AGENDA MEMORANDUM                        Item No.          6d 
ACTION ITEM                            Date of Meeting      January 8, 2019 
DATE:     December 14, 2018 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Paul Meyer, Senior Manager  Maritime Environmental Programs 
Matthew Mateo, Senior Environmental Management Specialist 
SUBJECT:  Memorandum of Agreement for Permitting Support between Port of Seattle and
Seattle Department of Construction and Inspections 
Amount of this request: No new funding requested. 
ACTION REQUESTED 
Request Commission authorization for the Executive Director to extend the term of the existing
interagency memorandum of agreement with the Seattle Department of Construction and
Inspections (SDCI) for up to five years. The agreement commits SDCI staff to expediting all Port
of Seattle permit reviews. Funding for this action is covered by divisional operating expense
allocations and was included in the 2019 budget. No new funding is requested with this action. 
EXECUTIVE SUMMARY 
This authorization request extends the existing agreement between the Port of Seattle and
SDCI for expedited permitting services. The agreement formalizes coordination with SDCI and
establishes expectations for each party to meet project timelines. 
This agreement applies to all Port of Seattle projects, including larger capital projects and
smaller expense projects, under review by SDCI. As examples, the existing agreement assisted
and helped expedite permitting for the Pier 69 Solar Array installation, Terminal 5 berth
improvements, Shilshole Bay Marina customer service facility improvements, as well as
numerous small works and maintenance capital or expense projects. 
The requested five-year authorization window aligns with the Port of Seattle's recently adopted
2019-2023 capital investment plan. Proposed investments in the plan require significant and
complex permit approvals.  The liaison services authorized under this agreement provide 
expedited permit reviews, dedicated SDCI staff familiar with Port operations, and continued
guidance throughout capital project implementation. 


Template revised April 12, 2018.

COMMISSION AGENDA  Action Item No.  6d                                Page 2 of 4 
Meeting Date: January 8, 2019 
The Port of Seattle Commission originally authorized this agreement on January 26, 2016. The
current authorization expires on January 26, 2019. Continued authorization would commit SDCI
staff to expediting Port of Seattle projects under permit review until January 26, 2024. 
JUSTIFICATION 
The 2019-2023 capital investment plan proposes improvements at Salmon Bay Marina, a new
cruise berth, development of Terminal 91 uplands, electrical power to the Central waterfront,
and development of Fishermen's Terminal Gateway building, among others. Each of these
projects will require close coordination with the City of Seattle to meet individual project
timelines. The agreement will minimize project delays, support the implementation of the
capital investment plan, and contribute to the following Century Agenda strategies: 
Position the Puget Sound region as a premier international logistics hub 
Advance this region as a leading tourism destination and business gateway 
Be the greenest, most energy efficient port in North America 
DETAILS 
The Port of Seattle Commission first authorized the agreement on January 26, 2016. Since that
time, the agreement has supported more than 60 capital and expense projects under review by
the Seattle Department of Construction and Inspections.  The agreement states that SDCI will
provide the following services: 
1.  Facilitate scheduling timely pre-submittal conferences and permit intake appoints; 
2.  Provide timely and accurate information on application submittal requirements; 
3.  Respond to questions and provide follow-up in a timely manner; 
4.  Facilitate coordinated review of projects with other departments; 
5.  Identify process and code issues early in the pre-application and review process; 
6.  Facilitate  timely  resolution  of  code  and  process  issues  within  SDCI  and  across
department lines; 
7.  Provide a timely and predictable process to raise and resolve code and permitting
issues; 
8.  Review projects within agreed upon timelines identified in the project schedule; 
9.  Provide a single point of contact for project facilitation of Port projects. 
Either party can discontinue the agreement given 30 days' advanced notice. This provides
flexibility if permitting project loads decrease. 
Sound Transit has maintained a similar agreement with the City of Seattle since 1998. Their
agreement covers the design and implementation of light rail in the City of Seattle. Under the
agreement, Sound Transit authorizes funds to  provide design coordination, plan reviews,
permit actions and other services needed to allow construction of light rail facilities within the
City of Seattle. Sound Transit recently authorized $1.2 million to the City of Seattle on April 26,

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No.  6d                                Page 3 of 4 
Meeting Date: January 8, 2019 
2018, for project administration and permit streamlining services for the West Seattle and
Ballard Link Extensions project. 
The Port of Seattle has similar agreements in place for dedicated liaison staff for expedited
permit review with the U.S. Army Corps of Engineers and for staff dedicated to National Marine
Fisheries Service consultation needed for in-water work approvals. 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1    Do not authorize agreement between the Port of Seattle and Seattle
Department of Construction and Inspections 
Cost Implications: $0 
Pros: 
(1)   Cost savings from not authorizing agreement. 
Cons: 
(1)   Permitting time will increase resulting in potential project delays. 
(2)   No early guidance from the City of Seattle in capital project implementation. 
This is not the recommended alternative. 
Alternative 2  Authorize agreement for LESS than the requested five years. 
Cost Implications: Approximately $190,000 per year for duration of authorization 
Pros: 
(1) Permitting review times coordinated with project timelines. 
(2) Guidance for complex capital projects. 
(3) Dedicated SDCI staff familiar with industrial marine development. 
(4) Potential cost savings from partially authorizing agreement 
Cons: 
(1)   Agreement  will  not  cover  the  full  implementation  timeframe  of  major  capital
improvements. 
(2)   Requires  more  administrative  effort  for  Port,  as  well  as  city  staff  in  processing
agreement renewals more often. It is inefficient. 
(3)   Missed renewals could increase permitting time for some projects. 
This is not the recommended alternative. 
Alternative 3  Authorize extension of existing agreement for up to five years coinciding with
adopted Capital Investment Plan 
Cost Implications: Approximately $190,000 per year for five years 
Pros: 
(1)   Permitting review times coordinated with project timelines. 
(2)   Guidance for complex capital projects. 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No.  6d                                Page 4 of 4 
Meeting Date: January 8, 2019 
(3)   Dedicated SDCI staff familiar with industrial marine development. 
Cons: 
(1)   Costs associated with SDCI agreement. 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
The agreement is estimated to cost $190,000 per year. The $190,000 stated in this request is an
estimate based on previous agreement costs between 2016 and 2018. Actual costs are subject
to change based on SDCI labor rates set annually by Seattle City Council. The Port of Seattle
reimburses the City of Seattle for work completed under the agreement.  The 2019 amount is
included in the 2019 approved budget. Future years will be included in annual budget requests. 
Annual Budget Status and Source of Funds 
No new funding is requested. Funding for this agreement is covered by allocated Maritime
divisional operating expenses. 
ATTACHMENTS TO THIS REQUEST 
(1)   Current Agreement with the Seattle Department of Construction and Inspections. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
January 26, 2016  The Commission authorized the Chief Executive Office to enter into a
new memorandum of agreement with Seattle Department of Construction and
Inspections for up to three years. 








Template revised September 22, 2016; format updates October 19, 2016.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.