6e. Memorandum

AGENDA MEMORANDUM                        Item No.          6e 
ACTION ITEM                            Date of Meeting       June 27,2017 
DATE:     June 19, 2017 
TO:        Dave Soike, Interim Executive Director 
FROM:    Jeffrey Brown, Director AV Facilities and Capital Program 
Wendy Reiter, Director, Aviation Security and Emergency Preparedness 
Wayne Grotheer, Director, Aviation Project Management Group 
SUBJECT:  Baggage Optimization Capacity Acceleration (CIP #C800612) 
Amount of this request:                 $637,000 
Total estimated project cost:        $445,050,000 
ACTION REQUESTED 
Request Commission authorization for the Executive Director to (1) authorize additional design 
and project management funds to expand the capacity of the baggage system at Seattle-
Tacoma International Airport to 60 million annual passengers (MAP); (2) use Port crews and
small works contracts to perform additional construction work; and (3)   amend Service
Agreement P-00317641 to add $10,160,000 for a total contract value of $31,160,000 to design
this additional capacity. The amount of this request is $637,000. 
EXECUTIVE SUMMARY 
This request is to incorporate a future capacity expansion of the Baggage Optimization project
now in order for the new outbound baggage system to accommodate 60 Million Annual
Passengers (MAP). The Baggage Optimization project was scoped in 2012 to accommodate 45
MAP with an expandable design to accommodate future growth. At the time, growth forecasts 
were flat and predicted 45 MAP would be adequate through 2027. The decision was made to
proceed in building an expandable 45 MAP system with the expectation that an expansion
would occur in the future in time to accommodate growth up to the 60 MAP level. Due to
unprecedented growth at the airport, the 45 MAP threshold was met in 2016, over ten years
earlier than anticipated. 
The cost associated with the Requested Action is $24,937,000. The project returned savings in
April 2017 in the amount of $24,300,000 (due to favorable Phase 1 Construction bids), which
will offset this request so that the total amount of this authorization request at this time is
$637,000. 
By designing and building the system to accommodate 60 MAP the Port can be assured that the
existing terminal will have enough baggage screening capacity until new facilities can be

Template revised September 22, 2016.

COMMISSION AGENDA  Action Item No. _6e___                              Page 2 of 8 
Meeting Date: June 27, 2017 
brought online pursuant to what is currently being advanced in the Sustainable Airport Master
Plan (SAMP). The 60 MAP baggage system will have the ability to potentially tie into a new
passenger terminal in the future. To meet near and long term baggage demand for the airport,
we are currently requesting to incorporate the planned expansion at this time. The nature of
baggage systems does not allow for small incremental capacity additions, therefore this request
is to build the system to its full capacity of 60 MAP.
This request seeks authority to increase the amount of design funding in order to accommodate
a baggage system capacity expansion, to amend a baggage consultant agreement to include
this additional capacity design, and to make equipment purchases and perform preliminary
enabling work to clear areas and speed up the coming contractor activities in future phases. 
This baggage system capacity acceleration would achieve the following outcomes: 
Increased outbound system capacity to 60 MAP 
Increased system redundancy and, therefore, increased system availability 
JUSTIFICATION 
One of the main objectives of the Baggage Optimization project has been to design and build a
system that can be efficiently expanded to 60 MAP in the future. While the current scope is to
build a system capable of servicing 45 MAP, the system was designed with future growth and
expansion in mind. 
After experiencing multiple years of compounding higher than projected passenger growth,
initiating the expansion previously expected in the future will minimize service disruptions to
airlines and passengers. Authorization at this time will allow the expansion to be efficiently
incorporated into Phase 2 and Phase 3, with no rework required to the Phase 1 scope currently
under construction. 
The airlines have been briefed about the proposed capacity expansion at the last five
Airline/Airport Affairs Committee (AAAC) meetings, and are aware that it will be on the next
Majority in Interest (MII) ballot for the amount of $150M. 
DETAILS 
The authorizations requested and actual project costs associated with this request are to: 
Authorize $19,937,200 additional design and project management funds to expand the
capacity of the baggage system to 60 MAP 
Authorize $5,000,000 to utilize Port crews and small works contracts to perform
additional construction work 
Authorization for these two items totals $24,937,200. 
The Port has contracted with BNP Associates for design of the baggage optimization
project. It is necessary to amend this contract to add an additional $10,160,000 for
design and construction support thru 2024. This Service Agreement P-00317641

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. _6e___                              Page 3 of 8 
Meeting Date: June 27, 2017 
increase is within Commission authorized project spending. In accordance with RCW
53.19, the Commission is notified that this amendment exceeds 50 percent value of the
original contract and this memorandum will be made available for public inspection. 
The total (all phases combined) project schedule would be extended 14 months and
total cost is estimated at $445,050,000. 
Scope of Work 
The requested capacity acceleration will include the following additions in order to expand the
capacity of the baggage system to 60 MAP: 
1)  Installation of additional CTX Machines (TSA provided) 
2)  Ticketing mainlines 
3)  Sortation mainlines 
4)  Additional recirculation lines 
5)  Building infrastructure to accommodate additional BHS capacity 
6)  Additional baggage inspection tables in Central Screening Area 
7)  Additional conveyor queues in Central Screening Area 
8)  Two South Satellite make-up devices and associated sortation lines 
9)  South Satellite tunnel make-up feed line addition 
10) Two new outbound make-up devices in International Arrivals Facility (IAF) and mainlines 
11) IAF manual encode station 
12) Necessary demolition of temporary IAF baggage system to allow this work to be
installed 
Much of the 60 MAP scope can be performed concurrently with the original Phase 2 and 3 
work, but portions cannot be done concurrently and will add 14 months to the total project
duration. 
The additional makeup units included in the 60 MAP scope (2 units in the new IAF and 2 units at
South Satellite) maximize the amount of makeup units that will fit within the current airport
footprint. Even with these additional makeup units the system will still have a shortage of 27
cart positions and would function more efficiently if these cart positions could be added in the
future, either by utilizing space created by future footprint expansion or potentially adding an
early bag storage facility. 
The following work has been designated for Port Construction Services to perform in order to
streamline the transition between Phases. This streamlining is not necessitated by the capacity 
expansion and will be necessary for either 45 or 60 MAP construction. This "pre-work" will
consist of the following items: 
1)  H-line wall code compliance for Phase 2 permit 
2)  Claim 13 conveyor input installation 
3)  Right of way clearances 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. _6e___                              Page 4 of 8 
Meeting Date: June 27, 2017 
4)  Right of way conveyor, MCP and conduit demolition 
5)  Change order alternative 
6)  Portering of bags to maintain operations during construction 
7)  Shutdown support 
8)  Equipment movement and TSA/contractor support 
9)  Tenant, TSA, Airline and Port move support 
10) Testing Support 
Schedule 
Activity 
Construction start                                2017 Quarter 2 
In-use date (45 MAP System)                   2023 Quarter 3 
In-use date (60 MAP System)                    2024 Quarter 4 
Cost Breakdown                          This Request           Total Project 
Design                                     $19,937,200           $61,101,936 
Construction                                $5,000,000          $383,948,064 
Total                                          $24,937,200           $445,050,000 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  Construct the 45 MAP design with no authorization for additional scope. 
Cost Implications: $0 
Pros: 
(1)   The project can continue to be completed on time and within budget as originally
scoped. 
Cons: 
(1) Risk of significant negative impacts to service for airlines and travelers (e.g. bags delayed
or missed delivery to airplanes during peak time periods). 
(2) Postponing the decision for action now creates the potential for increased urgency and
cost when expansion is implemented in the future. 
This is not the recommended alternative. 




Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. _6e___                              Page 5 of 8 
Meeting Date: June 27, 2017 
Alternative 2  Continue with the project construction as originally designed, and add the
increased capacity scope at the end of the project as a fourth phase. 
Cost Implications: $180,000,000 
Pros: 
(1)   Bid and construction of Phases 2 and 3 would continue as originally anticipated, while
designing and bidding the increased capacity would be added as an additional project
phase. 
Cons: 
(1)   Overall costs will be higher as it is more efficient to construct the expanded design
concurrently with Phases 2 and 3. 
(2)   The reliability of service for the airlines and travelers will be compromised until this
scope of work is completed. 
(3)   Fourth phase would extend current project schedule 2-1/2 years. 
This is not the recommended alternative. 
Alternative 3  Authorize increased scope of the Baggage Optimization project in order for the
new outbound baggage system to accommodate 60 MAP. 
Cost Implications: $150,000,000 
Pros: 
(1)   This will allow the new baggage system to meet airport growth. 
(2)   Results a cost savings versus designing and performing this work in the future due to
efficiencies gained by combining work with existing phases. 
(3)   Reduction in cost escalation compared to performing this work in the future. 
Cons: 
(1)   Increases the complexity of Phase 2 and Phase 3 construction. 
(2)   Adds 14 months to project versus original 45 MAP schedule. 
This is the recommended alternative. 






Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. _6e___                              Page 6 of 8 
Meeting Date: June 27, 2017 
FINANCIAL IMPLICATIONS 
Cost Estimate/Authorization Summary               Capital          Expense             Total 
COST ESTIMATE 
Original estimate                                  $4,850,000          $150,000        $5,000,000 
Previous changes  net                         $314,050,000                $0     $314,050,000 
Budget transfer from C800780                  $14,000,000                $0      $14,000,000 
Savings returned  net                          ($24,000,000)                 $0     ($24,000,000) 
Current request                                $136,000,000                $0     $136,000,000 
Revised estimate                              $444,900,000          $150,000     $445,050,000 
AUTHORIZATION 
Previous authorizations                         $135,525,000          $150,000      $135,675,000 
Available Authorization from 
$24,300,000                $0      $24,300,000 
Ph 1 Budget Savings 
Current Authorization Need: 
Design Consultant $10,160,000 
$24,937,200                $0      $24,937,200 
Design Support $9,777,200 
Small Works $5,000,000 
Reduced authorization from above
$637,200                $0         $637,200 
budget savings 
Total authorizations, including this
$136,162,200         $150,000     $136,312,200 
request 
Remaining amount to be authorized           $308,737,800               $0     $308,737,800 

Annual Budget Status and Source of Funds 
This project, C800612, was included in the 2017-2021 capital budget and plan of finance, but
without the accelerated scope. The funding sources will include the Airport Development Fund,
TSA funding ($93,220,422) and future revenue bonds. 
Financial Analysis and Summary 
Project cost for analysis              $445 million 
Business Unit (BU)                  Baggage System 
Effect on business performance     NOI after depreciation will increase. 
(NOI after depreciation) 
IRR/NPV (if relevant)                N/A 
CPE Impact                       $1.30 by 2025 


Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. _6e___                              Page 7 of 8 
Meeting Date: June 27, 2017 
ADDITIONAL BACKGROUND 
Baggage Optimization Project Update: 
The Baggage Optimization project increases the screening capacity of the Baggage Handling
System to process growing baggage volumes, increases flexibility to allow bags to be checked in
anywhere in ticketing and be conveyed to any makeup device, meets a minimum-connect-time
goal, and increases energy efficiency.  Meeting travelers'  baggage needs will significantly
contribute to increased customer service. 
This project will be constructed in three phases.  Project Phase 1 construction contract was
executed in March 2017 and notice to proceed is expected to be granted in May 2017. 
Phase 1 construction was advertised and bids were opened in Q4 2016. Three bids were
received; the lowest bidder was PCL Construction Services Inc. with a bid amount of $52M.
The bid amount was $28M below the Engineer's Estimate of $80M. The project returned $24M
due to the low bid. 
Pre-work began in December 2016 with Port Construction Services crews and small works
electrical contractors. A new makeup unit has been installed. Horizon moved their operations
to this new device in April 2017. The PCS crews are now working to complete a new odd-size
device, from which TSA will begin to operate at the end of June 2017. 
Small business requirements were also evaluated and set for the Phase 1 construction contract.
The requirement for this contract is that 15% of the total contract value, including change
orders, be performed by Small Business Enterprise(s). Within the 15% total requirement, at
least 5% of the total contract value work shall be performed by one or more Certified Small
Businesses. 

ATTACHMENTS TO THIS REQUEST 
(1)   Presentation slides 

PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
October 25, 2016  Baggage Quarter 4 Briefing 
July 12, 2016  Commission authorization to advertise and execute a contract for
construction Phase 1 
June 28, 2016 Baggage Program Briefing. 
May 17, 2016  Checked Baggage Optimization Project Briefing. 
March 8, 2016  Commission authorization for the Chief Executive Officer to amend the
Baggage Optimization Design Services contract. 
June 23, 2015  Checked Baggage Optimization Project Briefing. 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. _6e___                              Page 8 of 8 
Meeting Date: June 27, 2017 
September  10,  2013    The  Commission  authorized  the  execution  of  an  Other
Transaction Agreement (OTA) with TSA for reimbursable costs for design; construction,
and to authorize $15 million to continue from 30% to 100% design; and execute a
consultant service agreement for program management support services. 
August 20, 2013  Response to questions from Commissioners asked during August 6,
2013 Commission Meeting. 
August  6,  2013    The  Commission  was  briefed  on  the  near-term  and  long-term
challenges related to handling checked baggage at the Airport. 
January 22, 2013  The Commission authorized $5 million for staff to begin design
through 30%, and to enter into an agreement to allow reimbursement from the federal
government to the Port for eligible elements of the 30% design effort. 
January 8, 2013  Baggage Systems Briefing. 
August 14, 2012  Baggage system recapitalization/optimization was noted in the 2013
business plan and capital briefing as a significant capital project not included in 2013-17
capital program. 
August 7, 2012  Baggage system recapitalization/optimization was referenced as one of
the drivers for the need to develop an Airport Sustainability Master Plan. 
June 26, 2012  The Airport's baggage systems were discussed during a briefing on
terminal development challenges. 
May 10, 2012  TSA's interest in a national recapitalization/optimization plan for all
baggage-screening operations was referenced in a design authorization request for the
C60-C61 Baggage Handling System Modifications Project. 









Template revised September 22, 2016; format updates October 19, 2016.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.