8b Memo New Cruise Terminal Design Authorization

COMMISSION 
AGENDA MEMORANDUM                        Item No.          8b 
ACTION ITEM                            Date of Meeting      March 26, 2019 
DATE:     March 19, 2019 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Stephanie Jones Stebbins, Managing Director, Maritime Division 
Mike McLaughlin, Director, Cruise Operations 
Fred Chou, Capital Program Leader, Seaport Project Management 
SUBJECT:  New Cruise Terminal Design Phase Funding Request (CIP #C800582) 
Amount of this request:                           $5,600,000 
Total estimated project cost to the Port:        $100,000,000 
ACTION REQUESTED 
Request Commission authorization for the Executive Director to proceed with: (1) the design
development and permitting phase (2) execute contracts for consultant support in this work
and (3) prepare bid documents for the New Cruise Terminal Project at Terminal 46 for an
estimated cost of $5,600,000, in addition to the previously division-authorized amount of
$150,000. The total estimated project cost to the Port is $100,000,000. 
EXECUTIVE SUMMARY 
A priority capital investment identified in the Maritime Division budget planning is the
development of a new cruise terminal facility in Seattle. This new facility will be constructed at
the north end of Terminal 46 on a site that will not exceed 29 acres. A single vessel berth
capable of accommodating vessels with berth length of up to 1,500 feet, vessels up to 250,000
GRT, vessel draft restricted to minus 40 feet MLLW and unlimited air draft is envisioned along
with a new passenger terminal building that can accommodate home port vessels with
passenger capacity of at least 5000 passengers or greater. 
This project supports the Century Agenda, through the strategy to "advance this region as a
leading tourism destination" and the objective to "double the economic value of cruise traffic
to Washington state." At the Commission meeting on March 12, this project took its first
significant step forward with the Commission's adoption of the "Principlesof Cruise Business
Development" Motion. 
During the capital planning for this future development, estimated at $200 million, it was
envisioned that this project would be delivered through a public-private partnership splitting
the cost of investment, thus limiting the port's funding for said development at $100 million.

Template revised January 10, 2019.

COMMISSION AGENDA  Action Item No. 8b                                  Page 2 of 8 
Meeting Date: March 26, 2019 
The amount of the final investment will be further defined during the public-private partnership
agreement negotiation phase of the Project.  On March 13, staff released a Request for
Qualifications (RFQ) to formerly launch the process to secure a new partner. 
With the upcoming decision of the Northwest Seaport Alliance (NWSA) regarding the Terminal
5 Modernization Program, the opportunity to move this new cruise terminal project forward
will  become  feasible  at  Terminal  46  (T-46).  Port  staff,  in  collaboration  with  NWSA  staff,
developed very preliminary concepts for locating a new cruise terminal at this location.  In
addition, staff created a list of project elements the Port would be responsible for, beyond the
delivery of a cruise passenger terminal building and passenger boarding systems/equipment,
which are expected to be provided by a selected investment and operating partner. Design
development must begin now to enable environmental review efforts to commence this fall
and in parallel with selecting a new investment partner to meet the projected cruise market
demand (and intended target date for completion) for a new terminal for the 2022 cruise
season.
JUSTIFICATION 
This request launches a priority capital project that will support our cruise business and ties into
the financials around the Terminal 5 Modernization Program as well. The requested $5.6 million 
is included in the Maritime Division's 2019 budget and is a piece of the broader estimateof
$100 million port costs for the project (which is 50 percent of the total estimated cost of $200
million to complete the new cruise terminal project at T-46). 
Our other two cruise terminals,  providing  three cruise berths in our harbor,  will remain
operational. Development of the new facility is being carefully considered as an interconnected
piece of our harbor-wide cruise business. 
Growth in Alaska will be driven mainly by the deployment of larger vessels into the region to
replace smaller ships and increase capacity for key brands. New brands will be deployed to take
advantage of new consumer sectors demanding Alaska sailings. To support growth the
development of additional homeport facilities which can support larger vessels is required. The
cruise industry is excited about this new opportunity and we expect robust competition in
securing a partner for this project. 
T-46 will remain a NWSA-managed property. The Port of Seattle will enter into an interlocal
agreement with NWSA to manage 29 acres of the property to support the new cruise facility.
The remainder of the acreage will remain under NWSA management and is intended for marine
cargo use. 
The timing for this action is critical to keep the project moving and to reach the targeted 2022
delivery date. 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. 8b                                  Page 3 of 8 
Meeting Date: March 26, 2019 
DETAILS 
With the aggressive intended target completion date for a new cruise terminal for the 2022
cruise season, the Port must initiate design and environmental review efforts in parallel with
selection of an investment partner, while working closely with the NWSA to balance the needs
of the parties and different uses across Terminal 46.  Based on assessment of the Port's work
components, it is estimated that the total design costs for the non-terminal building
components would be approximately $9.6 million. Out of those estimated design costs,  $5.6
million would need to be authorized for the initial design phase.
Examples of work covered under this initial design phase authorization include: 
Detailed utility infrastructure and apron structure assessments and comprehensive base
mapping; 
Geotechnical investigations; 
Cruise fender systems 
Terminal ingress and egress/roadways design; 
Traffic and air quality analyses for environmental documentation and reviews; and 
Procurement, obligation and execution of large professional services contracts for
preliminary and final design for project elements inclusive of offsite mitigations and long
lead items for specialized systems such as electrical equipment for shore-power and
substations. 
A delayed start in getting early work underway would further challenge the tight schedule for
the  overall  design  development  and  permitting  and  the  subsequent  construction  and
implementation phases of the project, where some construction work can only be performed
during allowable in-water work period and may require multi-year windows to complete. Upon
the Commission's initial design funding approval, staff would proceed to procure consultant
services to prepare construction documents and permits. Design of project components that
can be performed by Port's in-house engineering team will be further explored.
On March 13, the Port began a parallel process to request qualifications and proposals to select
an investment partner to develop the cruise terminal  building and associated passenger
boarding systems/equipment. The "Principles of Cruise Business Development," adopted by
the Commission at the March 12 meeting, will be used to guide the selection of the investment 
and operating partner (among other criteria). 
Staff anticipates returning to the Commission for authorization to execute a lease agreement
with the partner and seek remaining design phase funding after design has progressed further, 
and roles and responsibilities between the Port and the partner have been fully defined.
Diversity in Contracting 
The new cruise terminal project staff is coordinating with the Diversity in Contracting
Department to develop the appropriate women-and minority-owned business enterprise

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. 8b                                  Page 4 of 8 
Meeting Date: March 26, 2019 
(WMBE) aspirational goals for our design contract and to include in the private-partnership 
agreement.
Environmental Sustainability 
As stated in the recently adopted cruise principles motion, the Port is committed to
incorporating leading edge environmental stewardship and sustainability practices and facilities
that can exceed existing regulations into the new facility. The project design team will consider
and incorporate low impact development design features to the extent feasible. Design aspects
for both the buildings and infrastructure will consider and evaluate sustainable elements such
as (but not necessarily limited to): 
Innovative (green) stormwater management, 
High efficiency plumbing fixtures, 
Energy efficient lighting, 
Passive and/or high efficiency heating/cooling, 
Use of recycled materials, 
Construction waste landfill diversion, 
Low- or zero-emitting paints and other materials, 
Light pollution reduction, 
Storage and collection of recyclables, 
Water efficient development and landscaping, 
Accommodations for alternative transportation, 
Integrated community connectivity, 
Public access, and 
Habitat enhancement. 
Due consideration will be given to meet the Port's Century agenda goals to be carbon neutral or
carbon negative by 2050, including installation of shore-power infrastructure for vessels to plug
in  to  while  at  berth,  transportation  demand  management  systems,  and  on-site  energy
generation (such as solar panels). Tenant use of this facility will require compliance with all
applicable local, state, federal, and international laws. 
Scope of Work 
Work will include the design of  improvements necessary to support the collective cruise
terminal facility development,  with the  cruise passenger terminal building and passenger
boarding systems/equipment to be provided by a selected investment partner. These project
components, which the Port anticipates leading may include, but are not limited to, the
following: 
(1)   Terminal entry improvements both on Port and public right-of-way 
(2)   On-site and off-site mitigation, including environmental and shoreline mitigation 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. 8b                                  Page 5 of 8 
Meeting Date: March 26, 2019 
(3)   Utility  infrastructure  improvements,  including  elements  such  as  new  electrical
substations and cruise vessel shore power systems, new sanitary sewer and water
mains, and stormwater treatment systems 
(4)   Apron/bulkhead   structure   upgrades,  new  fendering  and  bollard  upgrades   or
improvements 
(5)   Site development including lighting, way finding, and landscaping 
(6)   Support buildings/passenger shelters and canopies 
The Port will also lead the environmental review for the entire project  assessing the
environmental impacts from the project construction and future operations. Funding will
support detailed technical evaluations of noise, air, marine transportation, traffic and water
quality impacts of the project as part of State Environmental Policy Act (SEPA) review. Funding
will also start permit application process for the required state, local and federal permits
needed prior to starting construction. 
Schedule 
With the target 2022 date to begin cruise terminal operations, key milestones are provided
below. With the in vestment partner not yet identified and the complex project subject to
elements that are out of the Port's and investment partner's control, if the 2022 delivery date
cannot be met, a full year delay could result. 
Commission Authorization  Initial Design        March 12, 2019 
Funding (This Authorization) 
Investment Partner Solicitation (Request For     March 13 2019 
Qualifications) 
Design start - Port's Project Elements            2Q 2019 
Commission Authorization - Investment         4Q 2019 
Partner Lease Agreement 
Commission Authorization  Remaining Design  4Q 2019/1Q 2020 
Funding 
Commission Authorization  Port's Project       3Q/4Q 2020 
Elements Construction Funding 
Construction Start  Port's Project Elements      4Q 2020 / 1Q 2021 
Targeted Cruise Terminal In-Use Date            2Q 2022 
Cost Breakdown                                      This Request           Total Project 
Design and Environmental Review                       $5,600,000            $9,600,000 
Construction                                                       0            $90,400,000 
Total                                                          $5,600,000           $100,000,000 


Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. 8b                                  Page 6 of 8 
Meeting Date: March 26, 2019 

ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  Port develops a new cruise terminal at Terminal 46 without a private sector
partnership.  Port would be funding the entire $200 million investment inclusive of a total
estimated $22 million design phase funding request. Target new cruise terminal in operation
by the 2023 cruise season. 
Cost Implications: $200 million (Port's Investment) 
Pros: 
(1)   Port maintains full control of project delivery and outcomes 
(2)   Investment provides maximum ROI revenue potential 
(3) Maintains Seattle's lead position as a homeport serving the Alaska Cruise market
(4)   Supports growth of economic benefits to our region 
(5)   Enables the Port to serve the new class of larger cruise ships being built
Cons: 
(1)   Insufficient capacity in Port Maritime Division Capital Plan to fully fund project 
(2)   Port assumes all risk associated with project development and with the long-term
revenues from the cruise business 
(3)   Port project delivery system to perform entire project scope would not meet the
intended  2022  completion date and cruise market schedule drivers. Significant
financial consequence as relates to Terminal 46 rent would result 
This is not the recommended alternative. 
Alternative  2   Develop  new  cruise  terminal  at  Terminal  46  through  a  public-private
Partnership agreement with target facility completion by the start of the 2022 cruise season.
Request Commission to authorize initial $5.6 million design development and permitting phase
funding and return to the Commission for the remaining design funding of $5 million after an 
investment partner is on board 
Cost Implications: $200 million  Shared capital investment $100 million by Port of Seattle and
$100 million by a private partner 
Pros: 
(1)   Port's investment portion aligns with approved 2019 Maritime Capital Budget 
(2)   Development and long-term business risks and rewards are shared between the Port
and a private partner 
(3)   More likely to achieve aggressive target schedule of opening new cruise terminal in
2022 
(4)   Partnership secures additional/future revenue stream for Maritime
(5)   Additional berth capacity aligns with market demand, positioning the port for new
cruise ship deployment schedules 
(6) Maintains Seattle's lead position as a homeport serving the Alaska Cruise market 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. 8b                                  Page 7 of 8 
Meeting Date: March 26, 2019 
(7)   Supports growth of economic benefits to our region at earliest date 
(8)   Enables the port to serve the new class of larger cruise ships being built more
efficiently 
(9)   Having the $5.6 million initial design funds would allow early design development and
permitting work to proceed. The remaining funds necessary to complete the design
phase effort would be assessed after the investment partner is brought on board and
by then the scope and roles and responsibilities would be better defined with the help
of the investment partner. 
Cons: 
(1)   Port relinquishes some control of project outcomes 
(2)   Potential limitations on maximum return (ROI) 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
Cost Estimate/Authorization Summary               Capital        Expense           Total 
COST ESTIMATE 
Original estimate  Project Cost to the Port     $100,000,000               $0   $100,000,000 
AUTHORIZATION 
Previous authorizations (Division Approval)         $150,000                0        $150,000 
Current request for authorization                $5,600,000                0      $5,600,000 
Total authorizations, including this request       $5,750,000                0      $5,750,000 
Remaining amount to be authorized           $94,250,000             $0    $94,250,000 
Annual Budget Status and Source of Funds 
The New Cruise Terminal Project CIP C800582 is included in the 2019 Plan of Finance for a total
cost of $100,000,000. The estimated total project cost is $200,000,000, including $100,000,000
investment from a private partner. 
The Port's share of the project is being funded with the General Fund. 
Financial Analysis and Summary 
Project cost for analysis              $100,000,000 (Alternative 3) 
Business Unit (BU)                  Cruise Operations 
Effect on business performance     2022: $3.15M 
(NOI after depreciation)*           2027: $11.03M 
2032: $22.06M 
IRR/NPV (if relevant)*               NPV: $236.75M 
MIRR: 10.83% 
CPE Impact                        N/A 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. 8b                                  Page 8 of 8 
Meeting Date: March 26, 2019 

*Analysis and estimates are pre-decisional, preliminary, and subject to change. 
Future Revenues and Expenses (Total cost of ownership) 
The Port's share of annual operating and maintenance costs will be determinedafter project
proposals have been received, thoroughly reviewed,  a private partner  selected,  and an
agreement with the private partner finalized. Preliminary analysis has estimated a potential
project payback period of ten years. 
ATTACHMENTS TO THIS REQUEST 
PowerPoint Presentation Slides 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
COMMISSION SPECIAL MEETING, NOVEMBER 7, 2018 
The Commission was briefed on the proposed new cruise terminal (among other capital projects) at
a study session. The session's topic was specifically the 2019 five-year Capital Improvement plan for
the Maritime and Economic Development Divisions. 
COMMISSION MEETING, MARCH 12, 2019 
The Commission adopted Motion 2019-02  Principles for Cruise Business Development. 










Template revised September 22, 2016; format updates October 19, 2016.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.