7a report

Item Number:  7a_Report 
Meeting Date: Sep. 10, 2013


Commission Staff Brieng
Capital Improvement Projects
Second Quarter Report 2013

This page intentionally left blank









ii  Port of Seattle 2Q 2013 Report

Port of Seattle
Capital Improvement Project Report
Second Quarter 2013
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the status of the Port's capital projects.
Background
During 2013 the Port plans to invest over $225,500,000 to expand and upgrade the infrastructure that supports marine
and aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping
companies, airlines, rental car companies, concessionaires and public parking. About 4 percent of the Port's capital
budget comes from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in
transportation facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes a "Status Snapshot" illustrating at a
glance if the project is on schedule, within budget, the total number of change orders to date, and the total value of
executed change orders.
x Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x Budget addresses the total project budget and includes things like overall budget status, recent Commission
authorizations, forecasted overruns or savings, and scope changes.
x Change Orders provides a description of CO for the reporting period and information on any CO over $200,000 or
10% of the contract value.
x Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x Budget Transfers reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page and select the Audit/Accountability button. Use the form to ask a
question, make a comment or request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 2Q 2013 Report  1

Aviation
Overall Project  Variance since
Status        last report
CIP Number   Project Title                   Page       Schedule  Budget
C000683 et al .......3rd Runway Program .............................................6 ........... 
C100266 et al .......Rental Car Facility ............................................... 7-8..........
C102032 ...............Sanitary Sewer Pump Station Upgrade ................9 ...........
C102163................Main Terminal Baggage Screening ......................10 ..........
C102334 ...............Water System Isolation Valve Upgrade ................11 ..........
C102573 ...............Aireld Pavement Replacement ...........................12 ..........
C800019 ...............Gate Utilities Improvement ...................................13 ..........
C800034 ...............North Expressway Relocation ..............................14 ..........
C800061 ...............Main Terminal South Low Voltage ........................15 ..........
C800105 ...............Airport Owned Gate Infrastructure .......................16 ..........
C800107 ...............C4 UPS System Improvements ............................17 ..........
C800112................Runway 16C/34C Panel/Joint Sealant .................18 ..........
C800148 ...............GML Arrivals Hall Concessions ...........................19 ..........
C800168 ...............C60-C61 BHS Modications ................................20 ..........
C800174................FIS - New Primary Inspection Booths ..................21 ..........
C800203 ...............Common Use Lounge Remodel ...........................22 ..........
C800218 ...............Security Exit Lane Breach Control Phase I ..........23 .......... ...............
C800230 ...............Emergency Lighting Parking..............................24-25 .......
C800234 ...............Feeder 101 Tap Replacement ..............................26 ..........
C800237 ...............Terminal Escalators Modernization ......................27 ..........
C800238 ...............Central Plant Pre-Conditioned Air .....................28-29 .......
C800247 ...............Cargo 2 West Hardstand ......................................30 ..........
C800251 ...............Vertical Conveyance Modernization.....................31 ..........
C800253 ...............Parking System Replacement ..............................32 ..........
C800254 ...............Aircraft RON Parking Post Ofce Site..................33 ..........
C800267 ...............Port Owned Loading Bridges ...............................34 ..........
C800268 ...............Stage 2 Mechanical Energy Implementation .......35 ..........
C800274 ...............8th Floor Weather Proong ..................................36 ..........
C800276 ...............Common Use Equipment Expansion (CUSE) ......37 ..........
C800324 ...............Long-Term Cell Phone Lot ....................................38 ..........
C800334 ...............Two new CTE Freight Elevators ...........................39 .......... 
C800335 ...............EGSE Electrical Charging Stations ...................40-41 .......
C800374 ...............Claim Device 14 and Lower Inland .......................42 ..........
C800375 ...............Vertical Conveyance Modernization.....................43 ..........
C800376 ...............South Satellite HVAC, Lights, and Ceiling Repl. ..44 ..........
C800382 ...............BHS (C22-C1, MK1 and TC3) ............................45-46 .......
C800390 ...............Cargo 6 Enhancements ........................................47 ..........
C800406 ...............RW 16C/34C Reconstruction Design ...................48 ..........


2  Port of Seattle 2Q 2013 Report

Overall Project  Variance since
Status        last report
CIP Number   Project Title                   Page        Schedule  Budget
C800412 ...............South Satellite Concessions Project ....................49 ..........
C800414 ...............Access Control Door Additions ............................50 ..........
C800415 ...............ALCMS Upgrade...................................................51 ..........
C800417 ...............Lagoon 3 Bird Wires .............................................52 ..........
C800426 ...............FIS Improvement - Short Term .............................53 ..........
C800451 ...............Doug Fox Site Improvement .................................54 ..........
C800455 ...............Concourse D Common Use Environment ............55 ..........
C800459 ...............2011-2013 Roof Replacement Program ...............56 ..........
C800461 ...............IWTP Fiber Installation .........................................57 ..........
C800466 ...............South Satellite - Additional Gate Lobby ................58 ..........
C800467 ...............PLB Replacement .................................................59 ..........
C800472 ...............Exterior Gate Improvements ................................60 ..........
C800473 ...............CUSE at Ticket Counters/Gates - AR ..................61 .......... ................................................................................
C800474 ...............Airport Signage .....................................................62 ..........
C800475 ...............Miscellaneous Building Improvements - AR.........63 ..........
C800479 ...............Fire Station Electrical Upgrades ...........................64 ..........
C800484 ...............Laptop Power In Concourses ...............................65 ..........
C800490 ...............New Window Wall Ticket Zone 1 ..........................66 ..........
C800491 ...............Convert Ticket Zone 2 Pusback ...........................67 ..........
C800492 ...............Convert Ticket Zone 3 Flow Thru .........................68 ..........
C800495 ...............Facility Monitoring System Renewal ....................69 ..........
C800497 ...............Airport Wide Mechanical Controls System ..........70 ..........
C800541 ...............RAC Baggage Claim Renovation .........................71 .......... .............................. 
C800544 ...............NorthSTAR Program.............................................72 ..........
C800547 ...............NorthSTAR Concourse C Vertical Circ. ...............73 ..........
C800551 ...............Grease Interceptor Augmentation ........................74 ..........
C800555 ...............NorthSTAR Refurbish Baggage Systems ............75 ..........
C800556 ...............NorthSTAR North Satellite Renovations ...........76-77........
C800560 ...............MT Mezzanine Tenant Relocation ........................78 ..........
C800576 ...............Known Crew Member Employee Bypass .............79 ..........
C800605 ...............Security Exit Lane Breach Control .......................80 .......... .............................. 
C800609 ...............NSAT - STS Ceiling Leak Repair ..........................81 ..........
C800611 ...............Passenger Bridge & Walkway S16 Repl ..............82 ..........
C800612 ...............Checked Baggage Recapitalization/Optimzation.83 ..........
C800615 ...............Second Floor Mezzanine Infra Upgrade ..............84 ..........




Port of Seattle 2Q 2013 Report  3

Other Aviation ..........................................................................
Overall Project  Variance since
Status        last report
CIP Number   Project Title                   Page       Schedule  Budget
C200007...............Highline School Noise Insulation ..........................85 ..........
C200042 ...............Highline Community College Noise Insulation .....86 ..........
C200048 ...............Home Insulation Retrot .......................................87 ..........
C200093 ...............Single Family Home Sound Insulation .................88 ..........
C800146 ...............RMU/Kiosk Concession Program ........................89 ..........
C800150 ...............Burien Commercial Property Acquisition .............90 ..........
C800154 ...............Tenant Reimbursement ........................................91 ..........
C800498 ...............Snow Removal Equipment ...................................92 ..........

Seaport
Overall Project  Variance since
Status        last report
CIP Number   Project Title                   Page       Schedule  Budget
C102554............... Terminal 46 Development....................................93 ..........
C102858 et al ....... Street Vacations T-5/18/105.................................94 ..........
C800183 ...............P91 Fender System Upgrade ...............................95 ..........
C800349 ...............T-5 Crane Cable Reels .........................................96 ..........
C800430 ...............T-91 Building C175 Roof Replacement ................97 ..........
C800516 ...............SEA P-66 Apron Pile Wrap ..................................98 ..........
C800546 ...............Argo Yard Truck Roadway ................................99-100 ......
C800596 ...............P66 Security Camera Upgrade ...........................101 .........
C800603 ...............T-46 Dock Rehabilitation .....................................102 .........

WP Number   Project Title                 Page
E102007 ................East Marginal Way Grade Separation .................103 .........
E104324 ................Viaduct Construction Coordination .....................104 .........
E104840................T-5 and T-18 Maintenance Dredging ...................105 .........
Real Estate
Overall Project  Variance since
Status        last report
CIP Number   Project Title                   Page       Schedule  Budget
C800137 ...............FT C15 HVAC Improvements ..............................106 .........

4  Port of Seattle 2Q 2013 Report

Real Estate, cont.
Overall Project      Variance since
Statuslast report
CIP Number   Project Title                   Page       Schedule  Budget
C800313 ...............P69 N. Apron Corrosion Control .........................107 .........
C800314 ...............P69 Built Up Roof Replacement ..........................108 .........
C800571 ...............MIC Built-up Roof Replacement ..........................109 .........
C800625 ...............Pier 66 Steam Replacement................................110 .........
E104838................FT Net Shed Code Compliance ..........................111 .........
Corporate

Overall Project      Variance since
Statuslast report
CIP Number   Project Title                   Page       Schedule  Budget
C101117 ................Flight Information Systems (FIMS) II ...................112 .........
C800003 ...............Maximo Enterprise Implementation .....................113 .........
C800162 ...............ID Badge Replacement .......................................114 ......... .............................. 
C800222 ...............Airline Activity Management ................................115 .........
C800321 ...............Enterprise Project Cost Management ..................116 .........
C800322 ...............Records and Document Management .................117 .........
C800387 ...............Time Clock System ..............................................118 .........
C800392 ...............PeopleSoft Financial Upgrade .............................119 .........
C800393 ...............Police Records Management System .................120 .........
C800558 ...............Access Control Network Refresh ........................121 .........


Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Variance Status
Variance Since Last Report




Port of Seattle 2Q 2013 Report  5

SECOND QUARTER REPORT, 2013
3rd Runway Program
Status Snapshot
On Schedule
Project: C000683,           The 3rd Runway Program
On Budget
C001138, C001175,         constructed a new 8,500 foot long
19 Change Orders
C001331, C001751,         runway, connecting taxiways, and
Total Change Orders Amount:
C001760, C100172         related infrastructure.
$95,337
Budget: $918,994,759
Phase: Construction                                   Budget/Costs Incurred
Start: 05/27/1997
1150
Completion: 12/31/2011
1100
1050
Significant Developments                              1000  Millions
950
Pond M Modifications project is in contract closeout.                      900  Dollars in 850
Schedule                                          800
Authorized   Forecasted     Costs
The remaining construction work includes RST property site                                    Incurred
restoration. Buildings foundations and impervious surfaces are to be
removed from the site.
Construction Costs
Budget
2
The project forecast is within the approved budget and authorization.
1.5
Additional savings is anticipated.                                           Millions   1
Change Order
0.5
No change orders were executed this quarter.                           Dollars in 
0
Initial   Change   Spent
Risks                                                         Orders
None
Photo
Budget Transfer
None this quarter.



AIRPORT
6  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Rental Car Facility                                  Status Snapshot  Prior Report
Delayed Schedule  3Q 12
Project:    C100266,       The program will construct a           Under Budget            1Q 13
C102167, C800032        consolidated rental car facility (RCF)   1,751 Change Orders
Budget: $380,743,675     for all rental car companies at the      Total Change Orders Amount:
airport, a bus maintenance facility        $13,977,765
Phase: Construction
Start: 02/24/1998           (BMF), and mitigation with the off-site
roadway improvements (ORI), plus
Completion: Spring 2012
purchase a fleet of buses.               Budget/Costs Incurred
Significant Developments                                 400
395
The Consolidated Rental Car Facility is substantially complete.
390
Project is in closeout. Final claims negotiations are pending.                 385
380
Millions
The ORI project is in closeout. The FAA continues working on the          375
Dollars in  370
transfer of Port property to WSDOT and the City of SeaTac.
365
360
The BMF project is in closeout. The LEED construction submittal           355
was completed supporting a certified rating.                                      Authorized   Forecasted  Costs Incurre d
Schedule
Construction Costs
RCF opened May 17, 2012. Project closeout is substantially
complete except for RCF (2014 pending final claim resolution).              300
250
Budget                                            200
150
The total forecasted cost at completion, not including funding for
Millions
100
claims settlement, is $392,306,000 (capital and expense budgets).
The current forecast represents a total estimated program savings of      Dollars in   50
$27,000,000 based upon the total program budget of $419,306,000.         0
Initial   Change   Spent
Orders
Change Order
Approximately 47 change orders totaling $179,000 have been          Photo
processed and approved since the last report. These are primarily
closeout and final cost reconciliation type of Change Orders.
Risks
x For RCF: in closeout, claims resolution.
x For ORI: none identified.
x For BMF: none identified.

Port of Seattle 2Q 2013 Report  7

Budget Transfers
$17,111,099 was reduced from the budget and transferred out as Government Expense work. An
additional $1,327,000 was returned to savings.
Cost Growth of Construction
RCF Airport Wayfinding Signage and Curbside Modifications - MC-0316968 - Cumulative change
order percentage is 21.3% with no activity this quarter. This contract is closed.
Consolidated Rental Car Facility - Small Operator Build Out - MC-0317022 - Cumulative change
order percentage is 3.97% with minimal activity this quarter. This contract is closed.
Consolidated Rental Car Facility Offsite Roadway Improvements and SR99 Bridge Seismic Upgrade
MC-0316568 - Two (2) change orders executed this quarter for a total of $492,858. The cumulative
change order value through this quarter is $3,017,296 (39.6%). Final payment to the Contractor has
been made. This contract is in closeout.
Bus Maintenance Facility - MC-0316730 - The cumulative change order value is $300,190 (2.29%).
Final payment to the Contractor has been made. This contract is in closeout.
GCCM Final Construction (Phase 3 of 3)  MC-0315405 - On June 30, Commission authorized the
$32,000,000 suspension impact including a $6,973,300 budget increase and an increase in change
order limit from 10% to 18% requiring Commission notification. The current cumulative change order
percentage through this quarter is 4.2% with 8 change orders executed for a net increase of
$236,076. Final claim negotiations are underway. This contract is active.
TESC & Early Work (Phase 2 of 3)  MC-0315292 - Cumulative change order percentage is 19.4%
due primarily to removal of contaminated soils and associated impacts. This work and the final
contract reconciliation is complete and the contract is closed.
GCCM Pre-Construction (Phase 1 of 3)  MC-0314280  The cumulative change order percentage of
170.5% is the result of changes for additional contractor management and support beyond the extent
of the original scope to validate project costs and support the rental car companies and the Port on
final approval of the project. This work and the final contract reconciliation is complete and the
contract is closed.


AIRPORT
8  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Sanitary Sewer Pump Station Upgrade
Project:    C102032         This project upgrades the aging      Status Snapshot
Budget: $1,133,000        control systems of 22 sanitary       On Schedule
Phase: Design            sewer lift stations at Seattle-        On Budget
Start: 03/01/2013             Tacoma International Airport.         0 Change Orders
Completion: 5/31/2014                                    Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
1.2
Design work was completed. Control components have been
1
ordered.
Millions 0.8
0.6
Schedule
0.4
The project is currently on schedule.                                      Dollars in 0.2
0
Budget                                              Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                                     Construction Costs
Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT
Port of Seattle 2Q 2013 Report  9

SECOND QUARTER REPORT, 2013
Main Terminal Baggage Screening
Status Snapshot  Prior Report
Delayed Schedule  4Q 08
Project:    C102163       This project creates automated         Under Budget      4Q 09
Budget: $218,712,358     systems for explosive detection       665 Change Orders
Phase: Close Out        screening of baggage for the north     Total Change Orders Amount:
Start: 09/24/2002           Main Terminal and South Satellite.      $51,165,622
Completion: 02/13/2009   The systems will meet all security
requirements while reducing staffing    Budget/Costs Incurred
and providing capacity for future
235
growth.
230
Millions 225
Significant Developments
220
All work has been completed under this project. This will be the last
Dollars in 215
quarterly report for this project.                                                 210
Authorized   Forecasted  Costs Incurred
Schedule
The project is complete.
Construction Costs
Budget
200
The project forecast is within the approved budget and authorization.
150
Millions
Change Order                                        100
A total of 665 Change Orders have been issued on this project.              50
Dollars in 
0
Risks                                                     Initial  Change  Spent
Orders
None
Budget Transfers                                     Photo
None this quarter
Cost Growth of Construction
In 2006, the baggage handling system subcontractor was
terminated, as they were unable to meet the project schedule
requirements. The remaining work was rebid in the fall of 2006.
Alaska Airlines asked that we include the BHS work within the 2-step
ticket counter project which increased the amount of BHS work in the
bidding (attracting more competition), and eliminated the issues with
having two different BHS subcontractors in the same work area.
AIRPORT
10  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Water System Isolation Valve Upgrade-non AF
Status Snapshot  Prior Report
Delayed Schedule  3Q 12
Project:    C102334         This project replaces isolation        On Budget
Budget: $954,000          valves on the aging water          0 Change Orders
Phase: Close Out          distribution system, necessary for    Total Change Orders Amount:
Start: 10/01/2010             isolating portions of the system in     $0
Completion: 2/28/2013      the event of breaks, leaks, or tieins
, in non-airfield (AF) locations.      Budget/Costs Incurred
1.2
Significant Developments                                 1
Millions    0.8
Construction is complete and project is in closeout.
Dollars in     0.6
Schedule                                            0.4
0.2
Construction is complete.
0
Authorized       Forecasted      Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                                     Not Applicable
None
Risks
None identified at this time
Budget Transfers
None this quarter




AIRPORT

Port of Seattle 2Q 2013 Report  11

SECOND QUARTER REPORT, 2013
Airfield Pavement Replacement
Project:    C102573         The project is intended to be a        Status Snapshot
Budget: $30,262,035       multi-year pavement replacement    On Schedule
Phase: Construction       program to replace distressed       On Budget
Start: 05/02/2010             pavement and joint seal on the        6 Change Orders
Completion: 12/31/2016     airfield.                        Total Change Orders Amount:
$434,794
Significant Developments                              Budget/Costs Incurred
Commission approved design authorization for the 2013 construction
35
work on July 24, 2012. Bid opening is scheduled for April 23, 2013.
30
Gary Merlino Construction was the apparent low bidder. Contract
Millions  25
award date was May 21, 2013.                                        20
15
Schedule                                          Dollars in  10
The 2012 construction work is being closed out. The 2013                 5
construction work began on June 21, 2013. This was the third phase       0
Authorized   Forecasted  Costs Incurred
of a multi-year pavement replacement program to be performed from
2011 to 2015. The 2013 construction work is scheduled to be
completed in the fourth quarter of 2013.
2012 Construction Costs
Budget
15
The project forecast is within the approved budget.
Change Order                                       Millions  10
No change orders were executed this quarter.                               5
Dollars in 
Risks                                                  0
Initial   Change   Spent
None this quarter.
Orders
Budget Transfers
None this quarter.


AIRPORT
12  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Gate Utility Improvements
Status Snapshot  Prior Report
Delayed Schedule        3Q 12
Project:    C800019    This project will upgrade the South         On Budget
Satellite Port-owned loading bridges to
Budget: $12,883,000                                     0 Change Orders
the same standards, including 400Hz
Phase: Construction                                    Total Change Orders Amount:
power and potable water. This will
Start: 06/28/2007                                                  $0
reduce air emissions, improve energy
Completion: 8/29/2014 efficiency and save money for the       Budget/Costs Incurred
airlines.
15
Significant Developments                               Millions 10
Notice to proceed has been issued to the contractor.
5
Schedule                                           Dollars in 
After the design completion in December, the current schedule has         0
Authorized   Forecasted  Costs Incurred
the construction starting in third quarter of 2013 and being completed
in one year.
Budget                                         Construction Costs
The project forecast is within the approved budget and authorization.
6
5
Change Order
Millions    4
None                                                      3
2
Risks                                                Dollars in   1
Airport Operations at certain gates could be impacted during the              0
construction phase of the project.                                                 Initial  Change  Spent
Orders
Budget Transfers
To C800404 (Aeronautical Allowance)         $1,133,520



AIRPORT

Port of Seattle 2Q 2013 Report  13

SECOND QUARTER REPORT, 2013
North Expressway Relocation
Project:    C800034
The project reconstructs the North     Status Snapshot  Prior Report
Budget: $102,216,605      Airport Expressway and suports the   Delayed Schedule  2Q 11
Phase: Construction       extension of light rail to the Airport.   On Budget
Start: 07/27/2004             It also includes improvements to      226 Change Orders
Completion: 07/31/2012     Wall 14.                        Total Change Orders Amount:
$8,295,574
Significant Developments
Budget/Costs Incurred
The main contracts for reconstruction of the North Airport
Expressway and the light rail transit components are complete.            115
Commission approved the design and construction of additional
110
improvements to Wall 14 using project savings. The 90% design         Millions
effort for the Wall 14 Improvements was completed in May.               105
Schedule                                           Dollars in 100
The original schedule for the Wall 14 Improvements included the           95
completion of design by April 2013, and the completion of                      Authorized  Forecasted Costs Incurred
construction by October 2013. The final design and construction of
this project has been delayed until 2014 given the construction traffic
impacts to Air Cargo Road and to Cell Phone Lot operations.           Construction Costs
Budget                                           120
100
The project forecast is within the approved budget and authorization.
80
Change Order                                       60
Millions
40
One change order was issued this quarter.                               Dollars in  20
0
Risks
Initial    Change Order    Spent
None identified at this time.
Budget Transfers                                     Photo
None this quarter.


AIRPORT

14  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Main Terminal South Low Voltage
Project:    C800061     This project covers the renewal and       Status Snapshot  Prior Report
Budget: $1,925,000     replacement of low voltage (600 volts     Delayed Schedule  1Q 08
Phase: Design         and below) electrical distribution         On Budget
0 Change Orders
Start: 06/28/2007         equipment in the southern part of the
Total Change Orders Amount:
Completion: TBD       Main Terminal.
$0
Significant Developments
Budget/Costs Incurred
Due to project deferral and the possibility of changes in site
conditions and building codes, the design phase changed from 100%       5
to 90% complete. Project Notebook is being finalized to address
4
scope of work, schedule, and budget. Project Definition section of        Millions  3
the notebook has been presented to the Investment Committee(IC)
and the updated Project Notebook is scheduled to be presented to         2
IC on August 30, 2013.                                                 Dollars in   1
0
Schedule                                              Authorized  Forecasted Costs Incurred
Staff has finalized the scope of work, schedule and final design
budget. The 100% design documents for this project are scheduled
to be complete by the end of June 2014.                              Construction Costs
Not Applicable
Budget
The project budget is being evaluated based on delays and scope      Photo
changes.
Change Order
None
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will
be required to add additional crews to complete work in a timely
manner. This area is a 24/7/365 operation. Sequencing of this work
is critical and electrical power has to be maintained without
interruptions.
Budget Transfers
From C800404 (Aeronautical Allowance)          $2,331,000

AIRPORT
Port of Seattle 2Q 2013 Report  15

SECOND QUARTER REPORT, 2013
Airport Owned Gate Infrastructure
Status Snapshot  Prior Report
Project:    C800105         This project purchases and
Budget: $6,000,000        replaces passenger loading bridges   Delayed Schedule  3Q 12
(PLB) at gates throughout the         On Budget
Phase: Close Out                                       0 Change Orders
Start: 07/24/2007             airport. The project is being
performed in phases.                 Total Change Orders Amount:
Completion: 06/30/2013                                   $0
Significant Developments                              Budget/Costs Incurred
All work has been completed and this CIP is ready to be closed out.       6.6
6.4
Schedule
Millions 6.2
The work is complete and the project is in closeout.                         6
5.8
Budget                                           Dollars in 5.6
5.4
The project forecast is within the approved budget and authorization.
Authorized   Forecasted  Costs Incurred
Change Order
None                                                 Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter.





AIRPORT

16  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
C4 UPS System Improvements
Project:    C800107     Project will replace existing              Status Snapshot  Prior Report
Budget: $2,336,000     Uninterruptible Power Supply (UPS)      Delayed Schedule  1Q 09
Phase: Construction    System, including batteries, with a new   On Budget
Start: 06/28/2007         new system located in the Airport         0 Change Orders
Completion: TBD       Combined Communications and         Total Change Orders Amount:
Command Center (C4).                 $0
Significant Developments                              Budget/Costs Incurred
Due to project deferral and the possibility of changes in site
2.5
conditions and building codes, the design phase changed from 100%
to 90% complete. Progressing with new Project Notebook to include        2
a revised address scope of work, schedule, and budget. In 2nd           Millions 1.5
Quarter, the Investment Committee will be presented with the Project
1
Definition section of the notebook. A Service Directive is in the             Dollars in 0.5
review process and expects Consultant to be approved mid-3rd
quarter. A site visit was conducted in the first quarter of 2013 to              0
Authorized   Forecasted  Costs Incurred
review existing conditions and to determine any code and industry
changes that might affect the final design.
Schedule                                         Construction Costs
The project was reactivated. Staff is in the process of determining      Not Applicable
the scope of work, schedule and final design budget.
Photo
Budget
The project budget is being evaluated based on delays and scope
changes.
Change Order
None
Risks
The C4 center is a 24/7/365 operation and sequencing of this work is
critical and electrical power has to be maintained without
interruptions. It is not known when the construction will proceed as
this is specialized equipment and due to the complexity the new
system will require rigorous testing during the commissioning phase.
Budget Transfers
None this quarter
AIRPORT
Port of Seattle 2Q 2013 Report  17

SECOND QUARTER REPORT, 2013
Runway 16C/34C Panel/Joint Sealant
Replacement
Status Snapshot
The scope of work will remove and    On Schedule
Project:    C800112         replace the pavement and joint seal   On Budget
in areas on Runway 16C-34C.
Budget: $3,461,623                                      2 Change Orders
Phase: Close Out                                       Total Change Orders Amount:
Start: 02/26/2008                                                  $232,732
Completion: 09/01/2012
Budget/Costs Incurred
Significant Developments
6
Gary Merlino Construction was the low bidder. The intent of the            5
contract was to coordinate this work with an apron panel                    4
replacement project.
3
Millions
2
Schedule                                           Dollars in  1
The 2013 replacement of runway panels is nearly complete. The           0
2012 replacement of runway panels project is being closed out.                Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.   Construction Costs
Not Applicable
Change Order
One change order for one additional runway panel was executed this
quarter.                                                                  Photo
Risks
No risks have been identified at this time.
Budget Transfers
None this quarter.



AIRPORT

18  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Gina Marie Lindsey (GML) Arrivals Hall
Concessions
This project will provide a new         Status Snapshot   Prior Report
Project:    C800148         retail-merchandising corridor in the    Delayed Schedule  1Q 11
Gina Marie Lindsey Arrivals Hall.      On Budget
Budget: $1,033,000
The project includes installing three    0 Change Orders
Phase: Design            Retail Merchandizing Units (RMUs)   Total Change Orders Amount:
Start: 11/20/2007             and providing utilities to a new        $0
Completion: TBD          approximate 25-seat restaurant
and bar.
Budget/Costs Incurred
Significant Developments                                1.2
1
The design for utilities was previously completed in 2009 but put on
0.8
hold due to market conditions. The Concessions group will review        Millions
0.6
plans for the new food-beverage concession for viability via a cost
0.4
analysis to be performed later in 2013.                                    Dollars in 0.2
Schedule                                            0
Authorized   Forecasted  Costs Incurred
As previously reported, the project schedule delay was due to the
pending decision by the Business Development Group to proceed
with the concessionaire.                                                Construction Costs
Not applicable
Budget
The project forecast is within the approved budget and authorization.   Photo
Change Order
None
Risks
Due to delay in schedule, bidding climate may change when the
project is bid and additional budget may be required.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 2Q 2013 Report  19

SECOND QUARTER REPORT, 2013
C60 - C61 BHS Modifications
Project:    C800168         The work planned under this         Status Snapshot
Budget: $10,969,000       project represents a critical         On Schedule
Phase: Design            component in providing improved    On Budget
Start: 06/01/2012             operational baggage in-line           0 Change Orders
Completion: 04/30/2014     screening at the south end of the     Total Change Orders Amount:
Airport and provide more baggage    $0
make-up capacity for airlines.
Budget/Costs Incurred
12
Significant Developments
10
Design is 30% complete. The design documents were sent to TSA        8
for review. Project Team is waiting on TSA feedback of 30% design.
Millions
6
The project team is revisiting the project scope as defined to ensure
4
Airport receives needed baggage make-up capacity and computer       Dollars in   2
replacements. Team is coordinating with the Recapitalization project
0
to reduce any redundant work.                                              Authorized  Forecasted Costs Incurred
Schedule
The project is currently on schedule.                                    Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter

AIRPORT

20  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Federal Inspection Services - New Primary
Inspection Booths
This project will replace existing        Status Snapshot   Prior Report
Project:    C800174         primary inspection booths for         Delayed Schedule  4Q 12
Customs and Border Protection in     On Budget
Budget: $2,000,000
the International Arrivals Federal       0 Change Orders
Phase: Construction       Inspection Services (FIS) facility in   Total Change Orders Amount:
Start: 07/27/2010             the South Satellite.                   $0
Completion: 09/08/2011
Budget/Costs Incurred
Significant Developments
New signs are being procured to replace the defective signs.              2.5
2
Schedule                                           Millions 1.5
The project is substantially complete. The current schedule for
1
completion of the replacement signs is now the fourth quarter of           Dollars in 0.5
2013.
0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
Not Applicable
None
Risks                                              Photo
None identified at this time.
Budget Transfers
From C800405 (Non-Aeronautical Allowance)      $3,903




AIRPORT
Port of Seattle 2Q 2013 Report  21

SECOND QUARTER REPORT, 2013
Common Use Lounge Remodel
Status Snapshot  Prior Report
On Schedule
Project:    C800203         This project will relocate the Port's    Forecast Overrun  1Q 13
Budget: $1,061,000        common-use lounge from the       9 Change Orders
Phase: Close Out          mezzanine level to the departure     Total Change Orders Amount:
Start: 03/01/2011             level of the South Satellite.            $32,782
Completion: 02/28/2012     Improvements consist of new
finishes, new furnishings and other   Budget/Costs Incurred
minor cosmetic improvements.
1.2
1
Significant Developments
Millions 0.8
The Port Commission ratified the $3,903 authorization overrun this        0.6
project accrued during close out. Project is now complete and no          0.4
further charges are anticipated. This will be the last quarterly report       Dollars in 0.2
for this project.
0
Authorized   Forecasted  Costs Incurred
Schedule
Construction was completed in February 2012 and the lounge
opened on March 1, 2012.                                         Construction Costs
Budget                                           0.5
Project is on budget.
Change Order                                       Millions
None this quarter
Risks                                                Dollars in  0
None.                                                              Initial   Change Order  Spent
Budget Transfers
None this quarter



AIRPORT
22  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Security Exit Lane Breach Control - Phase 1
Project:    C800218         This project will procure and install    Status Snapshot
Budget: $1,310,000        new automated exit lane breach     Delayed Schedule
Phase: Construction       control equipment at the           On Budget
Start: 3/1/2012                Concourse B exit.                    0 Change Orders
Completion: 06/30/2013                                   Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
1.5
The breach control equipment was installed at Exit B.
1
Schedule                                          Millions
The project construction was completed late due to additional             0.5
commissioning of new equipment needed in the field.                    Dollars in 
0
Budget                                              Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                                     Construction Costs
Not Applicable
None
Risks
None this quarter.
Budget Transfers
None this quarter.




AIRPORT

Port of Seattle 2Q 2013 Report  23

SECOND QUARTER REPORT, 2013
Emergency Lighting - Parking
Project:    C800230         The purpose of this project is to
Budget: $1,157,081        provide electrical infrastructure for    Status Snapshot  Prior Report
Phase: Design            a new source of emergency power   Delayed Schedule  4Q 12
Start: 07/24/2012             to feed the parking garage            On Budget
Completion: 07/31/2014     emergency lighting circuits and      0 Change Orders
ensure that code-required level of     Total Change Orders Amount:
egress illumination is provided for      $0
safety.
Budget/Costs Incurred
Significant Developments
5
The Service Directive with Casne for design was executed on
4
September 24, 2012. The Building Deptarment permit has been
issued. During final review a constructability issue was raised and        Millions  3
some redesign work was required. The anticipated IFB documents         2
are expected from the Consultant in September.                         Dollars in   1
0
The ESCO contract with McKinstry was delayed due to design
Authorized   Forecasted  Costs Incurred
deficiencies. The Port worked closely with McKinstry to assist in
developing acceptable design documents. Construction Notice to
Proceed was issued on July 17. Construction has been going well.
Construction Costs
Schedule
1.5
The infrastructure portion of the contract has been delayed due to
constructablity issues that were caught after the 100% design was            1
complete. The design was going to require major shutdowns that         Millions
0.5
would significantly impact operations therefore redesign of portions
of the project is required.                                                      Dollars in     0
Initial   Change   Spent
0.5            Orders
The ESCO contract was delayed due to design deficiencies,
however they are making it up in Construction.
Budget
The project forecast is within the approved budget. Authorization of
design and construction of emergency lighting through State ESCO
contract was approved by the Commission.
Change Order
None

24  Port of Seattle 2Q 2013 Report

Risks
The biggest challenge has been parked cars that are in the way.
Budget Transfers
To C800405 (Non-Aeronautical Allowance)   $586,230












AIRPORT

Port of Seattle 2Q 2013 Report  25

SECOND QUARTER REPORT, 2013
Feeder 101 Tap Replacements
Project:    C800234         Project Scope and description:       Status Snapshot
Budget: $500,000          The project includes replacing the    On Schedule
Phase: Design            electrical feeds to 13 locations       On Budget
Start: 04/01/2013             along Air Cargo Road. Also, the      0 Change Orders
Completion: 10/31/2014     electrical transformer and          Total Change Orders Amount:
associated switchgear for Air Cargo   $0
#4 will be replaced.
Budget/Costs Incurred
Significant Developments                                3
The utilities were relocated at Air Cargo #4. The locations for the          2.5
electrical gear at Air Cargo #4 were modified.                             Millions  2
1.5
Schedule                                           1
Dollars in 0.5
The project is currently on schedule. Design is anticipated to be
0
complete November 2013. Construction is scheduled from January          Authorized  Forecasted Costs Incurred
2014 to October 2014.
Budget                                         Construction Costs
The project forecast is within the approved budget. Authorization of     Not Applicable
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
None.
Risks
Unplanned electrical shut downs could impact the project schedule.
Budget Transfers
None.



AIRPORT
26  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Terminal Escalators Modernization

Project:    C800237         This project will replace 42           Status Snapshot
Budget: $35,610,979       escalators in the Main Terminal,      On Schedule
Phase: Close Out         Concourse B, and South Satellite.    On Budget
In addition, two new escalators will     130 Change Orders
Start: 11/02/2007
be installed at the South Satellite.      Total Change Orders Amount:
Completion: 07/01/2013                                   $6,025,111
Significant Developments
Budget/Costs Incurred
Escalator installation is complete. Close out activities are underway.
60
Schedule                                           50
The project is in close out.                                                   Millions 40
30
Budget                                           20
Dollars in 
The project forecast is within the approved budget and authorization.      10
0
Change Order                                          Authorized Forecasted   Costs
Incurred
Progress made this quarter in negotiating change orders for
acceleration, reconciling force account work, and varying site
Construction Costs
conditions at South Satellite.
25
Risks
20
None identified at this time.                                                 Millions 15
10
Budget Transfers
5
None                                                   Dollars in 
0
Initial    Change Order    Spent
Cost of Construction Growth
Circumstances contributing to cost growth: differing site conditions
encountered at the South Satellite during the installation of the two
new escalators resulted in revisions to the architectural and
structural designs, increased cost of construction, acceleration of
operationally critical units, and impacted the critical path of the
project circumstances contributing to cost growth. The project also
experienced cost increases due to state inspector imposed
requirement for a hard barrier between escalators during
construction.

AIRPORT
Port of Seattle 2Q 2013 Report  27

SECOND QUARTER REPORT, 2013
Central Plant Pre-Conditioned Air
Project:    C800238       This project will provide a centralized    Status Snapshot  Prior Report
Budget: $46,635,000      pre-conditioned air (PC-Air) plant      Delayed Schedule  1Q 13
Phase: Construction     (PCAP), associated heating and       On Budget
Start: 06/15/2009           cooling piping systems, and jet bridge   161 Change Orders
Completion: 08/31/2013   terminal air handling units to serve     Total Change Orders Amount:
airplanes with heating and cooling       $6,493,110
while at the gates.
Significant Developments
Budget/Costs Incurred
Functional testing of the gate equipment started at Concourse A and
South Satellite. Pipe and electrical installation, testing and pipe             47
system flushing was completed at Concourse D and North Satellite.
46
PC-Air equipment is installed at 53 of the 73 total gates. The
remaining gates are South West and Alaska gates, which have           Millions 45
existing local PC Air equipment. These will be replaced in the third         44
quarter when the system is operational.                                  Dollars in  43
42
Schedule                                              Authorized  Forecasted Costs Incurred
The original contract completion date was December 11, 2012. Two
time extensions of 258 days were approved. Commission approved
the last extension on May 28, 2013. The new contract completion      Construction Costs
date is August 26, 2013. The delay is primarily due to Concourse D
redesign, as previously reported.                                             40
30
Budget                                           Millions
Negotiations with the contractor on potential change orders and              20
claims risk are in process. As negotiations proceed, potential budget
10
issues will be identified. Current project forecast including open            Dollars in 
claims exceeds approved budget and authorization by approximately         0
32%. Staff will return to Commission to request additional funding                Initial  Change  Spent
Orders
and authorization to execute change orders.
Change Order
Thirteen change orders were issued this quarter. The change orders
were issued for piping and electrical site conflicts on the concourse
and at the gates.
Risks
There is budget risk based on the dollar amount of open potential
change orders and claims. There is schedule risk as there is not an
approved schedule.
28  Port of Seattle 2Q 2013 Report

Budget Transfers
None this quarter
Cost of Construction Growth
Cost growth is still occuring due to shortcomings in the bid documents. Current cost of executed
Change Orders is 24% of the base contract price. The trended cost growth projection is currently 32%
over bid price. Approximately 20% are related to error and/or ommissions (owner or designer), 7%
are currently in some form of dispute. The remainder of the cost growth are due to site conditions,
discretionary tenant requests or scope changes and regulatory requirements respectively. The
current projections do not include any cost trending for potential claims due to late project completion
due to owner caused delay.










AIRPORT
Port of Seattle 2Q 2013 Report  29

SECOND QUARTER REPORT, 2013
Cargo 2 West Cargo Hardstand
Project:    C800247         This project will enlarge the          Status Snapshot  Prior Report
Budget: $11,830,000       western cargo hardstand in the      Delayed Schedule  3Q 12
Phase: Design            Cargo 2 area, it includes buyout of   On Budget
Start: 09/25/2012             two cargo buildings and tenant        0 Change Orders
Completion: 12/31/2014     relocations; relocation of FAA       Total Change Orders Amount:
antenna, security gate, and guard     $0
shack; and installation of 400Hz inground
power.                     Budget/Costs Incurred
15
Significant Developments
Cargo 2 will be combined with Cargos 5 and 6 as a single
10
construction contract. FAA antenna relocation agreement is to be         Millions
completed by the end of 2013.
5
Dollars in 
Schedule
0
Building acquisition is scheduled for the fall of 2013 with the tenant             Authorized  Forecasted Costs Incurred
relocated in 2014. Design is currently at 90% with anticipated 100%
review in the third quarter of 2013. Demolition of Building #2 is
scheduled for the first quarter of 2014 with hardstand completion       Construction Costs
scheduled for the second quarter of 2014. The current schedule       Not Applicable
reflects the combining of Cargo 2, 5, and 6 projects.
Photo
Budget
The project forecast is within approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None.

AIRPORT
30  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Vertical Conveyance Modernization Program -
Aeronautical - Phase I                             Status Snapshot  Prior Report
Perform modernization on 7          Delayed Schedule  4Q 12
Project:    C800251         existing elevators: SSAF, MT-2,      On Budget
MT-3, MT-4, MT-5, MT-6, MT-7,      0 Change Orders
Budget: $13,502,211
plus install cooling packages on 12    Total Change Orders Amount:
Phase: Design            existing hydraulic elevators         $0
Start: 10/25/2011             throughout Main Terminal.
Completion: 12/31/2015
Significant Developments                              Budget/Costs Incurred
Changing priorities concerning failure of existing Main Terminal
10
elevators has prompted further review of project scopes, and the
8
consolidation of all Main Terminal elevators to Phase I, and two new
South Satellite elevators to Phase II. Also added to the scope was        Millions  6
the design of one additional hydraulic oil cooling package for                4
Elevator Q; this elevator is experiencing overheating time-outs to          Dollars in   2
serve United Airlines' club associated with airline relocation to
0
Concourse A.
Authorized   Forecasted  Costs Incurred
Schedule
The construction is scheduled to begin in the first quarter of 2014,      Construction Costs
with construction completion in the second quarter of 2016..
5
Budget
4
The project forecast is within the approved budget. Authorization of        Millions   3
construction funding and authority to advertise for construction will
2
be requested when the bid documents are completed.
Dollars in     1
Change Order                                         0
Initial   Change   Spent
None
Orders
Risks
Final determination of scope and priorities could cause delays.
Budget Transfers
None this quarter

AIRPORT

Port of Seattle 2Q 2013 Report  31

SECOND QUARTER REPORT, 2013
Parking System Replacement
Status Snapshot  Prior Report
Project:    C800253         This project replaces the current      Delayed Schedule  2Q 12
Budget: $6,076,999.30      Parking Revenue Control System,    On Budget
Phase: Construction       which manages parking access      9 Change Orders
Start: 04/06/2010             and revenue collection in the          Total Change Orders Amount:
Completion: 08/31/2012     Airport's Main Parking Garage.      $195,780
Budget/Costs Incurred
Significant Developments
Scheidt & Bachmann (S&B), the system vendor, continues to resolve      12
reporting and system issues in preparation of transitioning to final           10
testing. The vendor's software has experienced a number of failures,      Millions  8
leading to reporting and operational issues.                                  6
4
Schedule                                           Dollars in  2
0
The system is substantially complete. However, schedule delays on
Authorized   Forecasted  Costs Incurred
the final work are being driven by repeated service outages of the
vendor's system, leading to delays in system commissioning.
Budget                                         Construction Costs
None this quarter
The project forecast is within the approved budget and authorization.
Photo
Change Order
Charges associated with correcting Labor and Industries (L&I)
inspection issues, and adding an additional employee exit gate to the
system.
Risks
This project is behind schedule. The Port is actively engaging the
Contractor at the executive level to address system issues.
Budget Transfers
None this quarter.


AIRPORT

32  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Aircraft RON Parking USPS Site
Status Snapshot  Prior Report
Delayed Schedule        1Q 11
Project: C800254           This project will prepare the site for
On Budget
Budget: $46,040,000       the construction of hardstands for
4 Change Orders
Phase: Design            use as Remain Overnight (RON)
Total Change Orders Amount:
Start: 08/26/2008             parking of aircraft at the Cargo 5
-$150,211
area.
Completion: 12/31/2014
Significant Developments                              Budget/Costs Incurred
Demolition of the USPS building is complete and the project is             50
closed out. With the design authorization of Cargo 2 and 6
40
approved by the Commission on September 25, 2012, they will be
added to Cargo 5 to produce a single construction contract with 3        Millions 30
cargo areas.                                                           20
Dollars in  10
Schedule
0
Project is at 90% design with anticipated 100% review in the third              Authorized  Forecasted Costs Incurred
quarter of 2013. Construction is scheduled to begin first quarter of
2014. Cargo 5 is scheduled to be completed by the end of the third
quarter of 2014.                                                       Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget.                     Photo
Change Order
None this quarter.
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT

Port of Seattle 2Q 2013 Report  33

SECOND QUARTER REPORT, 2013
Port-Owned Loading Bridge Renewal &           Status Snapshot
Replacement                                On Schedule
On Budget
Project:    C800267         This project will allow the Airport to    0 Change Orders
replace or refurbish Port-owned        Total Change Orders Amount:
Budget: $2,405,000
Passenger Loading Bridges (PLBs)    $0
Phase: Design            that have reached the end of their
Start: 02/28/2012             service life.
Completion: 12/31/2014
Budget/Costs Incurred
Significant Developments                                 3
The PLB and fixed walkway removal and replacement at S3 was          2.5
completed in February 2013. The S12 refurbishment work was           Millions  2
awarded in June and is schedule to begin in mid August. The design      1.5
for the S4 refurbishment is currently on hold due to potential conflicts        1
Dollars in 
with the upgrades planned in the South Satellite / International             0.5
Corridor Project.                                                              0
Authorized   Forecasted  Costs Incurred
Schedule
The project is currently on schedule.
Construction Costs
Budget
0.8
The project forecast is within the approved budget and authorization.
0.6
Change Order                                       Millions
0.4
None
Dollars in    0.2
Risks                                                  0
None identified at this time.                                                          Initial  Change  Spent
Orders
Budget Transfers
None this quarter


AIRPORT

34  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Stage 2 Mechanical Energy Implementation
Project:    C800268         This project will improve the energy
Budget: $2,872,900.00      performance of the mechanical
Phase: Construction       infrastructure systems at the        Status Snapshot  Prior Report
Start: 10/01/2011             Airport.                              Delayed Schedule  1Q 12
Completion: 09/25/2013                                   On Budget
0 Change Order
Total Change Orders Amount:
$0
Significant Developments
Additional costs are being incurred due to broken valves in Central     Budget/Costs Incurred
Plant which slowed schedule and had cost impact. Evaluating cost
3
of adding scope deleted from South Mezzanine terminals and North
2.5
Bridge Level.
Millions  2
Schedule                                           1.5
1
Targeting construction completion in September 2013.                   Dollars in 0.5
0
Budget
Authorized   Forecasted  Costs Incurred
The forecast is within the approved budget and authorization.
Change Order                                     Construction Costs
None
3
Risks                                                 2.5
2
None identified at this time.
1.5
Millions
Budget Transfers                                         1
Dollars in    0.5
To C800404 (Aeronautical Allowance)           $20,000
0
Initial   Change   Spent
Orders



AIRPORT
Port of Seattle 2Q 2013 Report  35

SECOND QUARTER REPORT, 2013
8th Floor Weatherproofing
Status Snapshot  Prior Report
Delayed Schedule  1Q 12
Project:    C800274         This project includes removal and     On Budget
Budget: $10,050,000       replacement of the floor covering     14 Change Orders
Phase: Construction       system on the eighth floor of the     Total Change Orders Amount:
Start: 03/23/2010             STIA parking garage and repair or     $65,182
Completion: 12/31/2013     replacement of expansion joints
and flashings.
Budget/Costs Incurred
Significant Developments                                15
The Port's contractor, PCL Construction, remobilized for 2013,
performed stripping of old weatherproofing, and crack repair on           Millions 10
sections B & C of the eighth floor garage deck. Unused portions of
the second floor were restriped and used as overflow parking for the        5
portions of the eighth floor under construction.                              Dollars in 
0
Schedule                                              Authorized  Forecasted Costs Incurred
The current schedule is for project completion by the end of 2013.
Budget                                         Construction Costs
The project forecast is within the approved budget and authorization.
8
Change Order                                        6
Millions
Four change orders were executed this quarter.                            4
2
Risks                                                Dollars in 
This is a weather-dependent project.                                       0
Initial    Change Order    Spent
Budget Transfers
None this quarter
Photo



AIRPORT
36  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Common Use Equipment Expansion (CUSE)
Project:    C800276         This project installs flexible           Status Snapshot
Budget: $2,581,000        passenger processing             On Schedule
Phase: Close Out          infrastructure and equipment at the   On Budget
Start: 09/01/2009             airline gates at some South           25 Change Orders
Completion: 09/30/2012     Satellite gates.                   Total Change Orders Amount:
-$11.926
Budget/Costs Incurred
Significant Developments
3
The contractor completed work on schedule at the end of August
2.5
2012. Project close out is nearing completion.                        Millions   2
Schedule                                          Dollars in   1.5
1
The project is in close out.
0.5
Budget                                            0
Authorized       Forecasted      Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
None
0.7
Risks                                                 0.6
Millions    0.5
None identified at this time                                                    0.4
Dollars in     0.3
Budget Transfers                                        0.2
0.1
None this quarter.                                                           0
Initial        Change Orders        Spent
0.1




AIRPORT

Port of Seattle 2Q 2013 Report  37

SECOND QUARTER REPORT, 2013
Long-Term Cell Phone Lot
Project:    C800324         Construct a new cell phone waiting    Status Snapshot  Prior Report
Budget: $1,768,000        lot to replace the existing lot that is   Delayed Schedule  1Q 13
Phase: Design            being displaced, and construct a     On Budget
Start: 12/11/2012             traffic control roundabout adjacent     0 Change Orders
Completion: 12/31/2014     to the lot on South 170th Street.      Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
2
Traffic engineering analysis and preliminary design of the South
170th St. roundabout and cell lot continued. Coordinating the              1.5
deactivation of the existing cell phone lot with the construction of the      Millions
1
new lot and roundabout to maintain cell phone lot service continued.
Dollars in 0.5
Schedule
0
The cell phone lot is planned to be constructed ahead of the                   Authorized  Forecasted Costs Incurred
roundabout, which is expected to require a longer time for design
and permit acquisition. Cell phone lot design planned to be
completed in the third quarter of 2013 followed by construction in       Construction Costs
fourth quarter 2013 and first quarter 2014. Roundabout construction    Not Applicable
will start in the second quarter of 2014 with completion in the fourth
quarter of 2014.                                                        Photo
Budget
The project forecast is within the approved budget.
Change Order
None
Risks
Schedule uncertainties related to roundabout design review and
permit acquisition time requirement. There is a potential of no cell
phone lot availability for up to several months if there are permit
acquisition or construction delays for the new cell phone lot.
Budget Transfers
None this quarter

AIRPORT
38  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Two New CTE Freight Elevators
Status Snapshot  Prior Report
Delayed Schedule  2Q 12
Project:    C800334         Provide two new freight elevators     On Budget
Budget: $8,318,000        to support concession operations in   1 Change Orders
Phase: Construction       the Central Terminal/Pacific        Total Change Orders Amount:
Start: 08/05/2011             Marketplace.                         $20,000
Completion: 07/31/2014
Budget/Costs Incurred
Significant Developments
The contract was awarded in April to Pease Construction. Notice to        10
proceed was issued in June for the contractor commenced                 8
sawcutting concrete pavement for North Freight elevator pit &             Millions  6
installation of new grease Interceptor.
4
Schedule                                           Dollars in  2
As previously reported, the project is anticipating a one-year delay          0
Authorized   Forecasted  Costs Incurred
due to scope changes included in the redesign efforts, and delays in
reviews.
Budget                                         Construction Costs
The project forecast is within the approved budget and authorization.
5
4
Change Order
Millions    3
Executed one change order this quarter.
2
Risks                                                Dollars in   1
No new risks identified this quarter.                                             0
Initial   Change   Spent
Orders
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 2Q 2013 Report  39

SECOND QUARTER REPORT, 2013
Electrical Ground Support Equipment (EGSE)
Electrical Charge Stations                        Status Snapshot
Delayed Schedule
On Budget
Airport-wide electrical charging        25 Change Orders
Project:    C800335         system for electrical ground          Total Change Orders Amount:
Budget: $30,198,000       support equipment (EGSE) at the    $103,135
Phase: Design            Concourses and the North and
Start: 10/26/2010             South Satellites.
Completion: 12/31/2015
Significant Developments                              Budget/Costs Incurred
Received Beneficial Occupancy for installation of 40 demonstration
charge stations on Concourse C2 for Horizon Airlines. Phase 1             35
includes balance of charge stations at Concourse C, D and North          30
Satellite. Contractor has issued partial Beneficial Occupancy for            25
in Millions    20
charge corrals at Concourse C, D and at North Satellite. Beneficial       Dollars    15
Occupancies are scheduled to be issued by September 30, 2013.
10
5
The consultant is scheduled to issue GSE Charger Phase 2 Project         0
Authorized       Forecasted      Costs Incurred
100% bid design documents for review that includes Concourse A, B
and South Satellite. Working to secure FAA VALE grant and for
Washington Sales Tax exemption for the GSE Charger Phase 2
Project.                                                                   Construction Costs
Schedule                                            4
Phase 1 construction is scheduled for completion on September 30,        3
2013; Phase 2 construction scheduled for completion in late 2015.        Millions
2
Dollars in                                                                                                    Budget                                                                                         1
The project forecast is within the approved budget. The remaining
0
authorization for the construction funding and authority to advertise               Initial   Change Order   Spent
for construction will be requested when the design and bid
documents are completed for GSE Charger Phase 2 Project.
Change Order
Twenty-five change orders issued.


40  Port of Seattle 2Q 2013 Report

Risks
Coordinate with other airfield projects and Airline Gate Realignment program. Budget and schedule
may affect project implementation and completion.
Budget Transfers
None this quarter.











AIRPORT

Port of Seattle 2Q 2013 Report  41

SECOND QUARTER REPORT, 2013
Claim Device 14 & Lower Inbound
Status Snapshot  Prior Report
Project:    C800374         This project will replace the slope-    Delayed Schedule  4Q 12
Budget: $2,900,000        plate bag claim device 14 and       On Budget
Phase: Close Out          associated controls, in addition to    23 Change Orders
Start: 04/01/2011             removing the lower feed conveyor     Total Change Orders Amount:
Completion: 3/31/2013      and replacing it with a new          $129,002
overhead feed.
Budget/Costs Incurred
5
Significant Developments
4
The baggage equipment arrived and the contractor installed the          Millions  3
claim 14 device and associated conveyor. The project team
commissioned the equipment and turned over the device to Airport         2
Operations for use. MD Moore has completed the major contract         Dollars in   1
work on the project. The project is currently in close-out.
0
Authorized   Forecasted  Costs Incurred
Schedule
The project was delayed due to Hurricane Sandy. Equipment was on
the dock at the Port of New York the day of the hurricane. The Port    Construction Costs
worked with the contractor to come up with a recovery schedule. The
construction was completed in March.                                     1.2
1
Budget                                           Millions 0.8
0.6
The project forecast is within the approved budget and authorization.
0.4
Change Order                                       Dollars in  0.2
0
None                                                        Initial  Change  Spent
Orders
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT
42  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Vertical Conveyance Modernization Aero Ph 2
Status Snapshot
On Schedule
Project:    C800375         Perorm modernization of 3           On Budget
Budget: $8,834,408        elevators: MT-3, MT-4 and MT-5 in   0 Change Orders
Phase: Design            Main Terminal, plus 12 escalators:   Total Change Orders Amount:
Start: 12/11/2012             4 at Concourse C STS station, 4 at    $0
Completion: 12/31/2015     NSAT STS station and 4 at
Skybridge 6.                        Budget/Costs Incurred
10
9
Significant Developments                                 8
7
NorthSTAR project to consolidate all work at North Satellite and             6
MillionsDollars in     5
Concourse C STS Station nessitating transfer of 8 escalators from          4
the North Satellite and C STS Stations to the NorthSTAR program.         3
2
Changing priorities concerning failure of existing Main Terminal             1
elevators has prompted further review of project scopes, considering        0
Authorized       Forecasted      Costs Incurred
consolidation of all Main Terminal elevators to Phase I and South
Satellite elevators to Phase II.
Schedule                                         Construction Costs
Not Applicable
Construction is scheduled to begin in first quarter 2014 with
construction completion in fourth quarter 2015.
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
None
Risks
Changing priorites could impact schedule.
Budget Transfers
None this quarter.

AIRPORT
Port of Seattle 2Q 2013 Report  43

SECOND QUARTER REPORT, 2013
South Satellite HVAC, Lights, and Ceiling
Status Snapshot
Replacement                                On Schedule
This project will replace the Heating    On Budget
Project:    C800376         Ventilation, lighting and ceiling        0 Change Orders
systems in the South Satellite.         Total Change Orders Amount:
Budget: $6,500,000
$0
Phase: Design
Start: 7/24/2012
Completion: 07/31/2016                                  Budget/Costs Incurred
40
Significant Developments
30
Thirty percent design was delayed pending the finalization of              Millions
mechanical equipment room locations and review of seismic              20
requirements. Design is scheduled to resume in the third quarter of
2013.                                                             Dollars in  10
0
Schedule                                              Authorized  Forecasted Costs Incurred
Project design schedule is contingent on where the mechanical
equipment rooms will be located and potential seismic upgrades.
Budget                                         Construction Costs
The project forecast is within the approved budget. Authorization of     Not Applicable
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
None
Risks
South Satellite siesmic analysis and strategy may impact project
costs and schedule. Seismic upgrade is not currently in the design
scope of work.
Budget Transfers
None this quarter

AIRPORT

44  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Baggage Handling System (C22-C1, MK1, and
TC3)                                        Status Snapshot
This project will replace the ticket      On Schedule
Project:    C800382         counter (TC3) conveyors and         On Budget
declines, reroute the conveyors of     42 Change Orders
Budget: $4,750,000
the C-22 system and connect it to     Total Change Orders Amount:
Phase: Close Out          the C-1 screening system, replace    $181,179
Start: 03/01/2011             the existing makeup (MK1) device,
Completion: 05/31/2013     and install a new odd size baggage  Budget/Costs Incurred
system.
8
6
Millions
Significant Developments                                4
The project team commissioned the central oddsize conveyor. MD      Dollars in  2
Moore has completed the major contract work on the project. The
0
project is currently in close-out.                                                   Authorized  Forecasted    Costs
Incurred
Schedule
The project is currently on schedule.                                    Construction Costs
Budget                                             2
The project forecast is within the approved budget and authorization.        1.5
Millions
1
Change Order
There are currently 42 change orders executed on this contract.           Dollars in   0.5
0
Risks
Initial   Change   Spent
None identified at this time.                                                                Orders
Budget Transfers
None this quarter.
Cost of Construction Growth
Three changes represent the majority of the cost growth: 1) Since
POS no longer required replacement of the existing C1-CS1
curbside conveyor, it was removed rather than replaced;


Port of Seattle 2Q 2013 Report  45

Cost of Construction Growth (Cont.)
2) The contract design to replace make-up device MK1 did not include POS ergonomic standards for
this kind of device; and 3) the original contact design for the conveyors in the C1-CS2 conveyor line
created unsafe electrical and mechanical conditions for maintenance works. Several other smaller
changes include fire sprinkler and architectural revisions, including a credit to remove a small scope
of work.












AIRPORT
46  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Cargo 6 Enhancements
Project:    C800390         This project will enlarge the Cargo    Status Snapshot  Prior Report
Budget: $6,428,000        6 off-gate hardstand to allow        Delayed Schedule  4Q 12
Phase: Design            simultaneous nose-loading of wide-   On Budget
Start: 09/25/2012             body freight aircraft as well as         0 Change Orders
Completion: 12/31/2014     provide fuel hydrant and ground      Total Change Orders Amount:
power capabilities.                     $0
Budget/Costs Incurred
Significant Developments
8
Cargo 6 will be combined with Cargo 2 and 5 as a single
construction contract.                                                        6
Millions
4
Schedule
Design is currently at 90% with anticipated 100% review in the third       Dollars in   2
quarter of 2013. Construction is scheduled to begin late summer
0
2014 with completion in the fourth quarter of 2014. The current                Authorized  Forecasted Costs Incurred
schedule reflects the combining of Cargo 2, 5, and 6 projects.
Budget                                         Construction Costs
The project forecast is within the approved budget and authorization.   Not Applicable
Change Order                                     Photo
None this quarter
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 2Q 2013 Report  47

SECOND QUARTER REPORT, 2013
RW16C/34C Reconstruction Design
Status Snapshot
On Schedule
Project:    C800406         This project will produce the 60%     On Budget
Budget: $669,000          design for the runway 16C/34C      0 Change Orders
Phase: Design            reconstruction. The design will      Total Change Orders Amount:
Start: 05/04/2010             include utilities, runway status         $0
Completion: TBD          lights, and other scope items
related to the project.                  Budget/Costs Incurred
Significant Developments                                0.8
The 60% design was issued in December 2010. Incorporation of          0.6
comments on the 60% design work has been completed.                Millions
0.4
Schedule                                           Dollars in 0.2
Staff will return to Commission for authorization of the remaining
0
design funds in mid-2014. The forecast will be reassessed when              Authorized  Forecasted Costs Incurred
staff returns to the Commission for authorization of the final design
funds.
Construction Costs
Budget                                         Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
48  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
South Satellite Concessions Project
Status Snapshot  Prior Report
Delayed Schedule  3Q 11
Project:    C800412         This project will demolish and        On Budget
Budget: $2,227,400        relocate the existing duty free shop,   0 Change Orders
Phase: Construction       electric/communications to support   Total Change Orders Amount:
Start: 01/01/2011             a temporary duty free location, and    $0
Completion: 09/30/2013     construct a new food and beverage
shell space in the South Satellite at
Sea-Tac Airport.
Budget/Costs Incurred
Significant Developments                                 2
The abatement of the new duty free space is complete. The space        1.5
was turned over on schedule in February of 2013. The project is on      Millions
1
hold until the duty free tenant builds out their space.
Dollars in 0.5
Schedule
0
As previously reported, the design concept alternatives required                Authorized  Forecasted Costs Incurred
more extensive review than anticipated. The new concept allows the
existing duty free to remain operational during construction, but
requires a longer construction period.                                   Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
This project schedule is tied closely to the Duty Free Request for
Proposal.
Budget Transfers
None


AIRPORT

Port of Seattle 2Q 2013 Report  49

SECOND QUARTER REPORT, 2013
Access Control Door Additions
Status Snapshot  Prior Report
Delayed Schedule  3Q 12
Project:    C800414         This project will provide biometric     On Budget
Budget: $1,480,000        access controls and security        4 Change Orders
Phase: Construction       cameras at airport terminal doors.    Total Change Orders Amount:
Start: 09/27/2011                                                  $23,123
Completion: 08/30/2013
Budget/Costs Incurred
2
Significant Developments
1.5
Construction completed at Concourse D and started on Concourse       Millions
C.                                                                 1
0.5
Schedule                                           Dollars in 
0
The project was advertised for bid in May 2012 and a single bid, 48%          Authorized  Forecasted Costs Incurred
above the engineer's estimate, was received and rejected. The
project was then divided into two parts, re-designed and will be rebid
in November. The North Satellite (NSAT) work has been moved    Construction Costs
into the NSAT project to avoid potential additional construction costs
to re-install North Satellite access controls if gates are reconfigured          0.6
during the NSAT project.                                                  0.5
Millions   0.4
Budget                                             0.3
Dollars in 
The project forecast is within the approved budget and authorization.        0.2
0.1
Change Order                                         0
Initial   Change   Spent
Replaced existing door stainless steel wrap-around plates at 24                        Orders
doors that had visible holes.
Risks
None identified at this time
Budget Transfers
None this quarter.


AIRPORT
50  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Airfield Lighting Control and Monitoring System
Status Snapshot
(ALCMS) Upgrades                          On Schedule
Provide modifications to the Airfield    On Budget
Project:    C800415         Lighting Control and Monitoring       0 Change Orders
System to update, enhance and      Total Change Orders Amount:
Budget: $2,129,144
stabilize the system to meet the       $0
Phase: Construction       latest FAA specifications.
Start: 01/01/2011                                                 Budget/Costs Incurred
Completion: 12/31/2014
2.5
2
Significant Developments                               Millions 1.5
Liberty Airport Systems was awarded the contract. Factory
1
Acceptance Testing was conducted at the Liberty plant in Ontatrio
Dollars in 0.5
Canada in April. Site work and Acceptance Testing will be
conducted in early July and the system will go operational on July           0
Authorized   Forecasted  Costs Incurred
12.
Schedule
Construction Costs
The project is currently on schedule.                                    Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None this quarter
Risks
Coordination with on-going airfield operations is a consideration.
The Port worked to eliminate unplanned outages when transitioning
from the older computer platform to the new one.
Budget Transfers
None this quarter.


AIRPORT

Port of Seattle 2Q 2013 Report  51

SECOND QUARTER REPORT, 2013
Lagoon 3 Bird Wires
Status Snapshot
On Schedule
Project:    C800417         This project will reduce access by     On Budget
Budget: $1,563,000        waterfowl to the industrial          15 Change Orders
Phase: Construction       wastewater system Lagoon 3,       Total Change Orders Amount:
Start: 10/11/2011             which is located near the south end   $135,824
Completion: 10/31/2012     of the airfield.
Budget/Costs Incurred
2
Significant Developments
1.5
Nordic Construction was the low bidder. The contractor began work       Millions
1
in July 2012.
Dollars in 0.5
Schedule
0
Major construction is complete. Minor work to correct chaffing                 Authorized  Forecasted Costs Incurred
remain.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
1
Change Order                                        0.8
Five change orders were executed this quarter.                          Millions  0.6
Dollars in 
0.4
Risks
0.2
No risks have been identified at this time.                                      0
Initial   Change   Spent
Budget Transfers                                                Orders
None this quarter.
Photo
Cost of Construction Growth
The contractor was compensated for additional costs for revisions to
access gate framing and ramp posts. This change order was the
result of a design error or omission.


AIRPORT
52  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Federal Inspection Services Short Term
Status Snapshot  Prior Report
Improvements                               Delayed Schedule 1Q 13
Short Term Improvements to the      On Budget
Project:    C800426         Federal Inspection Service area at    0 Change Orders
the South Satellite to improve          Total Change Orders Amount:
Budget: $1,041,000
through put and improve conditions    $0
Phase: Design            for passengers waiting in the
Start: 04/01/2012             International Corridor prior to
Completion: 2/28/2014      Primary Inspection.
Budget/Costs Incurred
Significant Developments                                1.2
1
Additional necessary construction elements identified during 60%
0.8
design review have been added to the design team's project scope.       Millions
0.6
The design team's contract has been extended to allow completion
0.4
of this work.                                                                   Dollars in 0.2
Schedule                                            0
Authorized   Forecasted  Costs Incurred
Added scope identified during the 60% design phase will delay
completion of this project.
Construction Costs
Budget
Not Applicable
The project forecast is trending over the approved budget. Project
sponsors will review an updated estimate with new scope and
request additional funding.
Change Order
None
Risks
Additional funding must be approved for new construction scope
before project design can be finalized.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 2Q 2013 Report  53

SECOND QUARTER REPORT, 2013
Doug Fox Lot Service Upgrades
Status Snapshot  Prior Report
Delayed Schedule  1Q 13
Project:    C800451         Construct a new drainage system,    Under Budget
Budget: $6,073,000        asphalt resurfacing, improved lot     0 Change Orders
Phase: Design            lighting, new building, and road      Total Change Orders Amount:
Start: 02/01/2012             signage to improve lot appearance,    $0
Completion: 09/30/2014     function, and revenue generation.
Budget/Costs Incurred
6
5
Significant Developments
Millions  4
Construction drawings are progressing towards bid-ready status.
3
2
Schedule                                           Dollars in  1
The schedule was delayed to complete the environmental review           0
process and resolve remaining design issues. Request for                    Authorized  Forecasted Costs Incurred
construction authorization followed by advertisement for bids is
planned for July 2013. Construction is planned to start in October
2013 and be completed in Fall 2014.                                  Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget. The existing        Photo
budget is expected to be reduced by $1,005,000 based on current
design and cost estimates.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

54  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Concourse D Common Use Environment
Status Snapshot  Prior Report
Delayed Schedule  3Q 11
Project:    C800455         This project installs a common-use    On Budget
Budget: $4,250,000        environment at all gates on         14 Change Orders
Phase: Construction       Concourse D. Scope includes new   Total Change Orders Amount:
Start: 03/01/2011             communications infrastructure,        $111,155
Completion: 04/30/2013     casework built to a new Airport
standard, new carpet, wall            Budget/Costs Incurred
coverings and task lighting.
5
4
Significant Developments
Millions  3
Completion of non-essential items, such as casework modifications,
are in progress.                                                              2
Dollars in   1
Schedule
0
Contractor is scheduled to complete non-essential project work prior           Authorized  Forecasted Costs Incurred
to contract end date in August 2013.
Budget                                         Construction Costs
The project forecast is within the approved budget and authorization.
1.5
Change Order
None                                                   Millions  1
0.5
Risks                                                Dollars in 
None.
0
Initial   Change   Spent
Budget Transfers                                                Orders
None this quarter



AIRPORT

Port of Seattle 2Q 2013 Report  55

SECOND QUARTER REPORT, 2013
2011-2013 Roof Replacement Program
Status Snapshot
On Schedule
Project:    C800459         This project will remove and          On Budget
Budget: $4,777,000        replace the roofing systems on the   0 Change Orders
Phase: Construction       fire station and north end of the      Total Change Orders Amount:
Start: 07/01/2011             main terminal.                       $0
Completion: 10/31/2013
Budget/Costs Incurred
5
Significant Developments
4
Bids were opened on March 26, 2013 and notice of intent to award
was issued.                                                          Millions  3
Dollars in 
2
Schedule
1
The project is currently on schedule.                                         0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
2
None
1.5
Risks                                                Millions
1
None at this time
Dollars in    0.5
Budget Transfers
0
None this quarter.                                                                Initial  Change  Spent
Orders




AIRPORT

56  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Industrial Waste Treatment Plant (IWTP) Fiber
Status Snapshot  Prior Report
Installation                                           Delayed Schedule  1Q 13
Install new Single Mode Fiber cable   Forecast Overrun   1Q 13
Project:    C800461         from Main Terminal to IWTP and      0 Change Orders
Gate E-45.                          Total Change Orders Amount:
Budget: $514,000
$0
Phase: Design
Start: 03/01/2012                                                 Budget/Costs Incurred
Completion: 10/31/2013
0.6
Significant Developments                                0.5
The Fiber Optic Cable has been installed from Main Terminal to the       Millions 0.4
new equipment termination cabinet near the Alaska Hangar and          0.3
Gate E-45. Selected new routing for conduits for remaining portion       0.2
of the route since co-use of existing conduits from E-45 to the IWTP       Dollars in 0.1
with FAA fiber optic cable is not permitted. Completed final design          0
for submission to FAA.                                                       Authorized  Forecasted Costs Incurred
Schedule
Schedule delay of approximately 3 months due to need to reroute      Construction Costs
conduits.                                                               Not Applicable
Budget
The project will require additional budget and authorization. When
the design for the revised route is completed, revised scope and
costs will be developed.
Change Order
None
Risks
Underground boring for new conduits beneath Taxiway "B" .
Budget Transfers
None this quarter.


AIRPORT

Port of Seattle 2Q 2013 Report  57

SECOND QUARTER REPORT, 2013
South Satellite - Additional Gate Lobby
Status Snapshot  Prior Report
Delayed Schedule  3Q 12
Project:    C800466         Demolition of glass partitions,        On Budget
Budget: $1,515,000        restrooms, relocation of gate        14 Change Orders
Phase: Design            podiums new flooring, ceilings and   Total Change Orders Amount:
Start: 11/01/2010             infrastucture to provide additional     $141,934
Completion: 09/15/2013     gate lobby in the South Satellite.
Significant Developments                              Budget/Costs Incurred
Demolition of the restrooms is complete. The space was turned over
for operational use as a temporary seating area as scheduled. The
next phase of this project is due to resume in July 2013 after the           2.5
associated duty free tenant build out is complete.                            2
Millions 1.5
Schedule
1
As previously reported, the project delay was caused by delayed          Dollars in 0.5
design negotiations and contracting. Additionally, a longer design
0
period is required due to dependency on the South Satellite
Authorized   Forecasted  Costs Incurred
Concessions Project (C800412).
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
2
Change Order
1.5
None
1
Millions
Risks
This project is tied closely to the Duty Free RFP in that it is closely         Dollars in   0.5
aligned with the South Satellite Concessions Project.                         0
Initial   Change   Spent
Orders
Budget Transfers
None this quarter.


AIRPORT

58  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Passenger Loading Bridge Replacement -
Status Snapshot
Airline Realignment                              On Schedule
This project entails Passenger         On Budget
Project:    C800467         Loading Bridge (PLB)               31 Change Orders
replacements associated with the     Total Change Orders Amount:
Budget: $14,874,000
one-time airline realignment (AR).     $168,886
Phase: Construction       The work will take place at
Start: 04/12/2011             Concourse D and Concourse B.
Completion: 09/30/2013
Budget/Costs Incurred
Significant Developments
20
The PLB replacement, refurbishment and relocation work at both
Concourse D and B has been completed. PLB work at North             15
Satellite will now take place under the NorthSTAR project.                Millions
10
Schedule                                           Dollars in  5
The project is currently on schedule.
0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will      Construction Costs
be requested when the design and bid documents are completed.
2.5
Change Order
2
None                                                   Millions  1.5
1
Risks
Dollars in    0.5
None identified at this time.
0
Initial   Change   Spent
Budget Transfers
Orders
None this quarter.



AIRPORT
Port of Seattle 2Q 2013 Report  59

SECOND QUARTER REPORT, 2013
Exterior Gate Improvements (Airline
Realignment)
This project will install new fuel         Status Snapshot
Project:    C800472         hydrant pits and aircraft docking      On Schedule
systems at exterior gates for the       On Budget
Budget: $4,064,000
airline reallocation program.            0 Change Orders
Phase: Close Out                                       Total Change Orders Amount:
Start: 06/01/2011                                                  $0
Completion: 10/31/2012
Budget/Costs Incurred
Significant Developments                                 5
The project construction was completed in the fourth quarter of 2012.       4
This is the last quarterly report for this project.                                Millions  3
Dollars in 
2
Schedule
1
The project was completed on schedule.
0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                                     Not applicable
None this quarter
Risks
None this quarter
Budget Transfers
None this quarter




AIRPORT
60  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
CUSE at Gates & Ticket Counters- Airline
Realignment
Provide common use equipment,     Status Snapshot  Prior Report
Project:    C800473         casework and infrastructure at        Delayed Schedule  3Q 12
gates and ticket counters for the       Under Budget
Budget: $2,371,000
Airline Realignment program.         0 Change Orders
Phase: Close Out                                       Total Change Orders Amount:
Start: 04/02/2012                                                  $0
Completion: 05/01/2013
Budget/Costs Incurred
Significant Developments                                2.5
The project construction was completed and is in closeout.                 2
Millions 1.5
Schedule
1
The project construction was completed.
Dollars in 0.5
Budget                                            0
Authorized   Forecasted  Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
None
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT

Port of Seattle 2Q 2013 Report  61

SECOND QUARTER REPORT, 2013
Airport Signage (Airline Realignment)
Project:    C800474         The project will provide airport        Status Snapshot  Prior Report
Budget: $646,000          directional signage for the airline     Delayed Schedule  1Q 13
Phase: Construction       realignment program.             On Budget
Start: 06/01/2011                                                  0 Change Orders
Completion: 06/30/2013                                   Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
Completed signage changes for all airline relocations. Now replacing      0.8
old and damaged signs.
0.6
Schedule                                           Millions
0.4
As previously reported, the change in schedule was based on the
0.2
overall Airline Realignment Program Schedule. Airline relocations        Dollars in 
were delayed.                                                         0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget.
Construction Costs
Change Order                                     Not Applicable
None this quarter
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

62  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Miscellaneous Building Improvements (Airline
Status Snapshot
Realignment)                                  On Schedule
On Budget
Project:    C800475         This project will install a new ramp    0 Change Orders
for passenger access to regional      Total Change Orders Amount:
Budget: $2,722,000
aircraft on Concourse A for the       $0
Phase: Construction       Airline Realignment program.
Start: 11/01/2011                                                 Budget/Costs Incurred
Completion: 07/31/2013
3
2.5
Millions  2
Significant Developments
1.5
Assembly of the ramp was completed in June.
1
Dollars in 0.5
Schedule
0
The ramp assembly is in operation for the airline realignment moves.           Authorized  Forecasted Costs Incurred
Complete Punchlist items in July/August for building exterior cladding
panels and handrail extensions.
Construction Costs
Budget                                         Not Applicable
The project forecast is within the approved budget.
Change Order
None
Risks
None this quarter.
Budget Transfers
None this quarter.



AIRPORT

Port of Seattle 2Q 2013 Report  63

SECOND QUARTER REPORT, 2013
Fire Station Electric Upgrades
Project:    C800479         This project will replace the existing   Status Snapshot
Budget: $2,033,000        208V transformer and 12.47 KV      On Schedule
Phase: Design            feeder, and add a 500 KV          On Budget
Start: 04/01/2013             generator and a 1000kVA            0 Change Orders
Completion: 10/31/14       transformer.                     Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The preliminary design is complete. A 30% design review is
scheduled for August of 2013.                                           2.5
2
Schedule
Millions 1.5   Dollars in 
The design is scheduled to be complete November 2013. The
1
construction phase is scheduled from January 2014 to October 2014.
0.5
Budget                                            0
Authorized   Forecasted  Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Construction Costs
Change Order                                     Not Applicable
None
Risks
Unplanned electrical shut downs could impact the project schedule.
Budget Transfers
None this quarter.




AIRPORT
64  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Laptop Power in Concourses
Project:    C800484         This project adds additional          Status Snapshot
Budget: $2,020,000        charging opportunities for personal   On Schedule
Phase: Construction       electronic devices at several        On Budget
Start: 6/26/12                 strategic locations throughout the     0 Change Orders
Completion: 12/31/2013     airport terminal.                  Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
2.5
Construction bids were received and the construction contract has
been awarded to low bidder, Regency NW.                              2
Millions 1.5
Schedule
1
The project is currently on schedule.                                      Dollars in 0.5
0
Budget
Authorized   Forecasted  Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                                     Construction Costs
None
1.2
Risks                                                  1
No risks identified at this time.                                                 Millions  0.8
0.6
0.4
Budget Transfers                                       Dollars in  0.2
None this quarter
0
Initial   Change   Spent
Orders



AIRPORT

Port of Seattle 2Q 2013 Report  65

SECOND QUARTER REPORT, 2013
New Window Wall Ticket Zone 1
Project:    C800490         This project will install new           Status Snapshot
Budget: $4,258,000        common use ticket counters and     On Schedule
Phase: Construction       new baggage system along the      On Budget
Start: 07/01/2012             window wall and baggage system     2 Change Orders
Completion: 12/28/2013     renovation.                     Total Change Orders Amount:
$38,683
Budget/Costs Incurred
Significant Developments
6
Contract has been executed with PCL Contractors, work started in
5
May 2013 and is proceeding.
Millions  4
3
Schedule
2
The project is currently on schedule.                                      Dollars in   1
0
Budget                                              Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                                     Construction Costs
None                                                      4
Risks                                                  3
Millions
None                                                      2
1
Budget Transfers                                       Dollars in 
None this quarter.                                                            0
Initial   Change   Spent
Orders



AIRPORT

66  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Convert Ticket Zone 2 Pushback
Project:    C800491         The scope of the project is to         Status Snapshot
Budget: $5,500,000        renovate the Ticket counters and     On Schedule
Phase: Construction       ATO spaces into a pushback        On Budget
Start: 12/11/2012             configuration.                        0 Change Orders
Completion: 11/30/2013                                   Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
5
Project was completed on schedule for United Airlines (UA) to
4
relocate their Ticketing counters from Zone 7 to Zone 2; counters
opened on May 22, 2013. Phase 2 of this project will be to move Air      Millions  3
Canada (AC), All Napon Airlines (ANA), to temporary ticket counters,       2
demolish the remaining counters and complete the UA pushback        Dollars in   1
ticket counters.
0
Authorized   Forecasted  Costs Incurred
Schedule
The project is currently on schedule.
Construction Costs
Budget                                         Not Applicable
The project forecast is within approved budget and authorization.
Change Order
This is a tenant reimbursement project and we do not keep track of
change orders.
Risks
None identified at this time
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 2Q 2013 Report  67

SECOND QUARTER REPORT, 2013
Convert Ticket Zone 3 Flow Through
Status Snapshot
On Schedule
Project:    C800492         This project will convert the Zone 3    On Budget
Budget: $13,136,000       Ticketing Area to a flow through      0 Change Orders
Phase: Construction       concept.                       Total Change Orders Amount:
Start: 08/07/2012                                                  $0
Completion: 10/31/2013
Budget/Costs Incurred
14
Significant Developments                                12
Delta moved in to their new ticket counters on May 23, 2013. Work      Millions 10
8
Dollars in 
continues on Phases III and IV which will build out the final sections        6
of the new ticket counters.                                                   4
2
Schedule                                           0
Authorized   Forecasted  Costs Incurred
The project is currently on schedule.
Budget                                         Construction Costs
The project forecast is within the approved budget and authorization.
0.6
Change Order                                        0.5
None                                                   Millions  0.4
0.3
Risks                                                 0.2
Dollars in    0.1
The enabling projects and tenant relocations were successfully
0
completed.
Initial   Change   Spent
Orders
Budget Transfers
None this quarter.



AIRPORT

68  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Facility Monitoring System Renewal
Project:    C800495         This project will provide a system     Status Snapshot  Prior Report
Budget: $3,426,000.00      upgrade that will allow the system    Delayed Schedule  1Q 13
Phase: Design            to maintain and expand monitoring   On Budget
Start: 01/22/2013             of critical systems such as            0 Change Orders
Completion: 08/31/2015     elevators, escalators, moving        Total Change Orders Amount:
walks, passenger boarding bridges    $0
and baggage systems.
Budget/Costs Incurred
4
Significant Developments
3
The passenger loading bridges portion of the work completed 60%       Millions
design. The network upgrade is progressing well. The Infomration        2
and Communications Technology (ICT) Architecture Committee has
Dollars in   1
approved the project's network architecture and the project can begin
purchase of equipment.                                                0
Authorized   Forecasted  Costs Incurred
Schedule
As previously reported, the project is currently behind schedule, the
Construction Costs
anticipated 90% will be submitted to the Port for review in
Not Applicable
September.
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 2Q 2013 Report  69

SECOND QUARTER REPORT, 2013
Airportwide Mechanical Controls System
Project:    C800497         Project Scope and description:       Status Snapshot
Budget: $274,000          Upgrade the HVAC Controls        On Schedule
Phase: Design            System for the Airport. This        On Budget
Start: 05/01/2013             includes adding a wireless            0 Change Orders
Completion: 06/30/2014     connection to the Logistics area to    Total Change Orders Amount:
the south of the Airport.                 $0
Budget/Costs Incurred
Significant Developments
2.5
The project is currently in the preliminary design phase.
2
Millions 1.5
Schedule
1
The project is currently on schedule. Design is scheduled to be
completed in November 2013.                                        Dollars in 0.5
0
Budget                                              Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.                 Construction Costs
Not Applicable
Change Order
None.
Risks
Unplanned electrical shut downs could impact the project schedule.
Budget Transfers
None this quarter.



AIRPORT
70  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
RAC Baggage Claim Renovation
Project:    C800541         Renovation of both rental car         Status Snapshot
Budget: $1,327,500        counter locations in baggage claim   Delayed Schedule
Phase: Design            into new waiting areas with vending   On Budget
Start: 10/01/2012             machines and other facilities for       0 Change Orders
Completion: 2/28/2014      special operations                Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
1.5
The Commission authorized the additional funds and extended
schedule to support the change to a major works construction
1
contract on April 2. The design team completed the 90% and 100%      Millions
design efforts. The project team is finalizing the contract documents
0.5
to support a planned advertisement date in July.                         Dollars in 
0
Schedule                                              Authorized  Forecasted Costs Incurred
The design was completed in June and the completion of
construction is anticipated in February 2014. Final Design/Bid
Documents were delayed for several weeks, which resulted in a two-   Construction Costs
month delay.                                                       Not Applicable
Budget
The project forecast is within the approved budget.
Change Order                                     .
None this quarter
Risks
None this quarter
Budget Transfers
Transfer of $161,000 from C800404 Aeronautical Allowance to
support the budget increase.


AIRPORT
Port of Seattle 2Q 2013 Report  71

SECOND QUARTER REPORT, 2013
NorthSTAR Program
Status Snapshot
On Schedule
Project:    C800544         This project includes the             On Budget
Budget: $16,300,000       programmatic project management   0 Change Orders
Phase: Design            and project controls costs for the     Total Change Orders Amount:
Start: 04/05/2012             NorthSTAR program, consisting of    $0
Completion: 12/31/2018     five capital projects that represents
a unique partnership between the    Budget/Costs Incurred
Port and Alaska Airlines.
20
Significant Developments                               15
The "NW Sense of Place" strategy was developed and will be            Millions 10
implemented on the North Satellite project. Analysis of taxi-lane
expansion options are underway. Construction Support Services        Dollars in  5
IDIQ and Commissioning Agent RFP was advertised and is pending      0
award. A Programmatic Project Labor Agreement (PLA) has been           Authorized Forecasted   Costs
Incurred
authorized by the Commission.
Schedule                                         Construction Costs
Not Applicable
PLA negotiations underway. Continuing to refine Program Master
Schedule for facility programming components/processes and
interface with other non-NorthSTAR projects. Developing Port
Commission requested NorthSTAR Operational Performance metrics
for September report.
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
None
Risks
Communication & coordination across multiple teams and
stakeholders along with identification/monitoring of all "linked"
Capital projects outside of NorthSTAR.
Budget Transfers
To C800545 (NS Main Terminal Improvements)      $100,000
AIRPORT

72  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
NorthSTAR Concourse C Vertical Circulation
Project:    C800547         Construct exterior, weather          Status Snapshot
Budget: $19,300,000       protected sloped walkways with      On Schedule
Phase: Design            elevators at Gates C2/4, C10/12,     On Budget
Start: 11/07/2012             and C14 to provide enhanced         0 Change Orders
Completion: 03/31/2015     access from concourse to aircraft    Total Change Orders Amount:
ramp for Alaska/Horizon regional      $0
operations.
Budget/Costs Incurred
Significant Developments                                25
The 90% design has been submitted and review is underway.            20
Millions 15
Schedule
10
Refining construction-phasing plan to address impact on airline           Dollars in   5
operations and construction site.
0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget.
Construction Costs
Change Order                                     Not Applicable
None
Risks
Construction phasing to minimize impact on airline operations and
potential for underground utility conflicts during construction.
Budget Transfers
None



AIRPORT

Port of Seattle 2Q 2013 Report  73

SECOND QUARTER REPORT, 2013
Grease Interceptor Augmentation
Project:    C800551         This project will install two           Status Snapshot
Budget: $1,559,200        underground 9,000 gallon grease    On Schedule
Phase: Design            interceptors to service the          On Budget
Start: 05/01/2013             Concourse C and South Satellite.     0 Change Orders
Completion: 10/31/2014                                   Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
The Commission authorized design funds for this project.                   2
Schedule                                           1.5
Millions
Design will be complete by December 2013. The project is currently       1
Dollars in 
on schedule.
0.5
Budget
0
The project forecast is within the approved budget. Authorization of             Authorized  Forecasted Costs Incurred
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Construction Costs
Change Order                                     Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT

74  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
NorthSTAR Refurbish Baggage Systems
Project:    C800555         This project will refurbish existing     Status Snapshot
Budget: $22,000,000       baggage systems in support of      On Schedule
Phase: Design            AAG operation at North Satellite     On Budget
Start: 11/6/2012              and Concourse D. The work will      0 Change Orders
Completion: 12/31/2015     extend the service life of part of the   Total Change Orders Amount:
C92 systems, C88 North Satellite      $0
systems, and C88 tunnel systems.
Budget/Costs Incurred
25
Significant Developments
20
The 90% design is currently in review. Three scope items were          Millions 15
added to the C88 system. The team is reviewing the failure analysis
10
of C92 system.
Dollars in   5
Schedule                                           0
Authorized   Forecasted  Costs Incurred
Currently tracking a two week delay to design due to new scope
items, which should not affect the final completion date. The project
will seek commission authorization for construction funding             Construction Costs
September 2013.                                               Not Applicable
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
None
Risks
Results of the International Air Transport Association (IATA) Study
on level of service requirements and TSA's re-capitalization may
impact the scope and schedule of the baggage project.
Budget Transfers
From C800556 (NS NSAT Renov NSTS Lobbies)   $939,400


AIRPORT
Port of Seattle 2Q 2013 Report  75

SECOND QUARTER REPORT, 2013
NorthSTAR North Satellite Renovation NSTS
Lobbies
Renovation of the North Satellite
Project:    C800556         terminal, including STS station           Status Snapshot
"refresh", ramp level, Concourse
Budget: $206,546,357                                      On Schedule
level, and new rooftop airline
Phase: Design                                            On Budget
lounge.
Start: 7/24/2012                                                      0 Change Orders
Completion: 05/31/2018                                     Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
The "NW Sense of Place" strategy was developed and will be
implemented on this project. Draft 2013, 2017 and 2021 gating
250
analysis is complete along with Alaska Air Group's (AAG) 15%
concept design for NSAT employee spaces and AAG Boardroom.        200
Port and AAG site trip to MSP concluded that an integrated hold          Millions150
room model is not suitable for the NSAT Renovations. A decision to      Dollars in 100
evaluate potential NSAT expansion options has been approved by
50
the Port Steering Committee.
0
Authorized   Forecasted  Costs Incurred
Schedule
International Air Transport Association (IATA) Level of Service study    Construction Costs
is close to completion. The 15% design package is delayed slightly     Not Applicable
to address expansion options and the Airport-wide Gate Analysis.
Budget
Commission authorized $32,933,556 inclusive of the transfers for
vertical circulation & grease interceptor. A pending transfer of
funding associated with the Main Terminal & Concourse C STS
Station remodels will bring the total project budget and forecast to
$208,346,357. Project is on budget.
Change Order
None
Risks
IATA Level of Service study may indicate the need for facility scope
changes. Airlines operational requirements may require changes to
the preliminary two-phased construction approach.

76  Port of Seattle 2Q 2013 Report

Budget Transfers
Transfer of $1,800,000 is pending within the program for renovation of STS lobbies on Concourse C
& Main Terminal.













AIRPORT
Port of Seattle 2Q 2013 Report  77

SECOND QUARTER REPORT, 2013
Main Terminal Mezzanine Tenant Relocations
Project:    C800560         This project will construct new        Status Snapshot
Budget: $1,750,000        tenant leased spaces in order to     On Schedule
Phase: Design            move existing tenants and provide    On Budget
Start: 3/26/2013              new leasable office space for         0 Change Orders
Completion: 6/30/2014      airlines on the mezzanine of the     Total Change Orders Amount:
main terminal.                         $0
Budget/Costs Incurred
Significant Developments
2
The project is currently in design.
1.5
Millions
Schedule
1
Dollars in 
The project is currently on schedule.
0.5
Budget                                            0
Authorized   Forecasted  Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
None this quarter
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT

78  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Known Crewmember Employee Bypass
Project:    C800576         This project will construct two new    Status Snapshot
Budget: $650,000          Known Crewmember and          On Schedule
Phase: Construction       Employee bypass locations at the    On Budget
Start: 12/11/2012             Airport.                              0 Change Orders
Completion: 12/31/2013                                   Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The design is complete for the north location. The South location is
being redesigned to accommodate a relocated Checkpoint 1.             0.8
Schedule                                           0.6
Millions
0.4
Dollars in 
The redesign of the south location has caused a schedule delay in
completing the Known Crew Member portion of the project.
0.2
Budget                                            0
Authorized   Forecasted  Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
None this quarter                                                     Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT

Port of Seattle 2Q 2013 Report  79

SECOND QUARTER REPORT, 2013
Security Exit Lane Breach Control-Phase 2
Project:    C800605         This project will procure and install    Status Snapshot
Budget: $5,767,000        new automated breach control       Delayed Schedule
Phase: Design            equipment at four security exits in    On Budget
Start: 10/1/2012              the airport terminal.                  0 Change Orders
Completion: 06/30/2014                                   Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The 90% design documents were completed.
8
Schedule
6
This Phase 2 project schedule was pushed out later to ensure that        Millions
there was adequate time for Airport Security and TSA testing of the         4
pilot project (completed in Phase 1).
Dollars in   2
Budget                                            0
Authorized   Forecasted  Costs Incurred
The project forecast is within the approved budget.
Change Order
None                                                 Construction Costs
Not Applicable
Risks
If the testing period of the equipment on the Phase 1 project
increases, it could delay completion of this Phase 2 project.
Budget Transfers
None




AIRPORT
80  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
North Satellite - STS Ceiling Leak Repair
Project:    C800609         This project will eliminate ceiling      Status Snapshot
Budget: $1,750,000        leaks at the North Satellite (NSAT)   On Schedule
Phase: Design             that occur between the satellite      On Budget
Start: 05/28/2013             transit station (STS) and the          0 Change Orders
Completion: 09/30/2014     elevators.                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Commission approved design authorization on May 28, 2013. The
project is beginning design with construction planned for mid-               2
2014.
1.5
Schedule                                           Millions
1
The project is currently on schedule.
Dollars in 0.5
Budget                                            0
Authorized   Forecasted  Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Construction Costs
Change Order                                     Not Applicable
None.
Photo
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT

Port of Seattle 2Q 2013 Report  81

SECOND QUARTER REPORT, 2013
Passenger Bridge and Walkway S16
Replacement
Replace existing Passenger          Status Snapshot
Project:    C800611         Loading Bridge (PLB) and Fixed      On Schedule
Walkway at Gate S16. Upgrade       On Budget
Budget: $1,000,000
existing foundations and install         0 Change Orders
Phase: Design            infrastructure to support new Wi-Fi   Total Change Orders Amount:
Start: 06/03/2013             capabilities                          $0
Completion: 12/31/2013
Budget/Costs Incurred
Significant Developments
Design is currently under way and the new (PLB) and Fixed               1.2
Walkway have been ordered from John Bean Technologies (JBT)          1
AeroTech - Jetway.                                                   Millions 0.8
0.6
Schedule                                           0.4
Dollars in 
Work on the foundation upgrades is scheduled to begin after Labor        0.2
Day. Removal of the old equipment and installation of the new PLB       0
Authorized   Forecasted  Costs Incurred
and Fixed Walkway is scheduled to be completed in the fourth
quarter of 2013.
Budget                                         Construction Costs
Not Applicable
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the bid documents are completed.
Change Order
None.
Risks
Delivery schedule of the equipment from JBT AeroTech - Jetway
Budget Transfers
None this quarter.


AIRPORT

82  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Checked Baggage Recapitalization/Optimization
Project:    C800612         TSA approached the Airport in        Status Snapshot
Budget: 4,850,000         2012 with plan to replace all        On Schedule
Phase: Design            federally owned and operated       On Budget
Start: 2/26/2013              baggage scanning equipment,        0 Change Orders
Completion: 12/31/2017     known as Explosive Detection       Total Change Orders Amount:
System (EDS) equipment. The       $0
EDS equipment is approaching the
end of its life.                              Budget/Costs Incurred
6
Significant Developments                                 5
The Port and TSA have executed an Other Transaction Agreement       Millions  4
(OTA). The design started in February 2013 and 30% design of the         3
TSA component was completed in June, per the OTA. The 30%           2
design for the airport component will be due in September.                Dollars in   1
0
The project team has submitted the TSA design component for                Authorized  Forecasted Costs Incurred
federal funding.
Schedule                                         Construction Costs
The project is currently on schedule.                                    Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 2Q 2013 Report  83

SECOND QUARTER REPORT, 2013
Second Floor Mezzanine Infrastructure Upgrade
Project:    C800615         This project is to upgrade and        Status Snapshot
Budget: $2,545,000        extend the infrastructure (HVAC,     On Schedule
Phase: Design            Communications, Electrical,        On Budget
Start: 08/01/2013             Plumbing, WiFi) to 14,000sq ft of      0 Change Orders
Completion: June 2014     future lease space on the second    Total Change Orders Amount:
floor, including 7,000 sq ft for a new    $0
USO.
Budget/Costs Incurred
Significant Developments
3
The project received Commission approval in June 2013. The            2.5
project is in the beginning stages of design.                                Millions  2
1.5
Schedule
1
The project is currently on schedule.                                       Dollars in 0.5
0
Budget                                              Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                                     Construction Costs
Not Applicable
None
Risks
None
Budget Transfers
None




AIRPORT
84  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Highline School Noise Insulation
Status Snapshot  Prior Report
Delayed Schedule  4Q 10
Project:    C200007         Highline School Insulation           On Budget
Budget: $101,797,000      Agreement will provide funding for    0 Change Orders
Phase: Construction       sound mitigation for 15 schools that   Total Change Orders Amount:
Start: 03/23/1999             are impacted by aircraft noise from    $0
Completion: 11/30/2021     Sea-Tac Airport.
Budget/Costs Incurred
Significant Developments                               120
100
Port funding is authorized and will become available when the FAA,
the State of Washington, and the Highline School District provide         Millions 80
matching funds.                                                        60
40
Schedule                                           Dollars in  20
0
The schedule for state funding is not known. The district's schedule
Authorized   Forecasted  Costs Incurred
is dependent on obtaining general election bonds at various
intervals. The school district has requested FAA grant funding for
Olympic Elementary in fourth quarter of 2013.
Construction Costs
Budget                                         Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
Not applicable
Risks
Project delayed due to funding issues with the Highline School
District.  Risk is if no bonds are passed in general election.  Obtain
FAA Airport Improvement Program (AIP) Grant funding.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 2Q 2013 Report  85

SECOND QUARTER REPORT, 2013
Highline Community College Noise Insulation
Project:    C200042         Highline Community College         Status Snapshot  Prior Report
Budget: $32,050,000       Insulation Agreement will provide    Delayed Schedule  4Q10
Phase: Construction       funding for up to 22 eligible         On Budget
Start: 01/11/2005             buildings that are impacted by        0 Change Orders
Completion: 12/31/2013     aircraft noise from Sea-Tac Airport.   Total Change Orders Amount:
$0
Significant Developments
Thirteen of the 22 eligible buildings have been sound insulated by      Budget/Costs Incurred
the college.
40
Schedule                                           30
Building #4 received FAA Airport Improvement Program (AIP) Grant
20
and began construction in winter 2012. Substantial completion for        in Millions
Building 4 is August, 2013. The schedules for the remaining              Dollars  10
buildings are dependent on state funding.
0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of
the remaining project budget will be requested for one building at a     Construction Costs
time from the Commission in the future when the schedule is           Not Applicable
determined.
Change Order
Not Applicable
Risks
The Highline Community College competes for state funding with
other colleges. If they do not receive adequate funding, projects will
be delayed.
Budget Transfers
None this quarter.


AIRPORT

86  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Home Insulation Retrofit
Project:    C200048         This project includes storm window    Status Snapshot  Prior Report
Budget: $5,344,000        retrofit of previously insulated       Delayed Schedule  4Q 11
Phase: Construction       homes.                        On Budget
Start: 01/11/2005                                                  0 Change Orders
Completion: 12/31/2013                                   Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The Port has identified eligible homes and notified homeowners of
their eligibility.  The Port is continuing with storm window retrofit.               6
5
Schedule                                            4
The Port is reviewing other potential homes for eligibility.                    Millions  3
2
Budget                                           Dollars in 1
The project forecast is within the approved budget and authorization.        0
Authorized   Forecasted  Costs Incurred
Change Order
None.                                                       Construction Costs
Not Applicable
Risks
The ability to accomplish the retrofit is dependent on homeowner's
schedules, and structural integrity of the home.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 2Q 2013 Report  87

SECOND QUARTER REPORT, 2013
Single Family Home Sound Insulation
Project:    C200093         Sound insulate remaining homes     Status Snapshot  Prior Report
Budget: $13,747,395       that are within the 1998 65 decibel    Delayed Schedule       4Q 11
Phase: Construction       day night level (DNL) noise         On Budget
Start: 03/27/2007             contour.                             0 Change Orders
Completion: 12/31/2013                                   Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
Thirty-seven homes are complete; five homes are in the process of        15
receiving sound insulation; 7 homes are on the waiting list.
Approximately 90 additional homes have been identified as eligible.       Millions 10
Schedule                                            5
Dollars in 
This project is currently on schedule.
0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within approved budget and authorization to
complete all homes currently in progress.                              Construction Costs
Change Order                                        4
None
3
Risks                                                 2
Millions
The ability to accomplish the insulation is dependent on the
Dollars in   1
homeowner's schedules, willingness to sign an aviation easement,
and obtain a subordination agreement from their lender, and                0
Initial    Change Order    Spent
structural integrity of the home. If more eligible homes than
anticipated are identified in the future, then additional funding may be
needed.
Budget Transfers
None this quarter.


AIRPORT
88  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
RMU/Kiosk Concession Program
Status Snapshot  Prior Report
Delayed Schedule  4Q 10
Project:    C800146     The project will provide design and       On Budget
Budget: $879,146       fabrication of Retail Merchandising      0 Change Orders
Phase: Construction    Units (RMUs); provide power,          Total Change Orders Amount:
Start: 11/20/2007         communications, and data to RMU        $0
Completion: 09/30/2013 locations; and install floor-mounted
receptacles for the utilities to allow easy
connection points as well as flexibility     Budget/Costs Incurred
for future utilization.
1.5
Significant Developments                               Millions 1
RMU utilities have been installed at the Concourse C location. The
0.5
procurement of the casework has been awarded and the contract         Dollars in 
was executed in June 2013. We are finalizing the design of the
0
casework and installation is scheduled for late September.
Authorized   Forecasted  Costs Incurred
Schedule
The utility infrastructure is complete. The casework is scheduled for     Construction Costs
installation 10 weeks from the final design approval; anticipate late      Not Applicable
September 2013.
Budget
The project forecast is currently within the approved budget and
authorization.
Change Order
None
Risks
The additional units on Concourse C may exceed the proposed
budget.
Budget Transfers
None this quarter.

AIRPORT

Port of Seattle 2Q 2013 Report  89

SECOND QUARTER REPORT, 2013
Burien Commercial Property Acquisition
Project:    C800150         Acquire commercial properties        Status Snapshot  Prior Report
Budget: $3,000,000        along Des Moines Memorial Drive,   Delayed Schedule       2Q 10
Phase: Implementation     and vacate one street, in the City of   On Budget
Start: 05/31/2007             Burien that is surrounded by Port-     0 Change Orders
Completion: 12/31/2013     owned properties.                Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
The remaining anticipated acquisitions will be street vacation of 12th
4
Place S. in Burien, Washington; possibly the 757 Convenience store;
and a small upholstery shop on the Lora Lake site.                         3
Millions
2
Schedule
Dollars in   1
It is anticipated that the acquisitions will occur in the 2013 time
frame.                                                                 0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget.
Construction
Change Order                                     Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
90  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Tenant Reimbursement
Status Snapshot
Project:    C800154       Build out of spaces for new and         On Schedule
Budget: $4,709,577      existing tenants. If more than a "basic   On Budget
0 Change Orders
Phase: Construction     finish" condition space is built for the
tenant, the tenant is required to           Total Change Orders Amount:
Start: 08/14/2007
reimburse the Port for the cost of the     $0
Completion: TBD
work beyond this "basic finish". These
reimbursements are allowed under     Budget/Costs Incurred
the guidelines described in the
"Tenant Reimbursement Policy".            5
4
Millions  3
Significant Developments
2
No activity in Second Quarter of 2013.
Dollars in   1
Schedule                                            0
Authorized   Forecasted  Costs Incurred
Schedules vary to meet the tenant's needs.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 2Q 2013 Report  91

SECOND QUARTER REPORT, 2013
Snow Removal Equipment - 2013
Project:    C800498         This project will purchase four        Status Snapshot
Budget: $2,000,000        pieces of runway snow removal      On Schedule
Phase: Implementation     equipment.                     On Budget  1Q 13
Start: 02/14/2012                                                  0 Change Orders
Completion: 01/22/2013                                   Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
All equipment has been received. The only work remaining is to
install the required radios on the four new plow & tow behind broom       2.02
snow removal units. The radio installs will be completed by the end
2
of September.
1.98
Schedule
1.96   in Millions
Equipment delivered on schedule.
1.94   Dollars 
Budget                                           1.92
Authorized   Forecasted  Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
None                                                 Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT
92  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
T-46 Lease Improvements
Project: C102554           Construct stormwater treatment       Status Snapshot
Budget: $6,000,000        system to comply with Ecology
Phase: Design            order by 09/30/2014. Terminal
0 Change Orders
Start: 04/12/2013             pavement overlay to fulfill lease
obligation.                               Total Change Orders Amount:
Completion: 2020                                        0
Significant Developments                             Budget/Costs Incurred
Commission approved project design funding on April 9, 2013.
7
Design consultant contract executed on April 12, 2013.                    6
Schedule                                          Millions 5
4
Stormwater treatment system to be completed by September 30,          3
2014.                                                            Dollars in   2
1
0
Budget
Authorized   Forecasted  Costs Incurred
$10,000,000 for Stormwater Treatment System. Currently within
budget.
Construction Costs
Change Order                                     None
Not Applicable
Risks
Complete stormwater treatment system within budget by September
30, 2014
Budget Transfers
Not Applicable



SEAPORT

Port of Seattle 2Q 2013 Report  93

SECOND QUARTER REPORT, 2013
Street Vacations T5,18,105
Status Snapshot
Delayed Schedule  4Q 11
Project: C102858,       Street vacation related real estate        On Budget
C102875, E104366      negotiations and agreements --T5,      0 Change Orders
Budget: $1,500,000     T18, and T105.                     Total Change Orders Amount:
Phase: Permitting                                      $0
Start: June 2010
Completion:  2014                                       Budget/Costs Incurred
2
Significant Developments                                1.5
Millions
Meetings with the City have restarted for Terminal 18 (T-18). T-105         1
Street Vacations have been completed.
Dollars in 0.5
Schedule                                            0
Authorized   Forecasted  Costs Incurred
Current effort involves resolving Street Vacation issues on T-18. T-5
Street Vacations issues will be addressed following completion of
T-18 issues.                                                          Construction Costs
Not Applicable
Budget
The budget has been revised for 2013 and beyond.                   Photo
Change Order
Not applicable
Risks
Not applicable
Budget Transfers
Not applicable



SEAPORT
94  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
P91 Fender System Upgrade
Project:    C800183         Upgrades to the vessel berths of      Status Snapshot
Budget: $5,700,000        P91 to better accommodate cruise    On Schedule
Phase: Design            ships and also serve the other       On Budget
Start: 01/31/10                industrial customers who utilize the    0 Change Orders
Completion: 8/1/2013       berths and adjacent dock/apron      Total Change Orders Amount:
areas on P91 for less than $6M by    $0
spring 2011.
Budget/Costs Incurred
Significant Developments
6
Fabrication of 7 camel barges complete. Camels in service for the
remainder of 2013 cruise season.
Millions  4
Potential to order more barges under existing purchase option.
2
Schedule
Dollars in 
Full Fender replacement completed April 2012.                            0
Camel Barge replacement completed by July 2013.                          Authorized  Forecasted Costs Incurred
Budget
Project is within approved budget.                                      Construction Costs
2.5
Change Order
2
None this quarter
Millions   1.5
Risks                                                  1
None this quarter                                                        Dollars in   0.5
0
Budget Transfers                                            Initial  Change  Spent
Orders
None




SEAPORT
Port of Seattle 2Q 2013 Report  95

SECOND QUARTER REPORT, 2013
T-5 Crane Cable Reels
Status Snapshot  Prior Report
Project:    C800349         Purchase Cable Reels for tenant.
Budget: $3,500,000                                      Delayed Schedule
Phase: Design                                         On Budget
Start: 05/04/10                                                    0 Change Orders
Completion: 03/31/11                                     Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The terminal tenant completed the installation of the cable reels
during the Quarter. This will be the final report
4
Schedule                                            3
Project installation complete
Millions  2
Budget                                           Dollars in 1
Project completed under budget                                         0
Authorized   Forecasted  Costs Incurred
Change Order
None
Construction Costs
Risks                                              Not Applicable
None
Photo
Budget Transfers
None




SEAPORT

96  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
T-91, Bldg C175 Roof Replacement
Status Snapshot  Prior Report
Project:    C800430         Replace roof on the C175 building
Budget: $240,000          at Terminal 91.                  Delayed Schedule
Phase: Design                                         On Budget
Start: 7/26/11                                                      0 Change Orders
Completion: Q4 2014                                     Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The project design is progressing with the 60 percent submittal
review to occur during the 3rd Quarter.
0.3
0.25
Schedule
0.2
As previously reported, the design is anticipated to be completed in       0.15    Millions
the third quarter followed by installation in 2014.
0.1
0.05   Dollars in
Budget
0
On budget                                                           Authorized  Forecasted Costs Incurred
Change Order
None                                                 Construction Costs
Not Applicable
Risks
None at this time                                                       Photo
Budget Transfers
None




SEAPORT
Port of Seattle 2Q 2013 Report  97

SECOND QUARTER REPORT, 2013
SEA P66 Apron Pile Wrap
Status Snapshot
Project:    C800516         Design and install a pile wrap
Budget: $3,010,000        system for corrosion protection of    On Schedule
Phase: Design            steel structural pilings associated    On Budget
Start: 3/6/12                  with Seaport structures at Pier 66.     0 Change Orders
Completion: 12/31/14                                     Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
Construction activities began. Work is being completed in                   4
conjunction with the P69 North Apron Corrosion Control Project
3
(CIP C800313).                                                    Millions  2
Dollars in 
Schedule
1
Based on the schedule submitted by the contractor, construction
should be completed by the end of March 2014.                           0
Authorized   Forecasted  Costs Incurred
Budget
Project is on budget.                                                    Construction Costs
Not Applicable
Change Order
None
Risks
Installation of pile wraps is tide and weather dependent.
Construction duration may lengthen due to unfavorable conditions.
Budget Transfers
None



SEAPORT

98  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Argo Yard Truck Roadway
Status Snapshot
Project:    C800546,        New Port of Seattle owned truck
E104751, E104754          roadway between SR 99 and        On Schedule
Budget: $2,800,000        Colorado Way Avenue right-of-way.   On Budget
Phase: Design                                         0 Change Orders
Start: 03/11/12                                                    Total Change Orders Amount:
$
Completion: 12/31/2014
Significant Developments                              Budget/Costs Incurred
Review comments received from project stakeholders regarding            3
MOU Supplemental Agreement and final negotiations are underway.
Sixty percent engineering design completed. Property appraisal for         2
the roadway easement areas completed.
Millions
1
Schedule                                           Dollars in
Design and permitting is scheduled to be completed by late 2013.          0
Authorized   Forecasted  Costs Incurred
Construction is to be completed in summer 2014.
Budget
Construction Costs
Project authorized budget is $2,800,000 (including $600,000 from      Not Applicable
FMSIB). Current preliminary project estimate is $3,200,000.
Change Order
None
Risks
Additional funding approval expected to be required when
authorization to advertise for construction bids is requested. The
actual start of utilization of the proposed Argo Yard truck roadway is
dependent upon the completion of separate off-site projects - EMW
Phase II (East Marginal Way surface street improvements) and
WSDOT's SR 99 timber trestle replacement scheduled for
construction completion by spring 2014. The EMW Phase II
improvements will also require timely approval by Union Pacific
Railroad and the Ash Grove Cement Co. in order to be completed
within 2014.


Port of Seattle 2Q 2013 Report  99

Budget Transfers
None













SEAPORT
100  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
P66 Security Camera Upgrade Project
Project:    C800596         P66 Cruise Terminal Security        Status Snapshot
Budget: $540,000          Camera Upgrade. Scope removes    On Schedule
Phase: Construction       29 cameras monitoring the cruise    On Budget
Start: 10/05/2012             facility, installs 36 new cameras,      2 Change Orders
Completion: 07/01/2013     and upgrades the infrastructure.     Total Change Orders Amount:
$500
Significant Developments
Budget/Costs Incurred
Construction is complete and in closeout.
0.6
Schedule
0.5
Installation Complete.                                                     Millions 0.4
Dollars in 
0.3
Budget                                            0.2
On Budget.                                                        0.1
0
Change Order                                          Authorized  Forecasted Costs Incurred
One no cost change order to extend contract time to allow
completion of punch list items. One change order to compensate
Contractor for switching around already installed camera.               Construction Costs
Risks
None.
Budget Transfers
None




SEAPORT
Port of Seattle 2Q 2013 Report  101

SECOND QUARTER REPORT, 2013
T-46 Dock Rehabilitation
Project:    C800603         Terminal 46 Dock Rehabilitation      Status Snapshot
Budget: $1,854,000        Project                        Delayed Schedule
Phase: Design                                         On Budget
Start: November 6, 2012                                          0 Change Orders
Completion: Q1 2016                                     Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The project continued design efforts working toward the 90percent
submittal. The construction schedule was delayed to allow the strom        2
water work from the T-46 Lease Amendment project to be completed
prior to starting the project.                                                      1.5
Millions
1
Schedule
Dollars in 0.5                                                                                                      To avoid conflicting construction projects and minimize disruptions to
the tenants operations the start of construction was delayed one
0
year. With the construction delayed the the design schedule was              Authorized  Forecasted Costs Incurred
relaxed one month. Instead of the 90 percent submittal be made in
June it was moved to be early in the 3rd quarter.
Construction Costs
Budget                                         Not Applicable
The project is on budget
Photo
Change Order
None
Risks
None at this time
Budget Transfers
None



SEAPORT
102  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
East Marginal Way Grade Separation
Status Snapshot  Prior Report
Project:    E102007         FAST Corridor funded project;        Delayed Schedule
Budget: $55,456,171       FHWA, State, City with Port         Forecast Overrun
Phase: Close Out          commitment of $20,437,841. Scope   59 Change Orders
Start: 5/2006                 is to construct grade separation in     Total Change Orders Amount:
Completion: Q1 2014       vicinity of T5 and T18 to minimize     $1,358,306
truck traffic/rail conflicts.
Budget/Costs Incurred
Significant Developments
53.6
Final landscaping improvements installed and are now under a 3-
53.58
year maintenance period before final acceptance by City. Other         53.56
miscellaneous construction loose ends are in process of being           53.54
completed. Final project Memo of Agreement (MOA) is in process        Millions
53.52
with the City. As-built drawings are in progress.                             53.5   Dollars in
53.48
Schedule                                          53.46
Authorized   Forecasted  Costs Incurred
Final acceptance by SDOT is anticipated by 1st Quarter 2014.
Budget
Construction Costs
Current construction costs based on unit line items and cost
reconciliation, which is part of the project closeout. Preliminary                25
investigation indicates potential overrun.
20
Change Order                                       Millions  15
10
Change orders have been executed for a total net amount of
$1,431,000.                                                          Dollars in    5
0
Risks                                                     Initial  Change  Spent
Orders
Additional POS funding will likely be needed to reconcile final project
costs.
Photo
Budget Transfers
None

SEAPORT

Port of Seattle 2Q 2013 Report  103

SECOND QUARTER REPORT, 2013
Viaduct Construction Coordination
Project:    E104324,         Participate in the design &           Status Snapshot
E104535-38               construction of the bored tunnel,     On Schedule 2Q 13
Budget: $2.9M            north & south portals, Holgate to     On Budget  2Q 13
Phase: Implementation     King St, Central Waterfront surface   0 Change Orders
Start: 1/1/2009                streets, and related projects to        Total Change Orders Amount:
ensure adequate connection to port   $0
Completion: 12/31/2018
facilities.
Budget/Costs Incurred
Significant Developments
3.5
Continued construction of SR99 South Holgate to King Stage 3             3
overpass to South Atlantic St. Delivery of SR 99 tunnel boring
Millions 2.5                                                                                                      machine via T-46 occurred April.  Contractor completed mitigation              2
works, building demolitions, and construction of conveyor at T-46 in        1.5
preparation for tunnel spoils transfer operations.                           Dollars in   1
0.5
Schedule                                            0
Authorized   Forecasted  Costs Incurred
Tunnel mining operations expected to begin July 2013. Funding
Agreement expected to be completed in Q3. Related City projects
are making steady progress (Mercer/Seawall/Central Waterfront).
Construction Costs
Not Applicable
Budget
Port staff costs were within anticipated 2013 spending.                  Photo
Change Order
Not applicable
Risks
There are multiple impacts to port tenants and general freight
mobility due to temporary road closures, detours, and other
necessary construction activities.
Budget Transfers
None


SEAPORT
104  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
T-5 and T-18 Maintenance Dredging
Status Snapshot
Project:    E104840         Maintenance Dredge T-5 Berth 1 to   On Schedule
Budget: $1,950,000        -45', Berth 2 and 3 to -50', and       On Budget
Phase: Design            perform T-18 high spot removal if    0 Change Orders
Start: 08/14/12                permit allows                        Total Change Orders Amount:
Completion: 02/28/2014                                   $
Budget/Costs Incurred
Significant Developments
2.5
T-5 Phase II maintenance dredging design and permitting is under
2
way. T-18 programmatic permit is under way now under a separate
1.5
budget and schedule.
Millions
1
Schedule                                           Dollars in 0.5
Project is on schedule. Final Commission authorization for                  0
Authorized   Forecasted  Costs Incurred
construction will be requested in 3rd quarter.
Budget
Construction Costs
Project is on budget.
Change Order
None
Risks
Port is reviewing feasibility to combine T-5 Phase II dredging with a
small maintenance-dredging project at T-91 for efficiency. T91 may
have its own permitting challenges and risks.
Budget Transfers
None



SEAPORT

Port of Seattle 2Q 2013 Report  105

SECOND QUARTER REPORT, 2013
FT C15 HVAC Improvements
Status Snapshot
Project:    C800137                                           Delayed Schedule  4Q 11
Budget: $3,987,000      Provide the preliminary planning,       On Budget
Phase: Design          design, and construction to replace     0 Change Orders
Start: 05/01/10             the existing HVAC systems within        Total Change Orders Amount:
Building C-15 that are at the end of
Completion: 5/31/2014                                    $0
their service life.
Budget/Costs Incurred
Significant Developments
5
Commission approved construction funding on May 14th.
Completed 100% internal design review.                                  4
Millions  3
Schedule
2
City's permit took longer to process due to misplaced calculations         Dollars in   1
and misunderstanding of design elements. City has since found the
0
calculations and approved the permit. Advertise contract early
Authorized   Forecasted  Costs Incurred
August and plan to complete construction Spring, 2014.
Budget
Construction Costs
On budget                                                    Not Applicable
Change Order
None
Risks
Equipment/construction costs for the specific type of equipment is
fairly volatile and difficult to predict.
Budget Transfers
None



REAL ESTATE

106  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
P69 N Apron Corrosion Control
Status Snapshot
Project:    C800313         Install a corrosion control system     On Schedule
Budget: $5,100,000        for the steel pilings, pile caps, and    On Budget
Phase: Construction       beams under the North Apron.      0 Change Orders
Start: 03/06/12                                                    Total Change Orders Amount:
Completion: 12/31/2013                                   $0
Budget/Costs Incurred
Significant Developments
6
Construction activities began.
Millions  4
Schedule
Based on the schedule submitted by the contractor, construction            2
should be completed by end of 2013 to allow for testing and              Dollars in 
closeout.                                                                   0
Authorized   Forecasted  Costs Incurred
Budget
Project is on budget.                                                    Construction Costs
Not Applicable
Change Order
None                                                 Photo
Risks
Installation of pile wraps is tide and weather dependent.
Construction duration may lengthen due to unfavorable conditions.
Budget Transfers
None at this time



REAL ESTATE

Port of Seattle 2Q 2013 Report  107

SECOND QUARTER REPORT, 2013
P-69 Built-up Roof Replacement
Project:    C800314         Replace the 65,000SF Roof at the    Status Snapshot
Budget: $445,000          P-69 Headquarters Office Building    On Schedule
Phase: Design                                         Forecast Overrun
Start: 2/26/12                                                      0 Change Orders
Completion: 10/30/2014                                   Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Preliminary reports are complete and the project is in the 90% design
phase.                                                            2.5
2
Schedule
Millions 1.5
The project is scheduled to be completed in Q4 2014
1
Budget                                           Dollars in 0.5
The project is currently below budget.                                       0
Authorized   Forecasted  Costs Incurred
Change Order
None
Construction Costs
Risks                                              Not Applicable
None
Budget Transfers
None




REAL ESTATE
108  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Maritime Industrial Center Built-up Roof
Replacement
Replace the 21,000SF Roof at the     Status Snapshot
Project:    C800571         MIC Office Building                 On Schedule
On Budget
Budget: $1,456,000
0 Change Orders
Phase: Construction                                    Total Change Orders Amount:
Start: 9/30/12                                                      $0
Completion: 10/30/2013
Budget/Costs Incurred
Significant Developments
Contractor submittals are in progress; the project is ready to proceed        2
with the onsite construction phase.
1.5
Millions
Schedule                                            1
The project is scheduled for completion in Q4 2013
Dollars in 0.5
Budget                                            0
Authorized   Forecasted  Costs Incurred
The project is currently on budget.
Change Order
Construction Costs
None                                                 Not Applicable
Risks
None
Budget Transfers
None




REAL ESTATE

Port of Seattle 2Q 2013 Report  109

SECOND QUARTER REPORT, 2013
Pier 66 Steam Replacement
Install new boilers to provide           Status Snapshot
Project: C800625
adequate heat and hot water          On Schedule
Budget: 1,400,000                                       On Budget
Phase: Construction       service for both the conference
Change Orders
Start: 6/2/2013               center and CTA operations.
Total Change Orders Amount:
Completion: 12/31/13
Significant Developments                              Budget/Costs Incurred
Initial design complete. Major works open order contract advertised
1.5
and awarded. Major mechanical equipment ordered.
Millions  1
Schedule
Seattle Steam delayed cutoff of steam service from September 2nd
0.5
to October 15th due to delay of City of Seattle seawall project             Dollars in 
0
Budget
Authorized   Forecasted  Costs Incurred
Project is within budget
Change Order
None                                                 Construction Costs
Not applicable
Risks
Working with Puget Sound Energy to upgrade natural gas service to
the building to accommodate increased demand from additional
equipment. Delay of this upgrade may impact the project schedule
and jeopardize the October 15th completion
Budget Transfers
None



REAL ESTATE
110  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
FT Net Shed Code Compliance
Project:    E104838         FT Net Sheds 3-11 building          Status Snapshot
Budget: $2,950,000        improvements required per City of    On Schedule
Phase: Design            Seattle building & fire codes        On Budget
Start: May 2012                                                   0 Change Orders
Completion: June 2015                                   Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Commission approved construction funding on June 25, 2013.
3.5
Schedule                                            3
Staff will procure racks, rack foundations and finalize permit before        Millions 2.52
beginning construction in late September/early October with intent of
1.5
completing all construction activities by the end of 2nd quarter of 2015
1
if all net sheds would be retrofitted. Net Shed No. 7 and 8 work            Dollars in 
0.5
would be deferred to the very end of construction.
0
Authorized   Forecasted  Costs Incurred
Budget
Project budget is on track.
Construction Costs
Change Order                                     Not Applicable
None
Risks
It is difficult to project the amount of stored materials that needs to be
moved out and moved back since tenant storage habit could vary
significantly. In addition, the amount of work required in each unit is
difficult to assess until stored materials are fully removed. These
would impact the overall project budget.
Budget Transfers
None


REAL ESTATE

Port of Seattle 2Q 2013 Report  111

SECOND QUARTER REPORT, 2013
Flight Information System (FIMS) II
Project: C101117         Procure, develop, and implement a      Status Snapshot
Budget: $8,220,000       FIMS system that includes             On Schedule
Phase:Implementation    replacement monitors, an airport       On Budget
Start: 5/4/2010             resource management system, and      5 Change Orders
Completion: 12/30/2013   a flexible digital signage system        Total Change Orders Amount:
capable of displaying flight                $395,223
information, visual paging, and
notifications.
Budget/Costs Incurred
9
Significant Developments
8
The first phase deployment of the flight information display (FIDS)          7
Millions   6
software was completed on-schedule in November 2012.
5
Deployment of the resource management system (RMS) was           Dollars in   4
deployed on-schedule in June 2013 with no major issues. This fully         3
2
replaces the previous FIMS software.
1
0
Authorized     Forecasted    Costs Incurred
Casework construction, display replacement, and small system
enhancements will continue through 2013.
Schedule                                         Construction Costs
On Schedule                                                     2.5
2
Budget
Millions  1.5
On Budget
1
Change Order                                      Dollars in  0.5
Prior report: Additional signage replacement was approved resulting         0
in a contract change order for construction design.                                Initial    Change    Spent
Orders
.
Risks
No significant risks.
Budget Transfers
None

CORPORATE

112  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Maximo Enterprise Implementation
Project:    C800003         Implement latest version of           Status Snapshot  Prior Report
Budget: $3,680,000        Maximo, merge Aviation and Real    Delayed Schedule
Phase: Implementation     Estate applications onto one        On Budget
Start: 11/25/2007             platform, and add service desk        0 Change Orders
Completion: 12/30/2013     module and wireless handheld       Total Change Orders Amount:
capabilities.                              $0

Significant Developments                              Budget/Costs Incurred
Major components of the program have been delivered, including the
4
deployment of Service Management software for the ICT Service
Desk in December 2008 and the upgrade and consolidation of             3
Marine Maintenance and Aviation Maintenance Maximo systems in
2
September 2010. The smaller mobility enhancement has been            Millions
deployed to a pilot group of Aviation and Marine Maintenance             Dollars in  1
personnel and additional interfaces will be created after the
0
Peoplesoft Financials upgrade.                                              Authorized  Forecasted    Costs
Incurred
Schedule
Prior Report - Several of the proposed new interfaces link the           Construction Costs
Maximo system to the Peoplesoft Financials Procurement module.     Not Applicable
Because of planned changes in the procurement process with the
Peoplesoft Financials Upgrade project, the delivery of these
interfaces will be delayed until after the completion of the upgrade
project.
Budget
On Budget
Change Order
None
Risks
Resource constraints may continue to delay the implementation of
the interfaces and mobility enhancements.
Budget Transfers
None

CORPORATE
Port of Seattle 2Q 2013 Report  113

SECOND QUARTER REPORT, 2013
ID Badge System Replacement
Project: C800162           Procurement and replacement of     Status Snapshot
Budget: $2,500,000         the Portwide ID Badge system       Delayed Schedule
Phase:Implementation      including software, hardware, and    On Budget
Start: 5/1/2012                equipment.                          0 Change Orders
Completion: 6/30/2014                                      Total Change Orders Amount:
$0
Significant Developments
Software configuration, data migration, and technical specifications     Budget/Costs Incurred
are in development.
3
2.5
Schedule
2
While deployment of the main software component will be delivered       1.5
Millions
on-schedule, a smaller mobile component will be released in a             1
second phase deployment in 2014.                                    Dollars in 0.5
0
Budget                                              Authorized Forecasted  Costs
Incurred
On Budget
Change Order                                     Construction Costs
Not Applicable
None
Risks
No significant risks
Budget Transfers
None




CORPORATE
114  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Airline Activity Management
Project: C800222           Development of an airline activity     Status Snapshot
Budget: $500,000           management system that           Delayed Schedule
Phase:Implementation      integrates with several Port         On Budget
Start: 6/19/2011               systems to replace aging reporting    0 Change Orders
Completion: TBD          system and supply data for airline    Total Change Orders Amount:
activity fees.                              $0

Budget/Costs Incurred
Significant Developments
0.6
The first phase delivery that includes replacement of the aging
0.5
activity reporting system has been delivered according to schedule.
0.4
0.3
Schedule                                            Millions
0.2
Requirements cannot be finalized until decisions are made regarding     Dollars in 0.1
the Resolution or update of the Signatory Lease and Operating
0
Agreement (SLOA). Components of the project that generate airline           Authorized  Forecasted    Costs
activity for billing have been put on-hold.                                                            Incurred
Budget                                         Construction Costs
On Budget                                                   Not Applicable
Change Order
None
Risks
Significant changes to the requirements for the Resolution or SLOA
update may further delay the project or require additional funding.
Budget Transfers
None



CORPORATE
Port of Seattle 2Q 2013 Report  115

SECOND QUARTER REPORT, 2013
Enterprise Project Cost Management
Project: C800321           Replace the current construction     Status Snapshot
Budget: $1,525,000         costing systems with a common      Delayed Schedule
Phase:Implementation      enterprise project cost             On Budget
Start: 4/21/2008               management system.                0 Change Orders
Completion: 12/30/2013                                     Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The first phase deployment has been completed and the software is
in-use by the Project Management Groups.                              2
1.5
Schedule
Availability of resources is impacting the completion of the remaining        1
Millions
components. These include features such as cash flows and trend
logs as well as additional interfaces that require resources currently       Dollars in 0.5
focused on the Peoplesoft Financials Upgrade project. We are in the       0
Authorized  Forecasted     Costs
process of procuring additional configuration assistance and expect                             Incurred
to deliver in phases over the next several months.
Construction Costs
Budget
Not Applicable
None
Change Order
None
Risks
Availability of Port resources may delay next phase deliverables.
Budget Transfers
None


CORPORATE

116  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Records and Document Management
Project:    C800322         Improve statutory compliance,        Status Snapshot
Budget: $800,000          increase functionality, and lower     Delayed Schedule
Phase: Implementation     operating costs by replacing        On Budget
Start: 6/23/2009              Hummingbird with SharePoint for      0 Change Orders
Completion: 9/30/2013      records and document             Total Change Orders Amount:
management.                    $0

Significant Developments                              Budget/Costs Incurred
The Sharepoint 2010 upgrade, training, and project-led organization
roll-out has been completed. Testing of Sharepoint 2010 Records         0.8
Center is in progress.                                                       0.6
0.4
Schedule                                            Millions
Resource availability due to competing priorities has delayed the full       Dollars in 0.2
implementation of the Sharepoint Records Center until September         0
2013.                                                                 Authorized  Forecasted   Costs
Incurred
Prior Report: Sharepoint 2010 implementation is dependent on the
completion of several infrastructure projects currently in progress       Construction Costs
and requires additional time to complete the upgrade of existing        Not Applicable
sites.
Budget
On Budget
Change Order
None
Risks
Projects with higher priority may continue to delay Records Center
implementation.
Budget Transfers
None

CORPORATE
Port of Seattle 2Q 2013 Report  117

SECOND QUARTER REPORT, 2013
Time Clock System
Project: C800387           Procure and implement a Time       Status Snapshot  Prior Report
Budget: $380,000           Clock System to accurately capture   Delayed Schedule
Phase: Planning            and track time and attendance for    On Budget
Start: 6/8/2010                approximately 230 employees in      0 Change Orders
Completion: 11/30/2013     Aviation Security and Airport         Total Change Orders Amount:
Operations organizations.             $0

Significant Developments                              Budget/Costs Incurred
Vendor was unable to deliver software that functioned in our
0.4
environment per the contract. We are working with the legal
department to determine our options for severing the relationship.            0.3
0.2
The project team has evaluated options and are moving forward with       Millions
the procurement and implementation of a simpler time clock system      Dollars in   0.1
from a different vendor. The scope of the implementation will not
0
include a Peoplesoft interface as originally planned.                              Authorized Forecasted   Costs
Incurred
Schedule
We are estimating deployment of the new solution in November        Construction Costs
2013.                                                           Not Applicable
Budget
$75,500 of the $240,000 spent to date on the project was directly
related to the previous vendor solution and will not contribute to the
value of a new product implementation. This was expensed against
the ICT Operations Budget in 2012. The new solution can be
delivered within the approved budget.
Change Order
None
Risks
No signfiicant risks at this time.
Budget Transfers
None
CORPORATE
118  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
PeopleSoft Financials Upgrade
Project: C800392           Upgrade of Peoplesoft Financials     Status Snapshot  Prior Report
Budget: $5,000,000         hardware and software             Delayed Schedule
Phase:Implementation                                    On Budget
Start: 9/28/2010                                                  0 Change Orders
Completion: 12/31/2013                                     Total Change Orders Amount:
$0
Significant Developments
Software configuration and development has been completed and      Budget/Costs Incurred
testing is in progress for a September 2013 implemenation.
6
5
Schedule
4
Prior Report - An implementation vendor was selected via a                3
Millions
competitive procurement but we were unsuccessful in negotiating an       2
acceptable contract. Because of resource constraints during the          Dollars in  1
year-end process, the next optimum window of opportunity for the          0
upgrade begins in mid-2012. This will delay the project one year.              Authorized  Forecasted    Costs
Incurred
Budget
On Budget                                                   Construction Costs
Not Applicable
Change Order
None
Risks
Significant resources will be required across multiple organizations
which may delay other technology projects.
Budget Transfers
None



CORPORATE
Port of Seattle 2Q 2013 Report  119

SECOND QUARTER REPORT, 2013
Police Records Management System
Project: C800393           Procure and implement a           Status Snapshot  Prior Report
Budget: $1,300,000         replacement Police Records         Delayed Schedule
Phase:Implementation      Management System              On Budget
Start: 10/10/10                                                    0 Change Orders
Completion: 8/31/2013                                      Total Change Orders Amount:
$0
Significant Developments
Testing of system in progress.                                         Budget/Costs Incurred
Schedule                                           1.5
Prior Report - A change request was approved to implement
1
additional software that will better meet business process for field
reporting. Technical problems installing the new software will delay         Millions
0.5
the implementation until August 2013.                                    Dollars in
0
Prior Report - Contract negotiations took significantly longer than
Authorized   Forecasted     Costs
anticipated delaying project completion by 8 months.                                             Incurred
Budget
On Budget                                                   Construction Costs
Not Applicable
Change Order
None
Risks
Continued issues with the vendor installation may further delay
project completion.
Budget Transfers
None



CORPORATE
120  Port of Seattle 2Q 2013 Report

SECOND QUARTER REPORT, 2013
Access Control Network Refresh
Project: C800558           Upgrade the Access Control         Status Snapshot
Budget: $1,500,000         Network switch infrastructure        On Schedule
Phase: Design             hardware and software            On Budget
Start: 3/26/2013                                                  0 Change Orders
Completion: 3/31/2014                                      Total Change Orders Amount:
$0

Significant Developments                              Budget/Costs Incurred
Design and procurement in progress.                                       2
1.5
Schedule
1
On schedule.
in Millions
0.5
Budget                                           Dollars    0
Authorized  Forecasted Costs Incurred
On budget.
Change Order
Construction Costs
None                                                 Not Applicable
Risks
Port resource availability may impact schedule.
Budget Transfers
None




CORPORATE

Port of Seattle 2Q 2013 Report  121

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.