9a Presentation CIP Update

Item No.: 9a_Supp
Meeting Date: December 11, 2018
Corrected: December 13, 2018 (slide 15)
Capital Improvement Projects
Third Quarter Report
2018

100 Capital Improvement Projects
Overall Status of Projects
100 Total Projects in report (87 CDD, 13 ICT)
47 Projects are within or ahead of target schedule and budget
46 Projects have either target schedule or budget off with 11 new
Reportable Variances for this Quarter.
7 Projects have both target schedule and budget off with 2 new
Reportable Variances for this Quarter.
3 Projects are Substantially Complete

Capital projects managed by CDD and ICT
2

CDD Projects by Status, by Quarter
Off Schedule and
Budget                 100%
5                     6                     8                     7
90%
Off Schedule              80%            35                                                              38
or Budget                             (Schedule)                                                       (Schedule)
70%                           37                38                 1
(Schedule)
60%                                           (Schedule)            (budget)
50%
On Schedule              40%
and Budget               30%
46                    40                    45                    41
20%
10%
0%
4Q17 Report             1Q18 Report             2Q18 Report             3Q18 Report
Series3             5                         6                         8                         7
Series2            35                        37                        38                        39
Series1            46                        40                        45                        41
Two new red and 10 new amber
3

CDD Projects by Dollar Value
Off Schedule and Budget  OLD VARIANCE
- Emergency Gen - $2.6 M
- IWS Segregation Improvements - $1.1M
$25M $14M -  Electric Utility SCADA - $9.6M
- Shilshole Bay Marina Paving - $2.0M
$121M - Shilshole Tenant Services Building - $10.1M

$2.18B                      Off Schedule and Budget  NEW VARIANCE
$683M - Telecommunications Meet Me Room - $3.9M
- Wi-Fi Enhancement for Ramp and Term - $10.6M
Off Schedule/Budget $25M or More  OLD SCHEDULE VARIANCE
- GSE Electrical Charge Stations - $30.7M
- Concourse D Hardstand Terminal - $38.4M
- Checked Bag Recap Optimization - $445M
Off Schedule/Budget $25M or More  NEW SCHEDULE VARIANCE
- Safedock Upgrade and Expansion - $28.2M
Projects on Schedule and Budget - $75M or More
- International Arrivals Facility - $931M
Total Budget = $3.03B - NS NSAT Renovations NSTS Lobbies - $672M

Two new projects off schedule & budget; 9 new projects off schedule and 1 off budget
4

Mortenson Seattle cost index
5

Mortenson Construction data
6

Mortenson Seattle Building Component Trends
7




Mega Project Commission Updates
International Arrivals Facility
Last Update to Commission: September 25, 2018
Document Set Link here
Total Budget: $968.4M
Expected Project Completion: Q4 2020
North Star / North Satellite
Last Update to Commission: November 27, 2018
Document Set Link here
Total Budget: $672.1M
Expected Project Completion: Q3 2021
Baggage Optimization
Last Update to Commission: October 23, 2018. Next update: January 22, 2019
Document Set Link here
Total Budget: $445M
Expected Phase 1 Completion: Q4 2019
Mega Project Updates
8

Aviation Project Summary  OLD VARIANCES
Projects with OLD Schedule and Budget Variances:
- IWS Segregation Improvements
- Electrical Utility SCADA
- Emergency Generator Controls
Projects with OLD Schedule or Budget Variance
- 160th GT Lot                                              - Concourse B Holdroom
- Highline School Insulation                                       - Concourse D Hardstand Terminal
- GSE Electrical Charge Stations                                   - SSAT Structural Improvements
- Security Lane Exit Phase 2                                       - GBAS Upgrade
- Checked Bag Recap Optimization                               - ADR Kiosk Expansion Project
- Construction Logistics Expansion                                 - Terminal Security Enhancements
- C3 Holdroom Expansion                                     - Delta Inflight Services TRA
- Concourse B and C Roof Replacement                            - Central Terminal Enhancements
- North Terminal Utilities Upgrade                                  - Automated Screening Lanes Checkpoint Conversions
- Concourse C New Power Center                                - Flight Corridor Safety Program Phase 1
- Auburn Mitigation Road Removal                               - Flight Corridor Safety Program Phase 2 and 3
- North East Redevelopment Area Program
List of Projects with Old Variances
9

Aviation Project Summary
Two projects with a new budget and schedule variance:
o Wi-Fi Enhancement for Ramp and Terminal  Delivery method evaluation impacting
budget and schedule
o Telecommunications Meet Me Room  Coordination with IAF causing delay and
potential budget increase
One project with a new budget variance:
o Passenger Loading Bridges (PLB) Renew and Replace Phase 2  In-ground utilities
requiring modifications to support PLB Locations

Two projects with budget/schedule variance; One with a budget variance
10

Aviation Project Summary
Eight projects with a new Schedule variance:
Lora Lake Apartment Remediation  Lake fill re-design not approved for construction to start in
2018
Air Cargo Road Safety Improvements  Design on schedule, but construction anticipated to take
longer than originally planned
Central Terminal Infrastructure Upgrade  Project is currently 90 days behind schedule, which
may affect substantial completion; schedule being monitored for recovery
Concourse B Holdroom  Holdroom is in use; Signage installation taking longer than expected
Safedock Upgrade and Expansion  Scope change
ARC Flash Hazard Mitigation  Delays due to resource constraints concerning consultant design
Parking Revenue Infrastructure  RFP Technical document review taking longer than anticipated;
Schedule being monitored for recovery
RCF Pavement Remediation  Early works on time, but design has been delayed.
Eight new schedule variances
11

Aviation Projects
Substantial Completion



Concourse B & C Roof Replacement
12

Aviation Projects
Substantial Completion



South 160th St GT Building
13

Aviation Project Focus
Reconfiguration of Taxiways A/B/L/Q
Currently Within Budget & Schedule
$47.5M
Completion expected December
2018                        Taxiway Q
Approximately 80% Complete
Acceleration Utilized Where/When
Appropriate to Maintain Schedule
Weather Continues to be the Major
Risk                                                   Taxiway A/B Reconfiguration
Taxiway Improvements
14

Aviation Project Focus
Renovate existing and build new
restrooms
Within Budget & Schedule
$38.4M
Split among five phases
Phase 1 Enabling Work Complete
Phase 2 Design Complete
Phase 3 FAA review underway
Advertise for Phase 2
construction in Q2 2019
FAA review could take longer than
anticipated
Concourse B, C, D Restroom Upgrades
15

Seaport Project Summary  OLD VARIANCES
Projects with OLD Schedule and Budget Variances:
- Shilshole Bay Marina Paving
- Shilshole Tenant Services Building

Projects with OLD Schedule or Budget Variance
- Fishermen's Terminal Redevelopment Phase 1
- FT Net Sheds 3,4,5 and 6
- Argo Yard Truck Roadway
- Terminal 46 Permit Mitigation
- East Marginal Way Grade Separation

List of Projects with Old Variances
16

Seaport Project Summary
One project with a new schedule variance:
P69 Solar Panel is behind schedule due to Shoreline Master Use permit variance
requirement by the City.




One New Schedule Variance
17

ICT Projects by Status, by Quarter
100%
Off Schedule                  90%
80%       40%
46%          46%
70%                    62%          57%
60%
50%
40%
30%       60%
54%          54%
On Schedule                 20%                 38%         43%
and Budget                  10%
0%
3Q17 Report     4Q17 Report     1Q18 Report     2Q18 Report     3Q18 Report
On Schedule/On Budget   Either Budget or Schedule off   Both Schedule and Budget off

13 Projects  All on or under budget
18

ICT Project Summary  OLD VARIANCES
Projects with OLD Schedule or Budget Variance
- Parking System Replacement
- Vessel Moorage System
- Remote Data Center Business Continuity
- Airport Data Network Switch Upgrade
- Checkpoint Wait Time
- SEA Smartphone App



List of Projects with Old Variances
19

Information & Communication Technology
Project Summary
One project with a new schedule variance
Project Delivery System  Functionality will be delivered every few months starting
in Q3 2018 but features for optimum business value will not be completed until Q1
2019.



One new variance out of a total of 13 ICT Projects .
20

Information & Communication Technology
Substantial Completion



Airport Communications Network Upgrade
21

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.