6i Rental Car Facility Camera Replacement Presentation

Item No. 6i_ supp
Meeting Date: December 10, 2019
Consolidated Rental Car Facility Camera
Replacement Project

December 10, 2019

Project Need
The camera system installed in the
Consolidated Rental Car Facility (CRCF)
has reached the end of its useful life.
The CRCF is chronically subject to theft
attempts.
Existing camera system provides poor
quality images.
Portions of the CRCF have no and/or
inadequate camera coverage.
Existing CCTV Footage Provides Limited Resolution


2

Project Definition & Planning
Scope of Work
1. Replace 24 existing and
install up to 32 additional
cameras
2. Camera locations are based
on feedback from key
stakeholders
3. Scope includes new
switches in
Communications Rooms
and related structural
improvements

New Cameras, Systems Infrastructure, and Structural Improvements

3

Project Costs
Replace 24 Existing Cameras,
Install up to 32 additional
Cameras
Cost Breakdown: $2,254,000
Planning & Design $720,000
Construction $1,534,000
Additional costs provide Comm &
Structural Improvements

Project Costs Cover up to 56 Cameras at the Rental Car Facility

4

Project Risk & Opportunity Assessment
1. Placement of cameras designed to cover
common and shared areas, not tenant
leaseholds.
2. A RCF Tenant Majority in Interest (MII)
review may impact project timeline
3. Project is being coordinated in parallel
with two other CRCF security-related
projects


Overall Risk to Project Timeline and Budget are Minor

5

Project Schedule
Project        2019           2020           2021
Capital Project Description         Project Sponsor
Manager
Consolidated Rental Car Facility Camera   AV Commercial    Richard   Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Replacement                         Management     Wright
Project Definition & Planning
Design Phase
Contractor Selection
Construction Phase
Cx & Activation
Design
Authorization       Construction
Authorization
New Camera In-
Use Date


6

Closing Summary
Strong need for security camera
upgrades at the CRCF
Project scope has been well
defined by key stakeholders
Necessary Communications and
structural upgrades supporting
the enhanced camera network are
included in project scope



7

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.