International Arrival Facility Briefing Presentation

Item No.               7b_supp 
Date of Meeting          February 26, 2019 
Sea-Tac International Airport
International Arrivals Facility Program 
Fourth Quarter 2018 Update 



1

AGENDA 
Project Overview 
2019 Quarter 1 Update 
Budget 
Schedule 
Challenges 
Accomplishments 
Progress 

International Arrivals Facility                                                                                        2

PROJECT OVERVIEW 
20 international gates 
760' long pedestrian
walkway 
450,000 sf facility 
2,600 pax per peak hour 
1,800 lf bag claim belt 
7 bag claim devices 
40 CBP officer podiums 
Key elements: 
CBP Offices and Processing          Airline Customer Service             International Gates 
Recheck Counter                   Iconic Pedestrian Walkway          Facial Recognition 
Baggage Claims 
International Arrivals Facility                                                                                        3

2019 Q1 Update 
Structural steel complete for Arrivals Building- Topping Out in Dec 2018 
Commenced Pedestrian Walkway erection at Cargo 2 
Steel fabrication now underway at seven different steel shops 
Completed Pedestrian Walkway concrete supporting elevator cores 
Pod B phased opening of 2 gates 
Capture turn over, operational Gate A9 
Capture of Gate A11 


Within contracted budget and schedule                                                                 4

PROGRAM COST PROGRESS OVERVIEW      (as of 12/31/18) 




Within contracted budget                                                                              5

GMP ALLOWANCE STATUS                (as of 12/31/18) 




Forecasted within budget                                                                                6

PAYMENTS TO DESIGN BUILDER (DB) (excludes Sales Tax)         (as of 12/31/18) 




Within contracted budget                                                                              7

SCHEDULE (December 2018 Progress Update) 
2018                     Today           2019                                                  2020                              2021
ID             Task Name
J     A     S     O    N    D     J     F    M    A    M    J     J     A     S     O    N    D     J     F    M    A    M    J     J     A     S     O    N    D     J     F    M
1   Baggage Handling System                                                                                                 Critical Path
2   IAF Building
Slab on Deck/Grade
Envelope
Finishes
Start Up & Commissioning
3   Sterile Corridor
Pod A
Pod B
Pod C
4   Pedestrian Walkway
Conc A Connection
SSAT Connection
Center Span
5   IAF ACTIVATION                                                                                                                                         IAF OPENING
6   Sterile Corridor - Pod D                                                                                                                                                    Closeout

IAF's Critical Path for on-time completion currently runs through the Baggage Handling System                8

SMALL BUSINESS/APPRENTICESHIP UTILIZATION 
March 2015 through December 31, 2018 
# Firms
Small Business                      $ Awarded 
Engaged 
SBE       120         $122M 
SCS       43           $26M 

Month of December 2018 
% of all         Hours
Apprentice Utilization 
Labor        Worked 
Total Apprentice Hours     20.45%       167,350 
Minority      20.4%        145,684 
Female      9.1%        21,665 

GMP participation commitment attained.                                                              9

CHALLENGES 
Steel fabrication schedules, deliveries and cascading effects 
Federal Shutdown  
CBP day-to-day coordination on hold 
TSA baggage design review may be delayed 
Shortages of workers in critical trades 


IAF - CHALLENGES                                                                                 10

ACCOMPLISHMENT: Arrivals Building Topping Out December 2018                                     11

ACCOMPLISHMENTS: Slab on Metal Deck Nearly Complete and CBP "Secure Construction" Inspections    12

ACCOMPLISHMENTS: Pencils Down, Terrazzo Selected, Temp Heat Activated                             13

ACCOMPLISHMENT: Pedestrian Walkway Concrete Support Cores  South Satellite                       14

ACCOMPLISHMENT: Pedestrian Walkway Concrete Support Cores  Concourse A                        15

ACCOMPLISHMENT: Pod B Turnover (Gate A9) and Pod C Construction Start                             16

PROGRESS: Arrivals Building Window Curtain Wall on East Face                                          17

PROGRESS: IAF Roof, Skylights, Window Curtain Wall and Escalators                                      18

PROGRESS: Arrivals Building CMU, MEP Rough-In, Lightwell Curtainwall                                   19

PROGRESS: Steel Fabrication Site Visits                                                                     20

PROGRESS: Pedestrian Walkway- Center Span Construction at Cargo 2                                21

PROGRESS: CBRA Construction, Warehouse and Baggage Handling System Header Steel                  22

PROGRESS: Warehouse Storage                                                                  23

QUESTIONS?                                                                                  22

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.