9a Presentation CIP Quarterly Update

Item No.: 9a_Supp 
Meeting Date: May 14, 2019 
CAPITAL PROJECT
QUARTERLY UPDATE 
Q1 2019

Service and Stewardship 
PRINCIPLES FOR CAPITAL PROJECT DEVELOPMENT 
Customer Service 
Meet expanded need for existing airport, 
seaport and real estate business lines                                                                                          CAPITAL DEVELOPMENT DRIVERS 
Community and Environmental Health 
Customer expectations 
Enhance environment or sustainability 
Economic Opportunity                                                                                               Changes in security needs 
Support business opportunities for the port and    TRENDS WE'RE ADDRESSING WITH CAPITAL PROJECTS                        Regional population and economic growth 
related industries 
Financial Stewardship and Asset Preservation        More people than ever travel by air 
Renew or replace outmoded or deteriorated        4.1 billion air passengers in 2017 
facilities                                                        Airfares, in real terms, averaged less than half what they
were in 1995. 
More than 20,000 cities are connected around the world. 
From IATA 2018 report                                                                                                                                                          2 
2

Where are our projects?                                   N 
Shilshole 
Bay 

Sea-Tac Projects                       Maritime Projects 
59 Projects                                 9 Projects 
$ 3 Billion                                  $ 159.7 Million                      Elliott Bay 

Downtown    Lake Union 
Seattle 

Economic Dev. Projects        Stormwater or Joint Venture       Technology Projects 
4 Projects                         4 Projects (Joint Venture)          12 Projects 
$ 50.9 Million               $72 Million                     $ 36.7 Million 

As of Q1 2019                                              Lake Washington                                          3

Capital Project Employment Benefits the Community 
Job Equivalents 
In 2018 = 700 
In Q1 2019 = 600 

Sales Tax on Construction 
In 2018 = $49 million 
In Q1 2019 = $12 million 


4

Projects: Improving the Customer Experience 
INTERNATIONAL ARRIVALS FACILITY 









Before                                                                                  After 

5

Projects: Improving the Customer Experience 
NORTH SATELLITE MODERNIZATION 









Before                                                                                  After 

6

Projects: Improving the Customer Experience 
CENTRAL TERMINAL RENOVATION 









Before                                                                                  After 

7

Major Projects Status 
INTERNATIONAL ARRIVALS FACILITY         NORTH SATELLITE MODERNIZATION              BAGGAGE OPTIMIZATION               TERMINAL 46 CRUISE TERMINAL 











8

International Arrivals Facility 




9

IAF Details                                   Project Overview 
Accomplishments:                                Budget Status         Schedule Status 
Flyover bridge steel erected 
POD B gates A9 & A10 operational 
Budget 
Pedestrian Walkway center span                            (millions) 
steel beginning erection                    $1,500
Upcoming Milestones:                                      $963 
$1,000
IAF Enclosure Complete (Q2)                                         $466 
$500
Pedestrian Walkway Move/Lift (Q3)          $0
Permanent Power Available (Q3)                           Budget  Actuals
Risks:                                                               Construction Schedule 
Customs & Border Patrol
requirements pending                   Construction Start Q1 2016             Planned Completion Q2 2020 
Trade worker availability 
2016             2017            2018             2019             2020 
10

North Satellite 




11

NSAT Details                             Project Overview 
Accomplishments:                             Budget Status        Schedule Status 
Phase 1A successfully opened on
schedule (5 gates) 
Opened west side restrooms in                         Budget 
expansion ahead of schedule                            (millions) 
$800                      $672 
Upcoming Milestones:                    $600
Phase 1B opening (remaining          $400                      $312 
portion of expansion, 4 gates)           $200
$0
Begin demolition of existing                             Budget  Actuals
building 
Risks:                                                          Construction Schedule 
Shortage of critical trade workers      Construction Start Q3 2012                Planned Completion Q3 2021 
Balancing turnovers between gate
needs & customer service 
12       13       14       15       16       17       18       19       20       21 

12

Baggage Optimization 




13

Baggage Details                          Project Overview 
Accomplishments                                         Budget Status          Schedule Status 
Structural steel on Central Terminal bump out
completed 
Conveyor Factory Acceptance Retest conducted                                Budget 
and successful                                                                      (millions) 
Phase 2 permit submitted to building department        600
Upcoming Milestones                                                $445 
400
Central Terminal bump out complete 
CBRA room complete                              200
$76 
Commission Authorization for Phase 2                   0
Construction (4/23/19)                                                                                                                                      Construction Schedule 
Phase 2 Advertisement (3rd Quarter)                                           Budget   Actuals
Risks 
Phase 1 Construction behind schedule affects
Phase 2 schedule                                                        Construction Schedule 
Baggage Handling/Steel Market Conditions for
Phase 2 Bid                                              Construction Start Q2 2013                   Planned Completion Q2 2025 
Replacement of damaged EDS machines critical to
overall schedule impact                                                                                                        Construction Start    Substantial Completion     Planned Completion 
13     14     15     16     17     18     19     20     21     22     23     24     25                 Q2 2013                     Q4 2025                       Q4 2025 

14

Terminal 46 Cruise Terminal 




15

Cruise Terminal Details                      Project Overview 
Accomplishments:                         Budget Status        Schedule Status 
Design and Consultant                             Budget 
(in millions) 
support funds received on 3/26                    Port Private Partner
Upcoming Milestones: 
Begin design work in Q2                     $100 
Continue process to select an                $100 
investment partner                         Budget                Actuals * 
*Minimal Actuals $42,000 
Risks:                                                        Draft Schedule 
Aggressive schedule 
2019                 2020                2021                 2022 


16 




2019                 2020                2021                 2022

Budget Variances on Projects in Implementation/Construction Phase 
Budget Status of Projects Under Construction                      New Variance 
40
1                                                                                ADR Kiosk Expansion 
35                5                                                            Reason: Concourse A Kiosk Location changed 
30                                                                            Impact: Project team was evaluating impact at
end of Q1. No impact to budget has now been
25                                                                            determined 
20                                                                            $ budget:  0 
15                32                                                           % of total project budget: 0 
Previously Reported Variances: 
10                                               0 
0                                    Wi-Fi Enhancement Project: Variance of $74K; 
5                                                                         % of total budget is <1% 
8                                    Baggage Optimization: Variance of $40-$80M; 
0                                                                         % of total budget is 9-18% 
CDD                       ICT                    Central Terminal Infrastructure: Variance of $2.5M; 
% of total budget is 15% 
On/Under     Previously Reported Variance     New Variance                Passenger Loading Bridge Phase 2: Variance of $2M; 
% of total budget is 20% 
Delta In-flight Services: Variance of $90K; 
% of total budget is 8% 
17

Q1 New Schedule Variances 
0 Major Variances       3 Minor Variances 
0                              1.  Mechanical Energy Conservation 
Reason: Contractor resource availability delayed the start of the project 
Impact: Delayed Energy Savings. Project team is working with the contractor to
recover schedule. 
2.  Pond Bird Deterrent Improvements 
Reason: Added scope due to damage sustained during February 2019 Storm 
Impact: Priority for 2019 are the damaged ponds. Project team is working with the
contractor to recover the approximately one month delay. 
3.  ADR Kiosk Expansion 
Reason: Concourse A Kiosk Location changed 
Impact: Identification of a new location has delayed the project approximately one
year 


18

Q1 New Schedule Variances - ICT 
0 Major Variances     2 Minor Variances 
0                            1.  Rental Car Facility Bus Tracking System 
Reason: Software Deployed; Signage installation delayed due to design changes 
Impact: Three month delay 
2.  Supplier Outreach and Procurement System 
Reason: Information & Communication Technology resource constraints 
Impact: Four month delay 




19

Q1 Completed Projects - Aviation 



STRUCTURAL RESILIENCY                         SECURITY 
North Satellite Modernization Phase 1A                  Terminal Security Enhancement Phase 1 
South Satellite Structural Steel                              Automatic Screening Lanes Check Point 2 


20

Q1 Completed Projects 



SUSTAINABILITY                                            RENEWAL 
Pier 69 Solar Panel Roof Array                                      Pier 69 Commission Chambers 

21

Q2 Focus Projects 



West Side Fire Station                Central Terminal Infrastructure 

22

Trends We Watch 
External Trends                          Internal Trends 
Tight labor market                    Changing scope 
Materials cost                         Staff capacity 
Tariffs                                     Aggressive schedules 
Value engineering 
Technical and
Regulatory Challenges                 Interdepartmental
coordination 
Weather                         Existing building
conditions 
23

Looking Ahead: Anticipated CD Commission Actions 
Q2 2019 
Accessibility and Safety Enhancements 
Westside Fire Station 
Employee Security Screening Phase 2 
Employee Services Center 
Bell Harbor International Conference Center Construction funds 
East Marginal Way Grade Separation property conveyance/easements to City of Seattle 
Maritime Innovation Center Design 
Electrical Utility SCADA 
Cargo 4 (BT Properties) building 420E 
Surface Area Management System 
Crowd Sourced Incident Reporting Mobile Application 
Customer Relationship Management System 

Action Items Subject to Change 
24

Questions?

Looking Ahead: Anticipated CD Commission Actions 
Q3 2019                                       Q4 2019 (TENTATIVE) 
Harbor Mooring Dolphins Design                                                 T117 Restoration 
P66 Shore power Design                                                            Main Terminal Space Conversions 
T91 Berths 6 & 8 Design                                                            Cruise Terminal P3 approval and Design 
Emergency Generator Control                                                      Water Hammer Attenuation 
CTE Curtain Wall Setback                                                           Parking Garage Boiler Replacement 
Checkpoint Smart LED Lighting                                                     Fire Suppression at Comm Rooms 
Central Terminal Infrastructure                                                     Utility Meter Networking 
RCF Camera Replacement                                                          Compactor Capacity 
Concourse C new Power Center                                                    Departure Drive Drainage Improvement 
Building Controls Upgrade                                                          2020 Airfield Pavement Replacement 
AOB Capacity Upgrades                                                             Variable Frequency Drive 
Remote Aircraft Deicing                                                             Surface Area Management 
Central Terminal Solid Waste Improvements                                     Air Cargo 4 Maintenance Upgrade 
Garage Elevator Shafts & Vestibules                                               EGSE Charging Stations Phase 2 
Concourse A, D, SSAT Seating Replacement                                       Lost and Found 
Phone System Upgrade                                                             North Employee Parking Lot 
Airport Common Use System Maintenance Renewal                            Parking Garage/Conc B/C Low Voltage Upgrade 
Fire Pump Replacement 
Baggage Claim Refresh 
Airport Wide & RCF LED Lighting 
POS Office WiFi Upgrade 
Action Items Subject to Change 
26

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.