Asset Management Services Contract Memo

COMMISSION 
AGENDA MEMORANDUM                        Item No.          6k 
ACTION ITEM                            Date of Meeting     February 26, 2019 
DATE:     February 6, 2019 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Jeffrey Brown, Director of Aviation Facilities and Capital Programs 
Michael Tasker, Senior Manager of Aviation Facilities and Infrastructure 
SUBJECT:  Aviation Asset Management Program 
Amount of this request:               $5,000,000 

ACTION REQUESTED 
Request Commission authorization for the Executive Director to execute an asset management
services contract for up to 5 years for Seattle-Tacoma International Airport, with an estimated
value of $5,000,000. 
EXECUTIVE SUMMARY 
The Airport has more than $4 billion in facilities and equipment assets (historical cost, before
depreciation). The capital program will be delivering many more assets to the Port of Seattle in
the near future. Asset Information is critical for managing the Port of Seattle infrastructure,
fleet,  and  facilities.  It  helps  inform  maintenance  and  capital  planning  for  renewal  and
replacement or for capacity enhancement, allowing the Port to manage total cost of ownership
and ensure investment in the right assets at the right time to achieve the right level of service. 
This request is for consultant services to assist Aviation staff in obtaining asset data that will be 
placed into system where the information can be can be readily used to inform decision makers 
on managing the airport's assets.
JUSTIFICATION 
Sound asset management practices reduce the total cost of ownership and enhance maximum
asset life and reliability. Asset management is widely recognized as a smart ownership practice
and widely adopted by large infrastructure system owners. Asset management is one of the
most cost-effective methods for ensuring system reliability, safety, and energy efficiency.
Typical Return on Investment (ROI) of the implementation of an Enterprise Asset Management
System and development of an asset inventory is as follows:
1.  Labor utilization/ productivity is improved by 10-20% through better organization of
work activities. (it is noted that the 10-20% improvement identified above includes

Template revised April 12, 2018.

COMMISSION AGENDA  Action Item No. _6k___                              Page 2 of 5 
Meeting Date: February 26, 2019 
improved  decisions  coming  from  an  asset  management  program  not  just
implementation of those decisions). 
2.  Inventory stock is typically reduced by 20-30% as a result of better managed work
activities  resulting in reduce stock holding, which has both a direct finance impact as
well as indirect through storage etc. 
3.  Asset downtime is typically reduced 5-20%. 
4.  Productivity benefit  20 - 30% reduction in labor hours after a 5 to 10-year period. 
5.  Improved safety  2 to 3 times reduction in safety incidents 
6.  Improved performance  40 to 80% improvement in customer service 
7.  Improved use of available resources  20 to 30% reduced outages, reduced overtime 
8.  Improved  environmental  performance    reduced  CO2   emissions  and  reduced
environmental incidents 
9.  Reduced risks  resulting in reduced insurance premiums (up to 30% reduction in
premiums), and incident payouts. 
Another perspective is that the asset will cost on average 20% less to maintain over its lifetime
to achieve the same performance outcomes. 
Effective  asset  management  provides  guidance  direction  and  optimization  of  intelligent
maintenance practices that become a resource generating substantial energy savings. 
Inadequate maintenance of energy-using systems is a major cause of energy waste.  Energy
losses from steam, water and air leaks, uninsulated pipes, maladjusted or inoperable controls,
and other losses from poor maintenance can be substantial. 
DETAILS 
The Aviation Division is looking to improve its existing asset management program by using 
industry best practices to place geo-referenced asset management and work order history
information into our Computerized Maintenance Management System (CMMS). This will allow 
reporting that will drive renewal and replacement strategies and maximize asset life, reducing
total cost of ownership. 
The current asset management system, begun in 2011-2012 for the Aviation Division, has
naming conventions, hierarchies, and asset condition analysis completed for approximately 50
percent of the airport assets. The system has identified and defined assets and links PeopleSoft
(financial) information with the Port's CMMS (Maximo) information. The data is currently
maintained in excel spreadsheets.
In January 2018, the Aviation Division began a gap analysis of its asset management program
and current practices against industry best practices. This gap analysis was done with WSP, an

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. _6k___                              Page 3 of 5 
Meeting Date: February 26, 2019 
industry leading asset management consulting firm, headed up by Dr. Christian Roberts. Dr.
Roberts was one of the authors of the ISO 55000: the international standard for asset
management. 
WSP leveraged their industry-leading Asset Management Capability Assessment model, which
draws on over 20 years of experience managing critical infrastructure, to assess the Port of
Seattle's Aviation Division level of asset management maturity.
Scope of Work 
The contract's scope of work includes the following: 
1.     Develop and Implement Enterprise Asset Hierarchies
2.     Develop Data Collection Process 
3.     Asset Inventory Data Collection 
4.     Develop Condition Assessment Guidelines and Scoring for All Asset Classes 
5.     Conduct Condition and Capacity Assessments across All Asset Classes 
6.     Develop Asset Management Reporting 
7.     Perform  PeopleSoft  / Maximo  Integration/  GIS   Integration  assess  applicability  of 
design attribute integration via a design management tool 
8.     Develop Introductory and Ongoing Asset Management Training 
9.     Migrate existing Asset data into Maximo 
10.   Develop Enhancements to Asset Commissioning/Onboarding Process 
11.   Develop a process for Asset Program Sustainability
Schedule 
Q3 2019     Selection of Asset Management Consultant. 
2019-        Develop and Implement Asset Hierarchies 
Develop Discovered Asset Process 
Develop Condition Assessment Guidelines and Scoring 
Begin Asset Discovery, Inventory Collection and Condition Assessment 
2020-         Develop Asset Management reporting 
Continue Asset Discovery, Inventory Collection and Condition Assessment 
Migrate Existing Data into Maximo 
Develop enhancements to Asset Commissioning Onboarding process 
Develop Introductory and ongoing asset management training 
2021-         Perform Tool integration 
Continue Asset Discovery, Inventory Collection and Condition Assessment 
Develop a process for Asset Program Sustainability 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. _6k___                              Page 4 of 5 
Meeting Date: February 26, 2019 

Diversity in Contracting 
This contract will include a 15 percent woman-  and minority-owned business enterprise
(WMBE) aspirational goal. 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  Use Port staff and existing resources.
Cost Implications: 
It is estimated that the current STIA Asset Management system has assessed approximately
50% of all  airport  facility capital assets over the course of the last 7 years, utilizing 
approximately   20,000   staff   hours   working   around   other   duties   as   assigned.
Completion of these tasks for the rest of the STIA assets would require roughly an additional
20,000 hours of staff engagement. 
Pros: 
(1)   Saves expense budget. 
(2)   Develops staff knowledge to be able to manage the future requirement 
Cons: 
(1)   Requires additional FTEs and resources to complete in a timeframe that supports the
capital program. 
(2)   Training required for the staff to implement industry best practices. 
(3)   Could take another 7 years to implement working around other job responsibilities. 
(4)   Capital program projections will be delayed. 
This is not the recommended alternative. 
Alternative 2  Hire additional staff and perform the work with in-house resources. 
Cost Implications: 
Assessing the remaining assets is approximately 20,000 hours. 
Pros: 
(1)   Develops staff knowledge to manage the future requirement. 
Cons: 
(1)   Training of staff will be required to implement industry best practices. 
(2)   Could take longer to implement as the time required would be dependent on the
number of staff hired. Once the bow wave of work implementation is accomplished
the number of staff required to sustain the program will be less. Staff would have to
be reassigned. 
This is not the recommended alternative. 


Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. _6k___                              Page 5 of 5 
Meeting Date: February 26, 2019 
Alternative 3  Hire an asset management consulting firm to implement industry best asset
management practices and develop a training and maintenance program where the work can
potentially be transitioned to staff in the future.
Cost Implications: 
$5,000,000 in expense authorization required over 5 years. 
Pros: 
(1)   Faster implementation of industry best practices. 
(2)   Better Capital Budget projection. 
(3)   Reduction in total cost of ownership. 
(4)   Better asset reliability. 
(5)   Better capital decision making, using data and metrics for informing decisions. 
(6)   Develop training programs to share with and mentor staff to develop best practices. 
Cons: 
(1)   Higher expense burn rate. 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
Annual Budget Status and Source of Funds 
The 2019 operating budget includes $1,000,000 for this effort. The remainder of the funding
will be included in the operating budget of future years. The funding source will be the Airport
Development Fund. 
ATTACHMENTS TO THIS REQUEST 
(1)   Presentation slides 
(2)   Aviation Asset Management Gap Assessment Report 
(3)   Facility Information Exchange (Fx) Roadmap 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
None 





Template revised September 22, 2016; format updates October 19, 2016.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.