7a

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA               Item No.      7a 
STAFF BRIEFING 
Date of Meeting     August 6, 2013 
DATE:    July 30, 2013 
TO:     Tay Yoshitani, Chief Executive Officer 
FROM:    Dave Soike, Director, Aviation Facilities and Capital Program 
Wendy Reiter, Director, Aviation Security and Emergency Preparedness 
SUBJECT:  Checked Baggage Recapitalization/Optimization Project Briefing 
SYNOPSIS 
The Transportation Security Administration (TSA) has near-term challenges, and the
Seattle Tacoma International  Airport (Airport) has both near-term and long-term
challenges, related to handling checked baggage.
The TSA's challenge is imminent and financially driven because its costs are too high at
airports across the country. The TSA financial challenges at our Airport are driven by
three factors: (1) the Explosive Detection System (EDS) machines, which were installed
after September 11, 2001, are very expensive to maintain and are approaching the end of
their design life so their reliability will soon decrease; (2)  the TSA inspection facilities
are spread in six areas across the Airport, which does not allow efficient staffing; and (3)
TSA employee-injury and safe-working-condition issues have arisen due to existing work
areas that are confined and non-air-conditioned. These financially driven problems are
exacerbated by the continuing federal budget pressures.
The Airport's near-term challenge is that a few of the existing separate baggage handling
systems, that are literally built immediately around the aging EDS machines, are reaching
their operational capacity maximums due to year-over-year passenger growth or because
of relocating large peak baggage loads onto certain systems. While this is important, the
Airport's long-term challenge is far more consequential. The long-term challenge is that
the existing separate baggage systems cannot be grown to effectively handle the loads
that Airport will have to handle in the future. The Airport handles 33 million annual
passengers (MAP), but it must continue to operate in an efficient manner all the way to
the Airport's maximum capacity of60 MAP. Twice the baggage load is a huge stretch
for separate systems, some of which are now struggling under current peak loads. 
A way has been found to solve both the TSA and the Airport's problems. TSA and
Airport staff have been working together based on the January 22, 2013, Commission
authorization and the January 8, 2013, Commission briefing, to identify options and
analyze them. The best option uses the available TSA funding to solve their near-term
problems by aggregating their inspection facilities from six to one. This option also
makes significant progress toward building a single baggage processing facility that
benefits the TSA short-term needs and allows the Airport to make great headway toward

Template revised May 30, 2013.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 30, 2013 
Page 2 of 5 
reconfiguring its baggage system to effectively allow it to expand efficiently all the way
to 60 MAP in the future.
It was fortunate that TSA brought the Airport an opportunity to first study, and then to
design, baggage improvements that meet both the Airport's needs and TSA needs. The
TSA will pay the major share of both the study and the final design needs.
When the Commission authorized proceeding with design to the 30-percent level last
January, it also allowed the Airport to take the opportunity to take advantage of the first
federal offer for funding. The resulting design is nearing completion, and has created a
unique second opportunity for the Airport in that TSA is willing to invest significant
federal monies (approximately one-third of the total cost) toward a Seattle baggage
project.
This second and very large opportunity for federal funding has recently been offered to
the Port. The offer is between $50 million and $100 million of federal cost sharing. T o
receive it, the Port must agree to fund its share (the remaining two-thirds currently
estimated between $150 million and $200 million) over many years. Further , the Airport
must accept the federal funding by September 10, 2013, to meet pending federal fiscal
year budget deadlines.  This approximate one-third offer of funding by the federal
government for the entire project is unique in that worsening federal fiscal pressures are
expected to significantly minimize chances of such funding in the future. Federal budget
pressures next year may both further limit the amount of federal participation and limit
the continuing nature of the annual proposed TSA share. 
This briefing and associated PowerPoint presentation will provide an update on various
elements of the proposed project including:
History of the baggage system. 
Age, function, and location of the various baggage systems including current
operating challenges. 
Existing limited capacity of the systems versus capacity necessary for the future. 
Alternatives considered. 
Discussion of similar challenges and work at other airports across the county. 
Recapitalization and optimization scenarios and cost estimate ranges and
upcoming timelines for federal cost sharing. 
Recommendation and next steps. 
Airport staff will return to the Commission on September 10, 2013, to seek the
Commission's authorization for an agreement with TSA covering cooperative baggage
improvements and budget for continued design. 
BACKGROUND 
The Airport system of baggage conveyors is one of the most complex systems in the
Airport. It gets high use and is aging. Portions of the system were rebuilt in rapid
fashion immediately after the events of September 11, 2001.  Installing these new

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 30, 2013 
Page 3 of 5 
baggage systems was expensive, took a number of years to complete and did not always
proceed as planned due to changes in TSA requirements and the evolution of technology.
As it is now built, the Airport system is not a single system, but rather many separate
systems that bags must transfer between. Separate systems were the best way to rapidly
increase security after September 11, and those separate systems were designed to
include a nominal amount of passenger growth. In addition, as specific airline needs
emerged over the ensuing years, or as airlines were relocated, the separate systems have
been modified to meet the carriers' specific operating needs. Although various baggage
projects have occurred to meet operating needs over the years, the systems continue to
have limited capacity to meet both near- and long-term growth needs of the Airport
overall.
The Airport is faced with two problems: the existing separate systems have major
subsystems, such as the controls, that are aging and must be replaced, and each system
has no capacity or adjacent room to be expanded to meet growing passenger demands.
Passenger growth is expected to increase from 33 million annual passengers to 60 million
annual passengers over approximately the next two to three decades. The Airport is
faced with developing a long-term strategy and associated set of projects to continue to
deliver bags for both traveler and airline customers.  This is a major and near-term
challenge for the Airport due to high capital costs, complexity to keep operations ongoing
during construction, and major space constraints in order to double the system's
capacity to meet future growth.
Although the challenge is large, the Airport is fortunate that the TSA is simultaneously
considering making investments in airports across the country. The TSA is pressured by
federal budget constraints and sequestration such that they are willing to invest to the
degree that their investments lower their own operating costs. The TSA at Seattle-
Tacoma International Airport has higher operating costs because of multiple systems in
six locations versus what they would have with a consolidated baggage system.
Therefore the Airport staff members are programming the Airport's long-term baggage
system growth plan while keeping the TSA needs and potential funding in mind. Airport
and TSA staff has been working cooperatively to determine the best long-term plan to
benefit both parties.
Chain of Custody: Checked baggage at airports across the United States is screened for
explosives and other dangerous materials before it is loaded onto aircraft. The typical
chain of custody flow of a checked bag is as follows: it begins with the traveler (who
bring bags to the airport); it transitions to the airlines (at ticketing counters), transfers to
Airport (as it moves along conveyors); then moves into TSA's control (which owns,
operates, and maintains the screening machines); then back to the Airport (further
conveyor travel); and finally to the airlines (or their contractors who load bags onto the
aircraft). The TSA-owned machines are the central security function within the entire
complex transportation system carrying bags from ticketing to aircraft.
Future Growth of Airport: Parts of the Airport baggage system controls and software are
aging and certain systems are experiencing problems at peak loads, such as mistracked

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 30, 2013 
Page 4 of 5 
bags. The Airport has a clear need to both reinvest in the baggage system to meet current
demands, and also to meet medium-and-longer-term demands. Medium-term demands
include being able to handle 50 percent more travelers in a decade and thus grow to 45
million annual passengers (MAP). The work of the 30% design has focused on preparing
designs and associated cost estimates to reach the 45 MAP horizon.  Longer-term
demands include being able to handle nearly 100 percent growth, thus growing to 60
million annual passengers which is the expected top-end limit of the Airport based on
both airfield and landside capabilities. The design has also focused building in easy
growth capability into the plan. Thus inherent in the 30% design is the ability to reach 60
MAP with minimal changes to the TSA security scanning and search areas. Published
Federal Aviation Administration growth rates indicate the Airport will reach its top-end 
limit (maximum operating capacity) sometime between two to three decades from now.
Earlier Port Authorization: On January 22, 2013, the Commission authorized $5,000,000
for staff to begin and complete design to a 30-percent level for a project to either install
new federally owned baggage scanning machines into the Airport's baggage system
("recapitalization" in federal terms), or reconfigure the system to receivenew federally
owned machines ("optimization" in federal terms). The 30-percent design for the TSA
screening system is complete, while the 30-percent Airport design is ongoing.
Independent Consultant:  The Port retained a baggage consultant, Vic Thompson
Company, which has done an independent cost estimate to validate the cost estimate of
the designer (BNP Associates) retained earlier by the Airport. In addition, these two
estimates will be used to validate two separate estimates being prepared by the TSA's
consultants. Other than preparing the estimate, Vic Thompson Company is not currently
associated with the Airport's project.  We have asked them to provide an independent
presentation to share their thoughts on recapitalization versus optimization with the Port
Commission on August 6, 2013. Its PowerPoint Presentation is also attached. 
ATTACHMENTS TO THIS BRIEFING 
Airport PowerPoint Presentation associated with this memo dated July 30, 2013. 
Vic Thompson PowerPoint Presentation dated August 6, 2013. 
Airport PowerPoint Presentation associated with the January 8, 2013, 
Commission authorization request. This PowerPoint is provided as background
and for context of earlier decisions for newer Commissioners what have more
recently joined the Commission.
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
January 22, 2013  The Commission authorized $5,000,000 for staff to begin
design, to take design to 30%, and to enter into an agreement to allow
reimbursement from the federal government to the Port for eligible elements of
the 30% design work.
January 8, 2013  Baggage Systems Briefing.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 30, 2013 
Page 5 of 5 
August 14, 2012  Baggage system recapitalization/optimization was noted in
the 2013 Business Plan and Capital Briefing as a significant capital project not
included in 2013-17 capital program. 
August 7, 2012  Baggage system recapitalization/optimization was referenced
as one of the drivers for the need to develop an Airport Sustainability Master
Plan. 
June 26, 2012  The Airport's baggage systems were discussed during a
briefing on Terminal Development Challenges. 
May 10, 2012  TSA's interest in a national recapitalization/optimization plan 
for all baggage screening operations was referenced in a design authorization
request for the C60  C61 Baggage Handling System Modifications Project.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.