6h Building Controls Upgrade Presentation

Item No. 6h_supp
Meeting Date: December 10, 2019
Building Controls Upgrade
CIP# C800944
Tyler Salisbury
AV PMG - Infrastructure

Project Scope and Location
Replace obsolete control panels (Approx. 100)
Renewal and Replacement
Expand the fiber backbone with required network equipment
Concourse A completed 2015



2

Building Controls Background
HVAC Systems
Safety interlocks in
tenant/restaurant kitchens
Metering of usage for domestic
water, natural gas, and other
utilities


3

Replacing Control Panels

Room for Future
Expansion




Control Processor
Existing                                                                         New

4

Schedule
Advertise for Design                     1st Quarter 2020
Award Design                       3nd Quarter 2020
Design complete                      1st Quarter 2021
Construction Authorization              2st Quarter 2021
Construction start                       3nd Quarter 2021
Substantial completion                  3rd Quarter 2022

5

Risks
1.  Regulated Material Management (RMM)  Replacement and rebalancing of
the control panels may require some panels to be relocated to an area that
requires RMM abatement.
Mitigation: The design team will consult the Good Faith Surveys that are available
followed up with field investigations of the panel locations and potential fiber pathways.
2.  Existing As-builts and ongoing construction  The fiber pathways connecting
the control panels will need to be designed. The potential pathways will be
routed through existing infrastructure and potentially through ongoing
construction areas.
Mitigation: The design team will work with the latest existing drawings to conduct field
investigations. The team will need to coordinate with ongoing construction to validate
drawing existing and future pathways.
6

Risk
3. Commissioning  The replaced panels will require systems to
be shut down for a period of time to complete the tie in and
start up of the new panels.
Mitigation  These outages will be coordinated and scheduled to
minimize the impact to passengers and tenants.


7

Appendix
Building Control System Background
Alternatives



8

Building Control System Background
The mechanical controls system at STIA dates back to the 1990's
Monitors and Controls Mechanical Equipment
Heating, Ventilation, and Cooling (HVAC); chilled water, steam, hot water
and Pre-Conditioned Air (PC Air)
Equipment that is customer and tenant facing
Equipment in critical spaces: port and tenant data centers, electrical
rooms, C4 area
Integrated with fire alarms to perform smoke control operations
Safety interlocks in tenant/restaurant kitchens
Metering of usage for domestic water, natural gas, and other utilities
9

Alternative 1
Do not proceed with the renewal and replacement project.
Cost Estimate: $0
Pros
No Capital funding would be required at this time.
Cons
Panel failure will have a negative effect on the passenger and tenant experience at STIA.
Future projects will be limited on expansion capabilities until the panels and fiber network
are replaced.
Future projects will be required to change panels out adding time, complexity, and cost to
their scopes.
Replacing panels on a project by project basis will increase the unit cost of the panel
replacement.
The fiber network will not be extended into Concourse B, C, and D.
The issue of intermittent data loss will not be addressed.
This is not the recommended alternative.
10

Alternative 2
Replace the obsolete control panels only.
Cost Estimate: $6,500,000
Pros
Lower capital investment
Replaces obsolete equipment and failing control panels.
Cons
The existing copper backbone will limit the expansion capabilities of the
control panels and the ability to add additional panels for future expansion.
The issue of intermittent data loss will not be addressed.
The fiber network will not be extended into Concourse B, C and D.
This is not the recommended alternative.
11

Alternative 3
Replace the obsolete control panels and expand the fiber
backbone throughout concourse B, C, and D.
Cost Estimate: $10,000,000
Pros
Replace obsolete equipment and failing control panels.
Extends the fiber network into concourse B, C, and D.
Provides infrastructure for future build outs with greater data requirements
and the ability to add additional capacity with new panels.
Mitigates existing data capacity issues on the copper backbone
Cons
This is the highest capital investment.
This is the recommended alternative
12

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.