7c report

Item Number:  7c _Report
Meeting Date: April 9, 2013


Commission Staff Brieng
Capital Improvement Projects
Fourth Quarter Report 2012

This page intentionally left blank









ii  Port of Seattle 4Q 2012 Report

Port of Seattle
Capital Improvement Project Report
Fourth Quarter 2012
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the status of the Port's capital projects.
Background
During 2012 the Port plans to invest over $319,000,000 to expand and upgrade the infrastructure that supports marine
and aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping
companies, airlines, rental car companies, concessionaires and public parking. About 4 percent of the Port's capital
budget comes from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in
transportation facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes a "Status Snapshot" illustrating at a
glance if the project is on schedule, within budget, the total number of change orders to date, and the total value of
executed change orders.
x Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x Budget addresses the total project budget and includes things like overall budget status, recent Commission
authorizations, forecasted overruns or savings, and scope changes.
x Change Orders provides a description of CO for the reporting period and information on any CO over $200,000 or
10% of the contract value.
x Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x Budget Transfers reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page and select the Audit/Accountability button. Use the form to ask a
question, make a comment or request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 4Q 2012 Report  1

Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C000683 et al .......3rd Runway Program .............................................6 ........... 
C100266 et al .......Rental Car Facility ............................................... 7-8 ..........
C102163................Main Terminal Baggage Screening .................... 9-10.........
C102334 ...............Water System Isolation Valve Upgrade ................11 ..........
C102573 ...............Aireld Pavement Replacement ...........................12 ..........
C800019 ...............Gate Utilities Improvement ...................................13 ..........
C800034 ...............North Expressway Relocation ..............................14 ..........
C800061 ...............Main Terminal South Low Voltage ........................15 ..........
C800105 ...............Airport Owned Gate Infrastructure .......................16 ..........
C800107 ...............C4 UPS System Improvements ............................17 ..........
C800112................Runway 16C/34C Panel/Joint Sealant .................18 .......... ................. ............................................
C800147 ...............Concessions Unit Readiness Program ................19 ..........
C800148 ...............GML Arrivals Hall Concessions ...........................20 ..........
C800168 ...............C60-C61 BHS Modications ................................21 ..........
C800174................FIS - New Primary Inspection Booths ..................22 ..........
C800203 ...............Common Use Lounge Remodel ...........................23 ..........
C800218 ...............Security Exit Lane Breach Control .......................24 ..........
C800230 ...............Emergency Lighting Parking.................................25 .......... ...............
C800237 ...............Terminal Escalators Modernization ...................26-27 .......
C800238 ...............Central Plant Pre-Conditioned Air .....................28-29 .......
C800242 ...............Security Checkpoint Cameras..............................30 ..........
C800247 ...............Cargo 2 West Hardstand ......................................31 ..........
C800251 ...............Vertical Conveyance Modernization.................. 32-33 ....... ...............
C800253 ...............Parking System Replacement ..............................34 ..........
C800254 ...............Aircraft RON Parking Post Ofce Site..................35 ..........
C800267 ...............Port Owned Loading Bridges ...............................36 ..........
C800268 ...............Stage 2 Mechanical Energy Implementation .......37 ..........
C800274 ...............8th Floor Weather Proong ..................................38 ..........
C800276 ...............Common Use Equipment Expansion (CUSE) ......39 ..........
C800324 ...............Long-Term Cell Phone Lot ....................................40 ..........
C800334 ...............Two new CTE Freight Elevators ...........................41 .......... 
C800335 ...............EGSE Electrical Charging Stations ................... 42-43 .......
C800374 ...............Claim Device 14 and Lower Inland .......................44 ........................................ 
C800375 ...............Vertical Conveyance Modernization.....................45 ..........
C800376 ...............South Satellite HVAC, Lights, and Ceiling Repl. ..46 ..........
C800382 ...............BHS (C22-C1, MK1 and TC3) ............................ 47-48........
C800390 ...............Cargo 6 Enhancements ........................................49 ........................................ 
C800406 ...............RW 16C/34C Reconstruction Design ...................50 ..........


2  Port of Seattle 4Q 2012 Report

Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule Budget
C800412 ...............South Satellite Concessions Project ....................51 ..........
C800414 ...............Access Control Door Additions .........................52-53 .......
C800415 ...............ALCMS Upgrade...................................................54 .......... 
C800417 ...............Lagoon 3 Bird Wires .............................................55 ..........
C800426 ...............FIS Improvement - Short Term .............................56 ........................................ 
C800451 ...............Doug Fox Site Improvement .................................57 ........................................ 
C800455 ...............Concourse D Common Use Environment ............58 ..........
C800459 ...............2011-2013 Roof Replacement Program ...............59 ..........
C800461 ...............IWTP Fiber Installation .........................................60 ..........
C800466 ...............South Satellite - Additional Gate Lobby ................61 ..........
C800467 ...............PLB Replacement .................................................62 .......... 
C800472 ...............Exterior Gate Improvements ................................63 ..........
C800473 ...............CUSE at Ticket Counters/Gates - AR ..................64 ..........
C800474 ...............Airport Signage .....................................................65 .......... 
C800475 ...............Miscellaneous Building Improvements - AR.........66 ..........
C800484 ...............Laptop Power In Concourses ...............................67 ..........
C800490 ...............New Window Wall Ticket Zone 1 ..........................68 ..........
C800491 ...............Convert Ticket Zone 2 Pusback ...........................69 ..........
C800492 ...............Convert Ticket Zone 3 Flow Thru .........................70 ..........
C800541 ...............RAC Baggage Claim Renovation .........................71 ..........
C800544 ...............NorthSTAR Program.............................................72 .......... 
C800547 ...............NorthSTAR Concourse C Vertical Circ. ...............73 ..........
C800555 ...............NorthSTAR Refurbish Baggage Systems ............74 ..........
C800556 ...............NorthSTAR North Satellite Renovations ..............75 ..........
Other Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C200007...............Highline School Noise Insulation ..........................76 ..........
C200042 ...............Highline Community College Noise Insulation .....77 ..........
C200048 ...............Home Insulation Retrof t .......................................78 .......... 
C200093 ...............Single Family Home Sound Insulation .................79 ..........
C800146 ...............RMU/Kiosk Concession Program ........................80 ..........
C800150 ...............Burien Commercial Property Acquisition .............81 ..........
C800154 ...............Tenant Reimbursement ........................................82 .......... 
C800482 ...............Rubber and Paint Removal Equipment ................83 ..........
C800498 ...............Snow Removal Equipment ...................................84 ..........


Port of Seattle 4Q 2012 Report  3

Seaport
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C102858 et al .......Street Vacations T-5/18/105.................................85 ..........
C800165 ..............Seaport Security Grant Round 7 .........................86 ..........
C800183 ...............P91 Fender System Upgrade ...............................87 ..........
C800349 ...............T-5 Crane Cable Reels .........................................88 ..........
C800430 ...............T-91 Building, C175 Rood Replacement ..............89 ..........
C800516 ...............SEA P-66 Apron Pile Wrap ..................................90 ..........
C800546 ...............Argo Yard Truck Roadway .................................91-92........
C800596 ...............P66 Security Camera Upgrade ............................93 ..........
C800603 ...............T-46 Dock Rehabilitation ......................................94 ..........

WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation ..................95 ..........
E104324 ................Viaduct Construction Coordination ......................96 ..........
E104559................T-18 Pile Cap Repair Pilot Project ........................97 ..........
E104610 ................Underdock Inspections .........................................98 .......... 
E104840................T-5 and T-18 Maintenance Dredging ....................99 ..........
Real Estate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800137 ...............FT C15 HVAC Improvements ..............................100 .........
C800187 ...............RE Maintenance Shop Solutions.........................101 .........
C800313 ...............P69 N Apron Corrosion Control ..........................102 .........
C800314 ...............P69 Built-up Roof Replacement ..........................103 .........
E104838................FT Net Shed Code Compliance Improvement ....104 .........
Corporate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C101117 ................Flight Information Systems (FIMS) II ...................105 .........
C800003...............Maximo Enterprise Implementation.....................106 ......... ............................ 
C800162 ...............ID Badge Replacement .......................................107 .........
C800222 ...............Airline Activity Management ................................108 .........
C800321 ...............Enterprise Project Cost Management .................109 ....................................... 
C800322 ...............Records and Document Management ................110 ....................................... 

4  Port of Seattle 4Q 2012 Report

Overall Project    Variance since
Statuslast report
CIP Number  Project Title             Page     Schedule  Budget
C800387 ...............Time Clock System ..............................................111 ....................................... 
C800392 ...............PeopleSoft Financial Upgrade .............................112 ....................................... 
C800393 ...............Police Records Management System .................113 ....................................... 
C800501 ...............Maintenance Planning System ............................114 ....................................... 

Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Variance Status
Variance Since Last Report














Port of Seattle 4Q 2012 Report  5

FOURTH QUARTER REPORT, 2012
3rd Runway Program
Status Snapshot
On Schedule
Project: C000683,       The 3rd Runway Program
On Budget
C001138, C001175,      constructed a new 8,500 foot long
13 Change Orders
C001331, C001751,      runway, connecting taxiways, and
Total Change Orders Amount:
C001760, C100172      related infrastructure.
$90,369.25
Budget: $920,415,659
Phase: Construction                       Budget/Costs Incurred
Start: 05/27/1997
1150
Completion: 12/31/2011
1100
1050
Significant Developments                    1000 MillionsDollars in 
950
Pond M Modifications project is complete. Maintenance Building
900
Demolition project is in contract closeout.                       850
800
Schedule                              Authorized Forecasted Costs Incurred
The remaining construction work includes RST property acquisition
and site restoration. All buildings and materials have been removed
from the site and site stabilization of the property is still to be        2012 Contract Const. Costs
completed. Fencing and gates will be installed in the first quarter of
2
2013.
1.5
Budget                             Millions 1
The project forecast is within the approved budget and authorization.
0.5
Additional savings is anticipated.                             Dollars in 
0
Change Order                             InitialChange OrdersSpent
None this quarter
Photo
Risks
None
Budget Transfer
None this quarter.


AIRPORT
6  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Rental Car Facility
Status Snapshot Prior Report
Delayed Schedule 3Q 12
Project:   C100266,     The program will construct a       Under Budget
C102167, C800032     consolidated rental car facility (RCF)  1,824 Change Orders
Budget: $400,311,000   for all rental car companies at the    Total Change Orders Amount:
Phase: Construction    airport, a bus maintenance facility    $14,228,389
Start: 02/24/1998        (BMF), and mitigation with the off-site
roadway improvements (ORI), plus
Completion: Spring 2012
purchase a fleet of buses.          Budget/Costs Incurred
Significant Developments                     420
410
The Consolidated Rental Car Facility opened May 17, 2012 has not
400
reached substantial completion and final claims negotiations are       Millions 390
pending. Representatives from the Rental car industry continue to      380
work with the Port on closing post-opening issues with resolution in      370
Q1 2013.                                      Dollars in 360
350
340
The ORI project obtained substantial completion in October 2012
Authorized  Forecasted Costs Incurred
and final claims negotiations are underway.
The BMF project is complete and anticipated resolution of the
remaining post-opening issues is Q1 2013. Remaining project      Construction Costs
elements are complete and undergoing final contract negotiations. 
300
The RCF has entered the last phase of project closeout and           250
approximately 85% of open purchase orders/contracts have been      Millions 200
closed or are in the process of closing. Asset plans have been         150
submitted and booked for all costs through year-end 2012.            100
Dollars in   50
Schedule                              0
Initial   Change   Spent
RCF opened May 17, 2012. Project closeout will be substantially               Orders
complete by February 28, 2013 except for those projects that will be
delayed by final claims resolutions. ORI claims are estimated to be
Photo
complete within 2013 and RCF by 2014 at the earliest.
Budget
Forecasted cost at completion of the program includes funding for
claim settlement. The forecast of $394,128,000 is $6,183,000 under
the approved budget. Savings anticipated on both ORI and BMF.
Change Order
A total of 34 change orders have been executed this quarter for a net
impact of $298,566.
Port of Seattle 4Q 2012 Report  7

Risks
x For RCF: claims resolution, quality issues, and post opening work completion.
x For ORI: claims resolution.
x For BMF: claims resolution.
Budget Transfers
$12,700,00 was reduced from the budget in recognition of a portion of the savings realized, along
with $25,000 transferred out to cover Expense work.
Cost Growth of Construction
RCF Airport Wayfinding Signage and Curbside Modifications - MC-0316968 - Cumulative change
order percentage is 21.3% with no activity this quarter. This contract is closed.
Consolidated Rental Car Facility - Small Operator Build Out - MC-0317022 - One (1) change order
executed this quarter for a time extension with no dollar impact. This contract was closed with an
overall change order percentage of 3.97%.
Consolidated Rental Car Facility Offsite Roadway Improvements and SR99 Bridge Seismic Upgrade
MC-0316568 - No change orders executed this quarter. The cumulative change order value is
$2,554,136 (33.5%). Final claim negotiations are underway.
Bus Maintenance Facility - MC-0316730 - Twelve (12) change orders executed at a net total $33,653
for various issues and credits. The cumulative change order value for this quarter is $310,034
(2.37%).
GCCM Final Construction (Phase 3 of 3)  MC-0315405 - On June 30, Commission authorized the
$32,000,000 suspension impact including a $6,973,300 budget increase and an increase in change
order limit from 10% to 18% requiring Commission notification. The current cumulative change order
percentage through this quarter is 4.1% with 21 change orders executed for a net increase of
$264,913. Final claim negotiations are underway
TESC & Early Work (Phase 2 of 3)  MC-0315292 - cumulative change order percentage is 19.4%
due primarily to removal of contaminated soils and associated impacts. This work and the final
contract reconciliation is complete.
GCCM Pre-Construction (Phase 1 of 3)  MC-0314280  the cumulative change order percentage of
170.5% is the result of changes for additional contractor management and support beyond the extent
of the original scope to validate project costs and support the rental car companies and the Port on
final approval of the project. This work and the final contract reconciliation is complete.

AIRPORT
8  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Main Terminal Baggage Screening
Project:   C102163     This project creates automated      Status Snapshot Prior Report
Budget: $218,712,358   systems for explosive detection     Delayed Schedule 4Q 08
Phase: Close Out     screening of baggage for the north   Under Budget   4Q 09
Start: 09/24/2002        Main Terminal and South Satellite.    665 Change Orders
Completion: 02/13/2009  The systems will meet all security    Total Change Orders Amount:
requirements while reducing staffing   $51,165,622
and providing capacity for future
growth.                    Budget/Costs Incurred
235
Significant Developments                     230
The C-1 baggage handling/screening system has been placed into     Millions 225
revenue service for the Alaska Air Group. The C-1 Lid Replacement    220
and Repair work is complete. The only work remaining on this project
Dollars in 215
is the installation of new Direct Digital Controls (DDC) to indicate to     210
boiler room when pumps are off-line.                            Authorized  Forecasted Costs Incurred
Schedule
Construction Costs
The project was delayed approximately two years from the original
completion date due to replacement of the original baggage
200
subcontractor, changing TSA requirements and other scope
150
changes. Turner Construction demobilized on May 31, 2009. The
GCCM construction contract with Turner Construction has been       Millions 100
closed. The remaining fire sprinkler and fire proofing work was
50
completed.                                      Dollars in 
0
Initial    Change    Spent
Budget                                   Orders
The project forecast is within the approved budget and authorization.
Photo
Change Order
A total of 665 Change Orders have been issued on this project.
Risks
None
Budget Transfers
None this quarter


Port of Seattle 4Q 2012 Report  9

Cost Growth of Construction
In 2006, the baggage handling system subcontractor was terminated, as they were unable to meet
the project schedule requirements. The remaining work was rebid in the fall of 2006. Alaska Airlines
asked that we include the BHS work within the 2-step ticket counter project which increased the
amount of BHS work in the bidding (attracting more competition), and eliminated the issues with
having two different BHS subcontractors in the same work area.












AIRPORT
10  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Water System Isolation Valve Upgrade-non AF
Status Snapshot Prior Report
Delayed Schedule 3Q 12
Project:   C102334      This project replaces isolation     On Budget
Budget: $954,000       valves on the aging water       0 Change Orders
Phase: Construction     distribution system, necessary for   Total Change Orders Amount:
Start: 10/01/2010         isolating portions of the system in    $0
Completion: 2/28/2013    the event of breaks, leaks, or tieins
, in non-airfield (AF) locations.    Budget/Costs Incurred
1.2
Significant Developments                      1
Millions    0.8
Dollars in 
The project is currently in construction.
0.6
Schedule                             0.4
0.2
The schedule was extended further to minimize operational impacts
due to unexpected challenges in shutting off water to locations where     0
Authorized       Forecasted      Costs Incurred
the remaining valves will be replaced.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
None
Risks
None identified at this time
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 4Q 2012 Report  11

FOURTH QUARTER REPORT, 2012
Airfield Pavement Replacement
Project:   C102573      The project is intended to be a
Budget: $30,262,035     multi-year pavement replacement   Status Snapshot
Phase: Construction     program to replace distressed     On Schedule
Start: 05/02/2010         pavement and joint seal on the     On Budget
Completion: 12/31/2016   airfield.                7 Change Orders
Total Change Orders Amount:
$413,259
Significant Developments
Port of Seattle Commission approved design authorization for 2013   Budget/Costs Incurred
construction work on July 24, 2012. Design for the 2013
35
construction work is 90% complete.
30
25
Schedule
20
Millions
The 2012 construction work is complete. This was the second phase    15
of a multi-year pavement replacement program to be performed from   Dollars in 10
2011 to 2015. The 2013 construction work is scheduled to start in      5
the second quarter of 2013.                               0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.              2012 Construction Costs
Change Order                           7
Seven change orders were executed this quarter.                  6
Millions   5
Risks                                  4
3
None this quarter.
Dollars in    2
1
Budget Transfers                           0
Initial   Change   Spent
None this quarter.                                               Orders



AIRPORT
12  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Gate Utility Improvements
Project:   C800019   This project will upgrade the South
Satellite Port-owned loading bridges to
Budget: $12,883,000                         Status Snapshot Prior Report
the same standards, including 400Hz
Phase: Design                            Delayed Schedule    3Q 12
power and potable water. This will
Start: 06/28/2007                                 On Budget
reduce air emissions, improve energy
Completion: 8/29/2014                        0 Change Orders
efficiency and save money for the       Total Change Orders Amount:
airlines.                            $0
Budget/Costs Incurred
Significant Developments
Sole source justification for the 400 Hz motor generators at South       15
Satellite has been approved. The 100% design drawings and
specification were completed in 2012. Bid period is expected to        10
begin in February 2013.                                 Millions
5
Schedule                            Dollars in
After the design completion in December, the current schedule has      0
Authorized  Forecasted Costs Incurred
the construction starting in June of 2013 and being completed in
June 2014. The project was rescheduled due to incorporating
lessons learned from PC Air and finalizing as-built conditions over
the last 3 months on the contract documents.                 Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
Airport Operations at certain gates could be impacted during the
construction phase of the project. Bid documents have provided
constraints of time/schedule although the risk of schedule remains, if
Operations cannot provide the gate when the contractor requests it.
CM/PM/OPS coordination is key to minimizing risk.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 4Q 2012 Report  13

FOURTH QUARTER REPORT, 2012
North Expressway Relocation
Project:   C800034
The project is a collaboration       Status Snapshot  Prior Report
Budget: $103,347,700    between the Port and Sound     Delayed Schedule 2Q 11
Phase: Construction     Transit. It reconstructs the North   On Budget
Start: 07/27/2004         Airport Expressway and brought    225 Change Orders
Completion: 07/31/2012   light rail to the Airport.         Total Change Orders Amount:
$8,314,360
Significant Developments
Budget/Costs Incurred
The main contract for reconstruction of the North Airport Expressway
and the light rail transit components is complete. The final contract      115
(paving, landscaping, the north entry art features) is now complete.
110
Aviation Division approved the additional improvements to Wall 14.     Millions
These improvements are estimated at $958,000 and will utilize        105
project savings.
Dollars in 100
Schedule
95
The main contract reached substantial completion in August 2008;         Authorized  Forecasted Costs Incurred
and plant establishment was completed in December 2010. The final
contract reached substantial completion in November 2011; and
plant establishment was completed in November 2012.           Construction Costs
Budget                             120
The project forecast is within the approved budget and authorization.    100
Millions 80
Change Order                          60
40
Thirteen change orders issued this quarter.                     Dollars in  20
Risks                                 0
Initial    Change Order    Spent
None identified at this time.
Budget Transfers
Photo
None this quarter


AIRPORT
14  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Main Terminal South Low Voltage
Project:   C800061   This project covers the renewal and     Status Snapshot Prior Report
Budget: $1,925,000   replacement of low voltage (600 volts   Delayed Schedule 1Q 08
Phase: Design      and below) electrical distribution      On Budget
0 Change Orders
Start: 06/28/2007      equipment in the southern part of the
Total Change Orders Amount:
Completion: TBD    Main Terminal.
$0
Significant Developments
Budget/Costs Incurred
Due to project deferral and the possibility of changes in site
conditions and building codes, the design phase changed from 100%    2.5
to 90% complete. A new Project Notebook is under development to
2
address scope of work, schedule, and budget for presentation to the    Millions 1.5
Investment Committee. Design Consultant submitted technical
documents that are currently being reviewed by project sponsor;        1
once comments are received work will continue on the Project        Dollars in 0.5
Notebook.
0
Authorized  Forecasted Costs Incurred
Schedule
The project was reactivated. Staff is in the process of determining
the scope of work, schedule and final design budget.             Construction Costs
Not Applicable
Budget
The project budget is being evaluated based on delays and scope    Photo
changes.
Change Order
None
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will
be required to add additional crews to complete work in a timely
manner. This area is a 24/7/365 operation. Sequencing of this work
is critical and electrical power has to be maintained without
interruptions.
Budget Transfers
None this quarter.

AIRPORT
Port of Seattle 4Q 2012 Report  15

FOURTH QUARTER REPORT, 2012
Airport Owned Gate Infrastructure
Project:   C800105      This project purchases and       Status Snapshot Prior Report
Delayed Schedule 3Q 12
Budget: $6,000,000      replaces passenger loading bridges
Phase: Construction     (PLB) at gates throughout the     On Budget
airport. The project is being        0 Change Orders
Start: 07/24/2007
performed in phases.           Total Change Orders Amount:
Completion: 06/30/2013                       $0
Significant Developments                    Budget/Costs Incurred
The old PLB removed from S10 in December of 2011 is being        6.1
refurbished by PCS. This refurbished PLB will replace the newly        6
manufactured PLB that was supposed to be installed at Gate D3 but    Millions 5.9
instead was diverted to replace the Delta owned PLB at S8 which      5.8
5.7
experienced catastrophic failure in July 2012.
Dollars in 5.65.5
Schedule                             5.4
Authorized  Forecasted Costs Incurred
The refurbishment of the old S10 PLB is in progress and is
scheduled to be delivered for installation at Concourese D in early
February 2013.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
16  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
C4 UPS System Improvements
Project:   C800107    Project will replace existing          Status Snapshot Prior Report
Budget: $2,336,000   Uninterruptible Power Supply (UPS)    Delayed Schedule 1Q 09
Phase: Construction  System, including batteries, with a new  On Budget
Start: 06/28/2007      new system located in the Airport      0 Change Orders
Completion: TBD     Combined Communications and      Total Change Orders Amount:
Command Center (C4).           $0
Significant Developments                    Budget/Costs Incurred
Due to project deferral and the possibility of changes in site
2.5
conditions and building codes, the design phase changed from 100%
to 90% complete. A new Project Notebook is under development to      2
address scope of work, schedule, and budget. The Notebook will be    Millions 1.5
presented to the Investment Committee. A Service Directive is in the
1
review process and expect Consultant to be approved mid third       Dollars in 0.5
quarter. A site visit will be conducted in the first quarter of 2013 to
review existing conditions and to determine any code and industry       0
Authorized  Forecasted Costs Incurred
changes that might affect the final design.
Schedule
The project was reactivated. Staff is in the process of determining    Construction Costs
the scope of work, schedule and final design budget.             Not Applicable
Budget                            Photo
The project budget is being evaluated based on delays and scope
changes.
Change Order
None
Risks
The C4 center is a 24/7/365 operation and sequencing of this work is
critical and electrical power has to be maintained without
interruptions. It is not known when the construction will proceed as 
this is specialized equipment and due to the complexity the new
system will require rigorous testing during the commissioning phase.
Budget Transfers
None this quarter
AIRPORT
Port of Seattle 4Q 2012 Report  17

FOURTH QUARTER REPORT, 2012
Runway 16C/34C Panel/Joint Sealant
Replacement
Status Snapshot
The scope of work will remove and   On Schedule
Project:   C800112      replace the pavement and joint seal  Under Budget
in areas on Runway 16C-34C.
Budget: $4,161,623                         2 Change Orders
Phase: Construction                        Total Change Orders Amount:
Start: 02/26/2008                                 $232,732
Completion: 09/01/2012
Budget/Costs Incurred
Significant Developments
6
Gary Merlino Construction was the low bidder. The intent of the
5
contract was to coordinate this work with an apron panel
Millions  4
replacement project, an airline realignment project, and a fuel
3
hydrant installation project all with similar work and timing.
2
Dollars in   1
Schedule
0
The 2012 replacement of runway panels is complete. Project is in         Authorized  Forecasted Costs Incurred
closeout. Any further work in 2013 will be at the Port of Seattle's
expense.
Construction Costs
Budget
The project forecast is within the approved budget and authorization.      4
Savings of approximately $700,000 is anticipated.
3
Millions
Change Order                           2
Two change orders were issued this quarter.
Dollars in    1
Risks                                  0
Initial   Change   Spent
No risks have been identified at this time.                                Orders
Budget Transfers
None this quarter                                    Photo



AIRPORT
18  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Concessions Unit Readiness Project
Project:   C800147      This project will upgrade         Status Snapshot Prior Report
Budget: $2,087,000      concession locations which were   Delayed Schedule    2Q 09
Phase: Close Out      previously vacated or slated to be   Under Budget
Start: 08/26/2008         vacated to Port standards for use    0 Change Orders
Completion: 06/30/2013   as specialty concession space.    Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Construction completed on this project on August 31, 2012. The
project is currently in close out. This will be the last quarterly report      1.5
for this project.
Millions  1
Schedule
The project is complete.                                  0.5
Dollars in 
Budget                             0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Savings of approximately $1,500,000 will be returned.
Construction Costs
Change Order
Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 4Q 2012 Report  19

FOURTH QUARTER REPORT, 2012
Gina Marie Lindsey (GML) Arrivals Hall
Concessions
This project will provide a new      Status Snapshot  Prior Report
Project:   C800148      retail-merchandising corridor in the  Delayed Schedule 1Q 11
Gina Marie Lindsey Arrivals Hall.    On Budget
Budget: $1,033,000
The project includes installing three   0 Change Orders
Phase: Design        Retail Merchandizing Units (RMUs)  Total Change Orders Amount:
Start: 11/20/2007         and providing utilities to a new      $0
Completion: TBD       approximate 25-seat restaurant
and bar.
Budget/Costs Incurred
Significant Developments                     1.2
1
The design for utilities was previously completed in 2009 but put on
0.8
hold due to market conditions. The Concessions group will review     Millions
0.6
plans for the new food-beverage concession for viability via a cost
0.4
analysis to be performed later in 2013.                        Dollars in 0.2
Schedule                             0
Authorized  Forecasted Costs Incurred
As previously reported, the project schedule delay was due to the
pending decision by the Business Development Group to proceed
with the concessionaire.                                Construction Costs
Not applicable
Budget
The project forecast is within the approved budget and authorization.  Photo
Change Order
None
Risks
Due to delay in schedule, bidding climate may change when the
project is bid and additional budget may be required.
Budget Transfers
None this quarter


AIRPORT
20  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
C60 - C61 BHS Modifications
Project:   C800168      The work planned under this      Status Snapshot
Budget: $10,969,000     project represents a critical      On Schedule
Phase: Design        component in providing improved   On Budget
Start: 06/01/2012         operational baggage in-line       0 Change Orders
Completion: 04/30/2014   screening at the south end of the   Total Change Orders Amount:
Airport and provide more baggage   $0
make-up capacity for airlines.
Budget/Costs Incurred
12
Significant Developments
10
Design is 30% complete. The design documents were sent to TSA      8
for review.
Millions
6
4
Schedule                            Dollars in  2
The project is currently on schedule.                           0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will    Construction Costs
be requested when the design and bid documents are completed.    Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 4Q 2012 Report  21

FOURTH QUARTER REPORT, 2012
Federal Inspection Services - New Primary
Inspection Booths
This project will replace existing     Status Snapshot  Prior Report
Project:   C800174      primary inspection booths for      Delayed Schedule 2Q 11
Customs and Border Protection in   On Budget
Budget: $2,000,000
the International Arrivals Federal    0 Change Orders
Phase: Construction     Inspection Services (FIS) facility in  Total Change Orders Amount:
Start: 07/27/2010         the South Satellite.             $0
Completion: 09/08/2011
Budget/Costs Incurred
Significant Developments
New signs are being procured to replace the defective signs.          2.5
2
Schedule                            Millions 1.5
The project is substantially complete. The current schedule for
1
completion of the replacement signs is during the second quarter of     Dollars in 0.5
2013.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
Not Applicable
None
Risks                               Photo
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
22  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Common Use Lounge Remodel
Status Snapshot
On Schedule
Project:   C800203      This project will relocate the Port's   On Budget
Budget: $1,061,000      common-use lounge from the     9 Change Orders
Phase: Close Out      mezzanine level to the departure   Total Change Orders Amount:
Start: 03/01/2011         level of the South Satellite.        $32,782
Completion: 02/28/2012   Improvements consist of new
finishes, new furnishings and other  Budget/Costs Incurred
minor cosmetic improvements.
1.064
1.063
Significant Developments
1.062   Millions
Project is in closeout awaiting asbuilts.
1.061
Schedule                            1.06 Dollars in 
Construction was completed in February 2012 and the lounge       1.059
opened on March 1, 2012.                                Authorized Forecasted Costs Incurred
Budget
The current project forecast is within the approved budget and       Construction Costs
authorization.
0.5
Change Order
None this quarter                                     Millions
Risks
Project is forecast to be completed within the current budget, but
without much remaining. If more soft costs hit the project than        Dollars in  0
anticipated, the project could run over budget.                        Initial  Change Order  Spent
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 4Q 2012 Report  23

FOURTH QUARTER REPORT, 2012
Security Exit Lane Breach Control - Phase 1
Project:   C800218      This project will procure and install   Status Snapshot
Budget: $950,000       new automated exit lane breach    On Schedule
Phase: Design        control equipment at the       On Budget
Start: 3/1/2012          Concourse B exit.             0 Change Orders
Completion: 9/30/2013                        Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
1
The design documentation was started in the fourth quarter of 2012.
0.8
Schedule                            Millions 0.6
The project is currently on schedule.                          0.4
Dollars in 0.2
Budget                             0
The project forecast is within the approved budget and authorization.       Authorized  Forecasted Costs Incurred
Change Order
Construction Costs
None                                 Not Applicable
Risks
If additional egress capacity is required by the permitting authorities,
additional budget will need to be requested.
Budget Transfers
None




AIRPORT
24  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Emergency Lighting - Parking
Status Snapshot
Project:   C800230      The purpose of this project is to    Delayed Schedule
Budget: $1,157,081      provide electrical infrastructure for   On Budget
Phase: Design        a new source of emergency power  0 Change Orders
Start: 07/24/2012         to feed the parking garage        Total Change Orders Amount:
Completion: 07/31/2014   emergency lighting circuits and    $0
ensure that code-required level of
egress illumination is provided for   Budget/Costs Incurred
safety.
6
Significant Developments                      5
Millions  4
The Service Directive with Casne for design was executed on
3
September 24, 2012. 60% design is completed and will proceed to
2
100%. The proposal for the emergency lighting portion of the project    Dollars in  1
by McKinstry through the State ESCO contract is due on March 1.
0
We will request funding from Commission for design and
Authorized  Forecasted Costs Incurred
construction for the lighting portion in March.
Schedule
Construction Costs
The project completion schedule was delayed five months due to    Not Applicable
decisions on scope delineations between the Casne and McKinstry
contracts.
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 4Q 2012 Report  25

FOURTH QUARTER REPORT, 2012
Terminal Escalators Modernization

Project:   C800237      This project will replace 42        Status Snapshot
Budget: $35,637,293     escalators in the Main Terminal,    On Schedule
On Budget
Phase: Construction    Concourse B, and South Satellite.
In addition, two new escalators will   93 Change Orders
Start: 11/02/2007
be installed at the South Satellite.    Total Change Orders Amount:
Completion: 07/01/2013                       $5,412,488
Significant Developments
Budget/Costs Incurred
Nine new escalators at the South Satellite and in the Main Terminal
were placed in service this quarter, for a total of 39. Replacement of     60
two escalators in South Satellite are expected to be in service in the     50
first quarter of 2013.                                       Millions 40
30
Schedule
20
The project is currently on schedule.                         Dollars in  10
0
Budget                               Authorized Forecasted  Costs
Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Change orders this quarter addressed reconciling force account       25
asbestos work and varying site conditions at the South Satellite.
20
Risks                                Millions 15
10
None identified at this time.
Dollars in   5
Budget Transfers                          0
Initial   Change Order   Spent
None
Cost of Construction Growth
Circumstances contributing to cost growth: differing site conditions
encountered at the South Satellite during the installation of the two
added escalators resulted in revisions to the architectural and
structural designs, increased cost of construction, and impacted the
critical path of the project circumstances contributing to cost growth:


26  Port of Seattle 4Q 2012 Report

Cost of Construction Growth (Cont.)
Differing site conditions encountered at the South Satellite during the installation of the two added
escalators resulted in revisions to the architectural and structural designs, increased cost of
construction, and impacted the critical path of the project subsequently extending the completion
date. In addition, differing site conditions have been encountered at all South Satellite escalators
required to be widened. Existing conditions examined by the Port of Seattle building department and
fire department have resulted in added scope of work to incorporate additional firesafing measures in
the areas surrounding the escalators prior to re-constructing the escalator enclosure and the upgrade
of existing handrails and guardrails to current code. The project continues to experience cost
increases due to state inspector imposed requirement for a hard barrier between escalators during
construction, correction of existing electrical that does not meet code but is adjacent to the new work,
and the removal of unanticipated asbestos.










AIRPORT
Port of Seattle 4Q 2012 Report  27

FOURTH QUARTER REPORT, 2012
Central Plant Pre-Conditioned Air
Project:   C800238     This project will provide a centralized
Budget: $46,635,000    pre-conditioned air (PC-Air) plant
Phase: Construction    (PCAP), associated heating and    Status Snapshot Prior Report
Start: 06/15/2009       cooling piping systems, and jet bridge  Delayed Schedule 3Q 12
Completion: 12/10/2012  terminal air handling units to serve   On Budget
airplanes with heating and cooling     139 Change Orders
while at the gates.                Total Change Orders Amount:
Significant Developments                    $6,582,163
The contractor has finished installation of major equipment and
piping in the PCAP. Equipment and system testing of PCAP started   Budget/Costs Incurred
in the fourth quarter. PC-Air equipment installed at 53 of 73 total
gates. Pipe and electrical conduit installation continue at the           48
Concourse C, Concourse D and North Satellite.                  46
Schedule                            Millions 44
42
Dollars in 
The original contract completion date was December 11, 2012. One     40
time extension of 37 days was approved. The contract completion      38
date is in January 2013; however, construction will not be completed.    36
CM is negotiating a new contract completion date of early third           Authorized  Forecasted Costs Incurred
quarter of 2013.
Budget                            Construction Costs
Negotiations with the contractor on potential change orders and
claims risk are in process. As negotiations proceed, potential budget      40
issues will be identified. Current project forecast including open
30
claims exceeds approved budget and authorization by approximately    Millions
20
Dollars in 
29%. Commission approved additional funding of $1,100,000 in the
fourth quarter. Staff will return to Commission to request additional
10
funding and authorization to execute change orders.
0
Change Order                             Initial Change Spent
Orders
Twenty-four change orders issued this quarter, the largest change
orders issued for piping and electrical site conflicts on the concourse
and at the gates.
Risks
There is budget risk based on the dollar amount of open potential
change orders and claims. There is schedule risk as there is not an
approved schedule.

28  Port of Seattle 4Q 2012 Report

Budget Transfers
From C800404 (Aeronautical Allowance)     $2,000,000
Cost of Construction Growth
Cost growth is still occuring due to shortcomings in the bid documents. Current cost of executed
Change Orders is 24.4% of the base contract price. The trended cost growth projection is currently
29% over bid price. Approximately 15% are related to error and/or ommissions (owner or designer),
9% are currently in some form of dispute. The remainder of the cost growth are due to site conditions,
discretionary tenant requested or scope changes and regulatory requirements respectively. The
current projections do not include any cost trending for potential claims due to late project completion
due to owner caused delay.










AIRPORT

Port of Seattle 4Q 2012 Report  29

FOURTH QUARTER REPORT, 2012
Security Checkpoint Cameras
Project:   C800242      This project has installed new      Status Snapshot Prior Report
Budget: $500,000       cameras to view passenger      Delayed Schedule 3Q 12
Phase: Construction     screening processes at passenger  On Budget
Start: 07/17/2011         security checkpoints.           0 Change Orders
Completion: 09/31/2012                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
0.52
Installation is complete at Checkpoints #4, #2, #3 & #5.              0.5
0.48
0.46   Millions
Schedule
0.44
The project was completed in September 2012, after a 3 month
0.42
delay, due to TSA installation of the new equipment and ordering of     Dollars in 0.4
parts.                                                0.38
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None at this time



AIRPORT
30  Port of Seattle 4Q 2012 Report

FOURTHH QUARTER RREPORT, 2012
Cargo 2 WWest Carggo Hardstand
Prooject:  C800247C          This project wwill enlarge the       Statuss Snapshott Prior Report
Buddget: $11,830,000     weestern cargoo hardstandd in the    Delayeed Schedulee 3Q 12
Phaase: Desiggn        Caargo 2 area, it includess buyout of  On Budget
Start: 09/25/22012         twoo cargo buiildings and tenant     0 Channge Orderss
Commpletion: 12/31/20114   relocations; reelocation off FAA     Total CChange Ordders Amounnt:
antenna, secuurity gate, aand guard    $0
shaack; and installation oof 400Hz in--
groound powerr.              Budgett/Costs Inccurred
15
Significant DDevelopmments
Carggo 2 will bee combined with Cargoo's 5 and 6 as a singlee
10
consstruction coontract. FAAA antenna relocation aagreement is to be      Millions
commpleted by the end of 22013.
5
Dollars in 
Schhedule
0
Buildding acquissition is schheduled for fall of 20133 with the teenant           Authorized  F o recasted Costs I n curred
reloccated in 2014. Designn is currently at 30% wwith anticipaated 60%
revieew in first qquarter of 20013. Demoolition of Blddg #2 is schheduled forr
first quarter of 22014 with hhardstand ccompletion scheduled for the     Construuction Cossts
secoond quarterr of 2014. TThe currentt schedule reflects thee combiningg  Not Appplicable
of CCargo 2, 5, aand 6 projects.
Photo
Buddget
The project foreecast is witthin approveed budget aand authoriization.
Chaange Ordder
Nonne
Rissks
Nonne identifiedd at this timee.
Buddget Trannsfers
Nonne.


AIRRPORT
Port of Seattle 4Q 2012 Report  31

FOURTH QUARTER REPORT, 2012
Vertical Conveyance Modernization Program -
Status Snapshot
Aeronautical                        Delayed Schedule
Perform modernization on 8       On Budget
Project:   C800251      elevators: SSAF, MT-2, MT-6, MT-   0 Change Orders
7, C-4, NSCF & 2 new elevators at   Total Change Orders Amount:
Budget: $9,773,150
S. Satelite, plus install cooling       $0
Phase: Design        packages on 11 existing hydraulic
Start: 10/25/2011         elevators throughout Main
Completion: 12/31/2015   Terminal.
Budget/Costs Incurred
Significant Developments
Phasing of the program has shown a critical link between            20
construction of two new elevators at South Satellite, which must be
15
completed prior to modernization efforts on SSB and SSC elevators.
Service Directives were executed for design of Phase I and for pre-
Millions 10
design of two new elevators at South Satellite. Installation of two new
elevators moved to Phase I, and elevators SSB, SSC & C4 moved to   Dollars in 5
Phase II. NorthSTAR project to consolidate all work at North Satellite
0
nessitating transfer of elevators C-4 and NSCF to NorthSTAR           Authorized Forecasted Costs Incurred
program. Still working out details of resulting scope and budget
impacts.
Construction Costs
Schedule                           Not Applicable
The project is scheduled to begin design in the second quarter of
2012; construction is scheduled to begin in the fourth quarter of
2013, with construction completion in the fourth quarter of 2015.
Budget
The project has been revised following Investment Committee (IC)
approval of revision of specific elevators in Phase I & Phase II. IC
approved revised scope and budget. Currently scheduled to request
additional design funds to include two new elevators at December
11, 2012 Commission Meeting. Authorization for construction funding
and authority to advertise for construction will be requested when the
design and bid documents are completed.
Change Order
None


32  Port of Seattle 4Q 2012 Report

Risks
Delays in siting two new elevators for South Satellite, will require re-siting of TSA passenger
checkpoint at SSAT.
Budget Transfers
From C800404 (Aeronautical Allowance)    $5,929,850












AIRPORT
Port of Seattle 4Q 2012 Report  33

FOURTH QUARTER REPORT, 2012
Parking System Replacement
Project:   C800253      This project replaces the current    Status Snapshot Prior Report
Budget: $6,777,000      Parking Revenue Control System,   Delayed Schedule 2Q 12
Phase: Construction     which manages parking access    On Budget
Start: 04/06/2010         and revenue collection in the      6 Change Orders
Completion: 08/31/2012   Airport's Main Parking Garage.    Total Change Orders Amount:
$173,550
Significant Developments                    Budget/Costs Incurred
Scheidt & Bachmann's (S&B) completed installation of the physical
components of the system. Kimley Horn performed Lane           12
Acceptance Tests (LAT) on the installed components. Currently       10
working to resolve reporting and system issues associated with final    Millions 8
system development and transition to final testing.                  6
4
Schedule                            Dollars in  2
0
Several issues during the initial contracting and development phases
Authorized  Forecasted Costs Incurred
of the project caused schedule delays, which were previously
reported.
Budget                            Construction Costs
None this quarter
The project forecast is within the approved budget and authorization.
Photo
Change Order
Two change orders issued this quarter for $45,620.
Risks
This project is behind schedule. The Port is engaging the Contractor
to address the system issues.
Budget Transfers
None this quarter



AIRPORT
34  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Aircraft RON Parking USPS Site
Status Snapshot Prior Report
Delayed Schedule     1Q 11
Project: C800254        This project will prepare the site for
On Budget
Budget: $45,906,000     the construction of hardstands for
4 Change Orders
Phase: Closeout       use as Remain Overnight (RON)
Total Change Orders Amount:
Start: 08/26/2008        parking of aircraft at the Cargo 5
-$150,211
area.
Completion: 12/31/2014
Significant Developments                    Budget/Costs Incurred
Demolition of the USPS building is complete and the project is        50
closed out. With the design authorization of Cargo 2 and 6
40
approved by the Port of Seattle Commission on September 25,
2012, they will be added to Cargo 5 to produce a single construction    Millions 30
contract with 3 cargo areas.                                20
Dollars in  10
Schedule
0
Project is at 30% design with anticipated 60% review in the first           Authorized  Forecasted Costs Incurred
quarter of 2013. Construction is schedule to begin first quarter of
2014. Cargo 5 is scheduled to be completed by the end of the third
quarter of 2014.                                     Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget.              Photo
Change Order
None this quarter
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 4Q 2012 Report  35

FOURTH QUARTER REPORT, 2012
Port-Owned Loading Bridge Renewal &       Status Snapshot
Replacement                     On Schedule
On Budget
This project will allow the Airport to   0 Change Orders
Project:   C800267
replace or refurbish Port-owned     Total Change Orders Amount:
Budget: $2,405,000
Passenger Loading Bridges (PLBs)  $0
Phase: Design        that have reached the end of their
Start: 02/28/2012         service life.
Completion: 12/31/2014
Budget/Costs Incurred
Significant Developments                      3
The PLB and fixed walkway removal and replacement at S3 was      2.5
awarded to Airport Mechanical. PCS will replace the foundations for     2
the fixed walkway and PLB. The design for the S12 refurbishment is    1.5
Millions
on schedule with the 90% drawings and specifications expected in      1
Dollars in 
early February 2013. The design for the S4 refurbishment will kick      0.5
off toward the end of the first quarter of 2013.                      0
Authorized  Forecasted Costs Incurred
Schedule
The project is currently on schedule.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

36  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Stage 2 Mechanical Energy Implementation
Status Snapshot Prior Report
Project:   C800268      This project will improve the energy  Delayed Schedule 1Q 12
Budget: $2,872,900.00    performance of the mechanical    On Budget
Phase: Design        infrastructure systems at the     1 Change Order
Start: 10/01/2011         Airport.                    Total Change Orders Amount:
Completion: 03/25/2013                       $8,235.09
Budget/Costs Incurred
Significant Developments                      4
The contract documents have been finalized. University Mechanical     3
Contractors (UMC) submitted 90% design. Comment responses      Millions
2
have been resolved. Waiting for verification of Abatement scope,
budget, and schedule prior to issuing Notice to Proceed with         Dollars in  1
construction to the State of Washington.
0
Authorized  Forecasted Costs Incurred
Schedule
The design schedule was delayed by three months during the
contract document review, as previously reported.
Construction Costs
Budget
3
The forecast is within the approved budget and authorization.          2.5
Change Order
Millions   2
1.5
A Change Order was written to authorize expidited fees for             1
equipment and systems needed for the Delta Ticket Counter project.    Dollars in  0.5
0
Risks                                   Initial Change Spent
Orders
None identified at this time.
Budget Transfers
From C800404 (Aeronautical Allowance)         $80,000


AIRPORT

Port of Seattle 4Q 2012 Report  37

FOURTH QUARTER REPORT, 2012
8th Floor Weatherproofing
Status Snapshot Prior Report
Delayed Schedule 1Q 12
Project:   C800274      This project includes removal and   On Budget
Budget: $10,050,000     replacement of the floor covering   10 Change Orders
Phase: Construction     system on the 8th floor of the STIA  Total Change Orders Amount:
Start: 03/23/2010         parking garage and repair or       $63,010
Completion: 12/31/2013   replacement of expansion joints
and flashings.
Budget/Costs Incurred
Significant Developments                     15
The Port's contractor, PCL Construction completed construction on
Sections D and E of the garage. The Port has requested a two-year    Millions 10
construction schedule, which would extend the completion to the end
of 2013.                                            5
Dollars in 
Schedule                             0
Authorized  Forecasted Costs Incurred
The current schedule is for project completion at the end of 2013
with work to resume in April.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.
8
Change Order                           6
Millions
No change orders issued this quarter.                         4
Dollars in   2
Risks
This is a weather-dependent project.                          0
Initial    Change Order    Spent
Budget Transfers
None this quarter
Photo



AIRPORT
38  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Common Use Equipment Expansion (CUSE)
Project:   C800276      This project installs flexible       Status Snapshot
Budget: $2,581,000      passenger processing         On Schedule
Phase: Close Out      infrastructure and equipment at the  On Budget
Start: 09/01/2009         airline gates at some South       0 Change Orders
Completion: 09/30/2012   Satellite gates.            Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
3
The contractor completed work on schedule at the end of August.
2.5
Project close out is in progress.                             Millions  2
Schedule                            Dollars in  1.5
1
The project is in close out.
0.5
Budget                              0
Authorized       Forecasted      Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
None
0.7
Risks                                 0.6
Millions    0.5
None identified at this time                                   0.4
Dollars in     0.3
Budget Transfers                          0.2
0.1
None this quarter.                                       0
Initial        Change Orders        Spent
0.1




AIRPORT

Port of Seattle 4Q 2012 Report  39

FOURTHH QUARTER RREPORT, 2012
Lonng-Termm Cell Phhone Lot
Prooject:  C800324C          Coonstruct a nnew cell phoone waitingg  Statuss Snapshott
Buddget: $1,7768,000     lot to replace the existingg lot that is  On Schedule
Phaase: Desiggn        being displaced, and connstruct a   On Budget
Start: 12/11/22012         traaffic control roundabouut adjacent   0 Channge Orderss
Commpletion: 06/30/20114   to the lot.              Total CChange Ordders Amounnt:
$0
Budgett/Costs Inccurred
Significant DDevelopmments
2
Fieldd survey coompleted foor use in sitee design.
1.5
Schhedule                            Millions
1
Design is undeerway and too be completed in the third quarter of 2013.
Connstruction wwill start in thhe fourth quuarter of 20013 with commpletion in   Dollars in 0.5
the ssecond quaarter of 2014.                               0
A uthorized  For ecasted Costs I n curred
Buddget
The project foreecast is witthin the appproved budgget. Authorization of
consstruction funding and aauthority too advertise ffor construcction will    Construuction Cossts
be requested wwhen the bidd documennts are completed.           Not Appplicable
Chaange Ordder                         Photo
Nonne
Rissks
Scheedule unceertainties related to rouundabout deesign revieww and
permmit acquisitiion time reqquirement.
Buddget Trannsfers
Nonne this quarter



AIRRPORT
40  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Two New CTE Freight Elevators
Status Snapshot Prior Report
Delayed Schedule 2Q 12
Project:   C800334      Provide two new freight elevators   On Budget
Budget: $8,318,000      to support concession operations in  0 Change Orders
Phase: Design        the Central Terminal/Pacific      Total Change Orders Amount:
Start: 08/05/2011         Marketplace.                $0
Completion: 07/31/2014
Budget/Costs Incurred
10
Significant Developments
8
The project design commenced third quarter 2011. Currently 100%     Millions 6
design is complete. Interferences with ongoing Pre-Conditioned Air
4
Project and Alaska Air Group (AAG) relocation program caused
scoping changes and redesign efforts. Finalizing documents for       Dollars in  2
issuing Invitation to Bid, in late January 2013.                      0
Authorized  Forecasted Costs Incurred
Schedule
Construction is anticipated to commence in second quarter of 2013.
As previously reported, the project is anticipating a one-year delay    Construction Costs
due to scope changes included in the redesign efforts, and delays in   Not Applicable
reviews.
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
There is a potential risk due to unknown conditions where the freight
elevator foundations will be constructed, i.e., outside of the Central
Terminal building envelope. Installation and relocation of grease
interceptors will require significant coordination during construction
with Horizon Air and their current use of the site for their ground
service equipment.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 4Q 2012 Report  41

FOURTH QUARTER REPORT, 2012
Electrical Ground Support Equipment (EGSE)
Electrical Charge Stations                Status Snapshot Prior Report
Delayed Schedule 1Q 12
On Budget
Airport-wide electrical charging     0 Change Orders
Project:   C800335      system for electrical ground       Total Change Orders Amount:
Budget: $30,198,000     support equipment (EGSE) at the   $0
Phase: Design        Concourses and the North and
Start: 10/26/2010         South Satellites.
Completion: 09/30/2014
Significant Developments
Design and construction consists of three parts: 1) Installation of 40   Budget/Costs Incurred
demonstration charge stations on Concourse C2 for Horizon Airlines.
This phase is commissioned and Horizon is in the process of
receiving their new electric GSE vehicles and will be using the new      35
chargers during the commissioning of the new GSE vehicles; 2)        30
Phase 1 includes balance of Concourse C charge stations,         Millions  25
20
Concourse D and North Satellite. Public bids received and the       Dollars in   15
construction implementation contract was executed with Lydig
10
Construction. Notice to proceed is expected to be issued by March 1,
5
2013; and 3) Phase 2 includes Concourse A, Concourse B and        0
Authorized       Forecasted      Costs Incurred
South Satellite - Service Directive is executed and design is
progressing with the 30% design review nearing completion.
Schedule                           Construction Costs
Demonstration charge station construction phase completed end of   Not Applicable
September 2012 with Commissioning by mid October 2012; Phase 1
Construction completion scheduled for September 30, 2013; Phase 2
construction scheduled for completion by end of 2014.
Budget
The project forecast is within the approved budget. Authorization for
the construction funding and authority to advertise for construction
will be requested when the design and bid documents are
completed.
Change Order
None


42  Port of Seattle 4Q 2012 Report

Risks
Coordinate with other airfield projects and Airline Gate Realignment program. Budget and schedule
may impact project implementation and completion.
Budget Transfers
None this quarter.











AIRPORT
Port of Seattle 4Q 2012 Report  43

FOURTH QUARTER REPORT, 2012
Claim Device 14 & Lower Inbound
Status Snapshot
Project:   C800374      This project will replace the slope-   Delayed Schedule
Budget: $3,900,000      plate bag claim device 14 and     On Budget
Phase: Construction     associated controls, in addition to   0 Change Orders
Start: 04/01/2011         removing the lower feed conveyor   Total Change Orders Amount:
Completion: TBD       and replacing it with a new      $0
overhead feed.
Budget/Costs Incurred
5
Significant Developments
4
The baggage equipment was on the dock in New York the day the     Millions 3
hurricane arrived. The ports were closed for a couple of weeks after
the storm. We received the baggage claim device late. Some of the     2
equipment sat in salt water for an extended period of time. The       Dollars in  1
project team requested that all parts damaged due to flooding be
0
replaced. We expect all the new parts to be onsite after the first of         Authorized  Forecasted Costs Incurred
the year. We are working with our contractor on a recovery schedule.
Schedule                           Construction Costs
The project was delayed due to Hurricane Sandy. Equipment was on
the dock at the Port of New York the day of the hurricane.             1.2
1
Budget                             Millions 0.8
0.6
The project forecast is within the approved budget and authorization.
0.4
Change Order                          Dollars in  0.2
0
None                                      Initial Change Spent
Orders
Risks
None identified at this time.
Budget Transfers
C800404 (Aeronautical Allowance)          $1,000,000


AIRPORT

44  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Vertical Conveyance Modernization Aero Ph 2
Project:   C800375      Perorm modernization of 3       Status Snapshot
Budget: $17,910,020     elevators: MT-3, MT-4 and MT-5 in  On Schedule
Phase: Design        Main Terminal, plus 12 escalators:  On Budget
Start: 12/11/2012         4 at Concourse C STS station, 4 at   0 Change Orders
Completion: 12/31/2015   NSAT STS station and 4 at      Total Change Orders Amount:
Skybridge 6.                 $0
Budget/Costs Incurred
Significant Developments
20
Phasing of the program has shown a critical link between            18
16
construction of NorthSTAR project elements at both Concourse C
14
and NSAT STS Station. Subsequent to Commission approval for       12
Millions
design authorization, parsing of 8 escalators from Aero Ph 2 is being   Dollars in   10
8
developed to transfer these escalators to NorthSTAR program.Still       6
4
working out details of resulting scope and budget impacts.
2
0
Authorized       Forecasted      Costs Incurred
Schedule
The project is scheduled to begin design in first quarter 2013;
construction is scheduled to begin in first quarter 2014 with
Construction Costs
construction completion in fourth quarter 2015.
Not Applicable
Budget
The project has been revised following Investment Committee (IC)
approval of revision of specific elevators in Ph 1 and Ph 2.
Commission authorized design at the December 11, 2012 meeting.
Authorization for construction funding and authority to advertise for
construction will be requested when the design and bid documents
are completed. Subsequent consolidation of NorthSTAR project
elements will result in significant budget and scope changes, still to
be finalized.
Change Order
None
Risks
Delays in final scope hinder design start.
Budget Transfers
From C800404 (Aeronautical Allowance)        $3,344,980
AIRPORT
Port of Seattle 4Q 2012 Report  45

FOURTH QUARTER REPORT, 2012
South Satellite HVAC, Lights, and Ceiling
Replacement                     Status Snapshot
This project will replace the Heating  On Schedule
Project:   C800376      Ventilation, lighting and ceiling     On Budget
systems in the South Satellite.      0 Change Orders
Budget: $6,500,000
Total Change Orders Amount:
Phase: Design                            $0
Start: 7/24/2012
Completion: 07/31/2016
Budget/Costs Incurred
Significant Developments
40
Commission approved funding for design. A design Service Directive
30
was issued to CDI Engineers. They started work in September. On     Millions
site system testing to verify the existing facility characteristics          20
Dollars in 
completed in December. Design completion expected in the first
quarter of 2014.                                        10
0
Schedule                               Authorized Forecasted Costs Incurred
The project is currently on schedule.
Budget
The project forecast is within the approved budget. Authorization of   Construction Costs
construction funding and authority to advertise for construction will    Not Applicable
be requested when the bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
46  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Baggage Handling System (C22-C1, MK1, and
TC3)
This project will replace the ticket    Status Snapshot
Project:   C800382      counter (TC3) conveyors and      On Schedule
declines, reroute the conveyors of   On Budget
Budget: $4,750,000
the C-22 system and connect it to   9 Change Orders
Phase: Construction     the C-1 screening system, replace  Total Change Orders Amount:
Start: 03/01/2011         the existing makeup (MK1) device,   $196,922.00
Completion: 05/31/2013   and install a new odd size baggage
system.                  Budget/Costs Incurred
8
6
Significant Developments                     Millions
4
MD Moore Company completed the new makeup unit and ticket
counter conveyor for the American, JetBlue and Frontier airline       Dollars in  2
moves. The project team will be commissioning the equipment the
0
first week of January and have it ready for operation.                 Authorized Forecasted  Costs
Incurred
Schedule
The project is currently on schedule.                        Construction Costs
Budget                              2
The project forecast is within the approved budget and authorization.     1.5
Millions
1
Change Order
There are currently nine change orders in process.                Dollars in  0.5
0
Risks
Initial   Change   Spent
None identified at this time.                                           Orders
Budget Transfers
None this quarter.
Cost of Construction Growth
Three changes represent the majority of the cost growth: 1) Since
POS no longer required replacement of the existing C1-CS1
curbside conveyor, it was removed rather than replaced;


Port of Seattle 4Q 2012 Report  47

Cost of Construction Growth (Cont.)
2) The contract design to replace make-up device MK1 did not include POS ergonomic standards for
this kind of device; and 3) the original contract design for the conveyors in the C1-CS2 conveyor line
create unsafe electrical and mechanical conditions for maintenance workers. Several other smaller
changes include fire sprinkler and architectural revisions, including a credit to remove a small scope
of work. None this quarter












AIRPORT
48  Port of Seattle 4Q 2012 Report

FOURTHH QUARTER RREPORT, 2012
Cargo 6 Ennhancemments
Prooject:  C800390C          This project wwill enlarge the Cargo   Statuss Snapshott
Buddget: $6,4428,000     6 ooff-gate harrdstand to aallow     Delayeed Schedulee
Phaase: Desiggn        simmultaneous nose-loadiing of wide--  On Budget
Start: 09/25/22012         body freight aaircraft as wwell as      0 Channge Orderss
Commpletion: 12/31/20114   proovide fuel hhydrant andd ground   Total CChange Ordders Amounnt:
power capabiilities.              $0
Budgett/Costs Inccurred
Significant DDevelopmments
8
Carggo 6 will bee combined with Cargoo's 2 and 5 as a singlee
consstruction coontract.                                     6
Millions
4
Schhedule
Design is curreently at 30%% with anticipated 60%% review in tthe first      Dollars in  2
quarrter of 20133. Construcction is scheduled to bbegin late summer
0
20144 with comppletion in thhe forth quaarter of 2014. The currrent            Authorized  F o recasted Costs I n curred
scheedule refleccts the combining of CCargo 2, 5, aand 6 projeects.
Buddget                           Construuction Cossts
The project foreecast is witthin the appproved budgget and autthorization.  Not Appplicable
Chaange Ordder                         Photo
Nonne this quarter
Rissks
Nonne identifiedd at this timee.
Buddget Trannsfers
Nonne this quarter



AIRRPORT
Port of Seattle 4Q 2012 Report  49

FOURTH QUARTER REPORT, 2012
RW16C/34C Reconstruction Design
Status Snapshot
On Schedule
Project:   C800406      This project will produce the 60%   On Budget
Budget: $669,000       design for the runway 16C/34C    0 Change Orders
Phase: Design        reconstruction. The design will    Total Change Orders Amount:
Start: 05/04/2010         include utilities, runway status      $0
Completion: TBD       lights, and other scope items
related to the project.            Budget/Costs Incurred
Significant Developments                     0.8
The 60% design was issued in December 2010. Incorporation of       0.6
comments on the 60% design work has been completed.          Millions
0.4
Schedule                            Dollars in 0.2
Staff will return to Commission for authorization of the remaining
0
design funds in mid-2014. The forecast will be reassessed when         Authorized Forecasted Costs Incurred
staff returns to the Commission for authorization of the final design
funds.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
50  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
South Satellite Concessions Project
Status Snapshot Prior Report
Delayed Schedule 3Q 11
Project:   C800412      This project will demolish and      On Budget
Budget: $2,227,400      relocate the existing duty free shop,  0 Change Orders
Phase: Construction     electric/communications to support  Total Change Orders Amount:
Start: 01/01/2011         a temporary duty free location, and   $0
Completion: 09/30/2013   construct a new food and beverage
shell space in the South Satellite at
Sea-Tac Airport.
Budget/Costs Incurred
Significant Developments                      2
This project has completed the abatement of the new duty free        1.5
space. Turn over of the space is on schedule for February of 2013.     Millions
1
The project will then take a break until the duty free tenant builds out
their space.                                           Dollars in 0.5
Schedule                             0
Authorized  Forecasted Costs Incurred
As previously reported, the design concept alternatives required
more extensive review than anticipated. The new concept allows the
existing duty free to remain operational during construction, but      Construction Costs
requires a longer construction period.                       Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
This project schedule is tied closely to the Duty Free Request for
Proposal.
Budget Transfers
To C800466 (SSAT - Additional Gate Lobby)      $450,000


AIRPORT
Port of Seattle 4Q 2012 Report  51

FOURTH QUARTER REPORT, 2012
Access Control Door Additions
Status Snapshot Prior Report
Delayed Schedule 3Q 12
Project:   C800414      This project will provide biometric   Forecast Overrun
Budget: $1,480,000      access controls and security     0 Change Orders
Phase: Design        cameras at airport terminal doors.   Total Change Orders Amount:
Start: 09/27/2011                                 $0
Completion: 08/30/2013
Budget/Costs Incurred
2
Significant Developments
1.5
Construction documents were completed and are ready to bid.        Millions 1
Schedule
0.5
The project was advertised for bid in May 2012 and a single bid, 48%   Dollars in 
0
above the engineer's estimate, was received and rejected. The           Authorized Forecasted Costs Incurred
project was then divided into two parts, re-designed and will be rebid
in November. The North Satellite work has been moved into the
NSAT project to avoid potential additional construction costs to re-    Construction Costs
install North Satellite access controls if gates are reconfigured during  Not Applicable
the NSAT project. The additional time needed to transfer the North
Satellite scope of work and budget to NorthSTAR program would
cause the bid award process to occur over the December 2012
holiday period and additional time will be needed for anticipated
holiday delays by the contractor.
Budget
Approximately $800,000 of scope and budget for the North Satellite
work was transferred out of this project with Commission
authorization. Additional budget (approximately $480,000) was
requested due to the added direct construction costs that were
missing from the previous cost estimate; the increased soft costs for
the duplicated efforts to re-design and re-bid; and the additional soft
costs to break the project into two parts with two different bid and
construction activities.
Change Order
None
Risks
None identified at this time.

52  Port of Seattle 4Q 2012 Report

Budget Transfers
To C800556 (NSAT Renov NSTS Lobbies)  $800,000
From C800404 (Aeronautical Allowance)     $480,000













AIRPORT
Port of Seattle 4Q 2012 Report  53

FOURTH QUARTER REPORT, 2012
Airfield Lighting Control and Monitoring System
Status Snapshot
(ALCMS) Upgrades                  On Schedule
Provide modifications to the Airfield   On Budget
Project:   C800415      Lighting Control and Monitoring    0 Change Orders
System to update, enhance and    Total Change Orders Amount:
Budget: $2,129,144
stabilize the system to meet the     $0
Phase: Construction     latest FAA specifications.
Start: 01/01/2011                                Budget/Costs Incurred
Completion: 12/31/2014
2.5
2
Significant Developments                     Millions 1.5
Liberty Airport Systems was awarded the design contract. The 60%
1
Submittal Design Review is scheduled for February 2013. Liberty
Dollars in 0.5
designed similar system with legacy equipment at Vancouver, B.C.
airport.                                                    0
Authorized  Forecasted Costs Incurred
Schedule
The project is currently on schedule.                        Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None this quarter
Risks
Coordination with on-going airfield operations is a consideration.
The Port is also working to eliminate unplanned outages when
transitioning from the older computer platform to the new one.
Budget Transfers
None this quarter.



AIRPORT
54  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Lagoon 3 Bird Wires
Status Snapshot
On Schedule
Project:   C800417      This project will reduce access by   On Budget
Budget: $1,833,000      waterfowl to the industrial       6 Change Orders
Phase: Construction     wastewater system Lagoon 3,     Total Change Orders Amount:
Start: 10/11/2011         which is located near the south end  $60,896.19
Completion: 10/31/2012   of the airfield.
Budget/Costs Incurred
2
Significant Developments
1.5
Nordic Construction was the low bidder. The contractor began work    Millions
1
in July 2012.
Dollars in 0.5
Schedule
0
Major construction is complete. Cables will be re-tensioned in            Authorized  Forecasted Costs Incurred
February 2013.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
1
Change Order                           0.8
None this quarter.                                     Millions  0.6
Dollars in 
0.4
Risks
0.2
No risks have been identified at this time.                         0
Initial   Change   Spent
Budget Transfers                                Orders
None this quarter
Photo
Cost of Construction Growth
Two change orders (CO) are the primary reason for the cost growth
to date. A CO, which compensated the contractor for additional costs
for adding a galvanized finish to the structural steel, and a CO that
directs the contractor to provide additional materials that are needed
to complete the installation of the bird netting and allows
performance of future maintenance on the bird netting. Both of these
change orders were the result of a design error or omission.

AIRPORT
Port of Seattle 4Q 2012 Report  55

FOURTH QUARTER REPORT, 2012
Federal Inspection Service Improvements -
Status Snapshot
Phase 1                         Delayed Schedule
Short Term Improvements to the    On Budget
Project:   C800426      Federal Inspection Service area at   0 Change Orders
the South Satellite to improve      Total Change Orders Amount:
Budget: $1,041,000
through put and improve conditions  $0
Phase: Design        for passengers waiting in the
Start: 04/01/2012         International Corridor prior to
Completion: 12/31/2013   Primary Inspection.
Budget/Costs Incurred
Significant Developments                     1.2
1
A 60% design phase was added to further explore layouts at the
Millions 0.8                                                                                 passport control and checkpoint areas.
0.6
Schedule                             0.4
Dollars in 0.2
Addition of a 60% design phase will delay completion of this project.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

56  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Doug Fox Lot Service Upgrades
Project:   C800451      Construct a new drainage system,   Status Snapshot
Budget: $6,073,000      asphalt resurfacing, improved lot   Delayed Schedule
Phase: Design        lighting, new building, and road    On Budget
Start: 02/01/2012         signage to improve lot appearance,  0 Change Orders
Completion: 05/31/2014   function, and revenue generation.   Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
8
Key decisions on building design and signage were made and
6
construction drawings are progressing towards 90% completion.      Millions
4
Schedule
2
The construction is planned to start in July 2013 and be completed in    Dollars in 
Spring 2014. The project completion is delayed 7 months due to        0
weather restrictions on when asphalt can be poured.                  Authorized Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of   Construction Costs
construction funding and authority to advertise for construction will    Not Applicable
be requested when the bid documents are completed.
Photo
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 4Q 2012 Report  57

FOURTH QUARTER REPORT, 2012
Concourse D Common Use Environment
Status Snapshot Prior Report
Delayed Schedule 3Q 11
Project:   C800455      This project installs a common-use  On Budget
Budget: $4,250,000      environment at all gates on      0 Change Orders
Phase: Construction     Concourse D. Scope includes new  Total Change Orders Amount:
Start: 03/01/2011         communications infrastructure,     $0
Completion: 04/30/2013   casework built to a new Airport
standard, new carpet, wall        Budget/Costs Incurred
coverings and task lighting.
5
4
Significant Developments
Millions  3
Gates D1, D2, and D5 have been completed in addition to gates D8
and D9.                                        2
Dollars in   1
Schedule
0
To date the contractor has met their interim project milestones.           Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Change Order                           1.5
None
Millions   1
Risks
0.5
Despite inclusion of the schedule milestones referenced above, the     Dollars in 
contractor is going to be challenged to keep the project on schedule
0
due to the long lead times for casework fabrication.                     Initial  Change  Spent
Orders
Budget Transfers
None this quarter



AIRPORT

58  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
2011-2013 Roof Replacement Program
Status Snapshot
On Schedule
Project:   C800459      This project will remove and      On Budget
Budget: $4,777,000      replace the roofing systems on the  0 Change Orders
Phase: Design        fire station and north end of the    Total Change Orders Amount:
Start: 07/01/2011         main terminal.                $0
Completion: 10/31/2013
Budget/Costs Incurred
5
Significant Developments
4
This project will go to the Commission for authorization to advertise
for construction in January 2013.                            Millions 3
2
Schedule                            Dollars in  1
The project is currently on schedule.                           0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization for
construction funding and authority to award for construction will be    Construction Costs
requested when the design and bid documents are completed.
0.5
Change Order                           0.4
None                                  Millions 0.3
0.2
Risks
Dollars in   0.1
None at this time
0
Initial   Change   Spent
Budget Transfers                                Orders
To C800404 (Aeronautical Allowance)        $118,000




AIRPORT
Port of Seattle 4Q 2012 Report  59

FOURTH QUARTER REPORT, 2012
Industrial Waste Treatment Plant (IWTP) Fiber
Installation
Install new Single Mode Fiber cable
Project:   C800461      from Main Terminal to IWTP and    Status Snapshot Prior Report
Gate E-45.                 Delayed Schedule 3Q12
Budget: $514,000
Forecast Overrun  3Q 12
Phase: Design                            0 Change Orders
Start: 03/01/2012                                 Total Change Orders Amount:
Completion: TBD                           $0
Significant Developments                    Budget/Costs Incurred
The Fiber Optic Cable has been installed from Main Terminal to the
new equipment termination cabinet near the Alaska Hangar.         0.6
Connectivity to Gate E-45 is complete. Information and             0.5
Communications Technology Group is developing the             0.4
communications portion of the project scope. Use of existing          0.3
in Millions
conduits from the equipment pad to the IWTP was based upon using    0.2
conduits, which are shared with FAA fiber optic cable. FAA has       Dollars 0.1
declined to allow co-use of existing conduits. The project will           0
continue to explore possible fiber routes with FAA.                    Authorized  Forecasted Costs Incurred
Schedule
The Port is investigating alternative means to continue fiber         Construction Costs
installation to the IWTP. This will result in a schedule delay.         Not Applicable
Budget
The project will require additional budget and authorization. The Port
is working up cost of alternative means and routes to continue
connectivity from the new equipment cabinet to the IWTP. Once the
design for revised route is completed, revised scope and costs can
be developed.
Change Order
None
Risks
Possible underground boring for new conduits beneath Taxiway "B"
is being investigated.
Budget Transfers
None this quarter.
AIRPORT
60  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
South Satellite - Additional Gate Lobby
Status Snapshot Prior Report
Delayed Schedule 3Q 12
Project:   C800466      Demolition of glass partitions,      On Budget
Budget: $1,515,000      restrooms, relocation of gate     0 Change Orders
Phase: Design        podiums new flooring, ceilings and  Total Change Orders Amount:
Start: 11/01/2010         infrastucture to provide additional    $0
Completion: 09/15/2013   gate lobby in the South Satellite.
Significant Developments                    Budget/Costs Incurred
Demolition of the restrooms is complete. The space was turned over
for operational use as a temporary seating area as scheduled. The
next phase of this project is due to resume in June of 2013 after the     2.5
associated duty free tenant build out is complete.                  2
Millions 1.5
Schedule
1
As previously reported, the project delay was caused by delayed      Dollars in 0.5
design negotiations and contracting. Additionally, a longer design
0
period is required due to dependency on the South Satellite
Authorized  Forecasted Costs Incurred
Concessions Project (C800412).
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
2
Change Order
1.5
None                                  Millions
1
Risks
Dollars in   0.5
This project is tied closely to the Duty Free RFP in that this project is
closely aligned with the South Satellite Concessions Project.            0
Initial   Change   Spent
Orders
Budget Transfers
From C800412 (South Sat Concessions Project)    $450,000


AIRPORT
Port of Seattle 4Q 2012 Report  61

FOURTH QUARTER REPORT, 2012
Passenger Loading Bridge Replacement -
Airline Realignment
This project entails Passenger
Project:   C800467      Loading Bridge (PLB)
replacements associated with the    Status Snapshot
Budget: $14,874,000
one-time airline realignment (AR).    On Schedule
Phase: Design        The work will take place at      On Budget
Start: 04/12/2011         Concourse D and Concourse B.    0 Change Orders
Completion: 09/30/2013                       Total Change Orders Amount:
$0
Significant Developments
The work at Concourse D continues. The replacement of bridges D1  Budget/Costs Incurred
and D2 was completed on time. The refurbishment of Gate D5 was
also completed on schedule; however, an issue with the controls       20
programming took this bridge out of service for two weeks until the
15
problem was resolved.                                Millions
10
The bid for the work at B1 and B11 was awarded to Lydig
Dollars in   5
Construction and work is on track to begin as scheduled at the end
of January 2013.                                      0
Authorized   Forecasted  Costs Incurred
Work at North Satellite will now take place under the NorthSTAR
project.
Construction Costs
Schedule
The project is currently on schedule. Commission approval for each      2.5
phase is being requested separately.                           2
Millions  1.5
Budget
1
The project forecast is within the approved budget. Authorization of
Dollars in   0.5
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.        0
Initial   Change   Spent
Orders
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter
AIRPORT62  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Exterior Gate Improvements (Airline
Realignment)
This project will install new fuel      Status Snapshot
Project:   C800472      hydrant pits and aircraft docking    On Schedule
systems at exterior gates for the     On Budget
Budget: $4,064,000
airline reallocation program.        0 Change Orders
Phase: Construction                        Total Change Orders Amount:
Start: 06/01/2011                                 $0
Completion: 10/31/2012
Budget/Costs Incurred
Significant Developments                      5
The project construction was completed in the fourth quarter of 2012.     4
Millions  3
Schedule
2
The project was completed on schedule.                     Dollars in  1
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
None                                 Not applicable
Risks
If the fuel system lease amendment is not finalized, it could limit the
use of the new fuel hydrants.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 4Q 2012 Report  63

FOURTH QUARTER REPORT, 2012
CUSE at Gates & Ticket Counters- Airline
Realignment
Provide common use equipment,    Status Snapshot Prior Report
Project:   C800473      casework and infrastructure at     Delayed Schedule 3Q 12
gates and ticket counters for the     On Budget
Budget: $2,371,000
Airline Realignment program.      0 Change Orders
Phase: Construction                        Total Change Orders Amount:
Start: 04/02/2012                                 $0
Completion: 05/01/2013
Budget/Costs Incurred
Significant Developments                      3
The casework was fabricated and delivered to the airport terminal for    2.5
installation.                                                Millions 2
1.5
Dollars in 
Schedule                             1
The project schedule was delayed five months based on the overall     0.5
Airline Realignment Program Schedule change.                  0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
From C800411 (Terminal Realignment)          $422,000




AIRPORT
64  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Airport Signage (Airline Realignment)
Project:   C800474      The project will provide airport     Status Snapshot Prior Report
Budget: $646,000       directional signage for the airline   Delayed Schedule 3Q 12
Phase: Design        realignment program.         On Budget
Start: 06/01/2011                                 0 Change Orders
Completion: 05/30/2013                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Design consultant completed 90% design of signage improvements.    0.8
Schedule                             0.6
Millions
As previously reported, the change in schedule was based on the      0.4
overall Airline Realignment Program Schedule.
Dollars in 0.2
Budget
0
The project forecast is within the approved budget. Authorization of        Authorized  Forecasted Costs Incurred
construction funding and authority to advertise for construction was
approved on December 4, 2012.
Construction Costs
Change Order                         Not Applicable
None this quarter
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 4Q 2012 Report  65

FOURTH QUARTER REPORT, 2012
Miscellaneous Building Improvements (Airline
Status Snapshot
Realignment)                       On Schedule
On Budget
Project:   C800475      This project will install a new ramp   0 Change Orders
for passenger access to regional    Total Change Orders Amount:
Budget: $2,722,000
aircraft on Concourse A for the     $0
Phase: Design        Airline Realignment program.
Start: 11/01/2011                                Budget/Costs Incurred
Completion: 07/31/2013
3
2.5
Significant Developments                     Millions 2
1.5
The design documentation was started in the fourth quarter of 2012.
1
Dollars in 0.5
Schedule
0
The project is currently on schedule.                             Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.              Construction Costs
Not Applicable
Change Order
None
Risks
If the aircraft assignments at the gates changes, the ramp would
need to be in a different location.
Budget Transfers
None this quarter.




AIRPORT
66  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Laptop Power in Concourses
Project:   C800484      This project adds additional       Status Snapshot
Budget: $2,020,000      charging opportunities for personal  On Schedule
Phase: Design        electronic devices at several     On Budget
Start: 6/26/12           strategic locations throughout the    0 Change Orders
Completion: 12/31/2013   airport terminal.            Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
2.5
Final design is in development.
2
Schedule                            Millions 1.5
The project is currently on schedule.                           1
Dollars in  0.5
Budget
0
The project forecast is within the approved budget. Authorization of        Authorized  Forecasted Costs Incurred
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Construction Costs
Change Order                         Not Applicable
None
Risks
No risks identified at this time.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 4Q 2012 Report  67

FOURTH QUARTER REPORT, 2012
New Window Wall Ticket Zone 1
Project:   C800490      This project will install new       Status Snapshot
Budget: $4,258,000      common use ticket counters and   On Schedule
Phase: Construction     new baggage system along the    On Budget
Start: 07/01/2012         window wall and baggage system   0 Change Orders
Completion: 09/30/2013   renovation.              Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
5
The project is currently out for bid with bid opening scheduled in first
4
quarter of 2013.
Millions  3
Schedule                             2
The project is currently on schedule.                         Dollars in  1
0
Budget                               Authorized Forecasted Costs Incurred
The project forecast is within the approved budget.
Change Order                         Construction Costs
Not Applicable
None
Risks
None
Budget Transfers
From C800404 (Aeronautical Allowance)         $233,000




AIRPORT

68  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Convert Ticket Zone 2 Pushback
Project:   C800491      The scope of the project is to      Status Snapshot
Budget: $5,500,000      renovate the Ticket counters and   On Schedule
Phase: Construction     ATO spaces into a pushback     On Budget
Start: 12/11/2012         configuration.                0 Change Orders
Completion: 11/30/2013                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
6
Construction should commence first quarter 2013.
5
Millions  4
Schedule
3
The project is currently on schedule.                           2
Dollars in   1
Budget                             0
The project forecast is within the approved budget.                   Authorized  Forecasted Costs Incurred
Change Order
Construction Costs
None                                 Not Applicable
Risks
None identified at this time
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 4Q 2012 Report  69

FOURTH QUARTER REPORT, 2012
Convert Ticket Zone 3 Flow Through
Project:   C800492      This project will convert the Zone 3
Budget: $13,136,000     Ticketing Area to a flow through    Status Snapshot
Phase: Design        concept.               On Schedule
Start: 08/07/2012                                 On Budget
Completion: 10/31/2013                       0 Change Orders
Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Delta awarded the construction contract to Turner and work began
14
on the new ATO in November. Turner proposed an accelerated
12
work schedule which has been approved by Delta and the Port. Port
Millions 10
staff worked with Delta's PM (AvAirPros) and Turner to reconcile the     8
contractor's bid with the Tenant Reimbursement Agreement between    6
the Port and Delta. Unforeseen conditions with a previously         Dollars in  4
unidentified seismic joint in the ATO space required additional         2
engineering by the design team which delayed the ATO schedule by    0
Authorized  Forecasted Costs Incurred
one month. A temporary certificate of occupancy is being pursued for
a portion of the ATO in order to keep the work in the Lobby on
schedule. Plan and Permit review of the Lobby design continued on
with permit issue expected in early February 2013.              Construction Costs
2.5
Schedule
2
The ATO portion of the project has been delayed by one month. The
1.5
Lobby portion of the project is currently on schedule.               Millions
1
Budget                             Dollars in  0.5
The project forecast is within the approved budget. Authorization of       0
construction funding and authority to advertise for construction will           Initial  Change  Spent
Orders
be requested when the design and bid documents are completed.
Change Order
None
Risks
The enabling projects and tenant relocations were successfully
completed.
Budget Transfers
From C800475 (Misc Building Improvements - AR)  $136,000

70  Port of Seattle 4Q 2012 ReportAIRPORT

FOURTH QUARTER REPORT, 2012
RAC Baggage Claim Renovation
Project:   C800541      Renovation of both rental car      Status Snapshot
Budget: $1,166,500      counter locations in baggage claim  On Schedule
Phase: Design        into new waiting areas with vending  On Budget
Start: 10/01/2012         machines and other facilities for     0 Change Orders
Completion: 06/30/2013   special operations           Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
1.5
Completed 50% design and design review effort. Completed
purchase order for new terminal seating in order to take advantage
of an existing contract and savings.                          Millions 1
0.5
Schedule                            Dollars in 
The project is currently on schedule.                           0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
None this quarter
Risks
The total construction cost may exceed the limits for a small works
construction contract. A change to a major works construction
contract would increase the project costs and delay the schedule.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 4Q 2012 Report  71

FOURTH QUARTER REPORT, 2012
NorthSTAR Program
Status Snapshot
On Schedule
Project:   C800544      For all programmatic project      On Budget
Budget: $16,400,000     management and project controls   0 Change Orders
Phase: Design        costs for the NorthSTAR program   Total Change Orders Amount:
Start: 04/05/2012         consisting of five capital projects    $0
Completion: 12/31/2018   that represents a unique
partnership between the Port and   Budget/Costs Incurred
Alaska Airlines.
20
Significant Developments                     15
The Port and Alaska Airlines (Alaska) continue to work             Millions 10
collaboratively with two Alaska staff co-located in Port offices
adjacent to the Port team. Completed contract negotiations and       Dollars in  5
signed contract with Jacobs for Program and Project Management     0
and Controls for the NorthSTAR program. Programmatic controls       Authorized Forecasted  Costs
Incurred
hav been developed. Alaska continues to build their internal
program team. A draft communication plan has been initiated.
Decision matrix and responsibilities chart have begun development.   Construction Costs
Not Applicable
Schedule
Commission authorized North Satellite project (NSAT) on schedule.
Project is on schedule.
Budget
Commission authorized $4,200,000 to manage the NorthSTAR
program estimated at approximately $300,000,000. Project is on
budget.
Change Order
None
Risks
The Airline Relocation project schedule changes potentially impacts
the NorthSTAR program schedule. Alaska's concurrence at specific
milestones is critical to the program moving forward. Timely
consultant procurement is critical to getting resources on board to
begin moving the program forward.
Budget Transfers
None this quarter
AIRPORT
72  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
NorthSTAR Concourse C Vertical Circulation
Project:   C800547      Construct exterior, weather       Status Snapshot
Budget: $19,300,000     protected sloped walkways with    On Schedule
Phase: Design        elevators at Gates C2/4, C10/12,   On Budget
Start: 11/07/2012         and C14 to provide enhanced      0 Change Orders
Completion: 03/31/2015   access from concourse to aircraft   Total Change Orders Amount:
ramp for Alaska/Horizon regional    $0
operations.
Budget/Costs Incurred
Significant Developments                     25
Completed project notebook in August 2012 and received MII        20
approval October 31, 2012. Commission authorized $3,100,000 for    Millions 15
design in the fourth quarter. Conceptual design is complete, and the
10
project is proceeding with 30% design.
Dollars in   5
Schedule                             0
Authorized  Forecasted Costs Incurred
The project is currently on schedule.
Budget                            Construction Costs
The project forecast is within the approved budget.              Not Applicable
Change Order
None
Risks
Meeting accelerated design/construction schedule and construction
phasing to minimize impact on airline operations.
Budget Transfers
None



AIRPORT
Port of Seattle 4Q 2012 Report  73

FOURTH QUARTER REPORT, 2012
NorthSTAR Refurbish Baggage Systems
Project:   C800555      This project will refurbish existing   Status Snapshot
Budget: $22,000,000     baggage systems in support of    On Schedule
Phase: Design        AAG operation at North Satellite   On Budget
Start: 11/6/2012          and Concourse D. The work will    0 Change Orders
Completion: 12/31/2015   extend the service life of part of the  Total Change Orders Amount:
C92 systems, C88 North Satellite    $0
systems, and C88 tunnel systems.
Budget/Costs Incurred
25
Significant Developments
20
Completed project notebook in September 2012. MII approval       Millions 15
received October 2012. Commission Authorization for Design Phase
10
received on November 6, 2012.
Dollars in   5
Schedule                             0
Authorized  Forecasted Costs Incurred
Project is currently on schedule
Budget                            Construction Costs
The project forecast is within the approved budget.              Not Applicable
Change Order
None
Risks
Results of the International Air Transport Association (IATA) Study
on level of service requirements may impact the scope of baggage
project.
Budget Transfers
.None this quarter



AIRPORT
74  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
NorthSTAR North Satellite Renovation NSTS
Lobbies
Status Snapshot
Renovation of the North Satellite       On Schedule
Project:   C800556      terminal, including STS station       On Budget
"refresh", ramp level, Concourse
Budget: $190,900,000                          0 Change Orders
level, and new rooftop airline
Phase: Design                             Total Change Orders Amount:
lounge.
Start: 7/24/2012                                    $0
Completion: 12/31/2016
Budget/Costs Incurred
Significant Developments
250
Contract negotiations finalized the prime design consultant (URS).
Service Directive 1 approved through 30% design. The design team    Millions 200
has begun reviewing existing as-built drawings and numerous        150
NorthSTAR and Alaska documents. Design team field investigations   Dollars in 100
are scheduled. Coordination meetings are underway to align
50
expectations in management and design.
0
Authorized  Forecasted Costs Incurred
Schedule
URS was given NTP on December 18, 2012. A draft baseline       Construction Costs
schedule has been prepared and is in review.                 Not Applicable
Budget
Authorization of $32,000,000 for design has been received. Budget
has been transferred to C800554 (NorthSTAR Program) associated
with overall program management and controls. The project forecast
is within the approved budget. Authorization of construction funding
and authority to advertise for construction will be requested when the
bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
From C800414 (Access Control Door Additions)    $800,000

AIRPORT
Port of Seattle 4Q 2012 Report  75

FOURTH QUARTER REPORT, 2012
Highline School Noise Insulation
Status Snapshot Prior Report
Delayed Schedule 4Q 10
Project:   C200007      Highline School Insulation        On Budget
Budget: $101,797,000    Agreement will provide funding for  0 Change Orders
Phase: Construction     sound mitigation for 15 schools that  Total Change Orders Amount:
Start: 03/23/1999         are impacted by aircraft noise from   $0
Completion: 11/30/2021   Sea-Tac Airport.
Budget/Costs Incurred
Significant Developments                     120
100
Port funding is authorized and will become available when the FAA,
the State of Washington, and the Highline School District provide      Millions 80
matching funds.                                     60
40
Schedule                            Dollars in 20
0
The schedule for state funding is not known. The district's schedule
Authorized  Forecasted Costs Incurred
is dependent on obtaining general election bonds at various
intervals.
Budget                            Construction Costs
Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
Not applicable
Risks
Project delayed due to funding issues with the Highline School
District. Risk is if no bonds are passed in general election. Obtain
FAA Airport Improvement Program (AIP) Grant funding.
Budget Transfers
None this quarter



AIRPORT
76  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Highline Community College Noise Insulation
Project:   C200042      Highline Community College      Status Snapshot Prior Report
Budget: $32,050,000     Insulation Agreement will provide   Delayed Schedule 4Q10
Phase: Construction     funding for up to 22 eligible      On Budget
Start: 01/11/2005         buildings that are impacted by      0 Change Orders
Completion: 12/31/2013   aircraft noise from Sea-Tac Airport.  Total Change Orders Amount:
$0
Significant Developments
Thirteen of the 22 eligible buildings have been sound insulated by    Budget/Costs Incurred
the college.
40
Schedule                             30
Building #4 received FAA Airport Improvement Program (AIP) Grant
20
and began construction in winter 2012. The schedules for the         in Millions
remaining buildings are dependent on state funding.               Dollars  10
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
the remaining project budget will be requested for one building at a
time from the Commission in the future when the schedule is       Construction Costs
determined.                                     Not Applicable
Change Order
Not Applicable
Risks
The Highline Community College competes for state funding with
other colleges. If they do not receive adequate funding, projects will
be delayed.
Budget Transfers
None this quarter.


AIRPORT
Port of Seattle 4Q 2012 Report  77

FOURTH QUARTER REPORT, 2012
Home Insulation Retrofit
Project:   C200048      This project includes storm window  Status Snapshot Prior Report
Budget: $5,344,000      retrofit of previously insulated     Delayed Schedule 4Q 11
Phase: Construction     homes.                On Budget
Start: 01/11/2005                                 2 Change Orders
Completion: 12/31/2013                       Total Change Orders Amount:
$
Significant Developments
Budget/Costs Incurred
The Port has identified eligible homes and notified homeowners of
their eligibility. Continue with storm window retrofit.                  6
5
Schedule                             4
Three homes are complete and one is in process. The Port is         Millions 3
reviewing other potential homes for eligibility.                      2
Dollars in  1
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
No change orders were issued, which include miscellaneous small   Not Applicable
items and City permits.
Risks
The ability to accomplish the retrofit is dependent on homeowner's
schedules, and structural integrity of the home.
Budget Transfers
None this quarter



AIRPORT
78  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Single Family Home Sound Insulation
Project:   C200093      Sound insulate remaining homes    Status Snapshot Prior Report
Budget: $4,947,395      that are within the 1998 65 decibel  Delayed Schedule    4Q 11
Phase: Construction     day night level (DNL) noise      On Budget
Start: 03/27/2007         contour.                   4 Change Orders
Completion: 12/31/2013                       Total Change Orders Amount:
$3351
Budget/Costs Incurred
Significant Developments
Thirty-seven homes are complete; five homes are in the process of      6
receiving sound insulation; 10 homes are on the waiting list for the       5
next group. Additional homes were identified to be eligible and will      Millions 4
need commission authorization for additional funding.               3
2
Schedule                            Dollars in  1
0
This project is underway and could be complete by summer 2013.
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within approved budget and authorization to   Construction Costs
complete all homes currently in progress. Any additional homes
identified as eligible will require additional funding authorization.         4
Change Order                           3
Millions
Change orders are miscellaneous small items and permits for the       2
cities.
Dollars in   1
Risks                                 0
Initial    Change Order    Spent
The ability to accomplish the insulation is dependent on the
homeowner's schedules, willingness to sign an aviation easement,
and obtain a subordination agreement from their lender, and
structural integrity of the home. If more eligible homes than
anticipated are identified in the future, then additional funding may be
needed.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 4Q 2012 Report  79

FOURTH QUARTER REPORT, 2012
RMU/Kiosk Concession Program
Status Snapshot Prior Report
Delayed Schedule 4Q 10
Project:   C800146    The project will provide design and     On Budget
Budget: $879,146     fabrication of Retail Merchandising    0 Change Orders
Phase: Construction   Units (RMUs); provide power,       Total Change Orders Amount:
Start: 11/20/2007      communications, and data to RMU     $0
Completion: 09/01/2013 locations; and install floor-mounted
receptacles for the utilities to allow easy
connection points as well as flexibility   Budget/Costs Incurred
for future utilization.
1.5
Significant Developments                     Millions 1
Additional RMU utilities and kiosks are being added to Concourse C.
0.5
The procurement of the casework is in process and the RFP should    Dollars in 
be released in the next two weeks.
0
Authorized  Forecasted Costs Incurred
Schedule
The utility infrastructure will be installed by PCS in March 2013. The
casework procurement is in process and the RFP will be issued in    Construction Costs
February 2013, with a delivery date of August 2013.             Not Applicable
Budget
The project forecast is currently within the approved budget and
authorization.
Change Order
None
Risks
The additional units on Concourse C may exceed the proposed
budget.
Budget Transfers
None this quarter.


AIRPORT
80  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Burien Commercial Property Acquisition
Project:   C800150      Acquire commercial properties     Status Snapshot Prior Report
Budget: $3,000,000      along Des Moines Memorial Drive,  Delayed Schedule    2Q 10
Phase: Implementation   and vacate one street, in the City of  On Budget
Start: 05/31/2007         Burien that is surrounded by Port-   0 Change Orders
Completion: 12/31/2013   owned properties.           Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The remaining anticipated acquisitions will be street vacation of
4
12th Place S. in Burien, Washington, possibly the 757 Convenience
store and a small upholstery shop on the Lora Lake site.             3
Millions
2
Schedule
Dollars in   1
It is anticipated that the acquisitions will occur in the 2013 time
frame.                                            0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.
Construction
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 4Q 2012 Report  81

FOURTH QUARTER REPORT, 2012
Tenant Reimbursement
Status Snapshot
Project:   C800154    Build out of spaces for new and      On Schedule
Budget: $4,709,577    existing tenants. If more than a "basic  On Budget
Phase: Construction   finish" condition space is built for the   0 Change Orders
tenant, the tenant is required to       Total Change Orders Amount:
Start: 08/14/2007
reimburse the Port for the cost of the   $0
Completion: TBD
work beyond this "basic finish". These
reimbursements are allowed under    Budget/Costs Incurred
the guidelines described in the
"Tenant Reimbursement Policy".        5
4
Millions  3
Significant Developments
2
Future tenant projects will likely be part of the Airline Realignment
over the next few years, so this project may have limited activity.       Dollars in  1
0
Schedule                               Authorized Forecasted Costs Incurred
Schedules vary to meet the tenant's needs.
Budget                            Construction Costs
Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
82  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Rubber and Paint Removal Equipment
Project:   C800482    Purchase and delivery of a          Status Snapshot
Budget: $600,000    Rubber/Paint Removal Truck       On Schedule
Phase: Implementation                       On Budget
Start: 02/14/2012                                 0 Change Orders
Completion: 08/31/2012                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The contract was awarded to Stripe Hog. Equipment was delivered
0.8
in August 2012.
0.6
Schedule                            Millions
0.4
Dollars in 
The project is currently on schedule.
0.2
Budget
0
The project forecast is within the approved budget and authorization.       Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter





AIRPORT
Port of Seattle 4Q 2012 Report  83

FOURTH QUARTER REPORT, 2012
Snow Removal Equipment - 2013
Project:   C800498      This project will purchase four     Status Snapshot
Budget: $2,000,000      pieces of runway snow removal    On Schedule
Phase: Implementation   equipment.              On Budget
Start: 02/14/2012                                 0 Change Orders
Completion: 01/22/13                        Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Project went out for bid in April 2012. The contract was awarded to
Cascadia International Inc.
2.5
2
Schedule
1.5
Equipment is anticipated to be delivered in March 2013.
in Millions  1
Budget                             Dollars 0.5
The project forecast is within the approved budget and authorization.     0
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT
84  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Street Vacations T5,18,105
Status Snapshot
Delayed Schedule 4Q 11
Project: C102858,     Street vacation related real estate     On Budget
C102875, E104366    negotiations and agreements --T5,    0 Change Orders
Budget: $1,500,000   T18, and T105.              Total Change Orders Amount:
Phase: Permitting                         $0
Start: June 2010
Completion: 2014                          Budget/Costs Incurred
2
Significant Developments                     1.5
Millions
Meetings with the City have restarted for Terminal 18 (T-18). T-105      1
Dollars in 
Street Vacations have been completed.
0.5
Schedule                             0
Authorized  Forecasted Costs Incurred
Current effort involves resolving Street Vacation issues on T-18. T-5
Street Vacations issues will be addressed following completion of
T-18 issues.                                       Construction Costs
Not Applicable
Budget
The budget has been revised for 2013 and beyond.             Photo
Change Order
Not applicable
Risks
Not applicable
Budget Transfers
Not applicable



SEAPORT
Port of Seattle 4Q 2012 Report  85

FOURTH QUARTER REPORT, 2012
Seaport Security Grant Round 7
Project:   C800165      Seaport Security Grant Round 7    Status Snapshot
Budget: $2,283,090                         On Schedule 4Q 11
Revised Budget $2,582,490                      On Budget
Phase: Construction                        1 change Orders
Start: March 2007                                Total Change Orders Amount:
$24,515.00
Completion: Dec 2010
Budget/Costs Incurred
Significant Developments
2.7
The construction is complete except for punch list items, and final
2.6
programming to get the system up and running. Invoices submitted
for grant reimbursement. Project is in close out. This will be the last     Millions 2.5
2.4
report on the project.
2.3
Dollars in 
Schedule                             2.2
2.1
On schedule as revised                                   Authorized Forecasted Costs Incurred
Budget
On budget as revised                               Construction Costs
Not Applicable
Change Order
No change orders over 10% in the aggregate.
Risks
None
Budget Transfers
No budget transfers over $200,000.



SEAPORT

86  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
P91 Fender System Upgrade
Project:   C800183      Upgrades to the vessel berths of    Status Snapshot
Budget: $5,700,000      P91 to better accommodate cruise  On Schedule
Phase: Design        ships and also serve the other    On Budget
Start: 01/31/10          industrial customers who utilize the   0 Change Orders
Completion: 8/1/2013    berths and adjacent dock/apron    Total Change Orders Amount:
areas on P91 for less than $6M by   $0
spring 2011.
Budget/Costs Incurred
Significant Developments
6
Design for Camel standoff barges completed. Purchase package bid
and awarded.
Millions  4
Schedule
2
Full Fender replacement has been completed by April 2012. Camel    Dollars in 
Barge replacement will be completed by July 2013.                0
Authorized  Forecasted Costs Incurred
Budget
Project is within approved budget.
Construction Costs
Change Order
2.5
None this quarter
2
Risks                                Millions 1.5
None this quarter                                        1
Dollars in   0.5
Budget Transfers
0
None                                      Initial Change Spent
Orders




SEAPORT
Port of Seattle 4Q 2012 Report  87

FOURTH QUARTER REPORT, 2012
T-5 Crane Cable Reels
Status Snapshot Prior Report
Project:   C800349      Purchase Cable Reels for tenant.
Budget: $3,500,000                         Delayed Schedule
Phase: Design                            On Budget
Start: 05/04/10                                   0 Change Orders
Completion: 03/31/11                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
No changes to the project since last report.
4
Schedule
3
The installation of the cable reels is still anticipated to begin the first
quarter of 2013. The revised completion date for the project remains
Millions  2
3rd quarter 2013.
Dollars in  1
Budget
0
None                                     Authorized Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
Schedule                                   Photo
Budget Transfers
None




SEAPORT

88  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
T-91, Bldg C175 Roof Replacement
Status Snapshot Prior Report
Project:   C800430      Replace roof on the C175 building
Budget: $240,000       at Terminal 91.            Delayed Schedule
Phase: Design                            On Budget
Start: 7/26/11                                    0 Change Orders
Completion: Q4 2014                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Negotiations with the designer were concluded and a Service
directive was completed. The designer prepared a draft Preliminary
0.3
Design report. The preliminary report confirmed that the roof would
0.25
not need to be replaced until 2014 as had originally been planned.
Millions 0.2
0.15
Schedule
0.1
The preliminary design report and schedule is to be finalized during
0.05   Dollars in 
the next quarter. The installation of the roof remains as planned for
0
2014.                                            Authorized Forecasted Costs Incurred
Budget
On budget                                   Construction Costs
Not Applicable
Change Order
None                                 Photo
Risks
None at this time
Budget Transfers
None



SEAPORT
Port of Seattle 4Q 2012 Report  89

FOURTH QUARTER REPORT, 2012
SEA P66 Apron Pile Wrap
Status Snapshot
Project:   C800516      Design and install a pile wrap
Budget: $3,010,000      system for corrosion protection of   Delayed Schedule
Phase: Design        steel structural pilings associated   On Budget
Start: 3/6/12            with Seaport structures at Pier 66.   0 Change Orders
Completion: 12/31/14                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Completed final design and received permits from the agencies.        4
Construction funding approved on November 6th. To maximize
3
efficiency, the construction contract of this project has been
packaged together with that of the P69 North Apron Corrosion
Millions  2
Control Project. The combined construction package was advertised
1
on November 27th and bids were opened on December 20th with very   Dollars in 
favorable bid result. Richard Philips Marine was the apparent low       0
bidder.                                                 Authorized  Forecasted Costs Incurred
Schedule
Construction Costs
With the direction to combine construction work into a single
Not Applicable
contract, the P66 Apron Pile Wrap design schedule was intentionally
delayed by a couple of months so the construction contract
advertisement would coincide with that of the Pier 69 North Apron
Corrosion Control Project. However, instead of multi-year
construction, the construction work is expected to be accelerated
and be completed by end of March 2014.
Budget
Project is on budget.
Change Order
None
Risks
Installation of pile wraps is tide and weather dependent.
Construction duration may lengthen as a result.
Budget Transfers
None

SEAPORT
90  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Argo Yard Truck Roadway
Status Snapshot
Project:   C800546,      New Port of Seattle owned truck
E104751, E104754       roadway between SR 99 and     On Schedule
Budget: $2,200,000      Colorado Way Avenue right-of-way.  On Budget
Phase: Design                            0 Change Orders
Start: 03/11/12                                   Total Change Orders Amount:
$
Completion: 12/31/2014
Significant Developments                    Budget/Costs Incurred
A Supplemental Agreement to the project's Memo of Understanding,     3
detailing specific processes and stakeholder obligations was drafted
by the Port and provided to the other stakeholders for their review      Millions 2
and approval. A Total Cost of Ownership financial analysis was
completed for various construction options and the final engineering      1
design has begun accordingly. Title search is in process for the       Dollars in 
roadway easement properties.                            0
Authorized  Forecasted Costs Incurred
Schedule
Design and permitting to be completed by fall 2013. Construction is
Construction Costs
to be completed by Spring 2014.
Not Applicable
Budget
Project authorized budget is $2,800,000 (including $600,000 from
FMSIB). Current preliminary project estimate is $3,200,000.
Change Order
None
Risks
Additional funding approval expected to be required when
authorization to advertise for construction bids is requested. The
actual start of utilization of the proposed Argo Yard truck roadway is
dependent upon the completion of separate off-site projects - EMW
Phase II (East Marginal Way surface street improvements) and
WSDOT's SR 99 timber trestle replacement scheduled for
construction completion by spring 2014. The EMW Phase II
improvements will also require timely approval by Union Pacific
Railroad and the Ash Grove Cement Co. in order to be completed
within 2014.

Port of Seattle 4Q 2012 Report  91

Budget Transfers
None













SEAPORT
92  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
P66 Security Camera Upgrade Project
Project:   C800596      P66 Cruise Terminal Security      Status Snapshot
Budget: $540,000       Camera Upgrade. Scope removes  On Schedule
Phase: Construction     29 cameras monitoring the cruise   On Budget
Start: 10/05/2012         facility, installs 36 new cameras,    0 Change Orders
Completion: 07/01/2013   and upgrades the infrastructure.    Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Design is complete. Contract for installation has been bid with intent
to award issued. ICT has purchased and addressed cameras.        0.6
0.5
Schedule
Millions 0.4   Dollars in 
Expect installation to begin in April.                             0.3
0.2
Budget
0.1
On Budget.                                      0
Authorized  Forecasted Costs Incurred
Change Order
Not Applicable
Construction Costs
Risks                               Not Applicable
Contractor may have difficulty working around building operations.
Budget Transfers
None





SEAPORT
Port of Seattle 4Q 2012 Report  93

FOURTH QUARTER REPORT, 2012
T-46 Dock Rehabilitation
Project:   C800603      Terminal 46 Dock Rehabilitation    Status Snapshot
Budget: $1,854,000      Project                On Schedule
Phase: Design                            On Budget
Start: November 6, 2012                            0 Change Orders
Completion: Q1 2016                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Commission authorization for project design issued on November 6,
2012                                      2
Schedule                             1.5
Millions
The project design began with internal staff and is anticipated to be      1
finalized during the 2nd Quarter 2013. Construction is planned to
0.5
commence the 4th Quarter of 2013 and conclude during the 1st        Dollars in 
Quarter of 2016
0
Authorized  Forecasted Costs Incurred
Budget
The project is on budget
Construction Costs
Change Order                         Not Applicable
None
Photo
Risks
None at this time
Budget Transfers
None



SEAPORT
94  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
East Marginal Way Grade Separation
Status Snapshot Prior Report
Project:   E102007      FAST Corridor funded project;      Delayed Schedule
Budget: $53,575,171     FHWA, State, City with Port      On Budget
Phase: Construction     commitment of $18,800,000. Scope  59 Change Orders
Start: 5/2006            is to construct grade separation in    Total Change Orders Amount:
Completion: Q2 2013     vicinity of T5 and T18 to minimize   $1,358,306
truck traffic/rail conflicts.
Budget/Costs Incurred
Significant Developments
53.6
Federal Highway Administration (FHWA) final audit completed.
53.58
Construction contractor's punchlist completed and final claims        53.56
settled. Final landscaping improvements are under construction by    53.54  Millions
the Port. Final project Memo of Agreement is in process with the      53.52
City. As-built drawings are in progress.                         53.5  Dollars in 
53.48
Schedule                            53.46
Authorized  Forecasted Costs Incurred
Final acceptance by SDOT is anticipated in 3rd Q 2013.
Budget
Construction Costs
Current construction costs based on unit line items and cost
reconciliation which as part of the project closeout.                   25
20
Change Order
Millions   15
Change orders have been executed for a total net amount of
$1,150K.                                        10
Dollars in    5
Risks                                  0
Initial   Change   Spent
Additional funding may need to be requested to reconcile final
Orders
project costs.
Budget Transfers                        Photo
None


SEAPORT

Port of Seattle 4Q 2012 Report  95

FOURTH QUARTER REPORT, 2012
Viaduct Construction Coordination
Project:   E104324,      Participate in the design &       Status Snapshot
E104535-38          construction of the bored tunnel,   On Schedule 4Q 12
Budget: $980,000       north & south portals, Holgate to   On Budget 4Q 12
Phase: Implementation   King St, Central Waterfront surface  0 Change Orders
Start: 1/1/2009          streets, and related projects to     Total Change Orders Amount:
ensure adequate connection to port  $0
Completion: 12/31/2018
facilities.
Budget/Costs Incurred
Significant Developments
3.5
Construction completed on mitigation works at T-46 as a condition of     3
leasing 5 acres for tunnel construction staging area. Construction of
SR99 South Holgate to King Stage 3 began installation of new        Millions 2.52
overpass to South Atlantic St. Excavation of future SR 99 tunnel       1.5
boring machine launch pit near T-46 continued through December.     Dollars in  1
0.5
Schedule                             0
Authorized  Forecasted Costs Incurred
Tunnel boring machine delivery via T-46 is expected by April 2013.
Related City projects are making steady progress
(Spokane/Mercer/Seawall/Central Waterfront.)
Construction Costs
Not Applicable
Budget
Port staff costs were within anticipated 2012 spending.            Photo
Change Order
Not applicable
Risks
There are multiple impacts to port tenants and general freight
mobility due to temporary road closures, detours, and other
necessary construction activities.
Budget Transfers
None

SEAPORT

96  Port of Seattle 4Q 2012 Report

THIRD QUARTER REPORT, 2012
T-18 Pile Cap Repair Pilot Project
Project:   E104559      T18 Pilot Pile Cap Repair Project    Status Snapshot
Budget: $1,500,000                         On Schedule 4Q 12
Phase: Construction                        On Budget 4Q 12
Start: 3/25/11                                    0 Change Orders
Completion: 12/31/12                        Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
2
Construction completed in October; and final report completed in
December.                                   1.5
Millions
1
Schedule
0.5
Project is complete.                                     Dollars in 
0
Budget                               Authorized Forecasted Costs Incurred
Costs are within budget.
Change Order                         Construction Costs
None
1.2
Risks                                  1
0.8
None
0.6
Millions
0.4
Budget Transfers                          Dollars in  0.2
None
0
Initial   Change   Spent
Orders



SEAPORT
Port of Seattle 4Q 2012 Report  97

FOURTH QUARTER REPORT, 2012
Dock System Condition Assessments
Project:   E104610-12;    Comprehensive Assessments: T5,   Status Snapshot
E104695 & 98         T18, T46, T25/30, and P66      On Schedule 4Q 12
Budget: $2,250,000      Rapid Assessments: T18       On Budget 4Q 12
Phase: Implementation                       0 Change Orders
Start: 1/1/2011                                   Total Change Orders Amount:
$0
Completion: 12/31/2012
Budget/Costs Incurred
Significant Developments
Inspections and final reports were completed for T-18, T-25, T-30       2.5
and P66.
2
Millions 1.5
Schedule
Dollars in 
1
Project is complete.
0.5
Budget                              0
Project completed within the budget.                            Authorized  Forecasted Costs Incurred
Change Order
Not applicable                                     Construction Costs
Not Applicable
Risks
Photos
None
Budget Transfers
None




SEAPORT

98  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
T-5 and T-18 Maintenance Dredging
Status Snapshot
Project:   E104840      Maintenance Dredge T5 Berth 1 to   On Schedule
Budget: $1,950,000      -45', Berth 2 and 3 to -50', and    On Budget
Phase: Design        perform T18 high spot removal if   0 Change Orders
Start: 08/14/12          permit allows                Total Change Orders Amount:
Completion: 02/28/2014                       $
Budget/Costs Incurred
Significant Developments
2.5
Finalized design; received all permits; project went out to bid and
2
awarded contract. Phase I (South Berth) construction is to begin in
1.5
January 2013.
Millions
1
Schedule                            Dollars in 0.5
Project is on schedule.                                    0
Authorized  Forecasted Costs Incurred
Budget
Project is on budget.                                   Construction Costs
Not Applicable at this time
Change Order
None
Risks
None
Budget Transfers
None




SEAPORT
Port of Seattle 4Q 2012 Report  99

FOURTH QUARTER REPORT, 2012
FT C15 HVAC Improvements
Status Snapshot
Project:   C800137                             Delayed Schedule 4Q 11
Budget: $3,748,000    Provide the preliminary planning,    On Budget
Phase: Design       design, and construction for replacing  0 Change Orders
Start: 05/01/10         the FT C15 HVAC System.         Total Change Orders Amount:
Completion: 5/31/2014                        $0
Budget/Costs Incurred
Significant Developments
5
90% design documents preparation is complete - adopted new
equipment design concept, which would significantly lessen           4
construction related impacts to building tenants.                  Millions 3
2
Schedule                            Dollars in  1
Design is behind schedule due to the departure of key consultant
0
staff. Adoption of new design concept resulted in additional design
Authorized  Forecasted Costs Incurred
effort.
Budget
Construction Costs
On budget                                   Not Applicable
Change Order
None
Risks
Equipment/construction costs for the specific type of equipment is
difficult to predict.
Budget Transfers
None



REAL ESTATE
100  Port of Seattle 4Q 2012 Report

SECOND QUARTER REPORT, 2012
RE Maintenance Shop Solution
Project:   C800187      Marine Maintenance Solution CIP   Status Snapshot
Budget: $2,640,000      facilities continued operations from  Projects Complete
Phase: Construction     the existing shop location by     On Budget
Start: August 2010       funding the following five projects:   0 Change Orders
Completion: November   MM Office Expansion; MM North-   Total Change Orders Amount:
end Office; MM Electrical Upgrade;
2012
MM Roof Replacement, and MM
Kitchen Upgrade.             Budget/Costs Incurred
2.65
Significant Developments
Millions 2.6
Projects are complete. Kitchen Replacement Project is in closing.
2.55
Schedule                            Dollars in 
Projects are complete.                                  2.5
Authorized  Forecasted Costs Incurred
Budget
Total CIP authorization is $2,640,000. Approximately $2,560,000    Construction Costs
has been spent to date. CIP will come in under budget.           Not applicable
Change Order
No change orders previous quarter.
Risks
N/A
Budget Transfers
None



REAL ESTATE

Port of Seattle 4Q 2012 Report  101

FOURTH QUARTER REPORT, 2012
P69 N Apron Corrosion Control
Status Snapshot
Project:   C800313      Install a corrosion control system    On Schedule
Budget: $5,100,000      for the steel pilings, pile caps, and   On Budget
Phase: Design        beams under the North Apron.    0 Change Orders
Start: 02/28/12                                   Total Change Orders Amount:
Completion: 12/31/2013                       $0
Budget/Costs Incurred
Significant Developments
6
Design is complete. Project went out to bid in November.
Millions  4
Schedule
Project is on schedule to start construction in spring 2013.             2
Dollars in 
Budget                              0
Authorized  Forecasted Costs Incurred
Project is on budget.
Change Order                         Construction Costs
None                                 Not Applicable
Risks                               Photo
None
Budget Transfers
None at this time




REAL ESTATE

102  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
P-69 Built-up Roof Replacement
Project:   C800314      Replace the 65,000SF Roof at the   Status Snapshot
Budget: $445,000       P-69 Headquarters Office Building  On Schedule
Phase: Design                            Forecast Overrun
Start: 2/26/12                                    0 Change Orders
Completion: 10/30/2014                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Preliminary reports are complete and the project is currently at the
60% design phase.                                 2.5
2
Schedule
Millions 1.5
The project is scheduled to be completed in Q4 2014
1
Budget                             Dollars in 0.5
The project is currently below budget.                          0
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
None
Budget Transfers
None




REAL ESTATE
Port of Seattle 4Q 2012 Report  103

FOURTH QUARTER REPORT, 2012
FT Net Shed Code Compliance
Project:   E104838      FT Net Sheds 3-11 building       Status Snapshot
Budget: $650,000       improvements required per City of   On Schedule
Phase: Design        Seattle building & fire codes     On Budget
Start: May 2012                                  0 Change Orders
Completion: June 2015                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Continue coordinating with Seattle Fire Department and locker
tenants on design. Developed new design concepts and applied       2.5
them to two net lockers. Open house for the new design concepts
2
was held on December 19. The plan was well received by those
who attended the open house. Fishermen's Terminal Advisory       Millions 1.5
Committee is also pleased with the design and open house.           1
Dollars in 0.5
Schedule
0
Final design will continue into 2013 and anticipate fieldwork for            Authorized  Forecasted Costs Incurred
retrofit to begin summer of 2013 and completed by 2nd quarter of
2015 if all net sheds would be retrofitted. Net Shed No. 7 and 8 work
would be deferred to the very end of construction.               Construction Costs
Not Applicable
Budget
Design budget is on track.
Change Order
None
Risks
It is difficult to project the amount of stored materials that need to be
moved out and moved back since the work would be phased over a
2-year period. In addition, the amount of work required in each unit
is difficult to assess until stored materials are removed.
Budget Transfers
None

REAL ESTATE
104  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Flight Information System (FIMS) II
Project: C101117      Procure, develop, and implement a    Status Snapshot
Budget: $8,220,000     FIMS system that includes        On Schedule
Phase:Implementation  replacement monitors, an airport     On Budget
Start: 5/4/2010         resource management system, and    3 Change Orders
Completion: 12/30/2013  a flexible digital signage system      Total Change Orders Amount:
capable of displaying flight           $717,355
information, visual paging, and
notifications.
Budget/Costs Incurred
9
Significant Developments
8
The first phase deployment of the flight information display (FIDS)       7
Millions   6
software was completed on-schedule in November 2012.
5
Dollars in    4
Software configuration and testing is in progress for the deployment     3
2
of the resource management system (RMS) scheduled for June
1
2013. Casework construction and display replacement began in July     0
Authorized     Forecasted    Costs Incurred
2012 and will continue through 2013.
Schedule
On Schedule                                 Construction Costs
2.5
Budget
2
On Budget                                   Millions 1.5
Change Order                           1
Prior report: Additional signage replacement was approved resulting    Dollars in  0.5
in a contract change order for construction design.                  0
.                                                                                      Initial     Change     Spent
Orders
Risks
A delay in the RMS software implementation would require a
contract extension with the current FIMS vendor for support of the
existing system.
Budget Transfers
None

CORPORATE
Port of Seattle 4Q 2012 Report  105

FOURTH QUARTER REPORT, 2012
Maximo Enterprise Implementation
Project:   C800003      Implement latest version of       Status Snapshot Prior Report
Budget: $3,680,000      Maximo, merge Aviation and Real   Delayed Schedule
Phase: Implementation   Estate applications onto one     On Budget
Start: 11/25/2007         platform, and add service desk     0 Change Orders
Completion: 12/30/2013   module and wireless handheld    Total Change Orders Amount:
capabilities.                    $0

Significant Developments                    Budget/Costs Incurred
Major components of the program have been delivered, including the
4
deployment of Service Management software for the ICT Service
Desk in December 2008 and the upgrade and consolidation of        3
Marine Maintenance and Aviation Maintenance Maximo systems in
2
September 2010. The smaller mobility enhancement is in progress      Millions
and additional interfaces will be created after the Peoplesoft          Dollars in 1
Financials upgrade.
0
Authorized Forecasted   Costs
Schedule
Incurred
Prior Report - Several of the proposed new interfaces link the
Maximo system to the Peoplesoft Financials Procurement module.
Construction Costs
Because of planned changes in the procurement process with the
Not Applicable
Peoplesoft Financials Upgrade project, the delivery of these
interfaces will be delayed until after the completion of the upgrade
project.
Budget
On Budget
Change Order
None
Risks
Resource constraints may continue to delay the implementation of
the interfaces and mobility enhancements.
Budget Transfers
None

CORPORATE
106  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
ID Badge System Replacement
Project: C800162        Procurement and replacement of   Status Snapshot
Budget: $2,500,000      the Portwide ID Badge system     On Schedule
Phase:Design         including software, hardware, and   On Budget
Start: 5/1/2012           equipment.                 0 Change Orders
Completion: 11/30/2013                         Total Change Orders Amount:
$0
Significant Developments
Software configuration requirements and technical architecture are in  Budget/Costs Incurred
development.
3
2.5
Schedule
2
On Schedule
1.5 Millions
1
Budget
0.5  Dollars in
On Budget
0
Authorized Forecasted   Costs
Change Order                                   Incurred
None
Construction Costs
Risks                               Not Applicable
No significant risks
Budget Transfers
None





CORPORATE
Port of Seattle 4Q 2012 Report  107

FOURTH QUARTER REPORT, 2012
Airline Activity Management
Project: C800222        Development of an airline activity   Status Snapshot
Budget: $500,000       management system that       On Schedule
Phase:Implementation    integrates with several Port      On Budget
Start: 6/19/2011          systems to replace aging reporting   0 Change Orders
Completion: 5/1/2013     system and supply data for airline   Total Change Orders Amount:
activity fees.                    $0

Budget/Costs Incurred
Significant Developments
0.6
Development in progress.
0.5
Schedule                             0.4
0.3
On Schedule                                   Millions
0.2
Dollars in 0.1
Budget
0
On Budget                                      Authorized Forecasted  Costs
Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
New requirements have been identified for the Resolution that will
replace the previous Signatory Lease and Operating Agreement.
These new requirements for airline billing may delay the schedule.
Budget Transfers
None




CORPORATE
108  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Enterprise Project Cost Management
Project: C800321        Replace the current construction    Status Snapshot
Budget: $1,525,000      costing systems with a common    Delayed Schedule
Phase:Implementation    enterprise project cost         On Budget
Start: 4/21/2008          management system.           0 Change Orders
Completion: 5/30/2013                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The first phase deployment has been completed and the software is
in-use by the Project Management Groups. To ensure resources are     2
available to focus on the current installation, work on the
development of additional interfaces in the final phase has been       1.5
delayed. They will instead be delivered in stages over the next six
Millions 1
months.
Dollars in0.5
Schedule
0
Prior Report - Vendor did not deliver software per original contract         Authorized Forecasted  Costs
and project was put on-hold to evaluate alternatives. A decision was                   Incurred
made to continue with Skire in July 2010. The estimated completion
date at this time is September 2011 although there may be interim    Construction Costs
deliveries prior to completion.                              Not Applicable
Prior Report - Configuration of the software took longer than
anticipated due to the availability of resources and complexity of the
software delaying the start of the interface development. The system
is scheduled to be deployed in May 2012 with several critical
interfaces in place.
Budget
None
Change Order
None
Risks
Availability of Port resources may delay next phase deliverables.
Budget Transfers
None
CORPORATE
Port of Seattle 4Q 2012 Report  109

FOURTH QUARTER REPORT, 2012
Records and Document Management
Project:   C800322      Improve statutory compliance,     Status Snapshot
Budget: $800,000       increase functionality, and lower   Delayed Schedule
Phase: Implementation   operating costs by replacing     On Budget
Start: 6/23/2009          Hummingbird with SharePoint for    0 Change Orders
Completion: 6/30/2013    records and document        Total Change Orders Amount:
management.             $0

Significant Developments                    Budget/Costs Incurred
The Sharepoint 2010 upgrade, training, and project-led organization
roll-out has been completed. Implementation and testing of          0.8
Sharepoint 2010 Records Center is in progress.
0.6
Schedule                             Millions 0.4
Resource availability due to competing priorities has delayed the full    Dollars in 0.2
implementation of the Sharepoint Records Center until June 2013.
0
Authorized  Forecasted    Costs
Prior Report: Sharepoint 2010 implementation is dependent on the                    Incurred
completion of several infrastructure projects currently in progress
and requires additional time to complete the upgrade of existing
Construction Costs
sites.
Not Applicable
Budget
On Budget
Change Order
None
Risks
Projects with higher priority may continue to delay Records Center
implementation.
Budget Transfers
None


CORPORATE
110  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Time Clock System
Project: C800387        Procure and implement a Time    Status Snapshot Prior Report
Budget: $380,000       Clock System to accurately capture  Delayed Schedule
Phase: Planning        and track time and attendance for   On Budget
Start: 6/8/2010           approximately 230 employees in    0 Change Orders
Completion: 11/30/2013    Aviation Security and Airport      Total Change Orders Amount:
Operations organizations.         $0

Significant Developments                    Budget/Costs Incurred
Vendor was unable to deliver software that functioned in our
0.4
environment per the contract. We are working with the legal
department to determine our options for severing the relationship.        0.3
0.2
The project team has evaluated options and will move forward with      Millions
the procurement and implementation of a simpler time clock system    Dollars in  0.1
from a different vendor. The scope of the implementation will not
include a Peoplesoft interface as originally planned.                  0
Authorized Forecasted   Costs
Incurred
Schedule
We are estimating deployment of the new solution in November
Construction Costs
2012.
Not Applicable
Budget
$75,500 of the $240,000 spent to date on the project was directly
related to the previous vendor solution and will not contribute to the
value of a new product implementation. This was expensed against
the ICT Operations Budget in 2012. The new solution can be
delivered within the approved budget.
Change Order
None
Risks
No signfiicant risks at this time.
Budget Transfers
None

CORPORATE
Port of Seattle 4Q 2012 Report  111

FOURTH QUARTER REPORT, 2012
PeopleSoft Financials Upgrade
Project: C800392        Upgrade of Peoplesoft Financials   Status Snapshot Prior Report
Budget: $5,000,000      hardware and software         Delayed Schedule
Phase:Implementation                        On Budget
Start: 9/28/2010                                 0 Change Orders
Completion: 12/31/2013                         Total Change Orders Amount:
$0
Significant Developments
Technical design and functional fit/gap workshops have been       Budget/Costs Incurred
completed. Software configuration and development is in progress.
6
5
Schedule
4
Prior Report - An implementation vendor was selected via a
Millions 3
competitive procurement but we were unsuccessful in negotiating an
2
acceptable contract. Because of resource constraints during the       Dollars in 1
year-end process, the next optimum window of opportunity for the
0
upgrade begins in mid-2012. This will delay the project one year.
Authorized Forecasted   Costs
Incurred
Budget
On Budget                                  Construction Costs
Not Applicable
Change Order
None
Risks
Significant resources will be required across multiple organizations
which may delay other technology projects.
Budget Transfers
None



CORPORATE
112  Port of Seattle 4Q 2012 Report

FOURTH QUARTER REPORT, 2012
Police Records Management System
Project: C800393        Procure and implement a       Status Snapshot
Budget: $1,300,000      replacement Police Records      Delayed Schedule
Phase:Implementation    Management System         On Budget
Start: 10/10/10                                   0 Change Orders
Completion: 8/31/2013                         Total Change Orders Amount:
$0
Significant Developments
Configuration and implementation in progress.                 Budget/Costs Incurred
Schedule                            1.4
1.2
A change request was approved to implement additional software
1
that will better meet business process for field reporting. Technical
0.8
problems installing the new software will delay the implementation       Millions
0.6
until August 2012.
Dollars in0.4
0.2
Prior Report - Contract negotiations took significantly longer than       0
anticipated delaying project completion by 8 months.                 Authorized Forecasted  Costs
Incurred
Budget
On Budget
Construction Costs
Change Order                         Not Applicable
None
Risks
Continued issues with the vendor installation may further delay
project completion.
Budget Transfers
None



CORPORATE
Port of Seattle 4Q 2012 Report  113

FOURTH QUARTER REPORT, 2012
Maintenance Planning Software
Project: C800501        Procure and implement        Status Snapshot Prior Report
Budget: $402,000       Maintenance Planning and       Delayed Schedule     2Q 11
Phase:Close Out       Scheduling software that integrates  On Budget
Start: 6/26/2011          with our Asset Management       0 Change Orders
Completion: 11/30/2012    system, Maximo.            Total Change Orders Amount:
$0
Significant Developments
Software deployment has been completed as originally scoped and   Budget/Costs Incurred
additional licenses have been purchased.
0.5
Schedule                             0.4
Prior report: A change request for additional licenses and reports has    0.3
been approved. This scope change will delay the schedule by 5        Millions
0.2
months.
Dollars in0.1
Budget                             0
Authorized Forecasted   Costs
On Budget                                               Incurred
Change Order
Construction Costs
None                                 Not Applicable
Risks
No significant risks
Budget Transfers
None




CORPORATE
114  Port of Seattle 4Q 2012 Report

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.