mechanical equipment room locations and review of seismic          20
requirements. Design is scheduled to resume in the 4th quarter of
2013. Staff is amending project scope to include improvements to     Dollars in  10
FIS area.
0
Authorized  Forecasted Costs Incurred
Schedule
Project design schedule is contingent on where the mechanical
equipment rooms will be located and potential seismic upgrades.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
None
Risks
South Satellite siesmic analysis and strategy may impact project
costs and schedule. Seismic upgrade is not currently in the design
scope of work.
Budget Transfers
None this quarter

AIRPORT

Port of Seattle 3Q 2013 Report  43

THIRD QUARTER REPORT, 2013
Baggage Handling System (C22-C1, MK1, and
Status Snapshot
TC3)                          On Schedule
This project will replace the ticket    On Budget
Project:   C800382      counter (TC3) conveyors and      42 Change Orders
declines, reroute the conveyors of   Total Change Orders Amount:
Budget: $5,861,000
the C-22 system and connect it to    $181,179
Phase: Close Out      the C-1 screening system, replace
Start: 03/01/2011         the existing makeup (MK1) device,  Budget/Costs Incurred
Completion: 05/31/2013   and install a new odd size baggage
8
system.
6
Millions
4
Dollars in 
Significant Developments
The project is currently in close-out.                            2
0
Schedule                              Authorized Forecasted  Costs
Incurred
The project is currently on schedule.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.
2
Change Order                           1.5
There are currently 42 change orders executed on this contract.       Millions
1
Risks                                Dollars in  0.5
None identified at this time.                                    0
Initial   Change   Spent
Orders
Budget Transfers
To C800404 (Aeronautical Allowance)          $900,000
Cost of Construction Growth
Three changes represent the majority of the cost growth: 1) Since
POS no longer required replacement of the existing C1-CS1
curbside conveyor, it was removed rather than replaced;




44  Port of Seattle 3Q 2013 Report

Cost of Construction Growth (Cont.)
2) The contract design to replace make-up device MK1 did not include POS ergonomic standards for
this kind of device; and 3) the original contact design for the conveyors in the C1-CS2 conveyor line
created unsafe electrical and mechanical conditions for maintenance works. Several other smaller
changes include fire sprinkler and architectural revisions, including a credit to remove a small scope
of work.












AIRPORT
Port of Seattle 3Q 2013 Report  45

THIRD QUARTER REPORT, 2013
Cargo 6 Enhancements
Project:   C800390      This project will enlarge the Cargo   Status Snapshot Prior Report
Budget: $6,428,000      6 off-gate hardstand to allow     Delayed Schedule 4Q 12
Phase: Design        simultaneous nose-loading of wide-  On Budget
Start: 09/25/2012         body freight aircraft as well as      0 Change Orders
Completion: 12/31/2014   provide fuel hydrant and ground    Total Change Orders Amount:
power capabilities.              $0
Budget/Costs Incurred
Significant Developments
8
Cargo 6 will be combined with Cargo 2 and 5 as a single
construction contract.                                     6
Millions
4
Schedule
100% Design has been completed. Final Design, Commission       Dollars in  2
Authorization for Construction, Contract Bid and Award will be
0
completed in the 4th quarter of 2013. Construction is scheduled to         Authorized  Forecasted Costs Incurred
begin late summer of 2014 and cannot be started until Cargo 2
Hardstand is completed. Completion of the Cargo 6 hardstand
enhancements will be completed in 4th quarter of 2014. The current   Construction Costs
schedule reflects the combining of Cargo 2, 5, and 6 projects.       Not Applicable
Budget                            Photo
The project forecast is within the approved budget and authorization.
Change Order
None this quarter
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

46  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
RW16C/34C Reconstruction Design
Status Snapshot
On Schedule
Project:   C800406      This project will produce the 60%   On Budget
Budget: $669,000       design for the runway 16C/34C    0 Change Orders
Phase: Design        reconstruction. The design will    Total Change Orders Amount:
Start: 05/04/2010         include utilities, runway status      $0
Completion: TBD       lights, and other scope items
related to the project.            Budget/Costs Incurred
Significant Developments                     0.8
The decision has been made to advance the reconstruction of        0.6
Runway 16C/34C by one year to 2015.                     Millions
0.4
Schedule                            Dollars in 0.2
Staff will return to Commission for authorization of the remaining
0
design funds in the 1st quarter of 2014. The construction is              Authorized  Forecasted Costs Incurred
scheduled to begin in the 2nd quarter 2015.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 3Q 2013 Report  47

THIRD QUARTER REPORT, 2013
South Satellite Concessions Project
Status Snapshot
Delayed Schedule
Project:   C800412      This project will demolish and      On Budget
Budget: $2,227,400      relocate the existing duty free shop,  0 Change Orders
Phase: Construction     electric/communications to support  Total Change Orders Amount:
Start: 01/01/2011         a temporary duty free location, and   $0
Completion: 12/31/2013   construct a new food and beverage
shell space in the South Satellite at
Sea-Tac Airport.
Budget/Costs Incurred
Significant Developments                      2
The new duty free opened for business in July 2013. The existing      1.5
duty free shop has been demolished and the new food and beverage   Millions
1
shell space construction is underway.
Dollars in 0.5
Schedule
0
The contractor will complete all work associated with this project in         Authorized  Forecasted Costs Incurred
early November. The delay is partially a result of the late start for the
second phase of this project caused by the tenant build out of the
new duty free shop.                                  Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None at this time.
Budget Transfers
None


AIRPORT

48  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Access Control Door Additions
Status Snapshot Prior Report
Delayed Schedule 3Q 12
Project:   C800414      This project will provide biometric   On Budget
Budget: $1,480,000      access controls and security     4 Change Orders
Phase: Construction     cameras at airport terminal doors.   Total Change Orders Amount:
Start: 09/27/2011                                 $23,123
Completion: 08/30/2013
Budget/Costs Incurred
1.6
Significant Developments
1.5
Substantial completion was reached this quarter.                 Millions 1.4  Dollars in 
Schedule
1.3
Construction was completed in August.
1.2
Authorized  Forecasted Costs Incurred
Budget
Project forecast is within the approved budget and authorization.
Construction Costs
Change Order
0.6
None this quarter.
0.5
Risks                                Millions 0.4
0.3
Dollars in 
None identified at this time
0.2
0.1
Budget Transfers
0
None this quarter.                                          Initial  Change  Spent
Orders




AIRPORT
Port of Seattle 3Q 2013 Report  49

THIRD QUARTER REPORT, 2013
Airfield Lighting Control and Monitoring System
Status Snapshot
(ALCMS) Upgrades                  On Schedule
Provide modifications to the Airfield   On Budget
Project:   C800415      Lighting Control and Monitoring    1 Change Orders
System to update, enhance and    Total Change Orders Amount:
Budget: $1,682,144
stabilize the system to meet the     $17,989
Phase: Construction     latest FAA specifications.
Start: 01/01/2011                                Budget/Costs Incurred
Completion: 12/31/2014
2.5
2
Significant Developments                     Millions 1.5
Liberty Airport Systems was operational on July 12, 2013. Training      1
of Port and FAA staff was conducted. O&M manuals are under
Dollars in 0.5
review.
0
Authorized  Forecasted    Costs
Schedule                                       Incurred
The project is currently on schedule.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None this quarter
Risks
Coordination with on-going airfield operations is a consideration.
The Port worked to eliminate unplanned outages when transitioning
from the older computer platform to the new one.
Budget Transfers
From C800404 (Aeronautical Allowance)          $300,000



AIRPORT
50  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Lagoon 3 Bird Wires
Status Snapshot
On Schedule
Project:   C800417      This project will reduce access by   On Budget
Budget: $1,563,000      waterfowl to the industrial       15 Change Orders
Phase: Construction     wastewater system Lagoon 3,     Total Change Orders Amount:
Start: 10/11/2011         which is located near the south end  $135,824
Completion: 10/31/2012   of the airfield.
Budget/Costs Incurred
2
Significant Developments
1.5
Nordic Construction was the low bidder. The contractor began work    Millions
1
in July 2012.
Dollars in 0.5
Schedule
0
The major construction work is complete. Some minor work to           Authorized Forecasted Costs Incurred
correct chaffing remains. One-year warranty period will end in
November 2013.
Construction Costs
Budget
The project forecast is within the approved budget and authorization.      1
0.8
Change Order                          Millions 0.6
Dollars in 
Five change orders were executed this quarter.                   0.4
0.2
Risks
0
No risks have been identified at this time.                            Initial  Change  Spent
Orders
Budget Transfers
Photo
None this quarter.
Cost of Construction Growth
The contractor was compensated for additional costs for revisions to
access gate framing and ramp posts. This change order was the
result of a design error or omission.


AIRPORT
Port of Seattle 3Q 2013 Report  51

THIRD QUARTER REPORT, 2013
Federal Inspection Services Short Term
Status Snapshot Prior Report
Improvements                    Delayed Schedule 1Q 13
Short Term Improvements to the    On Budget
Project:   C800426      Federal Inspection Service area at   0 Change Orders
the South Satellite to improve      Total Change Orders Amount:
Budget: $1,041,000
through put and improve conditions  $0
Phase: Design        for passengers waiting in the
Start: 04/01/2012         International Corridor prior to
Completion: 2/28/2014    Primary Inspection.
Budget/Costs Incurred
Significant Developments                     1.2
1
Project scope was further streamlined after the 60% estimate review
to include only essential additional necessary construction elements    Millions 0.8
0.6
identified during 60% design review. 90% design documents are in
0.4
progress including this updated scope.                       Dollars in 0.2
Schedule                             0
Authorized  Forecasted Costs Incurred
Added scope identified during the 60% design phase will delay
completion of this project.
Construction Costs
Budget
Not Applicable
The project team received additional funding for new scope. The
budget forecast is now trending within the approved budget. Project
sponsors will review an updated estimate at 90% with new scope
and confirm project is still within budget.
Change Order
None
Risks
Although some new scope has been cut, the project estimate at 90%
design may still trend over budget..
Budget Transfers
None this quarter


AIRPORT
52  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Doug Fox Lot Service Upgrades
Status Snapshot Prior Report
Delayed Schedule 1Q 13
Project:   C800451      Construct a new drainage system,   Forecast Overrun
Budget: $5,068,000      asphalt resurfacing, improved lot   0 Change Orders
Phase: Design        lighting, new building, and road    Total Change Orders Amount:
Start: 02/01/2012         signage to improve lot appearance,  $0
Completion: 09/30/2014   function, and revenue generation.
Budget/Costs Incurred
7
6
Significant Developments                      5
Construction bids were opened on September 5 and the low bid        4  Millions
exceeded the engineer's estimate by more than 10%. This bid         3
irregularity will require further Commission action.                 Dollars in  2
1
0
Schedule
Authorized  Forecasted Costs Incurred
Project schedule will be delayed to resolve the bid irregularity.
Construction is expected to start in mid-December 2013.
Construction Costs
Budget                            Not Applicable
The bid irregularity is expected to require a budget increase. The
amount of the increase is to be determined.                   Photo
Change Order
None
Risks
Wet/winter construction could cause additional delays to completion
date of September 30, 2014.
Budget Transfers
To C800405 (Non-Aeronautical Allowance)     $1,005,000



AIRPORT

Port of Seattle 3Q 2013 Report  53

THIRD QUARTER REPORT, 2013
Concourse D Common Use Environment
Status Snapshot Prior Report
Delayed Schedule 3Q 11
Project:   C800455      This project installs a common-use  On Budget
Budget: $4,100,000      environment at all gates on      14 Change Orders
Phase: Close Out      Concourse D. Scope includes new  Total Change Orders Amount:
Start: 03/01/2011         communications infrastructure,     $111,155
Completion: 04/30/2013   casework built to a new Airport
standard, new carpet, wall        Budget/Costs Incurred
coverings and task lighting.
5
4
Significant Developments
Millions  3
Casework modifications are complete. Project is in close out.
2
Schedule                            Dollars in  1
Contractor completed non-essential project work prior to contract        0
end date of August 2013.                                  Authorized Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Change Order                           1.5
None
Millions   1
Risks
0.5
None.                                      Dollars in 
0
Budget Transfers                             Initial Change Spent
Orders
To C800404 (Aeronautical Allowance)          $150,000



AIRPORT

54  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
2011-2013 Roof Replacement Program
Status Snapshot
On Schedule
Project:   C800459      This project will remove and      On Budget
Budget: $4,777,000      replace the roofing systems on the  0 Change Orders
Phase: Construction     fire station and north end of the    Total Change Orders Amount:
Start: 07/01/2011         main terminal.                $0
Completion: 10/31/2013
Budget/Costs Incurred
5
Significant Developments
4
Bids were opened on March 26, 2013 and Notice of Intent to Award
was issued.                                       Millions 3
2
Schedule                            Dollars in  1
The project is currently on schedule.                           0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
2
None
1.5
Risks                                Millions
1
Contractor began work late in the season. The contractor did not
anticipate the weather conditions and is working to meet the          Dollars in  0.5
completion deadline.
0
Initial   Change   Spent
Budget Transfers                                Orders
None this quarter.




AIRPORT
Port of Seattle 3Q 2013 Report  55

THIRD QUARTER REPORT, 2013
Industrial Waste Treatment Plant (IWTP) Fiber
Status Snapshot Prior Report
Installation                             Delayed Schedule 1Q 13
Install new Single Mode Fiber cable  Forecast Overrun  1Q 13
Project:   C800461      from Main Terminal to IWTP and    0 Change Orders
Gate E-45.                 Total Change Orders Amount:
Budget: $514,000
$0
Phase: Design
Start: 03/01/2012                                Budget/Costs Incurred
Completion: 10/31/2013
0.6
Significant Developments                     0.5
The Fiber Optic Cable has been installed from Main Terminal to the     Millions 0.4
new equipment termination cabinet near the Alaska Hangar and       0.3
Gate E-45. Selected new routing for conduits for remaining portion     0.2
of the route since co-use of existing conduits from E-45 to the IWTP    Dollars in 0.1
with FAA fiber optic cable is not permitted. Completed final design       0
for submission to FAA.                                     Authorized Forecasted Costs Incurred
Schedule
Schedule delay of approximately three months due to need to       Construction Costs
reroute conduits, which was previously reported.                Not Applicable
Budget
The project may require additional budget and authorization. When
the design for the revised route is completed, revised scope and
costs will be developed.
Change Order
None
Risks
Underground boring for new conduits beneath Taxiway "B".
Budget Transfers
None this quarter.


AIRPORT

56  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Fiber Infrastructure to Gate Backstands
Project:   C800464      This project extends airport       Status Snapshot
Budget: $3,284,000      provided communications       On Schedule
Phase: Design        infrastructure and wifi antennas to   On Budget
Start: 07/09/2013         additional gates on Concourses A,   0 Change Orders
Completion: 04/01/2015   B and C.                Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Design has been authorized by the Commission. Negotiation of
design fees is underway.                                 4
Schedule                             3
Millions
Design fee negotiations are taking longer than anticipated. Project      2
schedule will be updated at the completion of negotiations to
1
determine if lost time can be made up during design.              Dollars in 
0
Budget                               Authorized Forecasted Costs Incurred
Project is currently forcasted to complete with the current budget.
Change Order                         Construction Costs
None at this time.                                     Not Applicable
Risks
The project may be delayed if fee negotiations break down with the
current IDIQ design team and negotiations have to begin anew with
a different IDIQ design team.
Budget Transfers
None.



AIRPORT
Port of Seattle 3Q 2013 Report  57

THIRD QUARTER REPORT, 2013
South Satellite - Additional Gate Lobby
Status Snapshot Prior Report
Delayed Schedule 3Q 12
Project:   C800466      Demolition of glass partitions,      On Budget
Budget: $1,515,000      restrooms, relocation of gate     14 Change Orders
Phase: Design        podiums new flooring, ceilings and  Total Change Orders Amount:
Start: 11/01/2010         infrastucture to provide additional    $141,934
Completion: 09/15/2013   gate lobby in the South Satellite.
Significant Developments                    Budget/Costs Incurred
The shared waiting area is scheduled to open to the public on
October 2, 2013.
2.5
Schedule                             2
As previously reported, the project delay was caused by delayed      Millions 1.5
design negotiations and contracting. Additionally, a longer design       1
period is required due to dependency on the South Satellite          Dollars in 0.5
Concessions Project (C800412).
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
None                                    2
1.5
Risks
None this quarter.                                        1
Millions
Budget Transfers                          Dollars in  0.5
0
None this quarter.
Initial   Change   Spent
Orders



AIRPORT

58  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Passenger Loading Bridge Replacement -
Status Snapshot
Airline Realignment                    On Schedule
This project entails Passenger      On Budget
Project:   C800467      Loading Bridge (PLB)          31 Change Orders
replacements associated with the    Total Change Orders Amount:
Budget: $7,847,539
one-time airline realignment (AR).    $168,886
Phase: Construction     The work will take place at
Start: 04/12/2011         Concourse D and Concourse B.
Completion: 09/30/2013
Budget/Costs Incurred
Significant Developments
10
The PLB replacement, refurbishment and relocation work at both
Concourse D and B has been completed. PLB work at North         8
Satellite will now take place under the NorthSTAR project.           Millions 6
4
Schedule                            Dollars in  2
The project has been completed and is in closeout.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
None                                   2.5
2
Risks                                Millions 1.5
None identified at this time.
1
Budget Transfers                          Dollars in  0.5
0
To C800404 (Aeronautical Allowance)          $6,631,000
Initial   Change   Spent
Orders



AIRPORT

Port of Seattle 3Q 2013 Report  59

THIRD QUARTER REPORT, 2013
CUSE at Gates & Ticket Counters- Airline
Realignment
Provide common use equipment,    Status Snapshot Prior Report
Project:   C800473      casework and infrastructure at     Delayed Schedule 3Q 12
gates and ticket counters for the     On Budget
Budget: $1,293,000
Airline Realignment program.      0 Change Orders
Phase: Close Out                          Total Change Orders Amount:
Start: 04/02/2012                                 $0
Completion: 05/01/2013
Budget/Costs Incurred
Significant Developments                     2.5
Port Construction Services made post-construction modifications to      2
casework and display monitors.                           Millions 1.5  Dollars in 
Schedule                             1
0.5
Completed project construction and post-construction work.
0
Budget                               Authorized Forecasted Costs Incurred
Project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable
None
Risks
None identified at this time.
Budget Transfers
To C800404 (Aeronautical Allowance)          $1,500,000




AIRPORT
60  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Airport Signage (Airline Realignment)
Project:   C800474      The project will provide airport     Status Snapshot Prior Report
Budget: $646,000       directional signage for the airline   Delayed Schedule 1Q 13
Phase: Construction     realignment program.         On Budget
Start: 06/01/2011                                 0 Change Orders
Completion: 06/30/2013                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Completed signage changes for all airline relocations. Replacement     0.8
of old and damaged signs continues.
0.6
Schedule                            Millions
0.4
As previously reported, the change in schedule was based on the
0.2
overall Airline Realignment Program Schedule. Airline relocations     Dollars in 
were delayed.                                      0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.
Construction Costs
Change Order                         Not Applicable
None this quarter
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 3Q 2013 Report  61

THIRD QUARTER REPORT, 2013
Miscellaneous Building Improvements (Airline
Status Snapshot
Realignment)                       On Schedule
On Budget
Project:   C800475      This project will install a new ramp   0 Change Orders
for passenger access to regional    Total Change Orders Amount:
Budget: $2,172,000
aircraft on Concourse A for the     $0
Phase: Construction     Airline Realignment program.
Start: 11/01/2011                                Budget/Costs Incurred
Completion: 07/31/2013
2.5
2
Significant Developments                     1.5 Millions
Project construction was completed by Port Construction Services       1
and substantial occupancy was reached.                     Dollars in 0.5
0
Schedule                               Authorized Forecasted Costs Incurred
Punchlist items were completed in 3rd Quarter for building exterior
cladding panels and handrail extensions.
Construction Costs
Budget                            Not Applicable
Project forecast is within the approved budget and authorization.
Change Order
None
Risks
None this quarter.
Budget Transfers
To C800404 (Aeronautical Allowance)          $550,000



AIRPORT

62  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Fire Station Electric Upgrades
Project:   C800479      This project will replace the existing  Status Snapshot
Budget: $2,033,000      208V transformer and 12.47 KV    On Schedule
Phase: Design        feeder, and add a 500 KV       On Budget
Start: 04/01/2013         generator and a 1000kVA        0 Change Orders
Completion: 10/31/14    transformer.              Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The 60% design is complete.                            2.5
2
Schedule
Millions 1.5
The design is scheduled to be complete November 2013. The
construction phase is scheduled from January 2014 to October 2014.    1
Dollars in 0.5
Budget
0
The project forecast is within the approved budget. Authorization of        Authorized  Forecasted Costs Incurred
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Construction Costs
Change Order                         Not Applicable
None
Risks
Unplanned electrical shut downs could impact the project schedule.
Budget Transfers
None this quarter.




AIRPORT
Port of Seattle 3Q 2013 Report  63

THIRD QUARTER REPORT, 2013
Laptop Power in Concourses
Project:   C800484      This project adds additional       Status Snapshot
Budget: $2,020,000      charging opportunities for personal  On Schedule
Phase: Construction     electronic devices at several     On Budget
Start: 6/26/12           strategic locations throughout the    0 Change Orders
Completion: 12/31/2013   airport terminal.            Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
2.5
Construction contractor has received their notice to proceed and has
begun on site work.                                    2
Millions 1.5
Schedule
1
The project is currently on schedule.                         Dollars in 0.5
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
None
1.2
Risks                                  1
No risks identified at this time.                                 Millions 0.8
0.6
0.4
Budget Transfers                          Dollars in  0.2
None this quarter
0
Initial   Change   Spent
Orders




AIRPORT
64  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
New Window Wall Ticket Zone 1
Project:   C800490      This project will install new       Status Snapshot
Budget: $4,258,000      common use ticket counters and   On Schedule
Phase: Construction     new baggage system along the    On Budget
Start: 07/01/2012         window wall and baggage system   2 Change Orders
Completion: 12/28/2013   renovation.              Total Change Orders Amount:
$38,683
Budget/Costs Incurred
Significant Developments
6
Contract has been executed with PCL Contractors, work started in
5
May 2013 and is proceeding.
Millions  4
3
Schedule
2
The project is currently on schedule.                         Dollars in  1
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
None                                    4
Risks                                  3
Millions
None                                    2
1
Budget Transfers                          Dollars in 
None this quarter.                                        0
Initial   Change   Spent
Orders



AIRPORT

Port of Seattle 3Q 2013 Report  65

THIRD QUARTER REPORT, 2013
Convert Ticket Zone 2 Pushback
Project:   C800491      The scope of the project is to      Status Snapshot
Budget: $5,500,000      renovate the Ticket counters and   On Schedule
Phase: Construction     ATO spaces into a pushback     On Budget
Start: 12/11/2012         configuration.                14 Change Orders
Completion: 11/30/2013                       Total Change Orders Amount:
$401,403
Budget/Costs Incurred
Significant Developments
5
Project was completed on schedule for United Airlines (UA) to
4
relocate their Ticketing counters from Zone 7 to Zone 2; counters
opened on May 22, 2013. Phase 2 of this project will be to move Air    Millions 3
Canada (AC), All Nippon Airways (ANA), among others to temporary    2
ticket counters, demolish the remaining counters and complete the     Dollars in  1
UA pushback ticket counters.
0
Authorized  Forecasted Costs Incurred
Schedule
The project is on schedule for UA and Air Canada to open November
25, 2013.                                        Construction Costs
Not Applicable
Budget
The project forecast is within approved budget and authorization.
Change Order
We are presently working through change orders associated with the
UA Pushback.
Risks
None identified at this time
Budget Transfers
None this quarter.


AIRPORT
66  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Convert Ticket Zone 3 Flow Through
Status Snapshot
On Schedule
Project:   C800492      This project will convert the Zone 3  On Budget
Budget: $10,659,000     Ticketing Area to a flow through    0 Change Orders
Phase: Construction     concept.               Total Change Orders Amount:
Start: 08/07/2012                                 $0
Completion: 10/31/2013
Budget/Costs Incurred
14
Significant Developments                     12
Millions 10
Work was substantially completed on September 24, 2013 and the      8
prime contractor has demobilized. Final change order work and        6
work by Port Construction Services remain.                    Dollars in  4
2
Schedule                             0
Authorized  Forecasted Costs Incurred
The project is currently on schedule.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.
0.6
Change Order                           0.5
None                                  Millions 0.4
0.3
Risks                                 0.2
Dollars in   0.1
The enabling projects and tenant relocations were successfully
0
completed.
Initial   Change   Spent
Orders
Budget Transfers
To C800404 (Aeronautical Allowance)          $2,477,000



AIRPORT
Port of Seattle 3Q 2013 Report  67

THIRD QUARTER REPORT, 2013
Facility Monitoring System Renewal
Project:   C800495      This project will provide a system   Status Snapshot Prior Report
Budget: $3,422,680      upgrade that will allow the system   Delayed Schedule 1Q 13
Phase: Design        to maintain and expand monitoring  On Budget
Start: 01/22/2013         of critical systems such as        0 Change Orders
Completion: 08/31/2015   elevators, escalators, moving     Total Change Orders Amount:
walks, passenger boarding bridges   $0
and baggage systems.
Budget/Costs Incurred
4
Significant Developments
3
The passenger loading bridges portion of the work completed 60%    Millions
design. The network upgrade is progressing well. The Infomration     2
Dollars in 
and Communications Technology (ICT) Architecture Committee has
1
approved the project's network architecture and the project can begin
purchase of equipment.                                0
Authorized  Forecasted Costs Incurred
Schedule
As previously reported, the project is currently behind schedule, the
Construction Costs
anticipated 90% will be submitted to the Port for review in
Not Applicable
September.
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
To Expense                       $3,320


AIRPORT
68  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Airportwide Mechanical Controls System
Project:   C800497      Project Scope and description:     Status Snapshot
Budget: $274,000       Upgrade the HVAC Controls     On Schedule
Phase: Design        System for the Airport. This     On Budget
Start: 05/01/2013         includes adding a wireless        0 Change Orders
Completion: 06/30/2014   connection to the Logistics area to  Total Change Orders Amount:
the south of the Airport.           $0
Budget/Costs Incurred
Significant Developments
2.5
The 60% design is complete.
2
Millions 1.5
Schedule
1
The project is currently on schedule. Design is scheduled to be
completed in late November 2013. Plan to request authorizationfrom    Dollars in 0.5
Commission to bid the project in the 1st quarter of 2014.              0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will    Construction Costs
be requested when the bid documents are completed.           Not Applicable
Change Order
None.
Risks
Unplanned electrical shut downs could impact the project schedule.
Budget Transfers
None this quarter.


AIRPORT

Port of Seattle 3Q 2013 Report  69

THIRD QUARTER REPORT, 2013
RAC Baggage Claim Renovation
Project:   C800541      Renovation of both rental car      Status Snapshot Prior Report
Budget: $1,326,700      counter locations in baggage claim  Delayed Schedule 2Q 13
Phase: Construction     into new waiting areas with vending  On Budget
Start: 10/01/2012         machines and other facilities for     0 Change Orders
Completion: 02/21/2014   special operations           Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
1.5
The contract was advertised on July 19, 2013 and a contract was
executed on August 28, 2013 with Neeley Construction & Cabinet
Company. Port Construction Services began demolition on       Millions 1
September 3, 2013.
0.5
Dollars in 
Schedule
0
The construction contract was executed on August 28, 2013 with a        Authorized Forecasted Costs Incurred
substantial completion date of February 21, 2014.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.
0.3
0.25
Change Order
0.2
None this quarter                                     Millions
0.15
0.1
Risks
0.05   Dollars in 
None this quarter                                      0
Initial    Change Order    Spent
Budget Transfers
To C102066 (Art Pool)                    $800

.

AIRPORT

70  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
NorthSTAR Program
Status Snapshot
On Schedule
Project:   C800544      This project includes the         On Budget
Budget: $16,300,000     programmatic project management  0 Change Orders
Phase: Design        and project controls costs for the   Total Change Orders Amount:
Start: 04/05/2012         NorthSTAR program, consisting of   $0
Completion: 12/31/2018   five capital projects that represents
a unique partnership between the   Budget/Costs Incurred
Port and Alaska Airlines.
20
Significant Developments                     15
Construction Support Services and Commissioning Agent RFPs      Millions 10
Dollars in 
have been awarded and are currently in negotiations. The
NorthSTAR programmatic PLA requirements and agreement        5
framework have been resolved. Presented hypothetical program      0
metrics to the commission and gave an overall program overview        Authorized Forecasted  Costs
Incurred
with tour to Commissioner Bryant.
Schedule                           Construction Costs
Not Applicable
Continuing to define specific NorthSTAR program performance
metrics and develop programmatic public relations communication
plan. Briefing scheduled on Port-wide gate utilization and
forecasting analysis with AAG. Program master schedule updated to
the most current baseline assumptions due to changes in design
durations.
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
None
Risks
Communication and coordination across multiple teams and
stakeholders along with identification/monitoring of all "linked"
Capital projects outside of NorthSTAR.
Budget Transfers
None
AIRPORT
Port of Seattle 3Q 2013 Report  71

THIRD QUARTER REPORT, 2013
NorthSTAR Concourse C Vertical Circulation
Project:   C800547      Construct exterior, weather       Status Snapshot
Budget: $19,300,000     protected sloped walkways with    On Schedule
Phase: Design        elevators at Gates C2/4, C10/12,   On Budget
Start: 11/07/2012         and C14 to provide enhanced      0 Change Orders
Completion: 03/31/2015   access from concourse to aircraft   Total Change Orders Amount:
ramp for Alaska/Horizon regional    $0
operations.
Budget/Costs Incurred
Significant Developments
25
The 100% design package and cost estimate have been submitted
and reviewed. New construction phasing plans have been          20
developed and service directives for removal of C10, C12 and C14    Millions 15
passenger loading bridges executed. Decision made to remove       10
bridge C16 due to conflict with AAG walkway.
Dollars in   5
0
Schedule
Authorized  Forecasted Costs Incurred
Preparing request for Commission authorization of construction.
Working on AAG/Port cost sharing agreement for temporary
passenger walkways and signage.                      Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget.
Change Order
None
Risks
Construction phasing to minimize impact on airline operations and
potential for underground utility conflicts during construction.
Budget Transfers
None


AIRPORT

72  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Concourse D Roof Replacement
Project:   C800550      This project will remove and      Status Snapshot
Budget: $3,252,800      replace the roofing systems on    On Schedule
Phase: Design        Concourse D of the Airport; install   On Budget
Start: 07/01/2013         ladders, stairs and fall protection on  0 Change Orders
Completion: 10/31/2014   the penthouse sections; and make  Total Change Orders Amount:
repairs and where required        $0
replacments to the KalWall window
system.                  Budget/Costs Incurred
4
Significant Developments                      3
Millions
60% Design is complete                               2
Schedule                            Dollars in  1
This project is currently on schedule.                           0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
None
Risks
No risks at this time
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 3Q 2013 Report  73

THIRD QUARTER REPORT, 2013
Grease Interceptor Augmentation
Project:   C800551      This project will install two        Status Snapshot
Budget: $1,559,200      underground 9,000 gallon grease   On Schedule
Phase: Design        interceptors to service the       On Budget
Start: 05/01/2013         Concourse C and South Satellite.    0 Change Orders
Completion: 10/31/2014                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The Commission authorized design funds for this project.             2
Schedule                             1.5
Millions
The project is currently on schedule.                           1
Budget                             Dollars in 0.5
The project forecast is within the approved budget. Authorization of      0
construction funding and authority to advertise for construction will         Authorized  Forecasted Costs Incurred
be requested when the bid documents are completed.
Change Order                         Construction Costs
None                                 Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT

74  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
NorthSTAR Refurbish Baggage Systems
Status Snapshot
Project:   C800555      This project will refurbish existing   On Schedule
Budget: $22,000,000     baggage systems in support of    On Budget
Phase: Design        AAG operation at North Satellite   0 Change Orders
Start: 11/6/2012          and Concourse D. The work will    Total Change Orders Amount:
Completion: 12/31/2015   extend the service life of part of the  $0
C92 systems, C88 North Satellite
systems, and C88 tunnel systems.  Budget/Costs Incurred
25
20
Significant Developments                     Millions 15
Received Commission authorization for construction phase and use
10
of Port Crews. Developed evaluation criteria to minimize component
Dollars in   5
replacement and costs to refurbish.
0
Authorized  Forecasted Costs Incurred
Schedule
The project is currently on schedule. Construction effort has been
authorized. Bid opening scheduled January 2014 with anticipated    Construction Costs
construction start Q2 2014.                              Not Applicable
Budget
the project forecast is currently reflecting a $6,500,000 reduction due
to development of evaluation criteria and metrics which identified
opportunities to minimize component replacement in lieu of
refurbishment.
Change Order
None
Risks
NSAT scope changes may impact baggage handling system
refurbishment requirements due to forecasted baggage volume and
speed. TSA's recapitalization may impact scope and schedule of the
baggage project.
Budget Transfers
None

AIRPORT
Port of Seattle 3Q 2013 Report  75

THIRD QUARTER REPORT, 2013
NorthSTAR North Satellite Renovation NSTS
Status Snapshot
Lobbies
On Schedule
Renovation of the North Satellite       On Budget
Project:   C800556      terminal, including STS station       0 Change Orders
"refresh", ramp level, Concourse
Budget: $206,546,357                          Total Change Orders Amount:
level, and new rooftop airline
Phase: Design                             $0
lounge.
Start: 7/24/2012
Completion: 05/31/2018
Budget/Costs Incurred
Significant Developments
250
Fifteen percent conceptual design package was received. Proposed
Millions 200
concourse hold room, concessions and restroom options were
evaluated. Construction phasing studies were also completed for all    150
renovation options. Airport-wide gating analysis was presented to     Dollars in 100
Port Senior Management. Port and AAG teams identified
50
recommended options for NSAT renovation for presentation to
0
respective management.
Authorized  Forecasted Costs Incurred
Schedule
Construction Costs
Port and AAG Management to review renovation options for        Not Applicable
decision. Construction schedules being developed for renovation
options. Port Operations evaluating gate utilization and support
phasing.
Budget
Commission authorized $32,933,556 to date for design effort. The
current revised budget is $208,346,357 all inclusive through
Construction. Project is on budget.
Change Order
None
Risks
IATA Level of Service study may indicate the need for facility scope
changes. Airlines operational requirements may require changes to
the preliminary two-phased construction approach.
Budget Transfers
None
AIRPORT
76  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Main Terminal Mezzanine Tenant Relocations
Project:   C800560      This project will construct new     Status Snapshot
Budget: $1,750,000      tenant leased spaces in order to   On Schedule
Phase: Design        move existing tenants and provide  On Budget
Start: 3/26/2013          new leasable office space for      0 Change Orders
Completion: 6/30/2014    airlines on the mezzanine of the    Total Change Orders Amount:
main terminal.                $0
Budget/Costs Incurred
Significant Developments
2
The project is currently in design.
1.5
Millions
Schedule
1
Dollars in 
This project is currently on schedule.
0.5
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
None this quarter
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 3Q 2013 Report  77

THIRD QUARTER REPORT, 2013
Known Crewmember Employee Bypass
Project:   C800576      This project will construct two new   Status Snapshot
Budget: $650,000       Known Crewmember and       On Schedule
Phase: Construction     Employee bypass locations at the   On Budget
Start: 12/11/2012         Airport.                    0 Change Orders
Completion: 12/31/2013                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Construction is moving forward on the North and South locations.
The Employee Bypass Portal Vendor has been awarded and the      0.8
portals have been ordered.
0.6
Schedule                            Millions
0.4
Dollars in 
KCM is scheduled to be completed in the North and South locations
0.2
in October and the Employee Bypasses North and South are
scheduled to be completed at the end of November.               0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
None this quarter
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
78  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
International Arrivals Facility (IAF)
Project:   C800583       Pre-design and acquisition      Status Snapshot
Budget: 3,500,000       planning for a new international   On Schedule
Phase: Planning        arrivals facility for Seat-Tac     On Budget
Start: 06/25/2013          International Airport, including a    0 Change Orders
Completion: 06/30/2018    new Federal Inspection Services   Total Change Orders Amount:
Area.                    $0
Budget/Costs Incurred
Significant Developments
400
Presently selecting Project Management Consultant Team.
300
Millions
Schedule
200
Project Management Consultant Team will be selected in forth
Dollars in 100                                                                            quarter of 2013. The consultant is expected to start by the end of the
year.                                               0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the current budget.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT

Port of Seattle 3Q 2013 Report  79

THIRD QUARTER REPORT, 2013
Security Exit Lane Breach Control-Phase 2
Project:   C800605      This project will procure and install   Status Snapshot
Budget: $5,767,000      new automated breach control    Delayed Schedule
Phase: Design        equipment at four security exits in   On Budget
Start: 10/1/2012          the airport terminal.            0 Change Orders
Completion: 11/30/2014                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Construction bidding advertisement was authorized by the Port
Commission. The construction bid documents were completed.        8
Schedule                             6
Millions
This Phase 2 project schedule was pushed out later to ensure that      4
there was adequate time for Airport Security and TSA testing of the
Dollars in   2
pilot project (completed in Phase 1).
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget.
Change Order                         Construction Costs
None                                 Not Applicable
Risks
No major risks at this time.
Budget Transfers
None




AIRPORT
80  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
North Satellite - STS Ceiling Leak Repair
Project:   C800609      This project will eliminate ceiling    Status Snapshot
Budget: $1,750,000      leaks at the North Satellite (NSAT)  On Schedule
Phase: Design         that occur between the satellite    On Budget
Start: 05/28/2013         transit station (STS) and the       0 Change Orders
Completion: 09/30/2014   elevators.               Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Consultants will provide the project design due to workload of Port
Staff.                                                      2
Schedule                             1.5
Millions
The project schedule has been updated to reflect change in           1
design from Port led to Consultant led. This change will not affect
0.5
the overall schedule for construction completion.                  Dollars in 
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget. Commission
Authorization for construction funding and authority to advertise for
construction will be requested when the bid documents are        Construction Costs
completed.                                     Not Applicable
Change Order                         Photo
None.
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT


Port of Seattle 3Q 2013 Report  81

THIRD QUARTER REPORT, 2013
Passenger Bridge and Walkway S16
Replacement
Replace existing Passenger       Status Snapshot
Project:   C800611      Loading Bridge (PLB) and Fixed    On Schedule
Walkway at Gate S16. Upgrade    On Budget
Budget: $1,000,000
existing foundations and install      0 Change Orders
Phase: Design        infrastructure to support new Wi-Fi  Total Change Orders Amount:
Start: 06/03/2013         capabilities                 $0
Completion: 12/31/2013
Budget/Costs Incurred
Significant Developments
Rotunda and fixed walkway foundation upgrades have been         1.2
completed. The new bridge and walkway are scheduled to be         1
delivered on October 31, 2013.                            Millions 0.8
0.6
Schedule                             0.4
Dollars in 
The project is on schedule and the new PLB and fixed walkway will     0.2
be operational by the end of the year.                          0
Authorized  Forecasted Costs Incurred
Budget
Project forecast is within the approved budget. Authorization of
Construction Costs
construction funding and authority to advertise for construction will
Not Applicable
be requested when the bid documents are completed.
Change Order
None.
Risks
Delivery schedule of the equipment from JBT AeroTech - Jetway
Budget Transfers
None this quarter.



AIRPORT

82  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Checked Baggage Recapitalization/Optimization
Project:   C800612      TSA approached the Airport in     Status Snapshot
Budget: 317,000,000     2012 with plan to replace all      On Schedule
Phase: Design        federally owned and operated     On Budget
Start: 2/26/2013          baggage scanning equipment,     0 Change Orders
Completion: 12/31/2017   known as Explosive Detection     Total Change Orders Amount:
System (EDS) equipment. The     $0
EDS equipment is approaching the
end of its life.                    Budget/Costs Incurred
400
Significant Developments
300
The Port and TSA have executed an Other Transaction Agreement    Millions
(OTA). The design started in February 2013 and 30% design of the     200
TSA component was completed in June, per the OTA.
Dollars in 100                                                                            The TSA 30% design component was approved and the project team
is working to address TSA's formal comments. The Port and TSA       0
have executed an Other Transaction Agreement (OTA) for just over        Authorized Forecasted Costs Incurred
$93,000,000. The project team is working to complete an overall
airport 30% design by the end of this year.
Construction Costs
Schedule                           Not Applicable
The project is currently on schedule. Overall schedule will be refined
to reflect a ten year program.
Budget
The project forecast is within the approved budget. Commission
approved budet increase to $20,000,000.
Change Order
None
Risks
None identified at this time.
Budget Transfers
Budget Increase                 $297,150,000

AIRPORT
Port of Seattle 3Q 2013 Report  83

THIRD QUARTER REPORT, 2013
Second Floor Mezzanine Infrastructure Upgrade
Project:   C800615      This project is to upgrade and     Status Snapshot
Budget: $2,545,000      extend the infrastructure (HVAC,   On Schedule
Phase: Design        Communications, Electrical,      On Budget
Start: 08/01/2013         Plumbing, WiFi) to 14,000sq ft of    0 Change Orders
Completion: 06/30/2014   future lease space on the second   Total Change Orders Amount:
floor, including 7,000 sq ft for a new  $0
USO.
Budget/Costs Incurred
Significant Developments
3
The project received Commission approval in June 2013. The        2.5
project is in the beginning stages of design.                     Millions 2
1.5
Schedule
1
The project is currently on schedule.                          Dollars in 0.5
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable
None
Risks
None
Budget Transfers
None




AIRPORT
84  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Highline School Noise Insulation
Status Snapshot Prior Report
Delayed Schedule 4Q 10
Project:   C200007      Highline School Insulation        On Budget
Budget: $101,797,000    Agreement will provide funding for  0 Change Orders
Phase: Construction     sound mitigation for 15 schools that  Total Change Orders Amount:
Start: 03/23/1999         are impacted by aircraft noise from   $0
Completion: 11/30/2021   Sea-Tac Airport.
Budget/Costs Incurred
Significant Developments                     120
100
Port funding is authorized and will become available when the FAA,
the State of Washington, and the Highline School District provide       80
matching funds.                                     60
Millions
40
Schedule                            Dollars in 20
0
The schedule for state funding is not known. The district's schedule
Authorized  Forecasted Costs Incurred
is dependent on obtaining general election bonds at various
intervals. The school district has requested FAA grant funding for
Olympic Elementary in fourth quarter of 2013. FAA grant received.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
Not applicable
Risks
Project delayed due to funding issues with the Highline School
District. There is a risk if no bonds are passed in the general
election. Obtain FAA Airport Improvement Program (AIP) Grant
funding.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 3Q 2013 Report  85

THIRD QUARTER REPORT, 2013
Highline Community College Noise Insulation
Project:   C200042      Highline Community College      Status Snapshot Prior Report
Budget: $32,050,000     Insulation Agreement will provide   Delayed Schedule 4Q10
Phase: Construction     funding for up to 22 eligible      On Budget
Start: 01/11/2005         buildings that are impacted by      0 Change Orders
Completion: 12/31/2013   aircraft noise from Sea-Tac Airport.  Total Change Orders Amount:
$0
Significant Developments
Fourteen of the 22 eligible buildings have been sound insulated by    Budget/Costs Incurred
the college.
40
Schedule                             30
Building #4 received FAA Airport Improvement Program (AIP) Grant
20
and began construction in winter 2012. Substantial completion for     in Millions
Building 4 is August, 2013. The schedules for the remaining         Dollars  10
buildings are dependent on state and federal funding.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of
the remaining project budget will be requested for one building at a   Construction Costs
time from the Commission in the future when the schedule is       Not Applicable
determined.
Change Order
Not Applicable
Risks
The Highline Community College competes for state funding with
other colleges. If they do not receive adequate funding, projects will
be delayed.
Budget Transfers
None this quarter.


AIRPORT

86  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Home Insulation Retrofit
Project:   C200048      This project includes storm window  Status Snapshot Prior Report
Budget: $5,344,000      retrofit of previously insulated     Delayed Schedule 4Q 11
Phase: Construction     homes.                On Budget
Start: 01/11/2005                                 0 Change Orders
Completion: 12/31/2013                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The Port has identified eligible homes and notified homeowners of
their eligibility. The Port is continuing with storm window retrofit.          6
5
Schedule                             4
The Port is reviewing other potential homes for eligibility.              Millions 3
2
Budget                             Dollars in 1
The project forecast is within the approved budget and authorization.     0
Authorized  Forecasted Costs Incurred
Change Order
None.                                    Construction Costs
Not Applicable
Risks
The ability to accomplish the retrofit is dependent on homeowner's
schedules, and structural integrity of the home.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 3Q 2013 Report  87

THIRD QUARTER REPORT, 2013
Single Family Home Sound Insulation
Project:   C200093      Sound insulate remaining homes    Status Snapshot Prior Report
Budget: $13,747,395     that are within the 1998 65 decibel  Delayed Schedule    4Q 11
Phase: Construction     day night level (DNL) noise      On Budget
Start: 03/27/2007         contour.                   0 Change Orders
Completion: 12/31/2013                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
Thirty-seven homes are complete; ten homes are in the process of      15
receiving sound insulation. Approximately 59 additional homes have
been identified as eligible.                                   Millions 10
Schedule                             5
Dollars in 
This project is currently on schedule.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within approved budget and authorization to
complete all homes currently in progress.                    Construction Costs
Change Order                           4
None
3
MillionsDollars in 
Risks                                 2
The ability to accomplish the insulation is dependent on the
1
homeowner's schedules, willingness to sign an aviation easement,
and obtain a subordination agreement from their lender, and          0
Initial    Change Order    Spent
structural integrity of the home. If more eligible homes than
anticipated are identified in the future, then additional funding may be
needed.
Budget Transfers
None this quarter.


AIRPORT
88  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
RMU/Kiosk Concession Program
Status Snapshot Prior Report
Delayed Schedule 4Q 10
Project:   C800146    The project will provide design and     On Budget
Budget: $879,146     fabrication of Retail Merchandising    0 Change Orders
Phase: Construction   Units (RMUs); provide power,       Total Change Orders Amount:
Start: 11/20/2007      communications, and data to RMU     $0
Completion: 09/30/2013 locations; and install floor-mounted
receptacles for the utilities to allow easy
connection points as well as flexibility   Budget/Costs Incurred
for future utilization.
1.5
Significant Developments                     Millions 1
RMU utilities have been installed at the Concourse C location. The
0.5
procurement of the casework has been awarded and the contract      Dollars in 
was executed in June 2013. We are finalizing the design of the
0
casework and installation is scheduled for late September.
Authorized  Forecasted Costs Incurred
Schedule
The utility infrastructure is complete. The casework is scheduled for   Construction Costs
installation 10 weeks from the final design approval; anticipate late    Not Applicable
September 2013.
Budget
The project forecast is currently within the approved budget and
authorization.
Change Order
None
Risks
The additional units on Concourse C may exceed the proposed
budget.
Budget Transfers
None this quarter.

AIRPORT

Port of Seattle 3Q 2013 Report  89

THIRD QUARTER REPORT, 2013
Burien Commercial Property Acquisition
Project:   C800150      Acquire commercial properties     Status Snapshot Prior Report
Budget: $3,000,000      along Des Moines Memorial Drive,  Delayed Schedule    2Q 10
Phase: Implementation   and vacate one street, in the City of  On Budget
Start: 05/31/2007         Burien that is surrounded by Port-   0 Change Orders
Completion: 03/31/2014   owned properties.           Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The remaining anticipated acquisitions will be street vacation of 12th
4
Place S. in Burien, Washington; possibly the 757 Convenience store;
and a small upholstery shop on the Lora Lake site.                 3
Millions
2
Dollars in 
Schedule
1
It is anticipated that the acquisitions will occur in the 1st Quarter of
2014 time frame.                                     0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.
Construction
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
90  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Tenant Reimbursement
Status Snapshot
Project:   C800154    Build out of spaces for new and      On Schedule
Budget: $4,709,577    existing tenants. If more than a "basic  On Budget
Phase: Construction   finish" condition space is built for the   0 Change Orders
tenant, the tenant is required to       Total Change Orders Amount:
Start: 08/14/2007
reimburse the Port for the cost of the   $0
Completion: TBD
work beyond this "basic finish". These
reimbursements are allowed under    Budget/Costs Incurred
the guidelines described in the
"Tenant Reimbursement Policy".        5
4
Millions  3
Significant Developments
2
No activity in the 3rd Quarter of 2013, although anticipate a
reimbursement for Hudson during 4th Quarter of 2013.             Dollars in  1
0
Schedule                               Authorized Forecasted Costs Incurred
Schedules vary to meet the tenant's needs.
Budget                            Construction Costs
Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 3Q 2013 Report  91

THIRD QUARTER REPORT, 2013
Snow Removal Equipment - 2013
Project:   C800498      This project will purchase four     Status Snapshot
Budget: $2,000,000      pieces of runway snow removal    On Schedule
Phase: Implementation   equipment.              On Budget 1Q 13
Start: 02/14/2012                                 0 Change Orders
Completion: 01/22/2013                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
All equipment has been received. The only work remaining is to
install the required radios on the four new plow & tow behind broom    2.02
snow removal units. The radio installs will be completed by the end
2
of September.
1.98
Schedule                            1.96 in Millions
Equipment delivered on schedule.                         1.94  Dollars 
1.92
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
None                                 Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT

92  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
T-46 Lease Improvements
Project: C102554        Construct stormwater treatment    Status Snapshot
On Schedule
Budget: $6,000,000     system to comply with Ecology
order by 09/30/2014. Terminal     On Budget
Phase: Design                           0 Change Orders
Start: 04/12/2013        pavement overlay to fulfill lease
obligation.                     Total Change Orders Amount:
Completion: 2020                          0
Significant Developments
Completed review of the Stormwater Engineering Report, met with
Budget/Costs Incurred
Department of Ecology and agreed that an addendum to the
Engineering Report will be submitted based on the alternatives
7
evaluation. Completed preliminary pavement condition evaluation.      6
Schedule                            Millions 5
4
Stormwater treatment system to be completed by September 30,       3
Dollars in   2
2014.
1
0
Budget
Authorized  Forecasted Costs Incurred
$10,000,000 for Stormwater Treatment System. Currently within
budget.
Construction Costs
Change Order                        None
Not Applicable
Risks
Complete stormwater treatment system within budget by
September 30, 2014
Budget Transfers
Not Applicable



SEAPORT
Port of Seattle 3Q 2013 Report  93

THIRD QUARTER REPORT, 2013
Street Vacations T5,18,105
Status Snapshot
Delayed Schedule 4Q 11
Project: C102858,     Street vacation related real estate     On Budget
C102875, E104366    negotiations and agreements --T5,    0 Change Orders
Budget: $1,500,000   T18, and T105.              Total Change Orders Amount:
Phase: Permitting                         $0
Start: June 2010
Completion: 2014                          Budget/Costs Incurred
2
Significant Developments                     1.5
Millions
Meetings with the City have restarted for Terminal 18 (T-18). T-105      1
Street Vacations have been completed.
Dollars in 0.5
Schedule                             0
Authorized  Forecasted Costs Incurred
Current effort involves resolving Street Vacation issues on T-18. T-5
Street Vacations issues will be addressed following completion of
T-18 issues.                                       Construction Costs
Not Applicable
Budget
The budget has been revised for 2013 and beyond.             Photo
Change Order
Not applicable
Risks
Not applicable
Budget Transfers
Not applicable



SEAPORT
94  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
P91 Fender System Upgrade
Project:   C800183      Upgrades to the vessel berths of    Status Snapshot
Budget: $5,700,000      P91 to better accommodate cruise  On Schedule
Phase: Design        ships and also serve the other    On Budget
Start: 01/31/10          industrial customers who utilize the   0 Change Orders
Completion: 8/1/2013    berths and adjacent dock/apron    Total Change Orders Amount:
areas on P91 for less than $6M by   $0
spring 2011.
Budget/Costs Incurred
Significant Developments
6
Fabrication of 7 camel barges complete. Camels in service for the
remainder of 2013 cruise season.
Millions  4
Potential to order more barges under existing purchase option.
2
Schedule
Dollars in 
Full Fender replacement completed April 2012.                   0
Camel Barge replacement completed by July 2013.                 Authorized Forecasted Costs Incurred
Budget
Project is within approved budget.                         Construction Costs
2.5
Change Order
2
None this quarter
Millions  1.5
Risks                                  1
None this quarter                                     Dollars in  0.5
0
Budget Transfers                             Initial Change Spent
Orders
None




SEAPORT
Port of Seattle 3Q 2013 Report  95

THIRD QUARTER REPORT, 2013
T-91, Bldg C175 Roof Replacement
Status Snapshot Prior Report
Project:   C800430      Replace roof on the C175 building
Budget: $240,000       at Terminal 91.            Delayed Schedule
Phase: Design                            On Budget
Start: 7/26/11                                    0 Change Orders
Completion: Q4 2014                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The 60 percent design documents were completed and reviewed
during the 3rd Quarter. The 90 percent submittal is due during 4Q13.
0.3
0.25
Schedule
0.2
Project remains on schedule for installation during 2014.            0.15   Millions
0.1
Budget
0.05   Dollars in
On budget                                     0
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
None at this time
Photo
Budget Transfers
None




SEAPORT

96  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
SEA P66 Apron Pile Wrap
Status Snapshot
Project:   C800516      Design and install a pile wrap
Budget: $3,010,000      system for corrosion protection of   On Schedule
Phase: Design        steel structural pilings associated   On Budget
Start: 3/6/12            with Seaport structures at Pier 66.   2 Change Orders
Completion: 12/31/14                         Total Change Orders Amount:
$86,210
Significant Developments                    Budget/Costs Incurred
Construction is in progress. Work is being completed in conjunction      4
with the P69 North Apron Corrosion Control Project (CIP C800313).
3
Schedule                            Millions 2
Dollars in 
Projected construction completion date remains at the end of March
1
2014.
0
Authorized  Forecasted Costs Incurred
Budget
Project is on budget.
Construction Costs
Change Order                         Not Applicable
None
Photo
Risks
Installation of pile wraps is tide and weather dependent.
Construction duration may lengthen due to unfavorable conditions.
Budget Transfers
None




SEAPORT
Port of Seattle 3Q 2013 Report  97

THIRD QUARTER REPORT, 2013
Argo Yard Truck Roadway
Status Snapshot
Project:   C800546,      New Port of Seattle owned truck
E104751, E104754       roadway between SR 99 and     On Schedule
Budget: $6,600,000      Colorado Way Avenue right-of-way.  On Budget
Phase: Design                            0 Change Orders
Start: 03/11/12                                   Total Change Orders Amount:
$
Completion: 12/31/2014
Significant Developments                    Budget/Costs Incurred
Final MOU Supplemental Agreement draft and negotiations with        8
stakeholders underway. Ninety percent engineering design nearly
complete. Property appraisals for the roadway and stormwater        6
easement areas completed and awaiting approval by Prologis.         4
Millions
Decision made to construct proposed truck roadway of concrete
Dollars in  2
instead of asphalt.
0
Schedule                               Authorized Forecasted Costs Incurred
Design and permitting is scheduled to be completed by late 2013.
Construction is to be completed in summer 2014.
Construction Costs
Budget                            Not Applicable
Project authorized budget is $2,800,000 (including $600,000 from
FMSIB).
Change Order
None
Risks
Additional funding approval expected to be required when
authorization to advertise for construction bids is requested. Current
preliminary project estimate is $3,300,000. The actual start of
utilization of the proposed Argo Yard truck roadway is dependent
upon the completion of separate off-site projects - EMW Phase II
(East Marginal Way surface street improvements) and WSDOT's SR
99 timber trestle replacement scheduled for construction completion
by spring 2014. The EMW Phase II improvements will also require
timely approval by Union Pacific Railroad and the Ash Grove Cement
Co. in order to be completed within 2014.

98  Port of Seattle 3Q 2013 Report

Budget Transfers
None













SEAPORT
Port of Seattle 3Q 2013 Report  99

THIRD QUARTER REPORT, 2013
P66 Security Camera Upgrade Project
Project:   C800596      P66 Cruise Terminal Security      Status Snapshot
Budget: $540,000       Camera Upgrade. Scope removes  On Schedule
Phase: Construction     29 cameras monitoring the cruise   On Budget
Start: 10/05/2012         facility, installs 36 new cameras,    2 Change Orders
Completion: 07/01/2013   and upgrades the infrastructure.    Total Change Orders Amount:
$500
Significant Developments
Budget/Costs Incurred
Construction is complete and in closeout.
0.545
Schedule                            0.54
0.535
Installation Complete.
0.53   Millions
0.525
Budget                             0.52
0.515   Dollars in 
On Budget.                                     0.51
0.505
Change Order                            Authorized Forecasted Costs Incurred
One no cost change order to extend contract time to allow
completion of punch list items. One change order to compensate
Contractor for switching around already installed camera.          Construction Costs
Risks
None.
Budget Transfers
None




SEAPORT
100  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
T-46 Dock Rehabilitation
Project:   C800603      Terminal 46 Dock Rehabilitation    Status Snapshot
Budget: $1,854,000      Project                Delayed Schedule
Phase: Design                            On Budget
Start: November 6, 2012                            0 Change Orders
Completion: Q1 2016                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Completed 90% design documents during the 3rd quarter and the
review comments will be finalized during the 4th quarter.              2
1.5
Schedule                            Millions
1
As noted in the previous report the construction schedule was
delayed a year, from 2014 to 2015, to avoid conflicting construction     Dollars in 0.5
projects on the terminal. This being the case the final design has
0
been delayed as well until mid-year 2014.                         Authorized  Forecasted Costs Incurred
Budget
The project is on budget                               Construction Costs
Not Applicable
Change Order
None                                 Photo
Risks
None at this time
Budget Transfers
None



SEAPORT

Port of Seattle 3Q 2013 Report  101

THIRD QUARTER REPORT, 2013
East Marginal Way Grade Separation        Budget/Costs Incurred
Status Snapshot Prior Report
Project:   E102007      FAST Corridor funded project;      Delayed Schedule
Budget: $55,456,171     FHWA, State, City with Port      Forecast Overrun
Phase: Construction     commitment of $20,437,841. Scope  97 Change Orders
Start: 5/2006            is to construct grade separation in    Total Change Orders Amount:
Completion: Q2 2014     vicinity of T5 and T18 to minimize   $1,922,967
truck traffic/rail conflicts.
53.6
53.58
Significant Developments
53.56
Final landscaping improvements installed and are now under a       53.54  Millions
3-year maintenance period before final acceptance by City. Other     53.52
miscellaneous construction loose ends are in process of being        53.5  Dollars in 
completed. Final project Memo of Agreement (MOA) is in process    53.48
with the City. As-built drawings are in progress.                   53.46
Authorized  Forecasted Costs Incurred
Schedule
Anticipate final acceptance by SDOTby 2nd Quarter 2014.
Construction Costs
Budget
25
Current construction costs, part of project closeout, are based on unit
20
line items and cost reconciliation. Preliminary investigation indicates     Millions  15
potential overrun.
10
Change Order                          Dollars in  5
Executed change orders for a total net amount of $1,922,967.           0
Initial   Change   Spent
Orders
Risks
Additional POS funding is anticipated to be needed in early 2014 to
complete final project loose ends.                          Photo
Budget Transfers
None


SEAPORT
102  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Viaduct Construction Coordination
Project:   E104324,      Participate in the design &       Status Snapshot
E104535-38          construction of the bored tunnel,   On Schedule 3Q 13
Budget: $2.9M        north & south portals, Holgate to   On Budget 3Q 11
Phase: Implementation   King St, Central Waterfront surface  0 Change Orders
Start: 1/1/2009          streets, and related projects to     Total Change Orders Amount:
ensure adequate connection to port  $0
Completion: 12/31/2018
facilities.
Budget/Costs Incurred
Significant Developments
3.5
SR 99 tunnel boring machine began mining operations after           3
temporary delay due to labor issue. Funding agreement was
approved by Commission on August 6, 2013 and all signatures were    Millions 2.52
obtained on August 27, 2013. Mercer construction continued.        1.5
Seawall utility relocations continued in preparation for construction      Dollars in  1
start in Q3.                                              0.5
0
Authorized  Forecasted Costs Incurred
Schedule
Construction of Atlantic St. Overpass expected to complete by yearend.
Tunneling expected to continue through 2014. Related City
Construction Costs
projects are making steady progress: Mercer construction is
Not Applicable
underway; Seawall Phase I construction to begin Q3 13; Central
Waterfront SEPA scoping process began in Q2 13.
Photo
Budget
Port staff costs were within anticipated 2013 spending.
Change Order
Not applicable
Risks
Resolution of labor issue at T-46 is needed to prevent delays.
Budget Transfers
None

SEAPORT
Port of Seattle 3Q 2013 Report  103

THIRD QUARTER REPORT, 2013
T-5, T-91, and T-18 Maintenance Dredging
Status Snapshot
Project:   E104840,      Maintenance Dredge at T-5 all     On Schedule
U00033; U00067        three berths, and at T-91 East     On Budget
Budget: $1,950,000      cruise berth. Programmatic      0 Change Orders
Phase: Design        permitting for maintenance      Total Change Orders Amount:
Start: 08/14/12          dredging at T-18              $
Completion: 02/28/2014                       Budget/Costs Incurred
2.5
Significant Developments
2
T-5 Phase II maintenance dredging design and permitting is
1.5
complete and construction contracting is under way. T-18
1
Millions
programmatic permit is under way now under a separate budget and
schedule, and construction timing will depend on customer needs      Dollars in 0.5
and permit progress. In September, the Commission also authorized     0
Authorized  Forecasted Costs Incurred
funding for T91 East Cruise Berth maintenance dredging. Due to
complications and delays in permitting, T91maintenance dredging
construction is now delayed for construction in late 2014--early 2015.
Construction Costs
Schedule                           Not Applicable
T-5 Phase II maintenance dredging construction is expected to be    Photo
completed by February 2014, and T-91 East Cruise Berth
maintenance dredging to be completed by February 2015.
Budget
Project is on budget.
Change Order
None
Risks
Environmental permitting may cause major delays and scope change
to the dredging projects.
Budget Transfers
None

SEAPORT
104  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
FT C15 HVAC Improvements
Status Snapshot
Project:   C800137                             Delayed Schedule
Budget: $4,887,000    Provide the preliminary planning,    On Budget
Phase: Design       design, and construction to replace    0 Change Orders
Start: 05/01/10         the existing HVAC systems within     Total Change Orders Amount:
Building C-15 that are at the end of
Completion: 6/30/2014                        $0
their service life.
Budget/Costs Incurred
Significant Developments
6
Opened bids and low bid is over the Engineer's Estimate by more
5
than 10%. Commission approved additional project authorization on
4
October 8th. New total project budget is now $4,887,000.
3
Millions
Schedule                             2
Dollars in   1
With low bid over the Engineer's Estimate by 10% and the time
0
needed to obtain Commission approval for the additional project
Authorized  Forecasted Costs Incurred
authorization, construction contract execution will be delayed.
Construction completion estimated to occur at the end of June 2014.
Budget                            Construction Costs
Not Applicable
Additional project authorization approved on October 8, 2013.
Change Order
None
Risks
Construction related access to existing infrastructure will be difficult
and some work will be within areas currently concealed from view.
Challenges may arise and could impact construction costs and
schedule.
Budget Transfers
None


REAL ESTATE
Port of Seattle 3Q 2013 Report  105

THIRD QUARTER REPORT, 2013
P69 N Apron Corrosion Control
Status Snapshot
Project:   C800313      Install a corrosion control system    On Schedule
Budget: $5,100,000      for the steel pilings, pile caps, and   On Budget
Phase: Construction     beams under the North Apron.    0 Change Orders
Start: 03/06/12                                   Total Change Orders Amount:
Completion: 12/31/2013                       $0
Budget/Costs Incurred
Significant Developments
6
Construction is in progress.
Millions  4
Schedule
Construction is scheduled to be completed by end of 2013 to allow      2
for testing and closeout.                                   Dollars in 
0
Authorized  Forecasted Costs Incurred
Budget
Project is on budget.
Construction Costs
Change Order                         Not Applicable
None
Photo
Risks
Installation of pile wraps is tide and weather dependent.
Construction duration may lengthen due to unfavorable conditions.
Budget Transfers
None at this time




REAL ESTATE
106  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
P-69 Built-up Roof Replacement
Project:   C800314      Replace the 65,000SF Roof at the   Status Snapshot
Budget: $445,000       P-69 Headquarters Office Building  On Schedule
Phase: Design                            Forecast Overrun
Start: 2/26/12                                    0 Change Orders
Completion: 10/30/2014                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The project is in the 100% design phase.
2.5
Schedule
2
The project is scheduled to be completed in Q4 2014              Millions 1.5
Budget                              1
Dollars in 
The project is currently below budget.                         0.5
0
Change Order                            Authorized Forecasted Costs Incurred
None
Risks                               Construction Costs
Not Applicable
None
Budget Transfers
None





REAL ESTATE
Port of Seattle 3Q 2013 Report  107

THIRD QUARTER REPORT, 2013
FT C-2 Nordby HVAC and Roof Replacement
Project:   C800344      Replace 23,000SF of existing      Status Snapshot
Budget: $298,000       Roofing and roof top HVAC units   On Schedule
Phase: Design                            On Budget
Start: 2/26/12                                    0 Change Orders
Completion: 10/30/2014                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The project is in the 90% design phase. This project will be coupled
with the FT Net Shed 9 Roof Overlay project.                    2.5
2
Schedule
Millions 1.5
The project is scheduled for completion in Q4 2014
1
Budget                             Dollars in 0.5
The project is currently below budget.                          0
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
None
Budget Transfers
None





REAL ESTATE
108  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
FT Net Shed #9 Roof Overlay
Project:   C800527      Overlay 12,000SF of existing      Status Snapshot
Budget: $130,000       corrugated Roof at the FT Net     On Schedule
Phase: Design        Shed Building             On Budget
Start: 2/26/12                                    0 Change Orders
Completion: 10/30/2014                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The project is in the 90% design phase. This project will be coupled
with the FT C-2 Nordby HVAC and Roof Replacment project.         0.6
0.5
Schedule
Millions 0.4
Dollars in 
The project is scheduled for completion in Q4 2014                0.3
0.2
Budget
0.1
The project is currently below budget.                          0
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
None
Budget Transfers
None





REAL ESTATE
Port of Seattle 3Q 2013 Report  109

THIRD QUARTER REPORT, 2013
Maritime Industrial Center Built-up Roof
Replacement
Replace the 21,000SF Roof at the   Status Snapshot
Project:   C800571      MIC Office Building            On Schedule
On Budget
Budget: $1,456,000
4 Change Orders
Phase: Construction                        Total Change Orders Amount:
Start: 9/30/12                                    $48,390
Completion: 10/30/2013
Budget/Costs Incurred
Significant Developments
The project is in the construction phase with construction well          2
underway.
1.5
Millions
Schedule                             1
The project is scheduled for completion in Q4 2013
Dollars in 0.5
Budget                              0
Authorized  Forecasted Costs Incurred
The project is currently on budget.
Change Order
Construction Costs
None                                 Not Applicable
Risks
None
Budget Transfers
None




REAL ESTATE

110  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Pier 66 Steam Replacement
Install new boilers to provide       Status Snapshot
Project: C800625                               On Schedule
Budget: 1,400,000      adequate heat and hot water
On Budget
Phase: Construction    service for both the conference
center and CTA operations.            Change Orders
Start: 6/2/2013                                   Total Change Orders Amount:
Completion: 12/31/13
Significant Developments                    Budget/Costs Incurred
Initial design complete. Major works open order contract advertised
1.5
and awarded. Major mechanical equipment ordered.
1
Schedule                            Millions
Seattle Steam delayed cutoff of steam service from September 2nd
0.5
to October 15th due to delay of City of Seattle seawall project. Crews    Dollars in 
beginning work onsite in September.
0
Authorized  Forecasted Costs Incurred
Budget
Project is within budget
Change Order                        Construction Costs
None                                 Not applicable
Risks
Working with Puget Sound Energy to upgrade natural gas service to
the building to accommodate increased demand from additional
equipment. Delay of this upgrade may impact the project schedule
and jeopardize the October 15th completion
Budget Transfers
None



REAL ESTATE
Port of Seattle 3Q 2013 Report  111

THIRD QUARTER REPORT, 2013
FT Net Shed Code Compliance
Project:   E104838      FT Net Sheds 3-11 building       Status Snapshot
Budget: $2,950,000      improvements required per City of   On Schedule
Phase: Design        Seattle building & fire codes     On Budget
Start: May 2012                                  0 Change Orders
Completion: June 2015                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Advertised and opened bids on racks and rack footing procurement
contracts. Working with the City on various permit approvals.         3.5
3
Schedule
Millions 2.52
Construction is expected to begin on November 4th and the overall
1.5
construction completion is still scheduled to be completed by the end
1
of 2nd quarter of 2015 if all net sheds would be retrofitted. Defer work    Dollars in 
0.5
on Net Shed No. 7 and 8 to the very end of construction.
0
Authorized  Forecasted Costs Incurred
Budget
Project budget is on track.
Construction Costs
Change Order                         Not Applicable
None
Risks
It is difficult to project the amount of stored materials that needs to be
moved out and moved back since tenant storage habit could vary
significantly. In addition, the amount of work required in each unit is
difficult to assess until stored materials are removed. These would
impact the overall project budget.
Budget Transfers
None


REAL ESTATE
112  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Flight Information System (FIMS) II
Project: C101117      Procure, develop, and implement a    Status Snapshot
Budget: $8,220,000     FIMS system that includes        On Schedule
Phase:Implementation  replacement monitors, an airport     On Budget
Start: 5/4/2010         resource management system, and    5 Change Orders
Completion: 12/30/2014  a flexible digital signage system      Total Change Orders Amount:
capable of displaying flight           $395,223
information, visual paging, and
notifications.
Budget/Costs Incurred
9
Significant Developments
8
The first phase deployment of the flight information display (FIDS)       7
Millions   6
software was completed on-schedule in November 2012.
5
Deployment of the resource management system (RMS) was       Dollars in  4
deployed on-schedule in June 2013 with no major issues. This fully      3
2
replaces the previous FIMS software.
1
0
Authorized     Forecasted    Costs Incurred
New signage construction will continue through 2013 and small
enhancements to benefit airlines and Port operations will be
deployed through 2014. Planned integration with the Airport Breach
Notification System is no longer required and will not be delivered.    Construction Costs
2.5
Schedule
2
On Schedule
Millions  1.5
Budget                              1
On Budget                                   Dollars in  0.5
0
Change Order                             Initial  Change  Spent
Orders
Prior report: Additional signage replacement was approved resulting
in a contract change order for construction design.
.
Risks
No significant risks.
Budget Transfers
None

CORPORATE
Port of Seattle 3Q 2013 Report  113

THIRD QUARTER REPORT, 2013
Maximo Enterprise Implementation
Project:   C800003      Implement latest version of       Status Snapshot
Budget: $3,680,000      Maximo, merge Aviation and Real   Delayed Schedule
Phase: Implementation   Estate applications onto one     On Budget
Start: 11/25/2007         platform, and add service desk     0 Change Orders
Completion: 6/30/2014    module and wireless handheld    Total Change Orders Amount:
capabilities.                    $0

Significant Developments                    Budget/Costs Incurred
Major components of the program have been delivered, including the
4
deployment of Service Management software for the ICT Service
Desk in December 2008 and the upgrade and consolidation of         3
Marine Maintenance and Aviation Maintenance Maximo systems in     2
Millions
September 2010. Mobility enhancements were deployed for Aviation
Dollars in  1
and Marine Maintenance personnel in 2013.
0
Schedule                              Authorized Forecasted  Costs
Incurred
Business resource constraints will delay the implementation of the
new interfaces that link the Maximo system to the Peoplesoft
Construction Costs
Financials system until 2014.
Not Applicable
Budget
On Budget
Change Order
None
Risks
Resource constraints may continue to delay the implementation of
the interfaces.
Budget Transfers
None


CORPORATE
114  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
ID Badge System Replacement
Project: C800162        Procurement and replacement of   Status Snapshot Prior Report
Budget: $2,500,000      the Portwide ID Badge system     Delayed Schedule
Phase:Implementation    including software, hardware, and   On Budget
Start: 5/1/2012           equipment.                 0 Change Orders
Completion: 6/30/2014                         Total Change Orders Amount:
$0
Significant Developments
Software configuration, data migration, and interface development    Budget/Costs Incurred
are in progress.
3
Schedule
2
While deployment of the main software component will be delivered
Millions
on-schedule, a smaller mobile component will be released in a         1
second phase deployment in 2014.                        Dollars in
0
Budget                               Authorized Forecasted  Costs
Incurred
On Budget
Construction Costs
Change Order
Not Applicable
None
Risks
No significant risks
Budget Transfers
None




CORPORATE
Port of Seattle 3Q 2013 Report  115

THIRD QUARTER REPORT, 2013
Airline Activity Management
Project: C800222        Development of an airline activity   Status Snapshot
Budget: $500,000       management system that       Delayed Schedule
Phase:Implementation    integrates with several Port      On Budget
Start: 6/19/2011          systems to replace aging reporting   0 Change Orders
Completion: TBD       system and supply data for airline   Total Change Orders Amount:
activity fees.                    $0

Budget/Costs Incurred
Significant Developments
0.6
The first phase delivery that includes replacement of the aging
0.5
activity reporting system has been delivered according to schedule.
0.4
0.3
Schedule                             Millions
0.2
Aviation Properties is evaluating next phase requirements based on    Dollars in 0.1
new SLOA Agreement terms.
0
Authorized  Forecasted    Costs
Budget                                       Incurred
On Budget
Construction Costs
Change Order                         Not Applicable
None
Risks
Significant changes to the requirements for the Resolution or SLOA
update may further delay the project or require additional funding.
Budget Transfers
None



CORPORATE
116  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Enterprise Project Cost Management
Project: C800321        Replace the current construction    Status Snapshot
Budget: $1,525,000      costing systems with a common    Delayed Schedule
Phase:Implementation    enterprise project cost         On Budget
Start: 4/21/2008          management system.           0 Change Orders
Completion: 12/30/2013                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The first phase deployment has been completed and the software is
in-use by the Project Management Groups.                    2
1.5
Schedule
1
Availability of resources is impacting the completion of the remaining     Millions
components. These include features such as cash flows and trend
Dollars in0.5
logs as well as additional interfaces that require resources currently
0
focused on the Peoplesoft Financials Upgrade project. We are in the
Authorized Forecasted   Costs
process of procuring additional configuration assistance and expect                   Incurred
to deliver in phases over the next several months.
Construction Costs
Budget                            Not Applicable
None
Change Order
None
Risks
Availability of Port resources may delay next phase deliverables.
Budget Transfers
None


CORPORATE

Port of Seattle 3Q 2013 Report  117

THIRD QUARTER REPORT, 2013
Records and Document Management
Project:   C800322      Improve statutory compliance,     Status Snapshot
Budget: $800,000       increase functionality, and lower   Delayed Schedule
Phase: Close Out      operating costs by replacing     On Budget
Start: 6/23/2009          Hummingbird with SharePoint for    0 Change Orders
Completion: 9/30/2013    records and document        Total Change Orders Amount:
management.             $0

Significant Developments                    Budget/Costs Incurred
The Sharepoint Records Center was deployed in September 2013
and the system is available for Legal rollout of records management    0.8
processes.                                       0.6
0.4
Schedule                             Millions
Dollars in 0.2                                                                                       Prior Report: Resource availability due to competing priorities has
delayed the full implementation of the Sharepoint Records Center       0
Authorized  Forecasted   Costs
until September 2013.
Incurred
Prior Report: Sharepoint 2010 implementation is dependent on the
completion of several infrastructure projects currently in progress     Construction Costs
and requires additional time to complete the upgrade of existing      Not Applicable
sites.
Budget
On Budget
Change Order
None
Risks
None
Budget Transfers
None

CORPORATE

118  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Time Clock System
Project: C800387        Procure and implement a Time    Status Snapshot Prior Report
Budget: $380,000       Clock System to accurately capture  Delayed Schedule
Phase: Implementation    and track time and attendance for   On Budget
Start: 6/8/2010           approximately 230 employees in    0 Change Orders
Completion: 11/30/2013    Aviation Security and Airport      Total Change Orders Amount:
Operations organizations.         $0

Significant Developments                    Budget/Costs Incurred
Vendor was unable to deliver software that functioned in our
0.4
environment per the contract. We are working with the legal
department to determine our options for severing the relationship.        0.3
The project team has evaluated options and are moving forward with     Millions  0.2
the procurement and implementation of a simpler time clock system    Dollars in  0.1
from a different vendor. The scope of the implementation will not
include a Peoplesoft interface as originally planned.                  0
Authorized Forecasted   Costs
Incurred
Schedule
We are estimating deployment of the new solution in November
Construction Costs
2013.
Not Applicable
Budget
$75,500 of the $240,000 spent to date on the project was directly
related to the previous vendor solution and will not contribute to the
value of a new product implementation. This was expensed against
the ICT Operations Budget in 2012. The new solution can be
delivered within the approved budget.
Change Order
None
Risks
No signfiicant risks at this time.
Budget Transfers
None

CORPORATE
Port of Seattle 3Q 2013 Report  119

THIRD QUARTER REPORT, 2013
PeopleSoft Financials Upgrade
Project: C800392        Upgrade of Peoplesoft Financials   Status Snapshot Prior Report
Budget: $5,000,000      hardware and software         Delayed Schedule
Phase:Close Out                           On Budget
Start: 9/28/2010                                 0 Change Orders
Completion: 12/31/2013                         Total Change Orders Amount:
$0
Significant Developments
The Peoplesoft Financials Upgrade has been successfully deployed   Budget/Costs Incurred
with minimal issues.
6
Schedule
4
Prior Report - An implementation vendor was selected via a
Millions
competitive procurement but we were unsuccessful in negotiating an     2
acceptable contract. Because of resource constraints during the       Dollars in
year-end process, the next optimum window of opportunity for the       0
Authorized  Forecasted   Costs
upgrade begins in mid-2012. This will delay the project one year.
Incurred
Budget
Construction Costs
On Budget                                  Not Applicable
Change Order
None
Risks
Significant resources will be required across multiple organizations
which may delay other technology projects.
Budget Transfers
None



CORPORATE
120  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Police Records Management System
Project: C800393        Procure and implement a       Status Snapshot Prior Report
Budget: $1,300,000      replacement Police Records      Delayed Schedule
Phase:Implementation    Management System         On Budget
Start: 10/10/10                                   0 Change Orders
Completion: 4/1/2014                          Total Change Orders Amount:
$0
Significant Developments
Testing of the system is in progress for a deployment in October     Budget/Costs Incurred
2013. The deployment of non-critical components will be
implemented following the main deliverable.                    1.5
Schedule                             1
Configuration of the final design took longer than anticipated           Millions
0.5
because of complexity in the procured software.                 Dollars in
0
Prior Report - A change request was approved to implement
Authorized  Forecasted    Costs
additional software that will better meet business process for field                       Incurred
reporting. Technical problems installing the new software will delay
the implementation until August 2013.
Construction Costs
Prior Report - Contract negotiations took significantly longer than
Not Applicable
anticipated delaying project completion by 8 months.
Budget
On Budget
Change Order
None
Risks
Continued issues with the software configuration could delay the
October delivery.
Budget Transfers
None

CORPORATE
Port of Seattle 3Q 2013 Report  121

THIRD QUARTER REPORT, 2013
Construction Document Management
Project: C800521        Replacement of the Construction   Status Snapshot
Budget: $900,000       Document Management System    On Schedule
Phase: Planning        used by Construction Management  On Budget
Start: 9/10/2013          to accept, review, and distribute    0 Change Orders
Completion: 3/31/2015    critical documentation.         Total Change Orders Amount:
$0

Significant Developments                    Budget/Costs Incurred
Development of requirements for the Procurement are in progress.
1
Bid advertisement scheduled in 4th quarter 2013.
0.8
Schedule                              0.6
Millions
On Schedule                                    0.4
Dollars in   0.2
Budget
0
On Budget                                       Authorized Forecasted  Costs
Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
No signfiicant risks at this time.
Budget Transfers
None




CORPORATE
122  Port of Seattle 3Q 2013 Report

THIRD QUARTER REPORT, 2013
Access Control Network Refresh
Project: C800558        Upgrade the Access Control      Status Snapshot
Budget: $1,500,000      Network switch infrastructure     On Schedule
Phase: Design         hardware and software        On Budget
Start: 3/26/2013                                 0 Change Orders
Completion: 3/31/2014                         Total Change Orders Amount:
$0

Significant Developments                    Budget/Costs Incurred
Data Center site improvements, equipment configuration, and virtual      2
infrastructure design is in progress.
1.5
1
Schedule
in Millions   0.5
On schedule.
Dollars     0
Authorized  Forecasted   Costs
Budget                                       Incurred
On budget.
Construction Costs
Change Order
Not Applicable
None
Risks
Port resource availability may impact schedule.
Budget Transfers
None




CORPORATE

Port of Seattle 3Q 2013 Report  123

THIRD QUARTER REPORT, 2013
Radio System Upgrade
Project: C800586        Upgrade of the Radio System Core  Status Snapshot
Budget: $6,750,000      Hardware and Software and      On Schedule
Phase: Implementation    Dispatch Consoles           On Budget
Start: 6/9/2013                                   0 Change Orders
Completion: 5/31/2014                         Total Change Orders Amount:
$0

Significant Developments                    Budget/Costs Incurred
Procurements have been completed and system configuration is in
8
progress.
6
Schedule
Millions    4
On Schedule
Dollars in    2
Budget
0
On Budget                                       Authorized Forecasted  Costs
Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
No signfiicant risks at this time.
Budget Transfers
None




CORPORATE
124  Port of Seattle 3Q 2013 Report

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.