4b memo
PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 4b ACTION ITEM Date of Meeting August 19, 2014 DATE: August 12, 2014 TO: Tay Yoshitani, Chief Executive Officer FROM: Giuseppe Alvarado, Manager, Harbor Business and Operations, Recreational Boating Steve Miller, Capital Project Manager SUBJECT: Shilshole Bay Marina A-dock finger pier replacement (CIP #C800537) Amount of This Request: $60,000 Source of Funds: 2007A Bond Proceeds Est. Total Project Cost: $322,000 ACTION REQUESTED Request Commission authorization for the Chief Executive Officer to complete design and installation of the replacement of A-dock finger float serving slips 11 and 12 at Shilshole Bay Marina (SBM). T he amount of this request is $60,000, for a total estimated project cost of $322,000. SYNOPSIS SBM A Dock Replacement was originally expected to cost less than the $300,000 threshold requiring Commission authorization per Resolution No. 3605 as amended by Resolution No. 3628. Due to higher than expected procurement costs and additional scope, the project is now likely to exceed $300,000. This project will restore service capacity at lower A-dock by replacing the finger float serving dock slips 11 and 12. These slips provide moorage for large boats and generate significant revenue. The project is scheduled to be completed for occupancy by October 1, 2014. BACKGROUND Service issues with the existing 100 ft. float at A-dock led to design efforts in late 2013 to replace the float. Initial advertisement to procure the float led to a single bid received at approximately double the Engineer's Estimate, which was subsequently rejected. During repackaging of the bid documents, the condition of the float was an ongoing safety concern and led to its demolition and removal. After discussions with manufacturers on how to economize the design, the float procurement was re-advertised and again received only one high bid, slightly lower reflecting the removal of demolition work. To restore lost service and revenue at SBM without further delay, the bid was accepted and the Contract awarded to Bellingham Marine Industries, Inc. (BMI). Analysis of total estimated project costs later revealed multiple Template revised May 30, 2013. COMMISSION AGENDA Tay Yoshitani, Chief Executive Officer August 12, 2014 Page 2 of 4 incremental increases in materials and services needed to complete testing, inspection, and installation of the float. This project is currently on schedule to have the float constructed, inspected, delivered, fully installed and operational by October 1, 2014. PROJECT JUSTIFICATION AND DETAILS Project Objectives Replacement of A-dock finger pier float and associated revenue. Scope of Work The fabrication, delivery and installation of a new replacement float at A-dock, measuring approximately 100 ft. x 6 ft., to match previous existing float dimensions with new power centers and communication utilities. The new float will have an estimated 50-year service life. Schedule The project schedule through design and construction efforts to date and through anticipated completion are as follows: Preliminary Design & Planning August-October 2013 Initial bid for Construction November 2013 Demolition of Float January 2013 Second bid for Construction March 2014 Float submittal phase complete July 2014 Fabrication / Delivery / Assembly of Floats August 2014 Installation of Float Utilities / Final Acceptance September 2014 Substantial Completion October 2014 FINANCIAL IMPLICATIONS Budget/Authorization Summary Capital Expense Total Project Original Budget $262,000 $0 $262,000 Previous Authorizations $0 $0 $0 Current request for authorization $60,000 $0 $60,000 Total Authorizations, including this request $322,000 $0 $322,000 Remaining budget to be authorized $0 $0 $0 Total Estimated Project Cost $322,000 $0 $322,000 Project Cost Breakdown This Request Total Project Construction $42,000 $223,000 Construction Management $1,000 $6,000 COMMISSION AGENDA Tay Yoshitani, Chief Executive Officer August 12, 2014 Page 3 of 4 Design $15,000 $25,000 Project Management $12,000 $46,000 Environmental / Contract Admin -$10,000 $10,000 Permitting $0 $1,000 State & Local Taxes (estimated) $0 $11,000 Total $60,000 $322,000 Budget Status and Source of Funds This project was included in the 2014 Plan of Finance under CIP #C800537, RE 2013 Small Projects for a total cost of $200,000. The additional $122,000 required to fund this project will come from below budgeted spending on other capital projects such as FT C15 Building Subsidence. This project will be funded by 2007A Revenue Bond proceeds. Financial Analysis and Summary CIP Category Renewal/Enhancement Project Type Renewal & Replacement Risk adjusted 7% discount rate Key risk factors Future revenues could be less than currently expected. Actual costs could exceed the current estimates. Project cost for $322,000 analysis Business Unit Harbor Services Recreational Boating (BU) Effect on business Estimated impact on Net Operating Income (NOI) and NOI after performance Depreciation for years 2014 through 2018 is shown below. NOI (in $000's) 2014 2015 2016 2017 2018 NOI $8 $31 $28 $32 $28 Depreciation ($2) ($6) ($6) ($6) ($6) NOI After Depreciation $6 $24 $21 $25 $22 IRR/NPV NPV IRR Payback (in $000's) (in years) $80 6.8% 11 COMMISSION AGENDA Tay Yoshitani, Chief Executive Officer August 12, 2014 Page 4 of 4 STRATEGIES AND OBJECTIVES This work supports the Harbor Services' strategy of maintaining assets to meet market demands and provide compelling value to customers. ALTERNATIVES AND IMPLICATIONS CONSIDERED Alternative 1) Provide $60,000 additional funding to complete the project and restore service and revenue stream associated with the A-dock finger float 11/12. This is the recommended alternative. Alternative 2) Stop progress on the project. Float components will be inventoried for future use or sale. SBM to continue to operate the marina without float 11/12, as is currently being done. This alternative would negatively impact SBM by decreasing revenue due to continued loss of float moorage fees and resulting in less service to large boat owners. This is not the recommended alternative. ATTACHMENTS TO THIS REQUEST PowerPoint slide A-dock Finger Pier PREVIOUS COMMISSION ACTIONS OR BRIEFINGS None
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.