6a supp

ITEM NO: ______6a_Supp_______ 
DATE OF MEETING: October 1, 2013

Aviation Maintenance (AVM)
Monthly Sprinkler Riser 
Preventive Maintenance (PM)
Inspection

Background: AVM Monthly Sprinkler
Riser PM Inspection 
2 

366 sprinkler riser assets 
Maintained by operating
engineers in the AVM BLRM 
Inspections monthly and at 
3, 6, and 12 month intervals 
Regulatory requirement 
Annual labor hours: 1,593 
Annual labor cost: $91,370

Monthly Sprinkler Riser Inspections    Concourse A                     Feb 2013 

77 assets inspected 
77 work orders 
12 operating engineers 
20 trips 
10.6 miles round trip 
40.5 labor hours 





3

Monthly Sprinkler Riser Inspections     Concourse A                    July 2013 

64 assets inspected 
3 work orders 
3 operating engineers 
3 trips 
1.8 miles round trip 
13 labor hours 





4

Monthly Sprinkler Riser Inspections    Main Terminal                    Feb 2013 

Main Terminal (6 floors) 
72 assets inspected 
72 work orders 
19 operating engineers 
26 trips 
5.0 miles round trip 
37.75 labor hours 





5

Monthly Sprinkler Riser Inspections:    Main Terminal                      July 2013 

Main Terminal (6 floors) 
75 assets inspected 
6 work orders 
6 operating engineers 
6 trips 
1.9 miles round trip 
23 labor hours 




6

Monthly Sprinkler Riser PM Inspection
Target Sheet 
7 
CPI Target Sheet
CPI Event or Workshop: AVM Monthly Sprinkler Riser PM Inspection
Work area:         AVM BLRM to Concourse A and Main Terminal
Current    Future
%
Measures       State    State   Delta
Change
(Feb)     (July)
Assets Inspected                149      139     NA    NA
Labor Hours                 78.25     36.0     42.3    54%
Cycle Time per Inspection (min)       31.5      15.5     16.0    51%
Distance Travelled (miles)           15.6      3.7      11.9    76%
Work Orders                 149      9      140    94%
Work Order Administrative Time (hours)   12.4      0.75      11.7    94%
Labor Cost                  $4,364    $2,008   $2,356   54%

Labor Hours (projected annual)      1,593     756     837    53%
Labor Cost (projected annual)       $91,370   $42,184   $49,186   54%

Aviation Maintenance 
8 
Over the past 5+ years, through our           Our number of employees has
continuous improvement efforts, we have           remained almost flat, while
optimized our Preventive Maintenance          assuming responsibility for many
programs saving 7400+ labor hours            new facilities and systems 
annually 
Employees 
380
360
340
320
300
280
2008  2009  2010  2011  2012  2013  2014
3rd Runway            Airline Common Use Systems         Pre-conditioned Air 
Additional Loading Bridges         Electric Ground Support Equipment        International Arrivals Facility 
Rental Car Facility/Bus Maintenance Facility                  NorthSTAR Infrastructure

9 

Questions?

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.