Aviation Division 
2014 Capital Budget 
Commission Briefing 
October 1, 2013

Aviation Capital Budget - Contents 
Executive Summary  To be Presented 10/1 
Full Background Presentation 
' Two Views of Drivers of Program  Century
Agenda and Aviation Strategies 
' Large Projects Dominating Capital Program and
CPE Impact 
' Summary of Budget Spending - Chart 
' Existing, New, and Small Projects - Tables 
' Risks 
2

EXECUTIVE SUMMARY 


3

Aviation Capital Budget 
Executive Summary All Projects 
Figures in $000's
5-Year Capital Plan
Number of  2013                                    Total
Categories with example projects   Projects  Estimate   2014    2015    2016    2017    2018    2014-18
A. Commission Authorized/Underway   100    145,229  187,963  170,917  282,792  223,073  206,646  1,071,391
International Arrivals Facility
Checked Baggage Optimization
NorthSTAR - Renovate NSAT Concourse
Passenger and Cargo Aircraft Parking
Electrified Ground Support Equipment
B. Pending 2013-2014 Authorization     25      6,895   31,238  122,245   60,989   15,915    3,450    233,837
Runway 16C/34C Reconstruction
Service Tunnel Rehabilitations
C. Pending Future Authorization        22       240    6,698   23,665   54,119   59,878   63,000    207,360
Airfield Ramp Pavement
Aeronautical Allowance
D. Small Projects                   5       4,055    4,620    4,196    3,856    3,000    3,000     18,672
Aviation (and ICT) Small Jobs/Projects
Aviation Small Captial Purchases
Total               152     156,419        230,519        321,023        401,756        301,866        276,096        1,531,260 

4

Aviation Capital Budget 
Executive Summary All Projects 
$450,000
NorthSTAR       $285 mil 
$400,000
' Alaska Air Group Consolidation 
$350,000                                                               Int'l Arrivals Facility    $314 mil 
' Delta and other international airline
$300,000                                                                         traffic 
Baggage Optimization  $239 mil 
$250,000
' Modernization 
$200,000
Runway 16C/34C    $89 mil 
$150,000                                                                     ' Reconstruct failing concrete 
Total = $927 mil 
$100,000

$50,000                                                                    2014 New Projects Total = $ 71 mil 

$0
2014         2015         2016         2017         2018
Existing projects      New Projects      Allowance CIPs      Four Major Projects



5

Aviation Capital Budget 
Executive Summary New Projects 



6

Aviation Capital Budget 
Executive Summary 
Additional Considerations 
Capital program is moving into period
of increased spending: 
' Anticipating and managing possible
impacts to airlines, concessions and
travelers 
' Must strengthen and streamline
ancillary support systems - processes
and people in multiple departments 
' Electrical code changes anticipated 
' Some projects still being scoped - 
CIP allowances will provide budget 

7

FULL BACKGROUND
PRESENTATION 


8

Capital Budget Summary 
Cash Flows (Figures in $000s)          2014-18
2013    2014    2015    2016    2017    2018    Total
Major Projects
NorthSTAR                  8,062   31,142       33,508      128,750   48,651       43,494       285,545
International Arrivals Facility             1,962     5,400    13,900         84,300        106,200   104,238    314,038
Baggage Optimization              5,000   15,000        62,000        67,000        60,000        35,000        239,000
Runway 16C/34C Reconstruction              1,500   75,000        13,221                      89,721
Subtotal                        15,024   53,042       184,408  293,271  214,851  182,732   928,304
Other existing projects            141,395        161,450  100,581   52,359        30,653        26,914        371,957
Proposed New Projects            -     11,027       21,034       16,126       11,362       11,450        70,999
Allowance CIPs                 -      5,000   15,000       40,000       45,000       55,000       160,000
Total Proposed CIP             156,419       230,519  321,023  401,756  301,866  276,096  1,531,260



9

Projects Driven by Century Agenda 
Triple air cargo volume to 750,000 metric tons: 
' Cargo 2 and 6 facility improvements (Ongoing) 
Make Sea-Tac Airport the west coast "Gateway of
Choice" for international travel and double the number
of international flights and destinations: 
' Construct IAF Building and Skybridge/Tunnel (Approved in 2013) 
' Add new 12th Wide Body Gate to the South Satellite (New) 
Meet the regions air transportation needs for the next
25 years 
' Enhanced Wi-Fi Coverage in the terminal (New) 
' Develop Wireless Coverage on aircraft ramp areas (New) 

10

Projects Driven by Century Agenda 
Meet all increased energy needs through conservation and renewable
sources: 
Stage 2 Mechanical Infrastructure Improvements (Ongoing) 
Stage 3 Mechanical Infrastructure Improvements (New) 
Parking Garage Security Lighting Improvements (Ongoing) 
Parking Garage Area Lighting Improvements (New) 
Meet or Exceed Agency Requirements for Storm Water: 
IWS Segregation Meters (New) 
NERA 3 Storm Water Infrastructure (New) 
Reduce air pollutants and carbon emissions: 
Pre-conditioned Air project (Ongoing) 
Electrical ground service infrastructure and charging stations (Ongoing) 


11

Projects Driven by Airport Strategies 
1. Operate a World Class Airport 
a. Safe and Secure 
o CCTV Camera/Data Improvements (New) 
b. Anticipate/meet needs of airlines, tenant, travelers 
o 12th SSAT/FIS Wide Body gate (New) 
c. Manage our Assets to Minimize Long Term Costs 
o North Utility Tunnel Steam Piping (New) 
o Passenger Boarding Bridges (New) 
o Roofing Project (New) 
o Airfield Ramp Pavement (New) 
2. Top 10 Customer Service Airports 
o SSAT Departure Aesthetics (New) 

12

Projects Driven by Airport Strategies 
3. Lead in Environmental Innovation 
o IWS Segregation Meters(New) 
o Garage Area Lighting (New) 
4. Reduce Airline Costs
o Mechanical Energy Conservation (New) 
5. Maximize Non-aero operating income 
o Concessions Infrastructure (New)
6. Invest in Employee Development, Organizational 
Improvement, and Business Agility
o 2014 items within operating budget 
7. Develop Community Partnerships 
o NERA 3 Storm Infrastructure (New) 

13

New Capital Projects in 2014 - Detail 
Cash Flows (Figures in $000s)          2014-18
CIP    Description              Budget   2014   2015   2016   2017   2018   Total
1 C800483 Airfield Ramp Pavement Program    32,500    200   - 5,000       5,000   5,000  15,200 
2 C800662 12th SSAT/FIS widebody gate (CA)   4,750    300   4,000    450               4,750
3 C800629 South-end Over Ramp Bussing (CA)    787       20    767                      787
4 C800667 Automated Passport Control (CA)    2,207   2,207    -                       2,207
5 C800549 SSAT Depart Aesthetics         18,900    -      50    100    500   1,000   1,650
6 C800653 Passenger Boarding Bridge        7,250   1,650   1,000   1,000   1,000   1,000   5,650
7 C800642 CCTV Camera/Data Improvements   11,000    350   1,000   1,900   2,300   2,450   8,000
8 C800637 Re-roof projects              5,007    350   3,000   1,657               5,007
9 C800658 Mech. Energy Conservation (CA)     3,500    700   2,000    800               3,500
10 C800581 Parking Garage Lights (CA)        5,000   1,800   1,500   1,700               5,000
11 C800638 Concessions Infrastructure (CA)     10,900    250    900   1,200   2,000   2,000   6,350
12 C800579 NERA 3 Parcel Infrastructure       1,200   1,200                           1,200
13 C800585 Wireless Coverage - Ramps        3,000    350   2,650                     3,000
14 3 CIPs  Enhanced Wi-Fi Cov - Terminal      2,198    450    297    889    562   -      2,198
15 C800645 Cargo 4 (UAL) Freight Bldg HVAC    1,000    200    800                     1,000
16 C800631 Concourse A Bridge Level HVAC      650       150    500                      650
17 C800659 North Utility Tunnel Steam Pipe      1,000    150    850                     1,000
19 C800368 Refurbish Bag Claim Device 8        500       500   - -                   500
20 C800657 Domestic Water Piping          1,950    100    850   1,000               1,950
20 C800655 IWS Segregation Meters (CA)        900       100    800                      900
21 C800493 Water Right Supply Development      500       -      70    430                500
TOTAL               114,699  11,027      21,034      16,126      11,362      11,450      70,999 


14

AV Capital Budget Large Projects 
Entering period of growing investments
driven by: 
' Customer needs  NorthSTAR 
' Capacity growth for international passengers -
International Arrivals Facility 
' Renewal and replacement of key assets: 
Baggage Optimization 
Rebuild runway 16C/34C 
The 4 projects will dominate program and
cost nearly $930 million over 5 years 

15

Large Projects 
International Arrivals Facility            NorthSTAR 







16

Large Projects 
Baggage Optimization             Runway 16C/34C Reconstruction 






17

Capital Budget Summary 
With Major Projects Broken Out 
$450,000

$400,000

$350,000

$300,000

$250,000

$200,000

$150,000

$100,000

$50,000

$0
2014         2015         2016         2017         2018
Existing projects      New Projects      Allowance CIPs      Four Major Projects
18

CPE Impact of Large Projects 



19

CIP Summary by Category 
Figures in $000s 

Number of  2013
Category          Projects  Estimate   2014    2015    2016    2017    2018    2014-18
A. Commission Authorized/Underway   100    145,229  187,963  170,917  282,792  223,073  206,646  1,071,391
B. Pending 2013-2014 Authorization     25      6,895   31,238  122,245   60,989   15,915    3,450   233,837
C. Pending Future Authorization        22       240    6,698   23,665   54,119   59,878   63,000   207,360
D. Small Projects                   5       4,055    4,620    4,196    3,856    3,000    3,000    18,672
Total               152     156,419        230,519        321,023        401,756        301,866        276,096        1,531,260





20

A. Commission Authorized/Underway 
Figures in $000s 
2013
Description        Estimate   2014    2015    2016    2017    2018    2014-18
1 International Arrivals Fac-IAF      1,962   5,400   13,900   84,300  106,200       104,238        314,038
2 Checked Bag Recap/Optimization    5,000   15,000   62,000   67,000   60,000   35,000   239,000
3 NS NSAT Renov NSTS Lobbies      4,010   8,100   18,100   92,600   44,941   38,750   202,491
4 Aircraft RON Parking USPS Site      975   33,000   5,404    - - -     38,404
5 Highline School Insulation       12,363   7,274   15,700     - 1,102 -     24,076
6 NS Refurbish Baggage Systems     1,320   8,029   2,045   10,600     - -     20,674
7 SSAT HVAC,Lights,Ceiling Repl     2,240      -  - - 8,000      12,000    20,000
8 NS Conc C Vertical Circulation      1,185   11,556   3,460   3,000    - -     18,016
9 GSE Electrical Chrg Stations       9,561   5,000   10,000   2,777    - -     17,777
10 Community College            2,030      -    4,026    8,507    - 3,782        16,315
11 NS NorthSTAR Program          1,424    2,357    2,403    2,550    2,330    4,744    14,384
12 Airfield Pavement Replacement     6,041    6,406    3,529    3,256    - -     13,191
13 Vertical Convey Modn Aero Ph1      584    5,000    5,000    2,450    - -     12,450
14 Other (87 Projects)            96,534   80,841   25,350    5,752     500    8,132   120,575
Total            145,229        187,963        170,917        282,792        223,073        206,646        1,071,391 


21

B. Pending 2013/14 Authorization 
Figures in $000s 
2013
Description        Estimate   2014    2015    2016    2017    2018   2014-18
1 RW 16C/34C Reconstruction        -   1,500   75,000  13,221     - -    89,721
2 Utility ER Backup/Standby Pwr     167    300   8,000  12,000   9,750    -    30,050
3 NS Main Terminal Improvements    123   1,100   7,500  20,000   1,380    -    29,980
4 Service Tunnel Renewal/Replace    128   5,000   10,000   7,361   1,485    -    23,846
5 Camera/Data Improvements        -    350   1,000   1,900   2,300   2,450   8,000
6 Passenger Boarding Bridge Rene      -   1,650   1,000   1,000   1,000   1,000   5,650
7 Re-roof Projects              -    350   3,000   1,657    - -     5,007
8 Parking Garage Lights            -   1,800   1,500   1,700    - -     5,000
9 Other (17 Projects)           6,477  19,188   15,245   2,150    - -    36,583
Total             6,895   31,238   122,245        60,989   15,915   3,450   233,837 



22

C. Pending Future Authorization 
Figures in $000s 

2013
Description        Estimate   2014    2015    2016    2017    2018   2014-18
1 Airfield Ramp Program           -    200   - 5,000      5,000   5,000   15,200
2 Main Terminal HVAC Upgrades       -     -    500   4,000   3,875    -     8,375
3 Concessions Infrastructure         -    250    900   1,200   2,000   2,000   6,350
4 Aeronautical Allowance           -   3,000  10,000  30,000  30,000  40,000  113,000 
5 Non-Aeronautical Allowance        -   2,000   5,000  10,000  15,000  15,000   47,000
6 Other (17 Projects)            240   1,248   7,265   3,919   4,003   1,000   17,435
Total              240    6,698   23,665   54,119   59,878   63,000   207,360 




23

D. Small Projects 
Figures in $000s 

2013
Description      Estimate   2014    2015    2016    2017    2018   2014-18
1 Aviation Small Jobs          -     -    417   2,000   2,000   2,000   6,417
2 Aviation Small Capital        -    420    703   1,000   1,000   1,000   4,123
3 Aviation Small Jobs       2,290   2,000   1,876    - - -    3,876
4 AV/IT Small Capital Projects    888   1,200   1,200    856   - -    3,256
5 Aviation Small Capital       877   1,000    - - - -    1,000
Total           4,055   4,620   4,196   3,856   3,000   3,000   18,672




24

Program - Risks 
Capital program is moving into period of
increased spending: 
'Anticipating and managing possible impacts
to airlines, concessions and travelers 
'Must strengthen and streamline ancillary
support systems - processes and people in
multiple departments 
'Electrical code changes anticipated 
'Some projects still being scoped; CIP
allowances will provide budget 

25

Seaport Division 
2014 Capital Budget 
Commission Review 
October 1, 2013

Seaport 2014 Capital Budget Review 
Capital Budget reviewed by cross functional teams 
Reviewed all existing projects and identified new
projects as driven by: 
2014 Seaport Strategies and Century Agenda 
New developments and information from customers and tenants 
Continuing effort to identify specific renewal and replacement
projects 
First draft of Seaport 2014 Capital Budget presented
with Business Plan in August 2013. 
Primary change since Business Plan is acceleration of
the timing for T5 Upgrade of Existing Docks. 

27

Seaport 2014 Capital Budget Review (continued) 
Per policy effective in 2010, Seaport is financially
self-sustaining 
Funding capacity for projects not yet determined 
Projects have been ranked as follows: 
Priority  1-Highest:  In  progress  and/or  most  critical  to  2014 
business plan and/or lease commitment 
Priority 2-High: Critical to 2014 business plan, some uncertainty 
Priority 3-Medium: Less critical to 2014 business plan and/or
more uncertainty 



28

Seaport 2014 Capital Budget 

Capital Budget Summary 
$'s in 000's                           2014     2015     2016     2017     2018    2014-18
Commission Authorized/Underway      21,505   14,806   24,025   13,325     261   73,922
Pending 2013/2014 Authorization        1,618    1,375     100       0       0    3,093
Pending Future Authorization         10,698   25,327   27,400   63,450   55,255   182,130
Small Projects                   1,225    1,202    1,250    1,000    1,035    5,712
Total                          35,046   42,710   52,775   77,775   56,551   264,857





29

Seaport 2014 Capital Budget 
Commission Authorized*/Underway 
$'s in 000's                     Priority   2014     2015     2016     2017     2018    2014-18
Seaport P66 Apron Pile Wrap       1       400       0       0       0       0     400
T30 Alaskan Way Street Vacation     1        0     500    5,000       0       0    5,500
T5 Street Vacation Completion       1       300       0       0       0       0      300
T18 Street Vacation Completion      1      1,210       0       0       0       0    1,210
T30/91 Program               1       70       0       0       0       0      70
Cruise Cap Allow - CTA Lease       1       200     200     200     200     200    1,000
Cruise per Passenger Allowance      1        73      74      75      75      61     358
Argo Yard Roadway Element I       1      1,594       0       0       0       0    1,594
T-46 Development               1     12,450    4,000    9,000    9,050       0   34,500
P90 C175 Roof Replacement        1     2,261      0      0      0      0    2,261
T46 Dock Rehabilitation            1      1,347    9,000    9,000    4,000       0    23,347
T46 Public Access Mitigation at T117   1      1,600    1,032      750       0       0    3,382
Total                            21,505   14,806   24,025   13,325     261   73,922

Note*: Includes projects where some portion of the budget is authorized by
Commission 

30

Seaport 2014 Capital Budget 
Pending 2013/2014 Authorization 
$'s in 000's                      Priority   2014      2015      2016      2017      2018     2014-18
Terminal 91 Lighting Upgrade      1       368       0       0       0       0      368
T91 Substation Upgrades        1      1,150    1,275       0       0       0    2,425
T46 Viaduct Driven Capital Work    1       100      100      100       0       0      300
Total                           1,618    1,375     100       0       0    3,093






31

Seaport 2014 Capital Budget 
Pending Future Authorization 
$'s in 000's                     Priority   2014     2015     2016     2017     2018    2014-18
P34 Dolphns & Catwalks for 4 Barges   1      2,120     300       0       0       0    2,420
Second Gangway per Berth @ T91    2     1,000    3,500      0      0    5,000    9,500
T-91 Berth 6 & 8 Redevelopment      2       100     800    8,900    15,200       0    25,000
P91 South End Fender Replacement   2        0     150     950     150       0    1,250
T91 Camel Replacements         2        0      0      0      0    1,255    1,255
T18 Dock Rehabilitation            2      1,600    12,000    4,000       0       0    17,600
T5 Upgrade 600' Existing Docks      2         0    1,000    1,000    33,000    33,000    68,000
West Waterway Deepening        2        0     325     300     300     500    1,425
East Waterway Deepening         2        0     325     300     300     500    1,425
T5 Dock Rehabilitation             2         0       0      800     3,500    3,500    7,800
Contingency Renewal & Replace     2      5,000    6,000    6,000    6,000    8,500   31,500
Seaport Security Rnd 13           3       778      27       0       0       0     805
SCCT Freight Elevator            3       100      500      150       0       0      750
T46 Replace South Pier           3         0     400    5,000    5,000       0    10,400
Mega Berth (depth) Loc TBD        3        0       0       0       0    2,000    2,000
T30 Dock Rehabilitation            3         0       0       0       0    1,000    1,000
T25 Dock Rehabilitation **          3         0       0       0       0       0       0
Total                            10,698   25,327   27,400   63,450   55,255   182,130
For projects marked with asterisk **, the cash investment is forecasted to take place in the 2019-2023
timeframe. 

32

Seaport 2014 Capital Budget 

Small Projects 

$'s in 000's                 Priority   2014     2015     2016     2017     2018    2014-18
Small Capital Projects         1        550      500      500      500      500     2,550
Preliminary Planning         2       250      250      250      250      250    1,250
Seaport Technology Projects    2       250      250      250      250      250    1,250
Seaport Fleet Replacement     2       175     202     250       0      35     662
Total                         1,225    1,202    1,250    1,000    1,035    5,712






33

Seaport 2014 Capital Budget 
Century Agenda Connections 
Position Puget Sound region as a premier logistics hub: 
Grow container volume to 3.5 million TEU's 
Projects                             2014-2018   2019-2023     Total 
T18 Dock Rehabilitation                       17,600         0     17,600
T5 Upgrade 600' Existing Docks                 68,000      5,000     73,000
West Waterway Deepening                   1,425     18,500     19,925
East Waterway Deepening                    1,425     14,500     15,925
T5 Dock Rehabilitation                         7,800         0      7,800
Mega Berth (depth) Location TBD                 2,000     21,000     23,000
T30 Dock Rehabilitation                       1,000      9,000     10,000
T25 Dock Rehabilitation                          0      2,900      2,900
Total                                     99,250      70,900     170,150
Double the economic value of the fishing and maritime cluster 
Projects                             2014-2018   2019-2023     Total 
P34 Dolphins & Catwalk for 4 Barges               2,420         0      2,420
T91 Berth 6 & 8 Redevelopment                 25,000        0     25,000
T91 Substation Upgrades                      2,425        0      2,425
P91 South End Fender Replacement              1,250        0      1,250
Total                                    31,090         0      31,090

34

Seaport 2014 Capital Budget 
Century Agenda Connections 
Advance this region as a leading tourism destination and business gateway 
Double the economic value of cruise traffic to Washington State 
Projects                        2014-2018      Total 
Second Gangway per Berth @ T91           9,500        9,500 
Terminal 91 Camel Replacements             1,255        1,255 
Total                                 10,755        10,755 

Be the greenest and most energy efficient port in NorthAmerica** 
Meet all increased energy needs through conservation and renewablesources 
Projects                         2014-2018      Total 
Terminal 91 Lighting Upgrade                 368          368 
Total                                   368           368 
**Note: Northwest Ports Clean Air Initiatives are classified as Non-Operating Expense and will be
covered in the October 8th Briefing. 

35

Real Estate Division 
2014 Capital Budget 
Commission Review 
October 1, 2013

Real Estate Capital Budget Review 
Capital Budget reviewed by cross functional teams 
Reviewed all existing projects and identified new
projects as driven by: 
2014 Real Estate Strategies 
Continuing effort to quantify/identify specific renewal and
replacement projects 
First draft of Real Estate 2014 Capital Budget
presented with Business Plan in August 2013 
Overall 2014-2018 dollar amount of projects
remained at ~$55 million 
Funding capacity for projects not yet determined 

37

Real Estate 2014 Capital Budget 

Capital Budget Summary 
$'s in 000's                      2014      2015      2016      2017      2018     2014-18
Commission Authorized/Underway    8,998      0      0      0      0    8,998
Pending 2013/2014 Authorization      4,118    2,430    3,450    2,450       0    12,448
Pending Future Authorization        1,200    4,948    2,960    7,887    4,115    21,110
Small Capital and Other           3,327    2,842    2,106    2,231    2,022    12,528
Total                        17,643    10,220     8,516    12,568     6,137    55,084





38

Real Estate 2014 Capital Budget 

Commission Authorized*/Underway 
$'s in 000's                    Priority    2014      2015      2016      2017      2018     2014-18
P69 N Apron Corrosion Control        1        639       0       0       0       0      639
FT Net Shed 9 Roof Replacement      1       373       0       0       0       0      373
SBM Central Seawall Replacemnt     1       663       0       0       0       0      663
FT C-2 (Nordby) Roof & HVAC       1      1,823       0       0       0       0     1823
FT C15 HVAC Improvements        1      3,470       0       0       0       0     3470
Pier 66 Steam Replacement         1       279       0       0       0       0      279
P69 Built-Up Roof Replacement       1      1,751       0       0       0       0     1,751
Total                              8,998       0       0       0       0     8,998

Note*: Includes projects where some portion of the budget is authorized by Commission 

39

Real Estate 2014 Capital Budget 
Pending 2013/2014 Authorization 
$'s in 000's                  Priority    2014      2015      2016      2017      2018     2014-18
Bell Harbor Marina Pile Wraps      1        100     1,500     1,000        0        0     2,600
SBM Restroom Replacement     1       100     700    2,000    2,000      0    4,800
SBM Paving               1        0     100     450     450      0    1,000
FT Paving/Storm Upgrades       1      3,000      130       0       0       0    3,130
FT C-15 Bldg East Sewer Line     1       612       0       0       0       0      612
FT C15 Bldg Subsidence Improve    1       306       0       0       0       0      306
Total                           4,118     2,430     3,450     2,450       0    12,448





40

SBM Restroom Replacement 




41

SBM Restroom Replacement 




42

FT C-15 Bldg Subsidence Improvements 
(Sidewalk Subsidence with Differential Settlement) 







43

FT Paving / Storm Drain Upgrades 
(Alligator Cracking and Failed Asphalt) 







44

Real Estate 2014 Capital Budget 
Pending Future Authorization 
$'s in 000's                         Priority    2014      2015      2016      2017      2018     2014-18
SBM A Dock Finger Pier Rehabilitation       2        450       0       0       0       0      450
Harbor Island Marina E Dock             2        400       0       0       0       0      400
SBM Fuel Float and Bldg Improvements      2       200      900       0       0       0    1,100
FT Net Shed 3 or 8 Roof Replacement       2         0      541       0       0       0      541
MIC West & Central Piers Resurfacing       2         0      477      150       0       0      627
T102 Bldg Roof Replacement            2       150    2,280       0       0       0    2,430
FT 25 Year Plan Improvements           2         0      250      618       0       0      868
FT Net Shed 6 Roof Replacement          3         0       0      481       0       0      481
FT Net Shed 5 Roof Replacement          3         0       0      461       0       0      461
Harbor Island Marina C Dock             3         0       0      350       0       0      350
FT Dock 4 Fixed Pier Improvement         3         0       0      200     3,300       0     3,500
FT Dock 3 Fixed Pier Improvement         3         0       0      200     2,800       0     3,000
FT Net Shed 4 or 7 Roof Replacement       3         0       0       0      503       0      503
FT S Wall Wt End Improvements          3         0       0       0      174    1,500    1,674
FT C14 (Downie) Roof & HVAC           3        0       0       0     110     865     975
Harbor Island Marina ABD Dock           3         0       0       0       0      350      350
FT W Wall N Fender Replacement         3        0       0       0       0     200     200
FT W Wall N Sheet Pile Corr Protect        3         0       0       0       0      200      200
FT Net Shed Electrical System**           3         0       0       0       0       0       0
FT Net Shed 10 Roof Replacement**        3         0       0       0       0       0       0
FT Net Shed 11 Roof Replacement**        3         0       0       0       0       0       0
FT S Wall Ctrl Fender Repl & Corr Protect**    3          0        0        0        0        0        0
FT W Wall S Sheet Pile Corr Protect**       3         0        0        0        0        0        0
RE: Contingency Renew&Replace         3        0     500     500    1,000    1,000    3,000
Total                                  1,200     4,948     2,960     7,887     4,115    21,110
Note: For projects marked with asteriks **, the cash investment is forecasted to take place in the 2019-2023 timeframe. 

45

Real Estate 2014 Capital Budget 

Small Projects 
$'s in 000's                     Priority    2014      2015      2016      2017      2018     2014-18
Small Capital Projects              1       1,620     1,450      490      575      500     4,635
Preliminary Planning              1        250      250      250      250      250     1,250
RE Technology Projects           1       458      250      250      250      250     1,458
RE Fleet Replacement            1       699      592      816      856      722    3,685
Tenant Improvements - Capital        1        300      300      300      300      300     1,500
Total                              3,327     2,842     2,106     2,231     2,022    12,528





46

Corporate and Capital
Development Divisions
2014 Capital Budget 
Commission Briefing 
October 1, 2013

Enterprise, Corporate and CDD 
Capital Budget Overview 



48

Enterprise, Corporate and CDD 
Commission Authorized/Underway 
2014-2018 Project
Five Year Capital Plan                 2013   2014   2015   2016   2017   2018   Totals   Budget 
Commission Authorized Projects 
Radio System Upgrade (800MHz)     U  3,400  3,350                     3,350  6,750 
Maximo Enhancements & Upgrades   U   543  435                     435  3,780 
ID Badge System Replacement      U  1,405  1,070                     1,070  2,500 
PeopleSoft Financials Upgrade       U  4,635                              -  5,000 
SharePoint Records & Doc Mgmt     U    99                            -   800 
Constr Doc Mgmt Sys Replacement   U   100  800                      800   900 
Project Delivery System           N    439                           -  1,525 
Police Records Management System   U   879                            -  1,300 
Totals                           11,500  5,655      -  -  -  -   5,655 22,555 
N = New System U = System Upgrades or Replacements 

49

Enterprise, Corporate and CDD 
Pending 2014 Authorization 
2014-2018  Project
Five Year Capital Plan:           2014  2015  2016  2017  2018   Totals   Budget
Projects Pending 2014 Authorization
911 Computer Dispatch Upgrade     U   525                          525    525
Contractor Data System Replacement  U   500  1,000                        1,500   1,500 
Network Switch Replacement       U  1,500                             1,500   1,500 
Totals                           2,525      1,000          -     -     -     3,525    3,525 
N = New System U = System Upgrades or Replacements


50

Enterprise, Corporate and CDD 
Small Capital and 
Future Authorization: ICT Allowance 
2014-2018 
Small Capital                 2013   2014   2015   2016   2017   2018    Totals 
Technology Infrastructure        1,500   1,500   1,500   1,500   1,500   1,500     7,500 
Technology Business Applications    785   1,000   1,000   1,000   1,000   1,000    5,000 
Enterprise GIS Small Capital        200    250    250    250    250    250     1,250 
Corporate Small Capital           200    200    200    200    200    200     1,000 
Corporate Fleet Replacement      658    314    346    356    269    356    1,641 
CDD Small Capital              270    275    274    107     75    110      681 
CDD Fleet Replacement          456    264    744    759    585    644    2,996 
Total Small Capital               4,069   3,803   4,314   4,172   3,879   4,060    20,228 
Future Authorization: ICT Allowance 
ICT Allowance                  -      -   3,500   4,500   4,500   4,500    17,000 
Combined Totals               4,069  3,603  7,814   8,672   8,379   8,560    37,228 

51

Portwide Rollup 
2014 Capital Budget 
Commission Briefing 
October 1, 2013

Capital Budget Summary - Portwide 
Capital Budget Summary by Category 

$'s in 000's                        2014      2015      2016      2017      2018     2014-18
Commission Authorized/Underway    224,121  185,723  306,817  236,398  206,907 1,159,966
Pending 2013/2014 Authorization      39,499       127,050   64,539        18,365         3,450   252,903
Pending Future Authorization        18,596        57,440        88,979       135,715   126,870   427,600
Small Capital and Other            12,975        12,554        11,384        10,110        10,117        57,140 
Total                       295,191   382,767   471,719   400,588   347,344  1,897,609



53

Capital Budget Summary - Portwide 
Capital Budget Summary by Division 

$'s in 000's          2014      2015      2016      2017      2018     2014-18
Aviation          230,519   321,023   401,756   301,866   276,096  1,531,260
Seaport          35,046    42,710    52,775    77,775    56,551   264,857 
Real Estate         17,643    10,220     8,516    12,568     6,137    55,084
Corp & CDD       11,983    8,814    8,672    8,379    8,560   46,408
Total            295,191   382,767   471,719   400,588   347,344  1,897,609



54

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.