Shilshole Bay Marina

INTERNAL AUDIT REPORT 

SHILSHOLE BAY MARINA 
COMPREHENSIVE OPERATIONAL AUDIT 

JANUARY 1, 2013  JUNE 30, 2014 

ISSUE DATE: JULY 29, 2014 
REPORT NO. 2014-12

SHILSHOLE BAY MARINA                                                          INTERNAL AUDIT 
JANUARY 1, 2013  JUNE 30, 2014 

TABLE OF CONTENTS 


TRANSMITTAL LETTER .......................................................................................... 3 
EXECUTIVE SUMMARY ......................................................................................... 4 
BACKGROUND ..................................................................................................... 5 
FINANCIAL HIGHLIGHTS....................................................................................... 5 
HIGHLIGHTS AND ACCOMPLISHMENTS ................................................................ 5 
AUDIT SCOPE AND METHODLOGY ......................................................................... 6 
CONCLUSION ....................................................................................................... 7 









2

SHILSHOLE BAY MARINA                                                          INTERNAL AUDIT 
JANUARY 1, 2013  JUNE 30, 2014 

TRANSMITTAL LETTER 
Audit Committee 
Port of Seattle 
Seattle, Washington 
We have completed an audit of Shilshole Bay Marina. We reviewed information for the period January
1, 2013 - June 30, 2014. 
We conducted the audit in accordance with Generally Accepted Government Auditing Standards and
the International Standards for the Professional Practice of Internal Auditing. Those standards require
that we plan and perform the audit to obtain sufficient, appropriate evidence to provide a reasonable
basis for our findings and conclusions based on our audit objectives. We believe that the evidence
obtained provides a reasonable basis for our findings and conclusions based on our audit objectives. 
We extend our appreciation to the management and staff of the Harbor Services Department for their
assistance and cooperation during the audit. 


Joyce Kirangi, CPA, CGMA 
Internal Audit, Director 

AUDIT TEAM                                RESPONSIBLE MANAGEMENT TEAM 
Benjamin Wolfgram, Senior Auditor           Tracy McKendry, General Manager  Recreational Boating 
Jack Hutchinson, Audit Manager              Darlene Robertson, Director  Harbor Services (retired) 







3

SHILSHOLE BAY MARINA                                                          INTERNAL AUDIT 
JANUARY 1, 2013  JUNE 30, 2014 
EXECUTIVE SUMMARY 

AUDIT OBJECTIVES AND SCOPE 
The purpose of the audit was to determine whether Shilshole Bay Marina management controls are
adequate to ensure: 
1.  Guest Moorage, Dry Moorage, and Parking revenue is complete and charged at the appropriate
rate. 
2.  Rates are charged in accordance with the approved tariff. 
3.  Customer liability insurance complies with requirements. 
We reviewed information for the period January 1, 2013 - June 30, 2014. Details of our audit's scope
and methodology are on page 6. 

BACKGROUND 
Harbor Services within the Port of Seattle's Real Estate Division operate Shilshole Bay Marina. The
Commission-approved Moorage Tariff No. 6 governs the Department's revenue streams. The tariff
specifies the rates and charges for services provided by the Marina, including berthage and moorage,
electricity, live-aboard fees, equipment rental, and other services. 
Berthage and Moorage is the primary revenue stream for the Marina, which provides monthly and guest
moorage, primarily to recreational boating customers, including live-aboard customers. In addition to
moorage slips in the marina, Shilshole Bay Marina has dry moorage slips available for customers to store
their boats in a dedicated area out of the water, and the Marina makes additional space available for
this purpose in the off-season. Guest Moorage fees are determined by the length of stay and the overall
length of the vessel. Monthly moorage rates are determined by the length of the slip occupied by the
vessel. 
AUDIT RESULT
Management controls are adequate to ensure that Guest Moorage, Dry Moorage, and Parking revenue is
complete and charged appropriately. Management controls are also adequate to ensure compliance
with the approved tariff and customer insurance requirements. 





4

SHILSHOLE BAY MARINA                                                          INTERNAL AUDIT 
JANUARY 1, 2013  JUNE 30, 2014 

BACKGROUND BACKGROUND 
Shilshole Bay Marina is operated by Harbor Services within the Port of Seattle's Real Estate Division.
The Commission-approved Moorage Tariff No. 6 governs the rates and charges applicable to Marina
operations. The tariff specifies the rates and charges for services provided by the Marina, including
berthage and moorage, electricity, live-aboard fees, equipment rental, and other services. Shilshole
Bay Marina manages its operations using the Marina Management System, which is shared by all of the
Harbor Services facilities. 
Shilshole Bay Marina generates over $8 million in revenue annually. Berthage and Moorage is the
primary revenue stream for the Marina, which provides monthly and guest moorage, primarily to
recreational boating customers, including live-aboard customers. In addition to moorage slips in the
marina, Shilshole Bay Marina also has dry moorage available for customers to store their boats in a
dedicated area out of the water. Guest Moorage charges are determined by the length of stay and the
overall length of the vessel. Monthly moorage charges are determined by the length of the slip
occupied by the vessel. 
FINANCIAL HIGHLIGHTS 
FINANCIAL HIGHLIGHTS 
FINANCIAL HIGHLIGHTSFINANCIAL HIGHLIGHTS 
SHILSHOLE BAY MARINA DEPARTMENTAL REVENUES BY FISCAL YEAR 
AGREEMENT YEAR                     2011               2012               2013 
Berthage & Moorage: 
Monthly Moorage                $ 7,257,424           $ 7,201,171           $ 7,372,506 
Guest Moorage                      203,579              233,988              211,776 
Dry Moorage                        160,213              172,647              182,661 
Other Moorage                       18,197                8,987               12,440 
Parking                                  10,802                 14,931                 10,356 
Other Revenue                        592,412              607,835              658,695 
TOTAL                       $ 8,242,627         $ 8,239,560         $ 8,448,434 
Data Source: PeopleSoft Financials 

HIGHLIGHTS AND ACCOMPLISHMENTS HIGHLIGHTS AND ACCOMPLISHMENTS 
During the course of the audit, we noted the following highlights and accomplishments. The
Department: 
Developed an off-season dry storage line of business to expand dry moorage capacity throughout
the winter months. 
Participates in National Marina Day, a nationwide boating event dedicated to growing participation
in recreational boating. 
Hosts  an  event  for  National  Night  Out,  which  promotes  police-community  partnerships,
neighborhood camaraderie, and involvement in crime prevention activities. 


5

SHILSHOLE BAY MARINA                                                          INTERNAL AUDIT 
JANUARY 1, 2013  JUNE 30, 2014 

AUDIT SCOPE AND METHODOLOGY 
AUDIT SCOPE AND METHODLOGY 

We reviewed information for the period January 1, 2013 - June 30, 2014. We utilized a risk-based audit
approach  from  planning  to  testing. We  gathered  information  through  research,  interviews,
observations, and data analysis, in order to obtain a complete understanding of the operations of
Shilshole Bay Marina. We assessed significant risks and identified controls to mitigate those risks. We
evaluated whether the controls were functioning as intended. 
We applied additional detailed audit procedures to areas with the highest likelihood of significant
negative impact as follows: 
1.  Guest Moorage Revenue 
We selected a sample of 12 days during August and December 2013 and traced all vessels
identified  by  management's  boat  check  to  guest  moorage  assignments  in  the  Marina
Management System to determine whether all vessels observed in the marina were captured in
the system and billed the appropriate rate based on recorded vessel information. 
2.  Dry Moorage Revenue 
We conducted a physical inventory of the 92 slips in the dry moorage yard on June 24 & 26,
2014, and traced our observations to the dry moorage assignments in the Marina Management
System to determine whether all vessels in the dry moorage area were recorded as dry moorage
customers and whether there were unauthorized vessels present. 
3.  Parking Revenue 
We traced the log of all parking permits for 2014 issued through June 26, 2014 to the record of
documents issued in the Marina Management System to determine whether all permits were
recorded and whether customers were charged for permits as required by the Moorage Tariff. 
4.  Tariff Compliance 
We traced the billing rates contained in the Marina Management System to the current version
of the Moorage Tariff, effective May 1, 2014, to determine whether the rates in the system
agreed to the rates specified by the tariff. 
5.  Insurance Compliance
We selected a sample of 59 customers with monthly assignments in June 2014 and reviewed
their files to determine whether documentation of liability insurance was on file and in
compliance with requirements. 


6

SHILSHOLE BAY MARINA                                                          INTERNAL AUDIT 
JANUARY 1, 2013  JUNE 30, 2014 

CONCLUSION CONCLUSION 
Management controls are adequate to ensure that Guest Moorage, Dry Moorage, and Parking revenue is
complete and charged appropriately. Management controls are also adequate to ensure compliance
with the approved tariff, and customer insurance requirements. 

















7

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.