AGENDA MEMORANDUM                        Item No.          6p 
ACTION ITEM                            Date of Meeting     December 10, 2019 
DATE:     December 3, 2019 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Wendy Reiter, Director, Aviation Security 
Wayne Grotheer, Director, Aviation Project Management 
SUBJECT:  Vanderlande Contract Amendment, Automated Screening Lanes (CIP #C800920) 
Amount of contract amendment:       $445,000 
ACTION REQUESTED 
Request Commission authorization for the Executive Director to execute a contract amendment
with Vanderlande Industries Inc. in the amount of $445,000 for the Automated Screening Lanes
Project at Seattle-Tacoma International Airport. No additional project funding is requested. 
EXECUTIVE SUMMARY 
In 2017, the Port of Seattle Commission authorized this $17,000,000 project to increase security
effectiveness and efficiency and improve the passenger experience at the Airport by installing
Automated Screening Lanes (ASL) at three passenger security checkpoints and providing
equipment for a fourth. To meet a Transportation Security Administration (TSA) deadline, the
Port expedited the ASL equipment procurement and selected Vanderlande Industries Inc. in
September 2017. A contract in the amount of $8,715,000 (not including sales tax) was executed
for the purchase of 21 ASL lanes of equipment. 
The project has now proceeded through design, construction,  and installation at one
checkpoint and is continuing installation at the second checkpoint. Changes in contract scope
require an amendment to the Vanderlande contract in the amount of $445,000. While there is
no change in the overall project budget, this change will shift $445,000 of project budget from
capital to expense. 
JUSTIFICATION 
The Port is proposing the following change to the Vanderlande contract: 
To facilitate the installation of the new ASL equipment, existing third-party, TSA-owned security
equipment must be relocated, re-installed, and re-certified. The port excluded the movement
of this third-party equipment from the vendor contract because the equipment belonged to the
TSA and would be moved by the TSA. During design, TSA clarified that they were unable to

Template revised January 10, 2019.

COMMISSION AGENDA  Action Item No. __6p__                              Page 2 of 4 
Meeting Date: December 10, 2019 
complete the moves of their equipment and Vanderlande took on this effort as a part of their
work, not realizing the exclusion. This exclusion became apparent during the second checkpoint
installation. To complete the installation, Vanderlande undertook this additional work. This
proposed contract change in the amount of $445,000 will pay for the remaining work to move
third-party equipment at Checkpoints 2 and 3 and the International Arrivals Facility (IAF). 
Per the General Delegation of Authority, Section 4.2.3.8, Commission authorization is required
to execute a contract amendment greater than $300,000. 
Schedule 
Due to design challenges, electrical and data infrastructure construction contracting issues,
equipment damage, and most recently vendor equipment production issues, this project has
fallen behind schedule. The project has limited "windows" of time to complete equipment
installations and avoid peak travel periods. These issues have delayed the installation of the
remaining equipment until 2020, with an anticipated project completion of Q3 2020, which
includes the International Arrivals Facility (IAF) checkpoint installation. 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  Procure a separate entity to perform the remaining third-party equipment
moves and testing for the remainder of the project 
Cost Implications: $500,000 
Pros: 
(1)   The equipment move work would be competed among potential vendors. 
Cons: 
(1)   The pool of eligible vendors is limited by TSA contracting certification requirements. 
(2)   Internal costs to the project will increase for additional procurement and coordination
effort. 
(3)   Coordination during installation will be more difficult and risk of mis-communication
and change orders will increase. 
(4)   This will result in further schedule impacts to the project to acquire contract(s) with
different vendors. 
This is not the recommended alternative. 
Alternative 2  Complete the change order as requested 
Cost Implications: Increase to the contract of $445,000; there is no budget increase to the
project 
Pros: 
(1)   Less overall cost and performance risk to the project having Vanderlande supply thirdparty
equipment moves. 
(2)   Schedule will not be impacted by having to contract and coordinate separately with a
third-party equipment move vendor. 
Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. __6p__                              Page 3 of 4 
Meeting Date: December 10, 2019 
Cons: 
(1)   This work would not be competed as a separate procurement. 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
The budget for this project has not changed. 
Cost Estimate/Authorization Summary               Capital        Expense           Total 
COST ESTIMATE 
Original estimate                                $30,000,000               $0     $30,000,000 
Budget reduction/addition                    ($21,700,000)      $8,700,000   ($13,000,000) 
Previous Changes                               ($821,380)       $821,380 
Current change                                 ($445,000)       $445,000              $0 
Revised estimate                                $7,033,620      $9,966,380     $17,000,000 
AUTHORIZATION 
Previous authorizations                         $17,000,000               $0     $17,000,000 
Current request for authorization                         $0               $0               $0 
Total authorizations, including this request      $17,000,000               $0     $17,000,000 
Remaining amount to be authorized                    $0             $0             $0 
Annual Budget Status and Source of Funds 
The Automated Security Lane (CIP #C800920) was included in the 2020-2024 capital budget and 
plan of finance. The funding source for this project will be revenue bonds and airport
development fund. 
The ownership of the screening equipment will be transferred to the TSA. Accordingly, the cost
of the equipment and the costs of the equipment installation will be accounted for as public
expense. In the table above, the estimated cost of the screening equipment and installation are
indicated in the expense column. The cost of this expense has been included in the 2020
operating budget. 
Financial Analysis and Summary 
Project cost for analysis              $17,000,000 
Business Unit (BU)                  Terminal Building 
Effect on business performance     NOI after depreciation will increase due to inclusion of
(NOI after depreciation)             capital (and operating) costs in airline rate base. 
IRR/NPV (if relevant)                N/A 
CPE Impact                        $0.04 in 2020 

Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. __6p__                              Page 4 of 4 
Meeting Date: December 10, 2019 
Future Revenues and Expenses (Total cost of ownership) 
The ownership of the screening equipment will be assigned to the TSA, so the cost of the
equipment will be accounted for as public expense. 
ADDITIONAL BACKGROUND 
The Vanderlande contract has been amended four times: 
(1)   Amendment #1 for $188,000 addressed third-party equipment storage, and requests
from TSA end users for design changes to provide additional security enhancements,
including the purchase of additional secondary screening stations for the new ASL
lanes and additional screening resolution services to allow for remote screening. 
(2)   Amendment #2 for $252,000 addressed the completed third-party equipment moves
and was ratified at a staff level. 
(3)   Amendment  #3  for  $188,380  addressed  equipment  inspections  and  movement
required to respond to equipment damage resulting from a construction accident 
where a damaged fire sprinkler inundated two ASL lanes and required the equipment
to be replaced and was ratified at a staff level. 
(4)   Amendment #4 for $178,000 addressed purchase of an improved model for the IAF
security checkpoint. 
ATTACHMENTS TO THIS REQUEST 
None 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
January 22, 2019  The Commission authorized advertisement for bids and execution of a
major works contract. 
December 12, 2017  The Commission authorized construction and installation of lanes by
use of Port crews for construction efforts. 
July 25, 2017  The Commission authorized design, procurement of equipment and use of
Port crews. 






Template revised June 27, 2019 (Diversity in Contracting).

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.