4b

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA               Item No.      4b 
ACTION ITEM 
Date of Meeting    September 13, 2016 
DATE:    September 6, 2016 
TO:      Ted Fick, Chief Executive Officer 
FROM:   Wayne Grotheer, Director, Aviation Project Management Group 
Jeffery Brown, Director, Aviation Facilities and Capital Programs
SUBJECT:  Electrified Ground Support Equipment (EGSE) Charging Stations Construction
Authorization (CIP #C800335) 
Amount of This Request:        $4,600,000   Source of Funds:   Airport Development
Fund and Existing
Est. Total Project Cost:         $30,700,000 
Revenue Bonds 
Est. State and Local Taxes:         $60,000 
ACTION REQUESTED 
Request Commission authorization for the Chief Executive Officer to (1) advertise and award a
major works construction contract for Phase 2A (Concourse A) of the Electric Ground Support
Equipment (EGSE) Charging Stations project (the anticipated cost of $4.6 million is within the
amount already authorized by the Commission); (2) utilize Port crews to perform construction
work.
SYNOPSIS 
The Commission previously authorized funding necessary to complete the full EGSE design
documents as well as the Phase 1 construction. This request is for the advertisement and award
of a construction contract for phase 2A; no additional funding authorization is necessary for the
construction of Phase 2A. In March 2012, the airlines approved the full project in a Majority in
Interest vote. 
During Phase 1 construction, small business was utilized and the plan is to utilize small business
again for Phase 2A construction. 
This request enables staff to complete Phase 2A of this project, which installs EGSE charging
stations throughout the Concourse A ramp area and constructs telecommunications early work
necessary for Phase 2B (Concourse B and South Satellite). EGSE Phase 2B will be a later
separate authorization request to the Commission. The Phase 2A & 2B work completes full
airport coverage to enable the phase-out of fossil-fueled ground support equipment such as
baggage tugs and aircraft pushback tractors at Seattle-Tacoma International Airport. Delta,

Template revised May 30, 2013.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
September 6, 2016 
Page 2 of 6 
United and Southwest Airlines will utilize and benefit from the EGSE infrastructure provided by
this project as soon as it becomes available in 2017. 
This project will improve air quality by reducing particulate matter and carbon emissions from
ground support equipment, reduce airline maintenance costs, save fuel costs, and contribute to
the Century Agenda goal to "Be the greenest and most energy efficient Port in North America." 
Assuming full airline participation, a fuel savings of $2.8 million per year is anticipated with a
carbon reduction of up to 10,000 tons per year. 
BACKGROUND 
To accommodate recent growth in airline demand for EGSE, Port staff has divided the Phase 2
work into two construction packages (Phase 2A and Phase 2B). The EGSE charging stations can
be installed relatively quickly on Concourse A (Phase 2A) because no additional power
distribution switchgear is necessary. The phase 2B work is complex because sufficient power
distribution equipment does not currently exist to support charging stations on Concourse B and
the South Satellite. The Phase 2A work installs 20 charging stations by year-end and allows
airlines operating out of the south half of the airport to proceed with their immediate plans to
deploy EGSE in early 2017. 
The overall EGSE program consists of the following three packages: 
Phase 1 - Actual cost $14.3 million (This work is complete) 
o  Install 286 charger ports on Concourses C and D, North Satellite and Central
Terminal bag well 
Phase 2A - Estimated cost $4.6 million (This authorization) 
o  Install 76 charger ports on Concourse A 
Phase 2B - Estimated cost $17.2 million (This estimate exceeds the current authorized
budget of $30.7M and requires future commission action)
o  Install 142 charger ports on Concourse B and the South Satellite 
o  Install new Power Centers at B Concourse and the South Satellite
The Phase 2B design will be 90% complete in Q3 of 2017 and will include an updated Phase 2B
construction cost estimate. Staff anticipates returning to Commission in Q3 of 2017 requesting
an estimated $5.4 million budget increase to construct Phase 2B for a revised total project budget
of $36.1 million. The required budget increase is a result of the scheduled delay in Phase 2
construction. The Phase 2 design documents were completed in 2013. However, due to low
demand on the south half of the airport for EGSE, phase 2 construction was deferred. Demand
has since increased dramatically, with Delta, United, and Southwest all deploying EGSE in
2015-6 and demanding more charging infrastructure in the South half of the airport.
Previous Commission authorizations include $1.51 million on October 26, 2010, for preliminary
design; $8 million on April 3, 2012, to install 20 chargers at the demonstration site, order 

Revised

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
September 6, 2016 
Page 3 of 6 
charging units, and design the installation; and $16.2 million on October 23, 2012 to prepurchase
EGSE chargers, and execute the Phase 1 construction contract. 
Currently, Washington law allows a waiver of state sales tax on the purchase and installation of
energy-saving equipment until 2020, which will save approximately $2 million in taxes for the
entire project. 
PROJECT JUSTIFICATION AND DETAILS 
Project Objectives 
This Project will install EGSE Charging Stations at Seattle-Tacoma International Airport and
will: 
Reduce air pollutants such as particulate matter and carbon emissions 
Reduce fuel consumption by approximately one million gallons per year 
Reduce airline maintenance costs 
Take advantage of Washington state sales tax waivers that expire in 2020 for the project
elements related to utilizing electrical power vs. fossil fuel 
Scope of Work 
This authorization provides for the advertisement and award of a major works construction
contract that will install 76 charging points on Concourse A. 
Staff will return to commission in Q3 of 2017 seeking authorization for Phase 2B which will
upgrade two power centers and install approximately 142 charging points on concourse B and
the South Satellite. 
The entire program will ultimately install approximately 252 EGSE charging stations throughout
the Airport passenger terminal ramps capable of charging 504 pieces of ground service
equipment simultaneously. 
Schedule 
Phase 2A 
Design Complete                 4th Quarter 2016 
Advertise for Construction             4th Quarter 2016 
Substantial Completion              4th Quarter 2017 
Phase 2B 
Design Complete                 3rd Quarter 2017 
Advertise for Construction            3rd Quarter 2017 
Substantial Completion              3rd Quarter 2019 


Revised

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
September 6, 2016 
Page 4 of 6 
FINANCIAL IMPLICATIONS 
Budget/Authorization Summary              Capital     Expense   Total Project 
Original Budget                     $30,198,000     $502,000   $30,700,000 
Previous Authorizations                $25,348,227     $300,000   $25,648,227 
Current request for authorization                  $0          $0          $0 
Total Authorizations, including this request    $25,348,227      $300,000    $25,648,227 
Remaining budget to be authorized         $4,849,773     $202,000    $5,051,773 
Total Estimated Project Cost             $30,198,000     $502,000   $30,700,000 
Project Cost Breakdown                     This Request       Total Project 
Design Phase                                  $0         $4,000,000 
Construction Phase                                $0        $26,640,000 
State Tax                                       $0           $60,000 
Total                                           $0         $30,700,000 
Budget Status and Source of Funds 
The EGSE Charging Stations CIP #C800335 is included in the 2016-2020 capital budget and
plan of finance. The remaining source of funds for this project will include the Airport
Development Fund and existing revenue bonds 
Financial Analysis and Summary 
CIP Category             Renewal/Enhancement 
Project Type              Renewal & Replacement 
Risk adjusted discount rate     N/A 
Key risk factors             N/A 
Project cost for analysis        $4,600,000 Phase 2A 
Business Unit (BU)          Terminal /Gates 
Effect on business performance  NOI after depreciation will increase 
IRR/NPV             N/A 
CPE Impact             $0.02 in 2018 
STRATEGIES AND OBJECTIVES 
The Port's purchase and installation of EGSE charging stations will promote and expedite carrier
adoption of EGSE vehicles such as electric pushback tractors and tugs. Implementation of
EGSE reduces emissions at the Airport. The EPA considers electric vehicles the best alternative
vehicle fuel option for emission reductions. 
This project helps to clean the environment by reducing air pollutants such as particulate matter
and greenhouse gases, creates short-term construction jobs, and incorporates small business
opportunities to encourage small business participation in a major construction contract. 

Revised

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
September 6, 2016 
Page 5 of 6 
This project helps the environment by reducing fossil fuel consumption at the Airport and allows
our business partners to expand their operations. 
During phase one construction, small business was utilized and the plan is to utilize small
business again for Phase 2A construction. 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  Status Quo  Do not complete this project 
Cost Implications: Approximately $2.2 million in design fees will need to be expensed. 
Pros: 
(1)  No additional capital costs 
Cons: 
(1)  Most airlines will not be able to take advantage of EGSE 
(2)   The Port of Seattle will not be able to realize the environmental benefits of EGSE
on the south half of Sea-Tac Airport 
This is not the recommended alternative. 
Alternative 2  Complete Phase 2 of this project (Provides Full Airport Coverage)
Cost Implications: Project Cost Estimate $21.8 million 
Pros: 
(1)  Installs 218 EGSE charge ports on Concourse A, B and the South Satellite
(2)  Maximizes the reduction in carbon emissions from ground service equipment 
(3)  Allows all airlines operating out of Sea-Tac Airport to take advantage of EGSE 
Cons: 
(1)  Additional capital cost 
This is the recommended alternative. 
ATTACHMENTS TO THIS REQUEST 
Computer slide presentation 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
October 23, 2012, the Commission authorized $16,200,000 to: (1) advertise and
execute a construction contract for Phase 1 of the Ground Support Equipment-
Electrical Charging Stations Project-Installation of Chargers; and (2) pre-purchase
electrified ground support equipment (EGSE) chargers for Phase 2 of the project. 

Revised

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
September 6, 2016 
Page 6 of 6 
On April 3, 2012, the Commission authorized $ 8,000,000 to: (1) prepare full
design documents for the Electrified Ground Support Equipment charging station
Project; (2) for PCS to install approximately 20 chargers as a demonstration project;
(3) approve budget for the EGSE overall project; and (4) contract for long lead time
electrical equipment for power center upgrades. 
On September 12, 2011, the Commissioned authorized signing no-cost contracts for
EGSE vehicles and EGSE chargers. 
On May 10, 2011, the Commission was briefed regarding progress on the EGSE
project prior to soliciting pricing for rolling stock. 
On October 26, 2010, the Commission authorized $1,510,000 for preliminary
design, necessary contracts, and work by Port forces to begin to implement the
ultimate project; pre-purchase specialized equipment and materials through
competitive bid processes; and to authorize Port Construction Services to perform
Regulated Materials Management (RMM) investigations and self-perform
necessary associated work. 
On September 28, 2010, the Commission was briefed on the 2011 capital budget
that included the above-mentioned EGSE projects. 
On September 8, 2005, the Commission was briefed on the benefit of changing
from fossil fuel based GSE vehicles to EGSE based vehicles at Seattle-Tacoma
International Airport. 










Revised

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.