ACEC Response Letter

TESTIMONY OF VAN COLLINS IN RELATION TO THE PORT OF SEATTLE'S
INTERNAL AUDITS GROUP'S OPERATIONAL AUDIT ON ARCHTECTURE AND
ENGINEERING RATES

December 9, 2019

[ an
=O   of  the American
The ACEC has long had a partnering
relationship with the Port. We try to work with the Port in a respectful manner and attempt
to seek solutions to issues of mutual concern. We have a standing liaison committee that
regularly meets for this purpose in the hope of building trust and confidence.




Good friends must be willing to call balls and strikes sometimes with regards to each other

and this is such a time. Although we tried to do this differently, we were rebuffed, so here

we are. Yet, we still believe that defending the relationship between the Port and industry

is worthwhile and that preventing what we see as the development of inevitable distrust

with the publishing of this report is worth any short-term conflict. We believe that we have

been left with no choice but to respectfully and in the strongest terms possible disagree

with the conclusions and inferences being offered today even though it is our sincerest
hope that our efforts are understood in constructive manner in which they are offered.
First,wehaveseriousconcernsoverthemethodologyused. These concerns are detailed
more fully in the document | have also delivered to you.In'short;theIAGreportistlawed
becausethe methodology leadstoanoverestimationotprofit;ittailstoaccountforreal

American Council of Engineering Companies of Washington
1621 114th Ave SE Ste 115
Bellevue, WA 98004
(425) 453-6655

;
niv
-   y                            out iat tu      J                              \
meaningoftheword.The IAG did not review any firm's accounting records and is not
providing evidence as to any firm's actual profit on Port projects. Instead;the'IAGused










Many people, including people well versed in public procurements, often confuse lowest
cost procurement with the procurement of architectural and engineering services.  Unlike

the selection of construction services, the procurement of architectural and engineering

services is unique and does not in any way include the selection of a lowest price bid from

a group of minimally responsible bidders.  Lowest price is never a consideration, ever,

and it is a most qualified proposer which is important.

ACEC Washington  believes  this  confusion  occurs  primarily  because  there  is  a
misunderstanding as to the rationale and policies underlying state law for architectural
and engineering procurements. The law reads quite simply provides number 1... that a

public owner must determine, as stated, a most qualified proposer and then number 2,
the owner must attempt to negotiate a contract at a fair and reasonable price with that

proposer.  While these are steps are seemingly simple, they nonetheless contain highly
nuanced policies that must also be well understood.

The Port's current processes and procedures, which were recommended by the Boston
Consulting Group, do not support state policies.  This is because the value of the law is
not in following a mechanical step by step, turn the crack process, which tries to eliminate

human judgment, and which treats the work of one employee as fungible with another.

This is a lowest cost mentality at work. Thecentralpolicyunderlyingtheprocurementot



The Boston Consulting Group's processes and procedures implemented by the Port are
anything but.  They call for the negotiation of the fee of every employee of every prime
consultant and subconsultant on each project. At the same time, the Port looks solely to

its computer model as to what is allegedly a fair and reasonable rate for each employee.

No other public owner does this.  The Port is the outlier.  The Port also ignores any
contrary input from firms, even when the Port is provided with actual accounting data.
The  consultant's  accounting  documentation  is  deemed  irrelevant  and  facially

"unreasonable." The Port also removes from the negotiation process the involvement of

any Port project staff, i.e those who actually know something about the project's needs,
risks, and unique demands and with who the consultants will ultimately have to team with
going forward.

The cumulative result is that the Port's procurement and negotiation of architectural and
engineering services are lengthy, frustrating, focused solely on price, and often strongly
adversarial.  In this environment, distrust blossoms.

But, is this what state law really envisions or what leads to successful projects?  The
answer is a resounding, no. As stated above, state law first requires the selection of the

most qualified  proposer on a procurement.   Not any proposer.   The most qualified

proposer. While the Port performs this step well, it is not clear that the Port appreciates

why this selection matters.  It is because the most qualified proposer is the most likely to
offer solutions to problems in the most cost effective and beneficial manner. This is where

real project savings can be achieved, and it is this partnering and collegial environment

that the Port should be protect. Yet, it unfortunately does not seem to recognize this since

it takes more than just hiring a most qualified proposer to establish trust, collaboration

and creativity.

It takes real effort and awareness that begins at the very first involvement.    It is not

sufficient to start once the contract is signed. It is at the very beginning of the procurement

and negotiation process where a public owner has the first opportunity to either benefit

its project or to hinder it.   It is in the good faith process of give and take - you give a little

bit, you get a little bit where state law envisions the public interest being fulfilled through
the honing  process of negotiating a contract at a fair and reasonable price.   It is
unquestionable that the focus of state law is on the project holistically rather than just the
alleged profit of each employee.

Done well, the relationship flourishes and projects are benefitted.   Done poorly, the
relationship flounders and projects are harmed.

Lastly, even though we strongly disagree with the IAG's measurement and outcomes, the
audit report before you ostensibly still relates to an examination of profit.  So, why is profit

so important and what is its role in the success of Port projects? The federal government
offers this regulatory direction to its procurement officers:

It is in the Government's interest to offer contractors opportunities for financial

rewards sufficient to stimulate efficient contract performance, attract the best
capabilities  of  qualified  large  and  small  business  concerns  to  Government
contracts, and maintain a viable industrial base.

Negotiations aimed merely at reducing prices by reducing profit, without proper
recognition  of the  function  of  profit,  are  not  in  the  Government's  interest.
Negotiation of extremely low profits, use of historical averages, or automatic
application of predetermined percentages to total estimated costs do not provide
proper motivation for optimum contract performance.

eres When ACEC Washingtonffirst learned of the resent
review, we listened to a conversation regarding profit that occurred during the Port's
September Audit  Committee  meeting.   It was  from  this  conversation  that ACEC
Washington first became concerned about what was being said and the validity of the
pending review. This is because we were also aware of the very large anecdotal history
of concerns voiced over the past number of years by ACEC members as to how difficult

the Port is to contract with and how hard it is to make a profit.
Toattempttobetterunderstandandquality theACECWashington membership"views
aboutthePort'sprocurementprocesses andprocedures,asurveywassentoutto.each
ACECWashington'member.  That survey asked a series of questions about each
member's level of satisfaction. The full survey report, including specific comments made
by various ACEC members, is included as Exhibit "C" in the document provided to you.

\6
\



December 9, 2019

Commissioner Peter Steinbrueck                             HAND DELIVERED
Chair
Port of Seattle Audit Committee
Port of Seattle
PO Box 1209
Seattle, WA 98111

RE:   Consulting Engineering Industry Comments and Concerns with Port's Operational
Audit of Architectural and Engineering Rates

The American Council of Engineering Companies of Washington (ACEC Washington) is
concerned with the audit report offered today by the Port's Internal Audit Group (IAG).
We strongly disagree with its conclusions and inferences and detail our comments and
concerns in the attached "Comments on IAG Operational Audit of Architectural and
Engineering Consultant Rates."

ACEC Washington is a trade organization that represents more than 150 members in
Washington State involved in the consulting engineering industry.   Our membership
encompasses firms from large to small and those that perform a majority of their services
as subconsultants and  as prime consultants.   Our members employ over 7,500
professionals across the state.
These members also represent some of the best engineering talent in the country.  In
fact, firms from Washington have won the ACEC National "Grand Conceptor" award,
which is for the single best engineering project of the year, a total of nine times.  This is
more than any other state in the country, including New York and California.

Numerous ACEC Washington members also perform services for the Port and have
substantial experience with the Port's procurement and contracting procedures.  They
have provided services of all types and at all levels.  They have been involved in types
and levels, including engineering services procurements.  It is unquestionable that the
Port relies heavily upon these members for the success of critical Port projects.




American Council of Engineering Companies of Washington
1621 114th Ave SE Ste 115
Bellevue, WA 98004
(425) 453-6655

Lastly, ACEC and the Port have been engaged in a liaison relationship for many years
with the purpose of working collaboratively on mutual issues of concern and it is in that
spirit that we offer our comments and concerns.
Sincerely,


Van A. Collins
President/CEO

Cc   Commissioner Ryan Calkins, Secretary
Public Member Christina Gehrke
Executive Director Stephen Metruck
Chief Operating Officer David Soike
Director Glenn Fernandes

COMMENTS ON IAG OPERATIONAL AUDIT OF
ARCHITECTURE AND ENGINEERING RATES

STATE LAW BACKGROUND
Before exploring ACEC Washington's concerns with the IAG audit report, it is warranted
to  detail  the  legal  foundation  underpinning  the  procurement  of  architectural  and
engineering services in Washington.
Under Washington law, Chapter 39.80 RCW, a public owner must determine the most
qualified proposer on a project and then attempt to negotiate a contract at a fair and
reasonable price with that most qualified proposer.

It is ACEC Washington's experience that this law is very different than many people,
including government procurement officers, often think of with regards to government
procurements. The unique feature of this law is it does not include a lowest price selection
from a large group of minimally "responsible" bidders (as is the case under Chapter 39.04
RCW for the procurement and selection of construction services).  The rationale and
policies between the two statutes could also not be any more different. These important
differences are outlined in more detail in Exhibit "A" attached hereto.

In short, a person examining architectural and engineering rates must appreciate that the
procurement of architectural and engineering  services requires an entirely different
mindset to understand both its requirements and its underlying nuances.
FAILURE TO EXAMINE CRITICAL ROLE OF FAIR AND
REASONABLE PROFIT
It is self-evident that to be able to negotiate a fair and reasonable price one must also
have an understanding of the numerous factors that go into a most qualified firm's
revenue and costs.  In short, one must understand a firm's business model to be able to
evaluate the question of what constitutes fair and reasonable profit.

This is something that the Federal Government expressly provides for in statutory
guidance to contracting officers under an analogous federal procurement statute.  The
full language of this instructive guidance is attached hereto as Exhibit "B."
Notably, this federal regulation recognizes the difference between an "idealized" initial
profit and what is realized as a final "actual" profit.  "Just as actual costs may vary from
estimated costs, the contractor's actual realized profit or fee may vary from negotiated
profit or fee, because ofsuch factors as efficiency ofperformance, incurrence of costs the
Government does not recognize as allowable, and the contract type."

This regulation further examines the critical role that is performed by a firm's actual
realized profit to the governmental interest.  "/t is in the Government's interest to offer

contractors opportunities for financial rewards sufficient to stimulate efficient contract
performance, attract the best capabilities of qualified large and small business concerns
to Government contracts, and maintain a viable industrial base."
Lastly, the regulation touches upon the importance of good faith negotiations to a fair and
reasonable profit.   "Negotiations aimed merely at reducing prices by reducing profit,
without proper recognition of the function ofprofit, are not in the Government's interest."

The IAG's audit review fails to take any of these important policies into account.
FAILURES OF THE IAG METHODOLOGY
IAG Has Not Conducted an Audit and Provides No Validation as to the
Accuracy of its Modeled Data
The IAG conducted what has been termed an audit, but this is inaccurate given the limited
review undertaken.  The engineering firms involved were asked for the W-2s and pay
stubs for employees utilized on the Port's projects and for each of the firm's audited
overhead rates. The IAG already had in its possession each firm's pay requests.

From this limited information, the IAG used a simplistic computer model to estimate what
it calls "profit."  In its nomenclature, it is the profit earned by each professional from every
prime and subconsultant on the reviewed projects.  There is no statistical analysis nor
any data provided that indicates the accuracy of the IAG's model versus the accuracy
that would be afforded through a traditional audit.

This means that the report is potentially misleading and could provide readers with a false
belief  that  the  IAG's  estimations  have  been  validated  and  can  be  relied  upon.
Furthermore, it is through the use of this unvalidated data that the IAG uses to make
conclusions and inferences as to whether the Port's processes and procedures result in
the award of fair and reasonable profit.  This lack of validation makes this improper.

Could a more robust process have been undertaken to validate the IAG's report? Yes,
but the IAG did not take the step to conduct a traditional audit of any of the reviewed firm's
accounting records.  Accordingly, there was no proper determination of whether each
firm's accounting for revenues and costs for each project was proper under Generally
Accepted Accounting Principles (GAAP) and there is no comparison against which to test
its model. Without this step, the IAG is incapable of truly knowing the profitability of each
firm on the projects in question.

IAG Makes Improper Conclusions and Inferences Because It Only
Estimates Employee Level "Profit" Rather Than Firm Level

However, even if one assumes that the AG's information and estimations were correct
and valid, its conclusions and inferences are still improper and unsubstantiated because
the  IAG  does  not determine each firm's "actual"  profit per project.   Without this
information, how can the IAG make conclusions and inferences as to whether the Port's
processes and procedures result in overpayment?

This is because the IAG's model only estimated the alleged profit earned by each
employee and fails to include any evaluation of the sum total number of hours billed within
each profit band or any alternative evaluation of whether a fair and reasonable profit had
been paid to the firm's in question.

Instead, the IAG provides only employee level profit information in the following chart:
Profit              10%      11-19%      20-29%      30-39%      40-49%       Above
and                                                50%
below

Number of         139       81         72         60         30         18
Consultants

However, this presentation fails to demonstrate anything meaningful because it is, again,
firm level profit on a project that is determinative under state law.

The importance of this distinction can be explained by using a simple hypothetical.
Assume 100 hours are billed on a project at 9% individual profit (under the profit limitation
that the IAG states is Port guidelines) and two hours are billed at 50% profit.   The
combined "idealized" profit for this firm would be 9.8% (before accounting for any non-
reimbursed costs and a determination of the firm's "actual" realized profit on the project).
So, even though some individual rates might be well above Port guidelines, a firm's profit
on a project can still be within Port guidelines.  Extending the hypothetical even more, it
is even possible that, after accounting for all non-reimbursable costs, the firm's profit on
this project could be reduced to near zero or even become negative.

This means that it is the combination of all billed rates and the subtraction of all proper
non-reimbursed expenses (per Generally Accepted Accounting Principles) that is relevant
to the discussion of fair and reasonable profit of a firm on a project.  This can only be
determined through a formal audit and also means that reliance upon the IAG's presented
employee level profit numbers, even if assumed correctly estimated, is unjustified and
can be misleading.

The IAG further fails to provide any consideration that a person might actually be worth
50% profit.  Instead, the IAG holds that any individual profit rate that is over guidelines, is
impermissible.   However,  what  if there  are  but a  handful  of people with  certain
backgrounds, knowledge and experience who can uniquely perform a certain scope of
services.    Under those  circumstances,  the  market  rate  for  these  individuals  will
undoubtedly rise above the Port's 10% guideline. Yet, the Port might very much need the
skillsets offered by these individuals.  So, is it really to the Port's benefit to arbitrarily
provide limits on individual rates? We believe it is not and the determination of a person's
fair and reasonable rate is determined globally by the marketplace.

1 The chart provides one of the variables as ostensibly the "Number of Consultants."  However, this is not
accurate.  The actual variable being presented is the total number of employees who fit within each profit
band for all consulting firms and all reviewed projects.

At the same time, it should not be forgotten that firms are not free to just use employees
with the highest profit levels on projects because the firm is limited by the guaranteed
maximum price in the contract. A firm will instead perform the scope of work for which it
contracts by using the mix of forces that it believes will be the most efficient and cost
effective.  Such usage will minimize the firm's financial risk that it will run up against the
cap.

IAG Improperly Uses Safe Harbor Overhead Rate

The IAG states that it also utilized the WDOT Safe Harbor Overhead Rate for firms for
which it did not have an overhead rate. The current WSDOT Safe Harbor Overhead Rate
is 110%.  Yet, per the most recent national Deltek Clarity Architectural and Engineering
Industry Survey in 2018, the median overhead rate was 160% and the top quartile was
183%. Notably, this survey is readily available online for public and general use.

In addition, the IAG fails to disclose that the WSDOT "Safe Harbor Overhead Rate" is
designed for use by discrete type of firm.  From the WSDOT website:
WSDOT is one of the ten state [agencies] selected to participate in the "Safe
Harbor" indirect cost rate (ICR) pilot program. FHWA developed the Safe
Harbor Program to help remove potential financial barriers that may
otherwise prevent or inhibit new, small, and disadvantaged architectural
and engineering (A/E) consulting firms from entering the Federal-aid
Highway Program (FAHP) funded State Administered engineering services
market.

This leads to an obvious question.  Were the firms to which the IAG applied the Safe
Harbor Rate new, small or disadvantaged firms? If not, then the use of such an incredibly
low overhead rate will artificially inflate the calculation of profit for a firm when one is
examining the fully burdened rate method of payment that is utilized by the Port.
IAG Fails to Account for Loss of Profit Because of Subconsultant
Utilization

The IAG also fails to account for the fact that the use of subconsultants necessarily
reduces the profitability of a prime consultant or an upper tier subconsultant.  This is
because the hours that a firm would normally bill on a contract (and for which it would
otherwise earn a profit) are no longer available to be billed by that firm. These hours are
now being performed by a subconsultant.

IAG Fails to Account for Unbillable Costs

The IAG's methodology also neglects any evaluation of non-reimbursed costs that are
not part of a firm's audited overhead rate.  There are numerous examples of such costs
that reduce firms' profitability, including but not limited to:

eo   Unreimbursed  costs  associated  with  the  risk and  administration  of  using
subconsultants

e   Losses related to unreimbursed inflation

e   Unreimbursed direct costs

e   Project overruns or rework

oe   Marketing expenses

IAG Improperly Uses Information From Other Contracting Types to
Evaluate The Port's System

As discussed previously, the Port utilizes "fully burdened rates" in its procurements rather
than the "cost plus fixed fee" system utilized by the WSDOT.  WSDOT's method is
required  by the Federal Highway Administration through application of the Federal
Acquisition Rules (i.e. FARSs)).
The FARs are essentially a proxy and present a uniform, detailed, and validated system
for the determination and payment of fair and reasonable compensation. However, taking
one piece from that unique system out of context (i.e. audited overhead rates) and
applying it within the IAG's computer model in an effort to review the Port's system of fully
burdened rates is improper.

It is an apples to oranges comparison.  The approaches involved are entirely different.
Firms approach any negotiation of rates differently depending on the owner involved, the
contract type and the method of payment. Different strategies are necessarily employed
to ensure overall profitability.  Firms often also use different employees on projects using
these two different payment structures.

Given this, if one uses audited overhead rates in an analysis, which is an integral and
important component of the FAR system, one must also use the entirety of the FAR
system.  What are allowable fees, costs and, thus, profit are integrally bound together
within this system and must also be considered to even be minimally accurate and fair.
In for a penny, in for a pound, as it were.

IAG Improperly Uses WSDOT Allowable Profit Figure

The IAG references the amount of profit allowed by the WSDOT.
"Industry sources indicate you must consider a firm's overhead rate before
you can determine the profit markup you are paying. Consistent with this
standard, most state transportation departments typically pay a 10 percent
to 12 percent consultant markup on labor and overhead." The report also
references a maximum rate used by the Federal Highway Administration of
15 percent.

However, this profit is, again, at the firm level rather than the individual employee level
that is analyzed by the IAG and, as has been discussed previously, the level of individual
employee level profit can have little relevance to a firm's profit. The use of this firm level
information is, therefore, improper and irrelevant.

REALITY - ACEC MEMBER SURVEY
In mid-September, ACEC Washington learned of the activities of the IAG in relation to
reviewing certain engineering procurements.  It was at this time that ACEC Washington
also listened to the audiotapes of the September meeting of the Port's Audit Committee
where it was clearly  intimated that the  Port might well  believe  it is  overpaying  for
architectural and engineering services.  In fact, there was a discussion about how much
the Port could potentially save on the procurement of these services.

At the same time, ACEC Washington was aware of a long anecdotal history of members
commenting on how difficult the Port is to contract with and how hard it is to make a profit
on Port projects.

This presented a clear and obvious disconnect and, so it was decided to conduct a survey
of the ACEC membership to better characterize the membership's position on Port
procurements. The results of this survey are attached hereto as Exhibit "C."
The survey confirms the existence of a large disconnect between any assertion that the
Port systemically overpays engineering firms on its projects and what actually occurs in
reality.   For example, almost 70% of the respondents disagreed with the statement that
"[tlhe  Port  of  Seattle  is  fair and  reasonable when  it comes  to  negotiating  price."
Continuing this same sentiment, over 72% of the respondents disagreed with the
statement that "[tlhe Port of Seattle understands my firm's business model and what
determines its ultimate profitability on a project."

The large disconnect presented is patently obvious and leads inexorably to one question
how valid is the IAG's current model and how accurate is the Port's model used for the
calculation of fair and reasonable rates?
CONCLUSION
It is ACEC Washington's position that the Port is not overpaying for architectural and
engineering services and that the IAG report is fundamentally flawed. We further believe
that, given the difficulty expressed concerning negotiating and contracting with the Port
and given its poor payment history, the Port is no longer an "owner of first choice" for a
large portion of the ACEC Washington membership.
We believe that the Port's posture is detrimental to its own interest and only serves to
engender distrust on future projects.  Regardless of the contract type or methodology
used, the most important consideration for any public owner should be whether the firms
with which it is contracting are making a fair and reasonable "actual" profit on each project.
The amount of profit earned by and through each employee is in of itself not relevant.

In closing, ACEC Washington does not dispute the Port's interest in the present subject
matter nor its ability to  investigate  Port projects.   It is ACEC Washington's concern,
however, that the Port needs to have a clear understanding of state law policies and an
engineering firm's business model to effectively and fairly negotiate on its projects.

EXHIBIT "A"

IMPORTANT CONSIDERATIONS RELATED TO A/E
PROCUREMENTS

First and foremost, it must be remembered that Chapter 39.80 RCW is not in
law for the benefit of architectural and engineering firms.  These policies and
procedures are in Washington law because it is in the public interest and for
the public benefit.

It is in the public interest and for the public benefit that the law requires public
owners to select the "most qualified" firm and it is with this firm that the owner
negotiates.  Inherent in this process is the fact that a fair and reasonable price
is not a lowest or fixed cost. The price is relative to both the project and to the
most qualified firm.  For example, it might be proper to pay one most qualified
firm more because of its history of success, the experience and knowledge of
its team, etc.  Similarly, a project's risks, complexity, duration, and uniqueness
all impact price.

A contract "at a fair and reasonable price" refers to the overall amount paid on
the contract, not to the amount paid to each employee.

It is in the public interest and for the public benefit that state law recognizes the
importance of a public owner negotiating with the most qualified firm a contract
at a fair and reasonable price.  This necessarily means that it is in the public
interest and for the public benefit to undertake a give and take process where
the two parties work in good faith and collaboratively towards a mutually
beneficial result.  It is not state law to obtain the lowest price.

Focusing on lowest price is detrimental to the public interest and  leads to
distrust and adversarial relationships.

It is in the public interest and for the public benefit that state law requires public
owners to negotiate a contract, not just a fair and reasonable price.  There are
three basic elements to an engineering contract. These are the scope of work,
the terms and conditions, and the price for the services needed to perform the
scope of work.  All three elements of a contract are important factors in the
success of the negotiation and the project.

EXHIBIT "B"

CRUCIAL ROLE OF PROFIT TO SUCCESS OF PUBLIC
OWNERS GOALS

In 48 C.F.R. 15.404-4, which is titled "Profit", contracting officers are instructed to
negotiate architectural and engineering contracts with the following thoughts in mind
regarding profit (note  the blue text insertions are additions made by ACEC Washington's
to provide commentary and context as to the significance of the section following
immediately following thereafter):
(a) General. This subsection prescribes policies for establishing the profit or fee
portion of the Government prenegotiation objective in price negotiations based on
cost analysis.
Recognition of Idealized vs. Actual Profit
(1) Profit or fee prenegotiation objectives do not necessarily represent net
income to contractors. Rather, they represent that element of the potential total
remuneration that contractors may receive for contract performance over and
above allowable costs. This potential remuneration element and the Government's
estimate of allowable costs to be incurred in contract performance together equal
the Government's total prenegotiation objective. Just as actual costs may vary
from estimated costs, the contractor's actual realized profit or fee may vary
from negotiated profit or fee, because of such factors as efficiency of
performance, incurrence of costs the Government does not recognize as
allowable, and the contract type.
"Owner of First Choice"  Recognition of Value ofAttracting Highly
Qualified Firms
(2) It is in the Government's interest to offer contractors opportunities for
financial  rewards sufficient to stimulate efficient contract performance,
attract the best capabilities of qualified large and small business concerns
to Government contracts, and maintain a viable industrial base.
Recognition of Negative Effect on Projects if Goal is to Unduly Reduce
Profit
(3) Both the Government and contractors should be concerned with profit as a
motivator of efficient and effective contract performance.  Negotiations aimed
merely at reducing prices by reducing profit, without proper recognition of
the function of profit, are not in the Government's interest. Negotiation of
extremely low profits, use of historical averages, or automatic application of
predetermined  percentages to total  estimated  costs do  not provide  proper
motivation for optimum contract performance.



B-1

EXHIBIT "C"

RESULTS FROM ACEC MEMBERSHIP SURVEY REGARDING
PORT OF SEATTLE PROCUREMENTS

Explain your firm's historical involvement with        #           %
the Port of Seattle procurement of professional | Selected | Selected
services
My Firm is Currently or Recently Working for Port &
Would Like to Continue                                 23        44.2%.
My Firm is Currently or Recently Working for Port &
Does Not Desire to Continue                             1          1.9%.
My Firm is Currently or Recently Working for Port &
Are Unsure About Continuing                           13        25.0%.
My Firm Used to Perform and Would Like to Pursue
1           1.9%-                                                                                 Future Work

My Firm Used to Perform but Will Not Pursue
1           1.9%,                                                                                 Future Work

My Firm Has Not Performed, but Would Like to
10        19.2%a
Pursue Future Work
My Firm Has Not Performed Work for the Port and
3         5.8%el
Will Not Pursue Future Work.
Totals                                                     52        100.0%

Describe the role in which your firm has a
d   Ayted
performed work for the Port of Seattle
Fairly Equally as Sub and Prime                         11        28.2%
Primarily as a Prime                                      14        35.9%
Primarily as a Sub                                        14        35.9%
Totals                                                     39        100.0%

The Port of Seattle is fair and reasonable when it               Sel 5.08d     iesd |  Subtotals
comes to negotiating price.
Strongly agree                                                      1          2.6%
Substantially agree                                                    5         12.8%       23.1%
Slightly agree                                                           3          7.7%
Neither agree nor disagree                                           3         7.7%         7.7%
Slightly disagree                                                        6          15.4%
Substantially disagree                                                14        35.9%       69.2%
Strongly disagree                                                    7         17.9%
Average Score                                    -10.00


C-1

EXHIBIT "C"

The Port of Seattle understands myfirm's                    #          %       Subtotals
business model and what determines its                 Selected| Selected
ultimate profitability on a project.
Strongly agree                                                      1         2.6%
Substantially agree                                                   4         10.3%       12.8%
Slightly agree                                                           0          0.0%
Neither agree nor disagree                                           6         15.4%       15.4%
Slightly disagree                                                         3          7.7%
Substantially disagree                                                 18        46.2%        72.3%
Strongly disagree                                                    7         18.4%
Average Score                                    -13.95

i
Subtotals
Th              iatfal                 e Port of Seattle is fair and reasonable when iti            Selected| Selected
comes to negotiating allocation of risk.
Strongly agree                                                      0         0.0%
Substantially agree                                                    3          7.7%        12.8%
Slightly agree                                                           2          5.1%
Neither agree nor disagree                                           11        28.2%       28.2%
Slightly disagree                                                        12         30.8%
Substantially disagree                                                 4         10.3%       59.0%
Strongly disagree                                                    7         17.9%
Average Score                                    -8.46

The Port ofSeattle's procurement of                      #          %      Subtotals
professional services are organized and well                Selected | Selected
thought out.
Strongly agree                                                      3         7.7%
Substantially agree                                                    2          5.1%        20.5%
Slightly agree                                                           3          7.7%
Neither agree nor disagree                                           9         23.1%       23.1%
Slightly disagree                                                        10         25.6%
Substantially disagree                                                 9         23.1%       56.4%
Strongly disagree                                                    3         7.7%
Average Score                                    -5.38



The Port of Seattle's procurementof                      #          %
Subtotals
professional services are efficient and time                 Selected| Selected
effective.


C-2

EXHIBIT "C"

Strongly agree                                                      2         5.1%
Substantially agree                                                    2          5.1%        12.8%
Slightly agree                                                            1          2.6%
Neither agree nor disagree                                            3         7.7%        7.7%
Slightly disagree                                                         8         20.5%
Substantially disagree                                                 15         38.5%       79.5%
Strongly disagree                                                    8         20.5%
Average Score                                    -13.08
AE hot ofSeattle'sDee    et of                      4          %
a    iiiSUP
Selected| Salactaa|
projects.
Strongly agree                                                      3         7.7%
Substantially agree                                                    2          5.1%        28.2%
Slightly agree                                                            6          15.4%
Neither agree nor disagree                                           3         7.7%        7.7%
Slightly disagree                                                         7          17.9%
Substantially disagree                                                 13        33.3%       64.1%
Strongly disagree                                                    5         12.8%
Average Score                                     -7.63
|      2      |      0
The Port of Seattle exhibits a clear desire to be a                                      |  Subtotals
Selected')    Selected
"preferred client" of my firm.
Strongly agree                                                       3         7.7%
Substantially agree                                                    1          2.6%        15.4%
Slightly agree                                                            2          5.1%
Neither agree nor disagree                                           8         20.5%       20.5%
Slightly disagree                                                         5          12.8%
Substantially disagree                                                 10         25.6%       64.1%
Strongly disagree                                                    10        25.6%
Average Score                                    -10.77

TRSh Ta      2   %
that helps promote collaboration and oroatinie               Selected || Selec | Sublotals
Strongly agree                                                      2         51%
Substantially agree                                                    4         10.3%       23.1%
Slightly agree                                                            3          7.7%
Neither agree nor disagree                                           7         17.9%       17.9%


C-3

EXHIBIT "C"

Slightly disagree                                                        13         33.3%
Substantially disagree                                                  7         17.9%        59.0%
Strongly disagree                                                    3         7.7%
Average Score                                     -4.87

The Port of Seattle's procurement of
professional services ison par with the                      #          %
!                                               Subtotals
procurements of these services by other public              Selected| Selected
owners of a similar size and level of
sophistication.
Strongly agree                                                      2         5.1%
Substantially agree                                                    2          5.1%        20.5%
Slightly agree                                                           4         10.3%
Neither agree nor disagree                                           6         15.4%        15.4%
Slightly disagree                                                         4         10.3%
Substantially disagree                                                 13        33.3%       64.1%
Strongly disagree                                                    8         20.5%
Average Score                                    -10.26

The Port of Seattle's procurement staff are    |           | Sed |       ad |  Subtotals
professional and courteous.
Strongly agree                                                      4         10.3%
Substantially agree                                                    10        25.6%        48.7%
Slightly agree                                                           5         12.8%
Neither agree nor disagree                                           10        25.6%       25.6%
Slightly disagree                                                         8         20.5%
Substantially disagree                                                  1          2.6%        25.6%
Strongly disagree                                                    1          2.6%
Average Score                                     6.15


Commentsfrom Firms that are currently or have recently performed work for the Port
It appears that Port technical staff have as much angst with procurement as consultants do.
I have found that regardless of the data relative to direct labor rates, the port predetermines which level
of staff will be assigned to their projects, even before the project is defined.  They demand experience
but will not pay for it.  They maintain a DL Rates database and work to reduce those each year by
directing staff to drive down that in negotiations.

EXHIBIT "C"

As a firm with a long-time partnership/relationship with the Port, it has been a shame to lose the feeling
of true partnership and appreciation over the last 10 years or so. The rate negotiation process has been
completely removed from the end user of our services (project managers) who appreciate the services
we provide and recognize the value one consultant might provide over another.  The process is now
disconnected from any feedback about the quality of our performance, and feels a lot like buying a car.
If the goal was efficiency and cost savings, the Port would be much better served looking at the fair fees
on projects than nitpicking rates.  Many firms are more efficient and nimble than others, and the rate
negotiation process doesn't recognize the value good engineering can provide.    It feels like the
procurement group's goal is trying to cut costs more than be fair, especially since engineering fees are a
relatively small portion of the Port's overall budget.    Rather than encouraging the use of young "star"
performers by recognizing strong performance, it is easier to negotiate rates for older "average"
performers than recognize engineers who outperform their level of experience.   We still see all sorts of
inconsistencies between rates for firms (we see rates for other consultants that seem much different than
what we negotiated).  Sometimes the same person can be submitted on two different contracts and be
offered 20% different rates, so lack of consistency.


The current process has led to both the Port and the Consultant community being disappointed in each
other. The Port has not explained the basis for the rates allowed in the face of information at the federal,
state and local client levels to provide benchmarks for comparison.

The Port should be a good steward of the public trust. This means not unfairly distributing risks to those
upon whom they depend to design and deliver projects. The Port should compensate firms appropriately
for the risk taken and the value, creativity, innovation, service and quality delivered.  Between the current
version of the Professional Services Agreement and the compensation offered, there is no incentive to
participate in the Port's procurement process.

POS is unbending in recognizing what our firm pays in salaries to compete for talent. No ability to make
any profit on less experienced individuals. We get better rates for more experienced people but run into
the fee cap on projects with their hours.  Have more of a chance with fixed lump sum fees.

1. Many POS staff have indicated that their goal is to set billing rates at least 20% below market value.
2. POS established categories for consultant staff which do not align with our actual pay to individuals.
This causes some billing rates to be as much as 40% lower than market value.
3. POS has been unwilling to adjust billing rates for individuals who are promoted, and instead, insist of
keeping billing rates that were established several years prior.
The port has unrealistic rate expectations.  | only work with the Port because | value the relationship with
my Prime.  | do not make money on Port projects because they do not accept our rates that are below
industry already.
The Port likes hiring out of state firms to help limit long term memory of their doings (especially if things
go wrong)
When negotiating rates for an additional service to add geotechnical services to my contract, the sub-
consultant noted that they have a passion for working on projects and they were hoping to negotiate a
rate where they could get appropriate staff. The procurement staff from the airport laughed and rolled
their eyes. The Port ended up rejecting 80% of the staff submitted, including all of them with SeaTac
experience.
The main issue is the determination of rates.  The budgets seem somewhat fair, but the rates are not.
The rate  process is time-consuming, sometimes taking 4 or more iterations.   And then the  rates
themselves are poor - we are below break-even on some employees and then on others we get only 5-
6% profit. As soon as we give employees raises, we are losing money again (POS rate adjustments are
usually after one year of work, which could be months after we provide raises).  The margin is just too
razor thin and too risky.  There is no room for even the slightest scope creep.


C-5

EXHIBIT "C"

We look forward to working with the Port of Seattle to compete on par with other major public clients for
our industry expertise as a partner in delivery of significant infrastructure.

The technical staff have been great to work with and are among our most valued clients; they are open
to input as much as they are allowed and treat us as trusted business partners.  The CPO staff, on the
other hand, historically have been removed from any contact with the professional firms that they are
looking to hire. In the past they have sought to negotiate hard on a take it or leave it basis which has led
to hard feelings, and as a result the we among other firms have been inhibited from offering them the full
range of staff they need. It has felt more like a marathon than a dialogue when negotiating contracts and
service directives. This seems to be changing to a more professional approach to some extent recently
though they have a long ways to go. For example, we've been on three successive on call contracts (in
both prime and sub roles) and have only recently actually met our contracting officer face to face, and
then it was clear that she did not have the support of her management. We interface with the Port and
many other major agencies in a number of professional groups and task forces on issues like legislation,
funding and diversity. Though the technical staff are engaged, for the most part the Port's procurement
and contracting staff do not participate and hence lag their peers in their engagement with private industry
and in keeping up with much less leading the development of best practices. Other peers like Sound
Transit and WSDOT have active partnering efforts with industry, but to my knowledge the Port's CPO -
alone among its peers - does not. This needs to change.   For example, several years ago the national
CEO and regional chapter board of the Construction Management Association of America wrote to CPO
expressing  concern  about the  Port's  practices  in  the  procurement of professional  Construction
Management services, and offered to meet and partner to discuss and incorporate best practices
employed by other owners. To my knowledge the CPO never responded. The CEO of CMAA told me
that he could not think of another major owner who had refused to engage. This needs to change.

1.  After being awarded a Contract, it took us over 12 months to get under contract.
2.  Loading our individual hourly billing rates with all overhead expenses is very difficult.
3.  Cost for Security Badging should be covered by the Port.  At least a minimum 4 hours.













C-6

EXHIBIT "C"

We do a variety of work with the Port both under IDIQs and individual projects. The RFQ, proposal, and
interview process with the Port is very straightforward and clear. The proposal and selection process for
each solicitation is a good process and usually clearly communicated.   However, once selected the
contracting and rate negotiation process is very convoluted, subjective, and onerous.  Particularly on
IDIQs with multiple subs, the time required to submit individual resumes from all team members and the
time spent negotiating billing rates for each specific individual is excessive.  Typically the Port counters
with rates that are far below rates allowed by other public agencies in the state, particularly for senior
and higher positions.  They also limit multidisciplinary teams to one principal from the prime firm.  The
low allowable rates  makes us question our willingness to submit on future procurements.  We have
multiple IDIQs and contracts and each Port contracting staff seems to propose/negotiates different rates
for the same individual across different contracts and often won't accept a rate for a specific individual
that was just negotiated on another Port of Seattle contract.  Since each individual on a project has to
have a negotiated rate, adding staff to cover new service directives can be time consuming to negotiate
a rate for that new staff and get the rates approved.  With the high turnover in the Port contracting staff,
timely and consistent response has not happened.      During projects, invoicing and other tasks are
complicated with tracking each individual rate and invoicing requirements and coordination with subs on
using specific people and invoice formats, yet project administration time for invoicing is not allowed to
be chargeable.  The majority of public agencies we work for allow for project administration time of
invoicing a project to be charged to the project.  ~~ While the contracting, rate negotiations, and invoicing
have been very difficult, the Port Project Management, Operations, and Engineering staff are great to
work with, responsive, communicative, and work hard to make projects successful. If the Port contracting
process/staff could be as professional and consistent as the Port PM, operations, and engineering staff,
the Port would be a great entity to work for with a lot of great infrastructure projects and benefit to the
region.   We would absolutely like to continue to work with the Port on their infrastructure planning and
design needs, but the onerous process of contracting and often unreasonable counteroffer on rates, is
making us question our decision to continue to pursue Port of Seattle work.

The Port does not recognize the market value of professional services. We have found that the Port
relies on external statistics that do not match reality and that do not match market trends and market
value.  We would encourage the Port to adopt a multiplier approach that relies on direct salary plus
audited overhead plus an allowable profit percentage.  The would better match approaches taken by
WSDOT and other state agencies.
| think a primary issue is that it feels that the Port fundamentally distrusts consulting firms and think firms
charge too much, and in their drive to lower costs and try to have consistency between various firms,
they don't understand that each firm has very different cost structures and it's not fair to treat each firm
the same with respect to billing rates. Also the Port has leaned towards pushing more risk onto consulting
firms, but still push for lower than market rates.







Comments from Firms that have not performed work for the Port


C-7

EXHIBIT "C"

The scoring criteria is not fair.  Most firms can do the work.  So it ends up relationship based. As much
as the Port can try and other agencies. This needs to change.

We have not worked with POS; however, or experience with other public agencies in the Puget Sound
Region is that owners put undue liability on consultants in their contracting language (defense
obligations), and getting fair compensation is difficult to impossible.  There is too much red tape in doing
professional services consulting, but we have not personally experienced this with POS (since we have
not worked with them recently).
We are a minority owned engineering firm with offices in Seattle where we have 5 engineers with PEs
and MSEEs. We do work for Sound Transit, SPU, King County, and WSDOT, but not the Port.   Even
though we have aviation experience in other cities, we find it difficult to break in with the Port.



















C-8

PortAE(mmr                       Central Procurement Office
Seattle, WA 98111ps
of Seattle

December 9, 2019

To:          Glenn Fernandez, Director, Internal Audit
From:       Dave Soike, Chief Operating Officer
Nora Huey, Director, Central Procurement OfficeYY
Re:        Management Response, Report No. 2019-11, Operational Audit,
Architectural & Engineering Consultant Rates

In response to the Final Audit Report, please find our management response to the final
report for the December 9" Audit Committee. This response incorporates the final
report's recommendations as it made it easier to respond. We appreciate the
recommendations and look forward to getting started on improving our rate process.

Internal Audit Recommendations (portion copied/pasted from final report),
Finding #1:

CPO has not established guidelines for what is determined fair and reasonable.
Our testing of over 400 A&E consultants identified profit margins that exceed what
the industry deemed reasonable.

Recommendations:

The Procurement Council should determine what the Port deems as a fair and reasonable
rate.

Engage a third party to perform an independent model validation of the rate tool so that
management can gain confidence that the model produces accurate market rates.

Management Response/ Action Plan:

CPO Management appreciates the effort of Internal Audit's team to assist in identifying
areas for continuous improvements. This is consistent with the priority Port management
continues to place on this as well.

In early 2019, CPO Management determined further refinements of the existing tool and
process were necessary to improve efficiencies. CPO Management, with support of the
Executive, sponsored an initiative to evaluate the rate negotiation process involving a

Management Response, No. 2019-11                                                               Page 1 of 6

Central Procurement Office
PortA                        Seattle, WA 98111
A
www.portseattle.org
of Seattle
cross-functional team. We are working with the Continuous Process Improvement team
and involving management and front-line staff from across the Port in the Lean project
(referred to as the Rate Negotiation Lean project).

1.  Our plan below incorporates the first recommendation:

The implied profit margins identified in this audit require CPO Management, in
conjunction with Port Executive, to research further as part of the Port's delegated
authority to obligate Port funds. Our quick test of the data shows higher overhead
rates for some firms than utilized in the audit resulting in lower implied profit rates.
We plan to do a robust check and have conversations with the consulting
community to better understand the market and actual profitability.  The Port's
current contracting practice differs from cost-reimbursement type contract.  The
Port negotiates firm-fixed billing rates.  Indirect cost rates as they relate to direct
costs may differ between a cost-reimbursement type contracts and the Port's
approach utilizing firm-fixed billing rates. We will conduct our due diligence within
the next six months.

We will use the information gained from our research to present our
recommendations to the Executive to gain buy-in on our principals related to
compensation; including what the Port values and determines to be fair and
reasonable and market rates. Port procedures will be updated accordingly.

Our plan for the second recommendation includes finalizing our Rate Negotiation
Lean project to determine if validation of the model is the most appropriate step
taking into consideration the collaborative efforts recommended by the cross-
functional Lean team.  CPO Management, with support from the Executive, is
embracing and supporting our continuous process improvement culture which
fosters empowering the team who actually conducts the work to recommend
improvements.

DUE DATE: 6/30/2020





Internal Audit Recommendations (portion copied/pasted from final report),
Finding #2:

Management Response, No. 2019-11                                                               Page 2 of 6

-_SA                                           Central Procurement Office
Port ame                                   ASA
of Seattle
Management approval is not required when hourly rates exceed the maximum rates
produced by the service rate negotiation tool / model.

Recommendations:
Implement a management review process when consultant rates exceed the maximum.
This  review should  be documented  and contain  established criteria and  approval
thresholds (i.e. up to 20% over the maximum) for both the Services Agreement Manager
and Planning and Analytics Manager to approve.

If the thresholds exceed their authority or if agreement cannot be reached, approval
should be escalated to the appropriate person (i.e. director, COO) for approval, as
required by the authority guidelines.

Management Response/ Action Plan:

Our practice is to allow the team (the Rate Analyst, Contract Administrator and
Requesting Department Representative) the ability to exceed the maximum when all
three were in agreement without escalating to management. The purpose is to
empower the team and be more responsive during negotiations. Our existing process
can be refined by providing additional guidance on how to properly document the
decision.

In regards to the recommendation, the following steps have been taken to support this
program:

1.   In February 2019, CPO Management launched an enhanced Negotiation
Summary Memo template incorporating guidance on how to document decisions
made by the Contract Administrator with input from the Rate Analyst and Project
Manager; and/ or when escalated to management for approval.

2.  In July 2019, CPO Management launched a refined Service Agreements' filing
system to ensure rate decision documentation is filed and saved accordingly.

3.  In November 2019, CPO Management launched a Planning and Analytics' filing
system to ensure rate recommendation documentation is filed and saved
separately from the Service Agreements' filing system.

4.  In November 2019, CPO Management launched an interim enhancement to our
existing process while we conduct the continuous process improvement for rate
negotiations (The Rate Negotiation Lean Project).  We are testing this on three
professional service procurements. The goal is to test, refine, and update our
procedures accordingly by clarifying decision making ability in our procedures.

Management Response, No. 2019-11                                                               Page 3 of 6

Central Procurement Office
PortLodrd                      Seattle, WA 98111
www.portseattle.org
of Seattle
5.  As part of the Rate Negotiation Lean Project, Management will re-evaluate our
internal controls and escalation process. We anticipate engaging with Executive
by June 30, 2020.

DUE DATE: 06/30/2020

Internal Audit Recommendations (portion copied/pasted from final report),
Finding #3:

A reconciliation between the final negotiated rates and the contract does not occur.
As a result, we were unable to verify that all positions and rates reflected in the
contract were accurate.

Recommendation:

Retain documentation to evidence the agreed upon rate and position.

That documentation should then be used to verify that the rates are accurately captured
into the contract.

Management Response/ Action Plan:

It is accurate that CPO uses the rate negotiation tool (an Excel spreadsheet) to
document our rate negotiation offers/acceptance with the consultants. We use the
Excel spreadsheet as a tool to help us communicate offers and acceptance over
multiple rounds with the prime consultants and multiple subconsultants.  It is not part of
the contract. The contract represents the agreement between the Port and the
consultant.

We have learned through the efforts of this internal audit the Rate Analyst and the
Contract Administrators frequently used other supplemental sheets and email
exchanges to document/ finalize the rate negotiations.

Here are the efforts previously taken and our plan to refine our existing process in the
future:

1.  In February 2019, CPO Management launched a refined Negotiation Summary
Memo Template incorporating additional guidance on how to document rate
negotiation decisions.

Management Response, No. 2019-11                                                               Page 4 of 6

PortAama
Central Procurement Office
Seattle, WA 98111oo]
of Seattle

2.  In July 2019, CPO Management launched an enhanced Service Agreement filing
system to ensure rate recommendations and decision documentation is filed and
saved accordingly. This includes documenting when decisions were escalated to
management.

3.  In November 2019, CPO Management launched a Planning and Analytics filing
system to ensure rate documentation is filed and saved separately from the
Service Agreement's filing system. This is a departure from filing directly in
Service Agreement's filing system.

4.  In November 2019, CPO Management re-established the proper use of the rate
tool of transferring accurate rate data and verification between the Rate Analyst,
the Contract Administrator, the Contract Administrator and the consultant.  Using
supplemental sheets and email exchanges are appropriate; however, decision-
making must be documented as noted in item #1, above.

5.  As part of our Rate Negotiation Lean project, we will evaluate and implement
additional mechanical refinements to the existing tool to simplify the
documentation process with the intent to remove waste. We will update our
procedures accordingly.

DUE DATE: 06/30/2020


Internal Audit Recommendations (portion copied/pasted from final report),
Finding #4:

The Central Procurement Office is responsible for procuring all contracts related
to public works, consulting services, and goods and services. Governance with
Executive Leadership Team (ELT) oversight of CPO does not occur.


Recommendation:

The Chief Operating Officer should lead an effort to determine the meeting frequency and
information that is deemed necessary to perform effective governance.

We also recommend at a minimum, the CFO, Managing Directors of Aviation and

Management Response, No. 2019-11                                                               Page 5 of 6

PortAram                                     Central Procurement Office
yr                                                                                           Seattle, WA 98111
4                                             www.portseattle.org
of Seattle
Maritime, attend these meetings.

Finally, we recommend developing a charter that defines the purpose, objective, and
voting rights (if necessary) within the Governance Committee.

Management Response/ Action Plan:

Executive Leadership Team (ELT) oversight of CPO does occur.  CPO Management
engaged with the Executive Leadership Team on procurement matters multiple times
during the 2018 and 2019 leadership retreats.  Issues addressed in those meetings
included:  lessons learned from state audit and resulting proposed changes; Diversity in
Contracting; improvement initiatives; minority and women business enterprise (MWBE)
utilization  reporting  and  dashboard,  and  most  recently  updates  on  2019  process
improvements.  As the Port moves forward for efficiency reasons, issues related to
procurement will be covered in executive retreats.  When necessary, meetings with
additional staff outside of the Executive Leadership Team will be set up to handle specific
issues.


DUE DATE: 06/30/2020













Management Response, No. 2019-11                                                               Page 6 of 6

Port of Seattle

2019 Audit Engagement Service Plan







Provided to management and the Audit
Committee on December 9, 2019
0 MOSSADAMS

0 MOSSADAMS
control. Although control risk exists independently of the audit, and is the responsibility of
management, we will modify our audit procedures based upon assessment of the risk.

Detection risk represents the risk that the auditor will not detect a material misstatement that exists in
an assertion. lt is a function of the effectiveness of applying our audit procedures.

We assess audit risk at the overall financial statement level, individual account balance, transaction, or
disclosure level! during the planning phase of our audit (risk assessment procedures). Our overall
judgment about the level of the risks above will affect the scope of the audit, including the nature, timing,
and extent of our audit procedures.

Phase I - Planning

The following risk assessment activities are performed:

Entrance meetings with certain members of the Audit Committee represented by the Port
Commissioners, management and staff to discuss expectations, the audit process and timelines, and
to obtain key strategic, financial, and operational information.

Observation and inspection of documents.

Identify Port-specific transactions and industry developments that might require an expansion or
modification of audit tests.

Conduct risk brainstorming meeting with our own team as well as meetings with Port executives,
management, and other personnel.

Based on the results of the risk assessment procedures noted above, we conclude the planning phase by
performing the following:

Define the scope of the engagement including determination of potential major programs for the
Federal Uniform Guidance and the applicable audit procedures.

Ascertain timing of conduct and completion of audit, reporting submission deadlines, and nature of
reports to be issued.

Design an efficient audit approach and audit programs with sufficient risk coverage.

Establish preliminary materiality and non-posting threshold for trivial matters noted during the audit.

Materiality
Materiality is the maximum level of misstatement that can be tolerated in the financial statements without
causing a reasonable person's judgment about them to be significantly changed or influenced. We
determine materiality as follows:

Conduct preliminary analysis of financial statements to make initial judgment of materiality.

Consider the needs and expectations of the readers of the financial statements.

Consider both quantitative and qualitative factors.

(mw) MOSSADAMS
e    Environmental remediation liability and contingencies

e   Third party management

e    Financial close and reporting

Information technology (general and application computer controls)

e    Budgeting process

Obtain or update copies of system, policy, and procedure documentation from various departments.
We retain these copies in our permanent working paper files and update them annually.

Obtain knowledge of design and implementation of controls relevant to financial statement assertions
and compliance with laws and regulations that have direct and material effect on determination of
financial statement amounts. After gathering this information, we perform "walkthroughs" to verify that
our understanding of the system and its controls is accurate and that key controls exist and are
operating as designed.

Perform tests of controls that relate to financial statement assertions, and perform tests of controls
and compliance related to the Port's federal awards:

e   Allowable costs and activities

e    Cash management

*    Equipment and real property management

*    Matching and level of effort

o    Period of availability

*    Procurement and suspension and debarment

e    Program income

e    Reporting

e    Subrecipient monitoring

e    Special tests and provisions unique to the major programs, including compliance with the Davis-
Bacon Act.

Information Technology (IT) Systems and General Computer Controls
Determine application systems, databases, and operating systems in scope based on the business

process walkthroughs of our financial audit team.

Identify any application controls our financial audit team is planning to place reliance upon.

e    Procurement, cash disbursements

o    Payroll

e    Billing

e    Capital projects

e    Financial close and reporting

Identify key IT general computing controls that support automated and application controls to be
relied upon by our financial audit team.

e    Security and access

eo    System acquisition and implementation

MOSSADAMS

definition of a significant deficiency or a material weakness. We also conduct final engagement quality
control reviews and prepare required deliverables.

Finally, we are required by auditing standards to communicate, in writing, to management and those
charged with governance, all significant deficiencies and material weaknesses noted as a result of our
audit. For minor observations, we provide information on our observations regarding controls and various
other communications either verbally or in the form of a formal management letter of recommendations to
the Port.

0           ad                ti

We have highlighted certain matters of audit emphasis pertinent to the Port:

Bond Accounts

The bond related accounts always provide challenging audit and accounting issues. Among them are:

New debt issuances

Refunding, defeasances or extinguishment

Compliance with covenants

Arbitrage

Leases
Leasing issues are complex and are prevalent in all the Port's lines of business. For instance, we will
devote audit effort and resources to the following:

Real estate transactions within the Real Estate Division

New and significant leases at the Airport

Review of Port's controls over ongoing accounting and monitoring of existing leases

Implementation of new GASB 87, addressing leases and effective starting in 2020

Revenue Recognition

Revenue recognition complexities:

Airline lease agreements

Other operating revenue (including cruise ship terminal revenue)

Tax, PFC and federal grant receipts, and

Investment income

(mw)  MOSSADAMS
at least annually. Additionally, this statement requires disclosure of information about the nature of the
government's AROs, the methods and assumptions used for the estimates of the liabilities, and the
estimated remaining useful life of the associated tangible capital assets.

GASB No. 84 "Fiduciary Activities." Effective for the Port in 2019, this Statement addresses the
improvement of guidance regarding the identification of fiduciary activities for accounting and financial
reporting purposes, and how these activities should be reported.
GASB Statement No. 88, "Certain Disclosures Related to Debt, including Direct Borrowings and Direct
Placements". Effective for the Port in 2019, this Statement debt for purposes of disclosure in notes to
financial statements as a liability, and requires that additional essential information related to debt be
disclosed in notes to financial statements, including unused lines of credit; assets pledged as collateral for
the debt; and terms specified in debt agreements related to significant events of default with finance-
related consequences, significant termination events with finance-related consequences, and significant
subjective acceleration clauses.
GASB Statements that will be effective for the Port in future years, which should be evaluated are:

GASB No. 87 "Leases." Effective for the Port in 2020, this Statement is intended to better meet the needs
of financial statement users by improving accounting and financial reporting for leases. This standard
requires the recognition of certain lease assets and liabilities for leases that were previously classified as
operating leases and recognized as inflows of resources or outflows of resources based on the payment
provisions of the underlying contract. It establishes a single model for lease accounting based on the
foundational principle that leases are financings of the right to use an underlying asset and as such, a
lessee is required to recognize a lease liability and an intangible asset right-to-use asset, and a lessor is
required to recognize a lease receivable and a deferred inflow of resources, thereby enhancing the
relevance and consistency of information about the leasing activities. We will continue working with
management to determine the impact of this statement on the Port's financial statements.

GASB No. 89 "Accounting for Interest Cost Incurred before the End of a Construction Period". Effective
for the Port in 2020, this statement establishes accounting requirements for interest cost incurred before
the end of a construction period, and requires that interest cost incurred before the end of a construction
period be recognized as an expense in the period in which the cost is incurred.

(mw)  MOSSADAMS
Moss Adams Audit Team
The management team serving on our audits of the Port of Seattle is as follows:

Olga A. Darlington, CPA, Business Assurance Partner
Olga specializes in serving governmental entities and has significant experience
conducting audits in accordance with Government Auditing Standards and Federal
Uniform Guidance, and addressing complex transactions and technical issues.
Olga has over 20 years of public accounting experience and will serve as your lead
client service partner, overseeing all services provided to for the Port.

Tammy Erickson, CPA, Business Assurance Partner
Tammy specializes in serving governmental entities and has over 20 years of
public accounting experience and will serve as the concurring engagement
reviewer, performing a secondary review of our audit plan, the financial statements
and our reports and, as necessary, will consult on technical issues or key elements
of the audits.


Maria Braun, IT Consulting Audit Senior Manager

Maria has experience in governance, risk management, and compliance with a
strong background in technology. Maria will spend her time conducting the general
and application IT control test procedures as part of our assessment of the Port's
controls related to the audit.

Tyler Reparuk, CPA, Business Assurance Senior Manager
Tyler has ten years of public accounting experience and this will be his tenth year
serving the Port. Tyler has experience in performing governmental financial
statement audits. Tyler will manage the engagement and spend his time
overseeing our staff in the field, reviewing the work performed by staff and
addressing technical issues throughout the year.

Anna Waldren, CPA, Business Assurance Manager

Anna has five years of public accounting experience and this will be her fourth year
serving the Port. Anna has experience in performing governmental financial
statement audits and Federal Uniform Guidance audits. Anna will serve as a
manager and spend her time reviewing the work performed by staff in the field,
assisting with the supervision of staff in the field, and managing each of the audits
of the Port.

(m) MOSSADAMS
Ability to continue as a going concern

Legal, regulatory, or contractual requirements not encompassed in the current engagement

Consultation with other accountants, if any

Independence of Moss Adams

At the conclusion of our audits, we will present our reports, the results of our audit and the required
communications noted above, to the Audit Committee.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.