8c. Memo - Badge System Upgrade

COMMISSION 
AGENDA MEMORANDUM                        Item No.          8c 
ACTION ITEM                            Date of Meeting     November 9, 2021 

DATE :     November 1, 2021 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Wendy Reiter, Director Aviation Security 
Kenny Lyles, Director Maritime Operations and Security 
Krista Sadler, Director Technology Delivery 
SUBJECT:  Badge System Upgrade (CIP #C801201) 
Amount of this request:                 $800,000 
Total estimated project cost:            $800,000 
Estimated 10-year contract fee:        $2,500,000 
ACTION REQUESTED 
Request Commission authorization for the Executive Director to 1) proceed with the Badge
System Update project and 2) execute contract(s) for software, equipment, vendor services, and
ten years of software license and maintenance fees. The amount requested for project
implementation is $800,000 and the estimated ten-year software license and maintenance fee is
$2,500,000 ($250,000 Annually). Fees for the software license and maintenance contract will be
budgeted in the Information and Communication Technologies (ICT) operating budget. 
EXECUTIVE SUMMARY 
This project will upgrade the Badge System used Port-wide to create and manage approximately
22,000 access credentials for Seattle-Tacoma International Airport (SEA) and Port Corporate and
Maritime locations. System users include the Aviation Credential Office, Maritime Security,
Maritime Maintenance, Pier 69 Facilities, and Cruise Operators who vet credential requests
following location specific requirements and assign and maintain appropriate access for Port of
Seattle employees, tenants, consultants, and contractors. 
The current Badge System, SAFE from HID Global, was initially deployed in 2014 as a result of a
competitive procurement process. While additional features have been added, no significant
upgrades have been completed since initial implementation. An upgrade of this system will
ensure that security updates, system patches, and support are available for this critical system. 
ICT, Aviation Security, and Maritime Security will partner to complete this project with HID
Global. The capital project was included in the 2021-2025 capital budget and plan of finance in
the amount of $750,000. The additional $50,000 will be added to the capital budget and plan of

Template revised January 10, 2019.

COMMISSION AGENDA  Action Item No. 8c                                   Page 2 of 4 
Meeting Date: November 9, 2021 
finance for 2023. Recurring cost, estimated at $250,000 per year for up to ten years ($2,500,000), 
will be budgeted in the ICT operating budget. 
JUSTIFICATION 
Access authorization through credential management is a complex and critical process for Airport
and Maritime operations. At SEA, security requirements from the Department of Homeland
Security, Transportation Security Administration (TSA) include mandatory background checks for
new and renewed badge applications as well as continual vetting of badge holders against current
threats. For Maritime badging, the United States Coast Guard (USCG) has a requirement for a
Transportation Worker Identification Credential (TWIC) for several of our port locations. A robust
and reliable credential management system is essential for Airport and Maritime operations. 
Diversity in Contracting 
We are seeking a competition waiver to work with a HID Global as they are the only firm that can
provide the upgrade services for their equipment and software. We don't anticipate any
subcontracting opportunities given the specialized scope and will not include a WMBE goal on
this project. 
DETAILS 
Scope of Work 
(1)   Upgrade of the HID SAFE system to the latest version 
(2)   Server and Database infrastructure upgrades 
(3)   Migration of data to new system 
Schedule 
Commission authorization                      2021 Quarter 4 
Implementation Start                           2022 Quarter 1 
In-use date                                       2023 Quarter 2 
Cost Breakdown                                     This Request           Total Project 
Vendor Services                                           $500,000               $500,000 
Software or Hardware Upgrades                           $50,000               $50,000 
Port of Seattle Labor                                          $250,000                $250,000 
Total                                                           $800,000                $800,000 



Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. 8c                                   Page 3 of 4 
Meeting Date: November 9, 2021 

ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  Upgrade HID SAFE with private cloud hosting 
Cost Implications: $800,000 Capital Project Costs; $2,750,000 annual fees over 10 years 
Pros: 
(1)    Ensures availability of security updates, system patches, and provides updated features
of a new version. 
(2)   Reduction of Port Labor required to maintain Badge System infrastructure 
Cons: 
(1)   Annual support costs increase by $50,000 per year over recommended alternative. 
(2)   Increased risk of support delay, cyber security exposure, and unavailability due to
connectivity issues. 
This is not the recommended alternative. 
Alternative 2  Procure and implement or build a replacement Badge System 
Cost Implications: $2,500,000 Capital Project Costs; $2,500,000-$3,500,000 annual fees over 10
years 
Pros: 
(1)   Ensures availability of security updates, system patches, and provides updated features
of a new version. 
(2)   A custom developed solution could meet all system requirements. 
Cons: 
(1)    There are very few providers of badge systems to meet the business and regulatory
requirements for both an airport and seaport. A new procurement would likely require
a complex solution integrating software systems from more than one vendor. 
(2)   This alternative is both significantly more expensive than the alternative and will take
longer for implementation. 
This is not the recommended alternative. 
Alternative 3  Upgrade HID SAFE on Port supported infrastructure 
Cost Implications: $800,000 Capital Project Costs; $2,500,000 annual fees over 10 years 
Pros: 
(1)   Ensures availability of security updates, system patches, and provides updated features
of a new version. 
(2)   Port of Seattle infrastructure is architected to protect the sensitive data and availability 
requirements of this critical system. 
Cons: 
(1)   Capital funds are not available for other projects. 

Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. 8c                                   Page 4 of 4 
Meeting Date: November 9, 2021 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
Cost Estimate/Authorization Summary              Capital        Expense           Total 
COST ESTIMATE 
Original estimate                                   $800,000               $0        $800,000 
AUTHORIZATION 
Previous authorizations                                   $0                0               $0 
Current request for authorization                  $800,000                0        $800,000 
Total authorizations, including this request         $800,000                0        $800,000 
Remaining amount to be authorized                    $0             $0             $0 
Annual Budget Status and Source of Funds 
This project was included in the 2021-2025 capital budget and plan of finance at an amount of
$750,000. The remaining $50,000 will be budgeted in the 2023-2028 capital budget. The project
will be funded 92% from the Airport Development Fund and 8% from the General Fund. 
Financial Analysis and Summary 
Project cost for analysis              $800,000 
Business Unit (BU)                  Administrative, 92% allocation to Aviation 
Effect on business performance     NOI after depreciation will increase due to inclusion of
(NOI after depreciation)             capital (and operating) costs in airline rate base 
IRR/NPV (if relevant)                N/A 
CPE Impact                       Less than .01 in 2023 
Future Revenues and Expenses (Total cost of ownership) 
Ten-year recurring service, license, or maintenance fees, estimated at $2,500,000, will be
budgeted in the ICT annual operating budget beginning in 2022. 
ATTACHMENTS TO THIS REQUEST 
None 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
None 


Template revised June 27, 2019 (Diversity in Contracting).

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.