6a. Memo

COMMISSION 
AGENDA MEMORANDUM                        Item No.          6a 
ACTION ITEM                            Date of Meeting     February 28, 2017 
DATE:     February 21, 2017 
TO:        Dave Soike, Interim Chief Executive Officer 
FROM:    Michael Ehl, Director, Airport Operations 
Wayne Grotheer, Director, Aviation Project Management Group 
Clare Gallagher, Director, Capital Project Delivery/Public Affairs 
SUBJECT:  Flight Corridor Safety Program  Phase 2 and 3 
Amount of this request:                                     $2,373,000 
Total estimated project cost(Ph. 2 & 3):                       $7,227,000 

ACTION REQUESTED 
Request Commission authorization for the Chief Executive Officer to prepare environmental, 
design and contract bid documents for the Flight Corridor Safety Program now-combined Phase
2 and Phase 3 at Seattle-Tacoma International Airport for $2,373,000.  The total estimated
project cost is $7,227,000. 
EXECUTIVE SUMMARY 
This project is part of a multi-year program to manage obstructions consisting of trees and
other vegetation at and around Seattle-Tacoma International Airport, and replanting lowerheight
vegetation on or near the removal sites.  As the operator of the airport, the Port is
responsible for complying with Federal Aviation Administration (FAA) and State regulations 
regarding obstructions to protect flight operations into and out of the airport. Phase 1 work on 
some Port property is already in progress.  This request allows for the environmental process
for Phase 2 (public agency-owned properties) and Phase 3 (residential and commercial
properties) to begin, along with preparation of design and contract documents.  There is no
construction activity for Phase 2 and 3 resulting from this action. 
JUSTIFICATION 
This program is necessary to meet the Aviation Division's goals of ensuring safe and secure
aircraft operations. The program of obstruction removal and replanting vegetation is organized
into three phases. Phase 1 occurs on Port property, Phase 2 occurs on commercial and other
agency property, and Phase 3 occurs on private property.

Template revised September 22, 2016.

COMMISSION AGENDA  Action Item No. _6a___                              Page 2 of 7 
Meeting Date: February 28, 2017 
Phase 1 is currently underway with a contract executed in December 2016. Work in two areas
adjacent to residences has been deferred to allow for additional evaluation of options for these
sites.  Work in these two areas may occur in the latter part of 2017 or be transferred to a
subsequent contract.   The Port conducted an environmental review under the State
Environmental Policy Act (SEPA) for Phase 1 of the project and issued a Final Mitigated
Determination of Non-Significance for Phase 1 in August 2016.
Regulations concerning obstruction removal at airports and justification for this program are
based on the following: 
1.  Federal Aviation Administration Requirements for Airport Operators to Control Obstructions 
a.  Federal Aviation Regulation (FAR) Part 139, Certification of Airports 
b.  Advisory Circular (AC) AC 150/5300.13A, Maintenance of obstacle clearance surfaces 
c.   Grant Assurance 20 "Hazard Removal and Mitigation" 
d.  Grant Assurance 21 "Compatible Land Use" 
e.  Federal Aviation Administration Engineering Brief 91, "Management of Vegetation in
the Airport Environment" 
2.  State Requirement for Airport Operators to Control Obstructions
a.  RCW 14.12.020 "Airport hazards contrary to public interest" 
3.  Airport's Strategic Goals and Objectives 
a.  Strategic Goal No. 1, Operate a world-class international airport by: Ensuring safe
and secure operations. 
Environmental Review 
Phases 2 and 3 will be pursued as a combined phase for environmental reviews and design
rather than two separate, consecutive phases.  This will provide for a cumulative impacts
assessment for the remaining work, and facilitate the removal of obstructions as properties
become available for the removals to occur. Environmental review will be undertaken for all
property within the combined Phases 2 and 3, will take into account the environmental review
that occurred for Phase 1, and is anticipated to be complete in mid-2017. 
The combined Phases 2 and 3 also includes additional community engagement and negotiation
with property owners regarding removal and replanting on their property. Regular briefings to
Commission, in advance of construction authorization, is planned to occur this spring. 
Public Engagement 
As part of the project approval for Phase 1 work, the Commission altered the approach to
approve work beginning on select Port properties, and directing additional work to study
possible modifications for the remaining properties in Phase 1.  Port staff is undertaking
additional site evaluation regarding the removal and replanting approach for trees on Port
property near South 200th Street (Sites P-4 and P-5).  Most over-height conifers are located
within Sites P-4 and P-5, and both sites are also adjacent to residential properties.  These
factors, in part, raised community concerns regarding the obstruction management in this area
and the re-evaluation of options for these sites. 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. _6a___                              Page 3 of 7 
Meeting Date: February 28, 2017 

On February 1, Port staff hosted a public open house near the Airport to update residents.
Several stations provided information on program details, gathered feedback, and publicized an
"online open house" for the program.  Identical to the February 1 open house, the online
version seeks public input specifically on: 
Removal and replanting approaches for Port properties near South 200th Street 
The Port's Airport Communities Ecology Fund to invest in environmental projects and
programs in SeaTac, Burien, and Des Moines 
Approximately 85 people attended, and feedback is continuing to be gathered from the inperson
comment forms and the online open house.  Staff is reporting separately to the
Commission on the ongoing work with the Ecology Fund. 
Port Public Affairs is maintaining an email contact list to update residents directly regarding
activity and next steps in the program, including the recent open house and upcoming
Commission briefings on the program or related topics. In addition, updates also are provided
by direct communication to the Highline Forum members;  in the Port's Connections enewsletter
, which reaches 12,000 recipients; the Port's Air Mail newsletter, which reaches
31,000 households in the Airport area; and through local media and blogs. 
Future Commission briefings and actions are anticipated to include briefings in second and third
quarters of 2017 on proposed changes to Phase 1 following the community engagement, and
design plans and SEPA environmental review for Phases 2 and 3. Construction authorization for 
the combined Phase 2 and 3 work is anticipated to be requested in the third quarter of 2017.
The delivery method for the remaining work will be developed during the design process. 
DETAILS 
Scope of Work 
Scope of work for this authorization includes the development of environmental and design bid
documents for environmental review for the Flight Corridor Safety Program Phase 2 and Phase 
3, now combined. 
The program scope of work for combined Phase 2 and  Phase  3 includes removing
trees/vegetation  and  replanting  tree  and  shrub  vegetation. This  scope  also  includes
environmental review and permitting in compliance with applicable federal, state and local 
requirements.  The work may include installation of temporary erosion and sediment control
devices, removal of trees/vegetation, removal of invasive species, extensive tree replanting, 
extensive shrub replanting and restoration. 



Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. _6a___                              Page 4 of 7 
Meeting Date: February 28, 2017 
Schedule 
Activity 
Commission design and environmental         2017 Quarter 1 
authorization 
Design and environmental start                  2017 Quarter 1 
Commission briefing                            2017 Quarter 2 
Commission construction authorization          2017 Quarter 3 
Construction start                                2017 Quarter 4 
Cost Breakdown (Phase 2 and 3)                        This Request           Total Project 
Design                                                  $2,373,000             $2,720,000 
Execution                                                        $0             $4,507,000 
Total                                                         $2,373,000              $7,227,000 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  Do not authorize funds to prepare environmental, design and contract bid
documents, maintain work in Phase 1 only. 
Cost Implications: $0 
Pros: 
(1)   No expenditure required 
Cons: 
(1) Phase 2 and 3 work would be delayed further into 2017, contrary to discussions with
FAA 
(2) FAA could consider the Airport to be non-compliant with Federal rules and regulations.
The FAA would have a number of options on how to address the non-compliance. The
FAA's options would include: 
(a) Consider approach and/or departure procedures to be unsafe, and limit their
use; 
(b) Limit or eliminate FAA grant funding to the Airport until the obstructions are
removed. FAA entitlement grant funding is estimated to be ~$6.6 million in
2017. 
(c) Requiring airlines to take weight penalties, with an additional effect of not
serving certain markets, as aircraft would have to be lighter to take-off over
the obstructions. 
(3)   Does not meet the Airport's strategic goal of ensuring safe and secure operations. 
This is not the recommended alternative. 


Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. _6a___                              Page 5 of 7 
Meeting Date: February 28, 2017 
Alternative 2  Authorization to prepare environmental, design and contract bid documents for
Phase 2 and Phase 3, combined. 
Cost Implications: $2,373,000 
Pros: 
(1)   Complies with FAA and State regulations to manage identified obstructions in a timely
manner. 
(2)   Meets  the  Airport's  strategic  goals  and  objectives  of  ensuring  safe  and  secure
operations. 
(3)   Provides time for public engagement and outreach with the local communities 
(4)   Provides a manageable program to meet the FAA and state regulations to remove
identified obstructions. The FAA concurs with this approach. 
(5)   Allows the Port to apply lessons-learned from Phase 1, to Phase 2 and Phase 3. 
(6)   Allows time for coordination with local agencies and area residents. 
(7)   Allows areas with obstructions to be removed with sustainable lower growth species
meeting the long term goals of the community. 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
Cost Estimate/Authorization Summary              Phase 1     Phases 2&3           Total 
COST ESTIMATE (Phase 1, 2 and 3) 
Original estimate                                 $2,731,000               $0      $2,731,000 
Previous changes  net                            $475,000        $232,000        $707,000 
Current change                                        $0      $2,373,000      $2,373,000 
Future change                                         $0      $4,622,000      $4,622,000 
Revised estimate                              $3,206,000      $7,227,000    $10,433,000 
AUTHORIZATION 
Previous authorizations                          $3,206,000        $232,000      $3,438,000 
Current request for authorization                         $0      $2,373,000      $2,373,000 
Total authorizations, including this request       $3,206,000      $2,605,000      $5,811,000 
Remaining amount to be authorized                     $0      $4,622,000      $4,622,000 
Total Program                                  $3,206,000      $7,227,000    $10,433,000 

Annual Budget Status and Source of Funds 
The Flight Corridor Safety Program costs are expense costs. This work is estimated to be within
the $3,483,535 approved operating budget for 2017. Future annual budgets will include
provisions for the rest of the program. 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. _6a___                              Page 6 of 7 
Meeting Date: February 28, 2017 
Additional funding for Phase 2 and 3 monitoring and additional plantings as needed to offset
vegetation mortality will be included in the annual Aviation Operations operating budget. 
The full cost of the program will be included in the Airfield Movement Area cost center in the
year the costs are incurred and recovered from the airlines. The funding source is the Airport
Development Fund. The incremental impact on the airline cost per enplaned passenger would
be approximately $0.14 in 2017.
ADDITIONAL BACKGROUND 
Obstructions are any objects penetrating FAA-designated approach and departure paths at or
around an airport posing a potential risk to safe aircraft operations. Obstruction studies and
the related publication of obstruction charts were completed every ten years by the FAA until
approximately 1994. In preparing for the activation of the Third Runway, the FAA performed an
obstruction analysis in 2005 that led to the removal of trees in 2006-2008.   An aerial
obstruction analysis was conducted by the Port in 2015 that identified approximately 1,600
obstruction data points consisting of trees and other vegetation.  Subsequent field work was
performed by a third party to verify the aerial obstruction analysis data. The field verification of
the aerial obstruction data resulted in identifying approximately 2,800 tree obstructions at or
around the airport. 
The Port has developed a comprehensive Flight Corridor Safety Program that will address the
removal of obstructions in several phases and span multiple years: 
Phase 1: 2016/2017 - Port-Owned property 
Phase 2: 2017/2018  Public agency-owned properties including Highline Public School
District, Washington State Department of Transportation, Seattle Public Utilities and public
right of way within the cities of Burien, Des Moines and SeaTac. 
Phase 3: 2018/2019 - Residential and Commercial properties 
ATTACHMENTS TO THIS REQUEST 
None 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
November 22, 2016   Commission authorized (1) to award and execute a major works
construction contract to the lowest responsible bidder, notwithstanding the low bid
exceeding the engineer's estimate by more than 10 percent; (2) change the contract
duration as necessary and include additional scope that may be identified, including
deferral of work on selected sites; (3) increase the project budget by an amount not to
exceed $475,000 for a total new project cost of $3,206,000. 
November 1, 2016  Commission public meeting and briefing on the Flight Corridor Safety
Obstruction Management program. The briefing provided an overview of state and federal

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. _6a___                              Page 7 of 7 
Meeting Date: February 28, 2017 
laws/requirements, and staff's recommendation of options to modify the current program.
The public meeting also included an extensive public comment period. 
October 25, 2016  Commission considered authorization to award the irregular bid exceeding
10 percent of the engineer's estimate to the lowest responsible bidder but took no action. 
October 11, 2016  Commission considered authorization to award the irregular bid exceeding
10 percent of the engineer's estimate to the lowest responsible bidder but took no action. 
August 23, 2016  A special announcement to Commission by Aviation Operations Director,
Michael Ehl, in regards to the Port issuing the final environmental Mitigated Determination
of Non-Significance (MDNS) for tree removal and replanting as part of the Flight Corridor
Safety Program in Phase One. 
August 9, 2016  Commission authorized to advertise and execute a major works construction
contract in the amount of $1,831,000 for a total project cost of $2,731,000. 
February 9, 2016  Commission authorized to design, advertise and execute a major works
construction contract in the amount of $750,000 for a total estimate project cost of
$900,000. 
November 24, 2015   Commission briefed on the  Flight Corridor Safety Obstruction
Management program. The briefing provided an overview of state and federal
laws/requirements, and staff's recommendation of a phased delivery approach to complete
the program. 










Template revised September 22, 2016; format updates October 19, 2016.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.