6c Memo Emergency Backup Water Supply

COMMISSION 
AGENDA MEMORANDUM                        Item No.          6c 
ACTION ITEM                            Date of Meeting      January 22, 2019 
DATE:     January 14, 2019 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Wayne Grotheer, Director, Aviation Project Management Group 
SUBJECT:  Emergency Backup Water Supply (CIP #C800493) 
Amount of this request:               $2,614,000 
Total estimated project cost:           $2,739,000 
ACTION REQUESTED 
Request Commission authorization for the Executive Director  to (1) prepare design and
construction bid documents for the Emergency Backup Water Supply project at Seattle-Tacoma
International Airport; (2) advertise and award a major works construction contract; and (3) use 
Port of Seattle crews and small works contracts to perform construction work if required. The
amount of this request is $2,614,000. The total estimated project cost is $2,739,000. 
EXECUTIVE SUMMARY 
This project will develop the Tyee Golf Course well into an emergency backup water supply for
potable use and fire protection utilizing the Port's existing water distribution system. The Sea-
Tac Airport Water System has no backup water supply as called for by the State Department of
Health (DOH) for potable use and fire protection. 
The Seattle-Tacoma International Airport is currently supplied with domestic and fire protection
water by Seattle Public Utilities (SPU) via a single source. The Airport owns and operates a two
million gallon reservoir that can provide water for domestic use for up to three days, but if a
water outage from SPU is extended beyond two to three days, airport operations would be
critically impacted. 
The scope of this project will replace the existing well building with a new water treatment
facility at the same location to handle up to 350 gallons per minute of instantaneous water
flow. This facility will utilize the existing wellhead (well and pump), a manganese filtration
system, a chlorination system, a clear well, and a booster pump system. Water produced by the
treatment facility will be transmitted to the existing water distribution system. The addition of
this needed treatment system, not contemplated in the original cost estimate, adds $2,239,000 
to the project budget of $500,000 that is included in the 2019-2023 capital budget. 

Template revised April 12, 2018.

COMMISSION AGENDA  Action Item No. __6c__                              Page 2 of 5 
Meeting Date: January 22, 2019 
JUSTIFICATION 
Currently, all of the domestic and fire water needs for Airport are met by purchasing water
from SPU. In the event of disaster, water to the airport could be curtailed or shut off altogether. 
The Airport has no backup for potable and fire water other than the supply from SPU. Backup is
available for almost all other utilities. The Airport has a two million gallon reservoir that can
provide domestic water supply for up to three days, but at the risk of using all the water
required for fire reserve. As a vital regional asset in the event of a disaster, it is important that
the Airport has adequate water supply to operate in case of emergency. 
Our vulnerability was pointed out by DOH in a June 13, 2013, report. The DOH engineer
recommended that we should "consider conducting an evaluation of the pros and cons
associated with developing (our) existing well(s) as an emergency supply option in the event of
loss or service from Seattle." 
The project would upgrade the existing Tyee Golf Course well and pumping system to add
filtration, chlorination, an emergency generator, a new building, and piping as required to
augment the SeaTac Airport Water System. The facilit ies would be designed and constructed 
primarily for emergency purposes. The necessary change of use water right has been obtained
for this well from the Washington State Department of Ecology. Once the system is installed
and approved by DOH, the well can be tested and activated as an emergency supply within
three days of an outage of the SPU system (about the time at which our reservoir would be
depleted). The amount of water available would be approximately half of the normal usage, but
still enough to supply priority uses and maintain critical operations.
DETAILS 
This project will construct a water treatment facility at the existing Tyee Golf Course wellhead.
The existing Tyee Golf Course well building will be demolished. This new facility will provide an
emergency backup water supply for the airport water system and will be treated for
manganese to eliminate potential staining of plumbing fixtures. Treated water will be provided
to the existing Port distribution system via a new water main extension to the existing airport
piping system; filter backwash water will be disposed to the nearby sewer utility. 
Scope of Work 
The project will include the following work items: 
(1)   Demolition and removal of existing Well House and associated surface improvements; 
(2)   Construction of new well house, treatment system and pumping equipment; 
(3)   Construction of new improvements including sewer discharge, driveway, treatment
pad and instrumentation; 
(4)   Construction  of  new  water  transmission  line  with  connection  to  existing  Port
infrastructure. 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. __6c__                              Page 3 of 5 
Meeting Date: January 22, 2019 
Schedule 
Activity 
Design start                                       1st Quarter 2019 
Commission construction authorization          1st Quarter 2020 
Construction start                                2nd Quarter 2020 
In-use date                                       3rd Quarter 2021 
Cost Breakdown                                      This Request           Total Project 
Design                                                    $736,000              $861,000 
Construction                                             $1,878,000             $1,878,000 
Total                                                          $2,614,000              $2,739,000 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  Do not proceed with the project. 
Cost Implications: An estimated $75,000 in costs to date would need to be expensed if this
project is canceled. 
Pros: 
(1)   Does not require capital investment. 
(2)   Does not involve any shutdown of current facilities. 
Cons: 
(1)   This option will not reduce the risk involved with the lack of a backup water system for
the Airport. 
(2)   In the event of a regional incident which damages the current water supply infrastructure
provided by Seattle Public Utilities, the Airport would be without water for
an extended period of time, halting airport operations during a time of critical need. 
This is not the recommended alternative. 
Alternative 2   Design and construction of a basic water supply system (without water
treatment) consisting of only the well, pump and transmission line. 
Cost Implications: $500,000 
Pros: 
(1)   Would provide nominal water backup capacity in the event of a disruption to the
existing SPU water source. 
(2)   Construction would involve very little disruption to the activity of the existing system. 
(3)   Very low on-going maintenance cost since no filters to clean or replace, and no
chlorine to keep on-site. 
(4)   Water Treatment Plant Operator (WTPO) certification not required to operate this
system. 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. __6c__                              Page 4 of 5 
Meeting Date: January 22, 2019 
Cons: 
(1)   Upon operation the system would introduce manganese and other potentially harmful
substances into the Airport's distribution system. Even low-levels of manganese (0.05
mg/L) will lead to staining of the water and those facilities in contact with the water. 
This is not the recommended alternative. 
Alternative 3  Design and construction of a new water supply and treatment system consisting
of the well, pump, chlorination tank, manganese filter and transmission line. 
Cost Implications: $2,739,000 
Pros: 
(1)   Eliminates the risk involved with a solitary water supply to the airport. 
(2)   In  the  event  of  a  regional  incident  which  damages  the  current  water  supply
infrastructure provided by SPU, the Airport could continue to operate during a time of
critical need. 
(3)   Construction would not involve disruption to the existing system. 
(4)   Would not introduce manganese and other potentially harmful substances into the
Airport's distribution system. 
Cons: 
(1)   Requires WTPO certification to operate and maintain. 
(2)   Requires on-site storage of hazardous chemical (sodium hypochlorite which is the
active ingredient in household bleach). 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
Cost Estimate/Authorization Summary               Capital        Expense           Total 
COST ESTIMATE 
Original estimate                                   $500,000               $0        $500,000 
Previous changes  net                                    0               0                0 
Current change                                $2,239,000               0      $2,239,000 
Revised estimate                                $2,739,000               0      $2,739,000 
AUTHORIZATION 
Previous authorizations                            $125,000                0        $125,000 
Current request for authorization                $2,614,000                0      $2,614,000 
Total authorizations, including this request       $2,739,000                0      $2,739,000 
Remaining amount to be authorized                    $0             $0             $0 


Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. __6c__                              Page 5 of 5 
Meeting Date: January 22, 2019 
Annual Budget Status and Source of Funds 
This project (CIP #C800493) was included in the 2019  2023 capital budget and plan of finance
as a business plan prospective project with a total budget of $500,000. The budget increase is
due to the need to scope for a water treatment system.  The increase of $2,239,000 was
transferred from the Aeronautical Allowance C800753, resulting in no net change to the
Aviation capital budget. The funding source for this project will be the Airport Development
Fund and future revenue bonds. 
Financial Analysis and Summary 
Project cost for analysis              $2,739,000 
Business Unit (BU)                  Terminal Building 
Effect on business performance     NOI after depreciation will increase 
(NOI after depreciation) 
IRR/NPV (if relevant)                N/A 
CPE Impact                        $0.01 in 2022 
Future Revenues and Expenses (Total cost of ownership) 
This water production system is not expected to significantly increase future maintenance
costs. 
ATTACHMENTS TO THIS REQUEST 
(1)   Presentation slides 
(2)   June 18, 2013 letter from the DOH 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
None 







Template revised September 22, 2016; format updates October 19, 2016.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.