8k. Memo - Building Controls Upgrade Irregular Bid

COMMISSION 
AGENDA MEMORANDUM                        Item No.          8k 
ACTION ITEM                            Date of Meeting     November 9, 2021 
DATE:     October 29, 2021 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Eileen Francisco, Interim Director Aviation Facilities and Capital Programs 
Wayne Grotheer, Director, Aviation Project Management Group 
SUBJECT:  Building Controls Upgrade  Irregular Bid (CIP #800944) (Short Form) 
Amount of this request:                       $0 
Total estimated project cost:         $10,000,000 
ACTION REQUESTED 
Request Commission authorization for the Executive Director  to  award and execute a
construction contract to the low bidder for an irregular bid outcome with only one bid submitted.
There is no funding associated with this request and the project is currently authorized for
construction with a total estimated cost not to exceed $10,000,000. 
SUMMARY 
This request is asking for authorization to proceed with awarding and executing a construction
contract on an irregular bid as required by Resolution No. 3605 Paragraph 4.2.3.4. Only one bid
was received in response to the construction advertisement which qualifies the bid as irregular.
The Engineer's estimate was $4,693,000 and the bid received was $4,050,937 which represents 
a potential construction cost savings of $642,063.
The  building  control  system  regulates  and  controls  critical  airport  terminal  building
environmental features such as temperature, humidity, and air exchanges. In addition, the
system performs smoke control functions and provides water and gas utility metering. This
project will replace approximately 107 obsolete building control panels that are installed
throughout  the  Seattle-Tacoma  International  Airport. This  project  will  also  improve
communications and data throughput, allowing for improved system performance and future
system expansion. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
August 10, 2021  The Commission authorized construction 
May 15, 2020  The Commission authorized execution of a project specific design contract 
December 10, 2019  The Commission authorized design 
There are no attachments to this memo. 

Template revised April 12, 2018.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.